Smart Summary

Structured Summary of the Opinion (Delivered by The Chief Justice)

Factual and Procedural Background

On 17 September 1958 the State Government published a notification under S. 4(1) of the Land Acquisition Act proposing to acquire roughly 300 acres in Kodambakkam for rehabilitating slum dwellers in Kanniappanagar and other parts of Madras. That notification included, by exercise of powers under S. 17(4), a dispensation of S. 5-A on the ground that the acquisition was urgent. A subsequent publication under S. 6 occurred on 26 November 1958 and notices under S. 9(3) called for claims for compensation.

The appellant owned 2.44 acres (wet lands) in S. No. 154, subject to a mortgage. He filed a claim for compensation; the Special Deputy Collector awarded Rs. 16,836 for that land by notice dated 18 January 1961. The appellant was later called upon to deliver possession. Nearly three years after the S. 4(1) notification, the appellant and others petitioned under Article 226 seeking to quash the acquisition notification.

The primary ground urged was that the acquisition's original purpose had failed because the slum dwellers initially refused to move into the scheme area and the State Housing Board then allotted sites to low and middle income persons — an alleged diversion of purpose. During parallel proceedings W.P. Nos. 1094 of 1959 and 151 and 301 of 1960, Veeraswami, J. quashed the portion of the notification that purported to dispense with S. 5-A by relying on S. 17(4), while leaving the remainder valid. The Government thereafter indicated willingness to withdraw the S. 17(4) portion.

Legal Issues Presented

  1. Whether the acquisition notification under S. 4(1) remained valid in view of a claimed diversion of purpose when the Housing Board allotted sites to low and middle income groups rather than exclusively to slum dwellers.
  2. Whether, because the S. 17(4) emergency dispensation (relying on which S. 5-A was dispensed with) was held invalid, the entire notification (including the S. 4(1) portion) must be quashed, or whether the invalid part is severable.
  3. Whether changed circumstances (the unwillingness of some slum dwellers initially to migrate) meant that the necessity for acquisition had ceased and therefore the acquisition was illegal.
  4. Whether, if S. 17(4) is struck down, the affected owners have lost their statutory right under S. 5-A because more than thirty days elapsed since the original S. 4(1) notification — and if so, whether a fresh S. 4(1) notification is required to make S. 5-A effective.

Arguments of the Parties

Appellant's Arguments (as advanced by Mr. Arunachalam)

  • The original public purpose failed because slum dwellers initially refused to migrate, so necessity for acquisition ceased and the notification became invalid.
  • The Housing Board's allotment of sites to low and middle income persons amounted to a diversion of the original purpose, making the acquisition invalid; reliance was placed on R.H. Galloway v. Mayer and Commonality of London.
  • Because S. 5-A had been dispensed with by S. 17(4) in the original notification, and more than thirty days had elapsed since that notification, striking down only the S. 17(4) part renders S.5-A meaningless unless the entire S. 4(1) notification is reissued — therefore the whole notification should be quashed to protect statutory objection rights.

Government / Respondent Arguments and Positions

  • The Government conceded (and informed the court) that the S. 17(4) portion dispensing with S. 5-A could be withdrawn and that they were willing to hear objections under S. 5-A.
  • The Special Deputy Collector's counter-affidavit stated that the Government's intention was not to confine allotments solely to slum dwellers; the notification itself did not specify such a restriction.
  • The Special Government Pleader argued that objections under S. 5-A could be filed within thirty days of the substance of the notification being published by the Collector, and need not necessarily depend on the original S. 4(1) publication date; hence the appellant could still effectively make objections.
  • Implicitly, the Government relied on the separability of the S. 17(4) portion from the S. 4(1) portion so that the invalidity of one does not vitiate the other.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
R.H. Galloway v. Mayer and Commonality of London Private bodies authorised to acquire land for a specified purpose cannot compulsorily acquire for a different or collateral object; however, the decision recognises a distinction where public bodies (e.g., municipal corporations) entrusted with public improvements may have broader power not subject to strict and restrictive construction. The Court distinguished the present facts from Galloway: because the acquisition was by a public body for a public purpose, the allotment of sites to other needy persons did not constitute an impermissible diversion.
Parshottam Jethalal v. Secretary of State Held that where a scheme is revised or altered, the public purpose may remain essentially the same; the Land Acquisition Act requires notification under S. 4 and then under S. 6 but does not demand identity of the scheme's means of execution throughout. The Court relied on this authority to support the proposition that a revised or broadened mode of carrying out the project (including allotting sites to low/middle income persons) does not invalidate the acquisition if the public purpose remains substantially the same.
Ramabrahmam v. State of Andhra Pradesh; Madhavi Ammal v. Revenue Divisional Officer, Kozhikode; Naga Mills Tea Co. v. State of Assam Authorities for the proposition that where a single original notification contains both a S. 4(1) notification and an S. 17(4) order dispensing with S. 5-A, the invalidity of the S. 17(4) portion will not necessarily vitiate the S. 4(1) portion (i.e., severability). The Court applied this line of authority to hold that the invalidity of the emergency dispensation (S.17(4)/S.5-A) did not automatically invalidate the S. 4(1) notification; the S. 4(1) notification could stand separately.

