Smart Summary

Factual and Procedural Background

The appellant contractor's tender for the construction of a vertical extension of the T.E Building at Chanakya Puri, New Delhi, was accepted on 29th July 1980. The work was scheduled to commence on 13th August 1980 and to be completed by 12th August 1981. The work was not completed by the stipulated date, and the agreement was rescinded by the respondent through a letter dated 21st August 1982. The appellant contended that the rescission was illegal and unjustified and invoked the arbitration clause. The arbitrator, Shri N.N Chakraborty, delivered an award on 31st January 1986, holding the rescission unjustified and allowing various claims by the appellant, including a substantial claim for escalation of rates (Claim No. 3).

The respondent Union of India filed objections to the award before the learned Single Judge, who set aside the award regarding Claim No. 3 and refused to grant interest from the date of award till the date of decree on the allowed claims. The appellant challenged the Single Judge's judgment dated 12th March 1987, specifically contesting the setting aside of Claim No. 3 and the refusal of pre-decree interest.

Legal Issues Presented

  1. Whether the award allowing Claim No. 3 (extra payment due to escalation of rates for work performed after the stipulated completion date) should be upheld or set aside.
  2. Whether interest should be granted from the date of the award till the date of decree on the claims allowed by the learned Single Judge.

Arguments of the Parties

Appellant's Arguments

  • The rescission of the contract was illegal and unjustified as the delay in commencing work was due to the respondent's failure to provide drawings and access in a timely manner.
  • The contractor executed work valued at Rs. 5,11,741.45 after the due completion date, and due to a 57% increase in market rates of construction materials, the appellant was entitled to Rs. 2,91,693 as escalation.
  • The respondents did not file a reply disputing the cost analysis submitted by the appellant, which should be treated as undisputed evidence entitling the appellant to the claimed amount.
  • The quality or sufficiency of evidence should not be re-examined by the court since the arbitrator, an experienced engineer and senior officer of the respondent, was satisfied with the evidence and made the award accordingly.
  • Relied on precedents such as Delhi Municipal Corpn. v. Jagan Nath Ashok Kumar and Jagdish Chander v. Hindustan Vegetable Oils Corpn to support non-interference with the arbitrator’s award.

Respondent's Arguments

  • The case is not about the sufficiency or quality of evidence but the complete absence of any evidence supporting the escalation claim except the cost analysis chart.
  • The claimant did not lead any independent evidence apart from the cost analysis, which is insufficient to sustain the claim.
  • The total value of work done after the stipulated date included Rs. 2,60,711.57 worth of steel and cement supplied by the department at agreed rates, on which no escalation was applicable.
  • The escalation, if any, could only be allowed on Rs. 2,17,447.43 (total minus steel and cement), not on the entire amount of Rs. 4,78,159.
  • Submitted that the arbitrator misconducted himself by allowing escalation on the total amount without excluding the supplied materials.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Delhi Municipal Corpn. v. Jagan Nath Ashok Kumar, 1987 4 SCC 497 Non-interference with arbitration awards by experienced arbitrators who are experts in the trade. Appellant relied on this precedent to argue against interference in the arbitrator's award regarding Claim No. 3.
Jagdish Chander v. Hindustan Vegetable Oils Corpn, AIR 1990 Delhi 204 Similar principle of respecting awards made by arbitrators with relevant expertise. Appellant cited this case to support the validity of the arbitrator's findings.
Secretary, Irrigation Department, Govt. of India v. G.C Roy, 1992 1 SCC 508 Entitlement to pendente lite interest on awarded amounts. Court applied this precedent to hold that the appellant is entitled to interest from the date of award till payment.
Hindustan Construction Co. Ltd. v. State Of Jammu & Kashmir, 1992 4 SCC 217 Clarification on entitlement to pendente lite interest in construction contract disputes. Supported the modification of the decree to grant interest on awarded amounts from the date of award.

Court's Reasoning and Analysis

The court acknowledged that the rescission of the contract by the respondent was illegal and unjustified and agreed with the arbitrator that the delay in work commencement was attributable to the respondent. The court accepted that the contractor executed work after the stipulated date and was entitled to escalation in principle. However, the court found that the appellant failed to produce any independent evidence beyond the cost analysis chart to substantiate the claimed escalation amount. The respondent did file a reply and rejoinder before the award was passed, negating the appellant's argument of non-traverse.

The court emphasized that mere filing of cost analysis without supporting evidence does not constitute proof of expenditure for escalation. It also held that escalation could not be allowed on the entire amount of work done after the due date because the cost of steel and cement supplied by the respondent at agreed rates (Rs. 2,60,711.57) did not attract escalation. The arbitrator's allowance of escalation on the total amount was therefore found to be without basis.

Regarding interest, the court noted the respondent's concession in light of Supreme Court precedents that the appellant was entitled to pendente lite interest on the claims allowed by the learned Single Judge. The court accordingly modified the decree to grant interest at 12% per annum from the date of award till payment on Rs. 55,425.