Court's Reasoning and Analysis

The Court proceeded through a sequence of factual findings and legal applications:

  1. Existence of public purpose on publication date: The Court accepted (on the petitions) that on the date of the S. 4(1) notification there was a genuine need to rehabilitate slum dwellers, which is a bona fide public purpose. The Government also believed slum dwellers would take up the offered accommodation.
  2. Treatment of subsequent facts: The Court noted that while slum dwellers initially hesitated to move, there was later a gradual change and "almost all the families in Kanniappa Nagar have moved into the scheme area now" (as stated in the Special Deputy Collector's counter-affidavit). The property acquired exceeded the needs of Kanniappa Nagar alone and the object included other slum areas; hence offering sites to other needy low and middle income persons falls within a beneficent and broadly construed public purpose.
  3. On diversion of purpose: Drawing on Galloway and Parshottam Jethalal, the Court distinguished private-body doctrines from public-body acquisitions and relied on Parshottam Jethalal for the proposition that identity of scheme mechanisms is not required so long as the public purpose remains. The Court interpreted "slum" and "slum-dweller" broadly and adopted a liberal construction of the notification to include low and middle income persons who, due to scarcity, may be living in crowded or unhealthy localities. Consequently, allotments to such persons did not constitute an impermissible diversion.
  4. On severability and the effect of striking S. 17(4): The Court accepted authorities (Ramabrahmam, Madhavi Ammal, Naga Mills) showing the S. 17(4) portion's invalidity did not necessarily vitiate the S. 4(1) notification. It rejected the appellant's contention that striking S. 17(4) alone would render S. 5-A rights illusory such that the entire notification must fall.
  5. On the timing of objections under S. 5-A: The Court observed the argument by the Special Government Pleader that objections could be entertained within thirty days of publication by the Collector and not strictly tied to the original S. 4(1) publication date, but observed that it was unnecessary to decide that point. Crucially, the Government had indicated willingness to hear objections now and to consider abandonment of acquisition for any part of the land if justified.
  6. Discretion under Article 226: Given the factual findings (ongoing public purpose, many slum dwellers having moved in) and the Government's stated willingness to hear objections and potentially abandon parts of the acquisition, the Court concluded there was no case to exercise the discretionary power under Art. 226 to quash the whole S. 4(1) notification.

Holding and Implications

Holding:

The appeal fails and is dismissed. The portion of the notification under S. 17(4) dispensing with S. 5-A had already been struck down by the earlier judgment; the remaining S. 4(1) notification is to stand.

Direct consequences and practical implications:

  • The S. 4(1) notification for acquisition remains valid and will continue to have effect.
  • The Government has undertaken to hear and dispose of relevant objections that the appellant may lodge; if the Government are persuaded by objections, they have the statutory power to abandon the acquisition as to any part of the land.
  • No order as to costs was made.

Broader precedent or legal significance: The Court applied existing precedents on severability and the construction of public-purpose acquisitions but did not indicate the setting of a new legal precedent beyond the application of those authorities to the facts. If the opinion discusses no further broader implications, the direct effect is limited to upholding the S. 4(1) notification while permitting objections to be considered by the Government.

V.C.S

    S. Srvaprakasa Mudaliar v. State Of Madras

    (Delivered by The Chief Justice.)

    On 17th September 1958, the State Government by a notification under S. 4(1) of the Land Acquisition Act proposed to acquire a large tract of land measuring about 300 acres in Kodambakkam area for the purpose of rehabilitation of the slum dwellers in Kanniappanagar and other slum areas in the City of Madras. By the same notification and indeed as part of it, the Government in exercise of their powers under S. 17(4) of the Act, dispensed with the provisions of S. 5-A of the Act as the proposed acquisition, in their opinion was an urgent one. The notification mentioned above was in due course followed by a publication under S. 6. That was on 26th November 1958. Sometime later notices were issued to the various owners under S. 9(3) calling upon them to file their claims for compensation. It appears that there were some objections to the acquisition before the Government and it took sometime for them to consider and dispose of the same. The appellant owns 2.44 acres of wet lands in S. No. 154, in the area proposed to be acquired; that was subject to a mortgage created by him in favour of one Jambulinga Mudaliar. Like other owners of land in the locality the appellant filed his claim for compensation. Compensation was fixed by the Special Deputy Collector for land acquisition, who by his notice dated 18th January 1961 intimated his award to the mortgagee that a sum of Rs. 16836 had been awarded as compensation for 2-44 acres of land in S. No. 154. Soon thereafter the appellant was called upon to deliver possession of the property. It was at that stage, i.e, nearly three years after the notification under S. 4(1) of the Act, that he and a number of other owners filed applications under Art. 226 of the Constitution to this Court to quash the notification relating to the acquisition of the land.