Holding and Implications

The appeal was partly allowed and partly dismissed. The court upheld the learned Single Judge's setting aside of the award on Claim No. 3 due to lack of supporting evidence and improper basis for escalation calculation. However, the court modified the decree to grant pendente lite interest at 12% per annum from the date of award till payment on the allowed claims.

The direct effect of this decision is that the appellant contractor is not entitled to the escalation claim under Claim No. 3, but is entitled to interest on the awarded amounts from the date of the arbitration award. The decision does not create any new precedent beyond applying established principles regarding evidence sufficiency and entitlement to pendente lite interest.

    Kochar Construction Co. v. Union Of India And Another

    Arun Kamar, J.:— This is contract's (claimant) appeal against the judgment and decree dated 12th March, 1987 passed by the learned Single judge whereby the award dated 31st January, 1986 was set aside with respect, tn claim No. 3 and the claim regarding future interest. For the rest a decree was passed in terms of the award granting interest at the rate of 12 per cent per annum from the date of decree till payment in the event of failure of the respondent to pay the decretal amount within two months from th; date of decree. The appellant is aggrieved by the decision of the learned Single Judge in-setting aside the award regarding claim No. 3 and refusal to grant interest from the date of award till the date of decree on the claims which were allowed by the learned Single Judge.

    2. The appellant's tender for construction of vertical extension of T.E Building, Chankya Puri, New Delhi, was accepted by the respondents on 29th July, 1980. The work was to commence on 13th August, 1980 and was to be completed by 12th August, 1981. The work could not be completed by the stipulated date and the agreement was rescinded vide letter dated 21st August, 1982.

    3. According to the appellant the rescission of the contract by the respondent was illegal and unjustified. The contractor invoked arbitration clause. The claims raised by the contractor and the counter claims of the respondent were finally adjudicated upon by Shri N.N Chakraborty, Superintending Engineer. The learned arbitrator gave his award on 31st January, 1986 holding that the rescission of the contract by the respondent was unjustified. As per the award the following claims were allowed:

    “No. of claim Name of claim Amount claimed Amount allowed Claim No. 1 Refund of security deposit Rs. 32,000 modified to Rs. 33,641 Rs. 33,641 Claim No. 2(a) Claim for further payment for part rates items Rs. 12,188.89 later modified to Rs. 8,996.98 Rs. 655 Claim No. 2(b) Claim for further payment for extra items Rs. 1,443.83 Rs. 631 Claim No. 2(d) Claim for further payment for the work already done Rs. 43,698.22 Rs. 18,355 Claim No. 3 Claim for extra payment due to escalation of rates Rs. 2,91,390 modified to Rs. 2,91.693 Rs. 2,86,895 Claim No. 5 Claim for payment of dismantling alleged to have been done by chiselling Rs. 4,000 Rs. 2,143
    Claim No. 15 Claim for pendente lite interest (i) interest at 12% p.a from March 3, 1983 to the date of the award on items No. L, 2(a), 2(b) and 2(d) and (ii) from the date of the award till the date of payment or decree on the entire amount of Rs. 3,42.320.”

    4. The mutter came up before the learned Single Judge for making the award rule of the court and for passing a decree ia terms thereof. Objections to the award were filed on behalf of the respondent Union of India. After considering the objections the learned Single Judge set aside the award regarding claim No. 3. The learned Single Judge also disallowed interest on the amount awarded with respect to other claims from the date of award tilt the date of decree. The appellant has challenged tho judgment of the learned Single Judge regarding both these points.

    5. So far as the question of non-grant of pendente lite interest Let interest from the date of award till the date of decree on the claims allowed, the learned counsel for the respondent conceded at the time of hearing that in view of the latest judgments of the Supreme Court the appellant is entitled to pendente lite interest on the claims allowed by the learned Single Judge. Therefore, the only point of controversy in the present appeal has been regarding the decision of the learned Single Judge on claim No. 3 ia con* cerned.

    6. Claim No. 3 pertains to extra payment due to escalation of rates for the work performed after the due date completion of works. The case of the appellant regarding the said claim is that under the agreement the work was to commence on 13th August, 1980 and was to be completed by 12th August, 1981. The respondents, however, finalised the drawings and gave the same to the contractor only in December 1980. They failed to provide access to the terrace where the work was to be executed. The side stair case was constructed only in July 1981. In the circumstances the contractor could not start the execution of the work before July 1981. The contractor had to execute the work of the value of Rs. 5,11,741.45 after August 1981, i.e, after the due date of completion of work. The market rate of cons* traction material to be procured by the contractor had gone up by 57% over the tender cost and, therefore, the contractor was entitled to 57% of Rs. 5,11,741.45, i.e, Rs. 2,91,693. The time was not the essence of the contract and under these facts the rescission of the contract was unjust and illegal. In their reply the respondents almost admitted the fact that delay in commencement of the work was on their account. The respondents, therefore, had granted extension of time to the contractor.

    7. Considering all the circumstances the learned Arbitrator held that the respondents had been in default and had committed breach of contract inasmuch as the delay in commencement of work was on their account. The learned arbitrator further held that the contractor/claimant had executed work of gross value of Rs. 4,78,159 after the stipulated date of completion of work and was entitled to increase at the rate of 60 per cent on the said amount which worked out to Rs. 2,86,895. The Contractor was thus allowed this amount under claim No. 3.

    8. The learned Single Judge has upheld the finding of the arbitrator that the rescission of the contract by the respondents was illegal and unjustified. The learned Single Judge also did not find any fault with the finding of the learned arbitrator that prolongation of work was caused by the defaults and breaches on the part of the respondent and that the contractor was entitled to claim revision of rate because of increase in the cost of construction. Further on the merits of the claim the learned Single Judge did not sustain the finding of the learned arbitrator and, therefore, the claim was disallowed. The real point in issue in this connection is—whether there was any material on record to sustain the claim of the claimant for the amount claimed by it under this head ? The appellants have mainly relied on cost analysis submitted by them which is Annexure ‘D’ to their statement of claim. According to the appellants the respondents failed to file ‘Uny reply to the said analysis or dispute the same and therefore, the appellant is entitled to the amount claimed by it on the basis of analysis submitted by them. A reference has been made to the arbitration proceedings dated 3rd August, 1985 wherein the arbitrator directed the respondents to file their reply to the said analysis. The arbitration proceedings concluded on 23rd November, 1985. A reply to the cost analysis of the claimant was filed by the respondent before the arbitrator on 6th January 1986 and the claimant filed a rejoinder thereto on 21st January, 1986. Thus according to the learned counsel for the appellant upto 23rd November, 1985 no reply to the cost analysis of the appellant was filed by the respondent. Therefore, it should be taken as a case of non-traverse and the appellant should be held entitled to the amount claimed. It is further submitted on behalf of the appellant that quality or quantity of evidence or sufficiency of evidence is not to be gone into by the court and since the arbitrator had felt satisfied about the evidence in this behalf the claim ought to have been decreed. The learned counsel for the appellant has relied on Delhi Municipal Corpn. v. Jagan Nath Ashok Kumar . 1987 4 SCC 497 and Jagdish Chander v. Hindustan Vegetable Oils Corpn. . AIR 1990 Delhi 204. to contend that when the arbitrators is a man of the concerned trade, being an experienced Engineer in the present case and being a senior officer of the respondent, the award of such an arbitrator ought not to be interfered with.

    9. In reply the learned counsel for the respondent has submitted that it is not a case of quantity or quality of evidenfe or sufficiency of evidence, but it is a case of no evidence at all. According to the learned counsel filing of cost analysis alone is not sufficient. In order to sustain its claim the claimant has to lead some evidence in its support. No evidence was at all lead by the claimant on the point except filing of the chart containing cost analysis. Apart from this our attention has been drawn by the learned counsel for the respondent to the fact that admittedly the claimant had executed the work of the value of Rs. 4,78,159 after the date of completion of the work. This figure of Rs. 4,78,159 included a sum of Rs. 2,60,711.57 which was the price of steel and cement supplied by the department to the contractor on the original agreed rates, meaning thereby that there was no question of escalation in the cost to this extent. If the amount of Rs. 2,60,711.57 was excluded from the figure of Rs. 4,78,159 the contractor had spent only Rs. 2,17,447.43 by way of material and wages and at the most increase could be allowed on this amount and not on the total amount. Thus, according to the respondents, the learned arbitrator, misconducted himself and the proceedings in allowing the increase on percentage basis on the total amount of work done by the contractor after the due date of completion.

    10. Both the above submissions on behalf of Union of India found favour with the learned Single Judge and, therefore, the claim on account of escalation in the cost of construction after the stipulated due date of completion was disallowed and the award in this respect was set aside. We find ourselves in total agreement with the reasoning of the learned Single Judge in this behalf. In the facts and circumstances of the case mere filing of cost analysis cannot be accepted as the evidence of expenditure on account of increased cost of construction even if the cost analysis was not traversed by the respondent. While on question of traverse it may be mentioned that the respondent had filed a reply in opposition, though after the date of completion of arbitration proceedings and the claimant filed a rejoinder thereto. These were both before the date of the award.

    11. The fact remains that no independent evidence has been led in support of the claim. The case, therefore, is one of total lack of evidence. Apart from this we also agree that assuming escalation could be allowed on percentage basis, the same could not be allowed on the total amount of work done after the date of due completion, i.e on Rs. 4,78,159. The cost of steel and cement supplied by the respondent at the agreed rates, i.e without any escalation, amounting to Rs. 2,60,711.57 was in any case liable to be excluded from the said total amount. Under the circumstances we find &0 merit in the submissions on behalf of the appellant on claim No. 3.

    12. However, in view of the latest position in law emerging from Secretary, Irrigation Department, Govt, of India v. G.C Roy . 1992 1 SCC 508 and Hindustan Construction Co. Ltd. v. State Of Jammu & Kashmir. . 1992 4 SCC 217, the appellant is entitled to pendente lite interest. The impugned judgment and decree dated 12th March, 1987 is modified to the extent that the appellant decree holder is entitled to interest on the amount of Rs. 55,425 at the rate of 12 per cent per annum from the date of award till the date of payment. The appeal is disposed of in these terms leaving the parties to bear their respective costs.