    The substantial ground urged in support of the applications was this: The intended purpose of the scheme had failed as the slum dwellers for whose benefit the lands were sought to be acquired refused to move into the scheme area; the State Housing Board in whom the lands stood vested proceeded however to allot building sites in the area to persons belonging to the low and middle income groups; that amounted to a diversion of the original purpose which the Government had no authority to do.

    It is necessary at this stage to digress a little into the other connected proceedings relating to this acquisition. During the time when the present applications were pending W.P Nos. 1094 of 1959 and 151 and 301 of 1960 which related to certain properties covered by the same notification, came up for disposal before Veeraswami, J., who quashed a part of the notification, namely, that which purported to be under S. 17(4), dispensing with the applicability of S. 5-A of the Act.

    The learned Judge, however, declared that the rest of the notification would be valid. Having due regard to that decision the Government intimated the Court in these cases that they are willing to withdraw that portion of the notification which applied the emergency provisions under S. 17(4) of the Act. In so doing, it cannot be said that the Government had sufficient regard for what had transpired already, namely, the publication of the various notifications, the passing of the award etc. However, that withdrawal meant that the Government had an open mind on the question whether the acquisition was for a public purpose; presumably they were willing to consider all those objections that could be filed under S. 5-A. If that were to be so, and if as a result of the representations the Government were to hold that the original acquisition was not for a public purpose what would happen to all that had been done, i.e, what would be the position of the persons who had applied for allotment of sites, in that area, obtained them and spent monies thereon are matters which do not appear to have been considered. That Is only by the way.

    To resume the narrative, it is clear from the petitions filed in the case that there was no controversy about one fact, namely, that on the date when the notification under S. 4(1) of the Act was published, there was a genuine need to rehabilitate the slum dwellers. That would undoubtedly be a public purpose. There was no doubt that the Government believed that the slum dwellers would avail themselves of the opportunity of having better houses in healthier surroundings. It has been stated in the counter affidavit filed by the Special Deputy Collector for Land Acquisition, that the intention of the Government was not to confine the allotment under the scheme to slum dwellers alone. The notification does not say anything specific about it.

    Sometime after the acquisition, the slum dwellers exhibited an initial reluctance to leave their existing homes; but subsequently there appears to have been a gradual change in their attitude, it is said, that almost all the families in Kanniappa Nagar have moved into the scheme area now. But the property sought to be acquired was more than sufficient to meet the needs of the residents of Kanniappa Nagar. The object of the scheme was also to provide better houses for persons living in other slum areas in the city. Therefore, the Government decided to offer sites in the area to persons of the low and middle income groups, who but for this concession would have to reside in crowded places and in unhealthy surroundings. Some of which could perhaps be termed as scarcely better than the so-called slums.

    It has been contended on behalf of the petitioners that as the admission of the members of the low and middle class income groups into the scheme area was not the avowed object of the acquisition, the attempt of the Housing Board to benefit persons of those groups would amount to a diversion from the original purpose and that, therefore the entire acquisition would be regarded as invalid. Veeraswami, J., did not consider it necessary to decide whether the contentions of the appellant were well founded or not. The learned Judge accepting the concession made on behalf of the Government, quashed that part of the notification which dispensed with the obligation of conforming to the provisions of S. 5-A leaving the petitioners before him with the opportunity of making their objections to the acquisition under that section to the concerned authority. Therefore the substantial question raised as to the validity of the acquisition proceedings is still undecided. Only the notification, in so far as it dispensed with the obligation under S. 5-A was struck down as invalid. The rest of the notification which came within the ambit of S. 4(1) was retained.

    The appellant feeling aggrieved by this order has filed the present appeal.

    Mr. Arunachalam appearing for the appellant has contended that the learned Judge was in error in not deciding the question as to whether in view of the changed circumstances the notification in question could at all be regarded as valid the argument being that although the original purpose might be a public one, that purpose having been found to be impossible of fulfilment by reason of the unwillingness of the slum dwellers to migrate to the scheme area, necessity for the acquisition has ceased and that the further proceedings therein should be regarded as illegal. Support for this contention was sought in the decision, R.H Galloway v. Mayer and Commonality of London(1). In that case a railway company was authorised to take compulsorily lands of any person for a particular purpose. It was held that the company could not compulsorily acquire property albeit it made duo compensation to the owner, for another object. That was a case where a private body was authorised by Parliament to acquire property for a specified purpose. It could not obviously exercise that power for any other purpose of a collateral kind. The decision itself recognises that the case will be different where for example an existing public body such as a corporation of a city is entrusted by the Legislature with the duty of making public improvements in its city. In such a case it has been held that the powers entrusted to It for such purposes will not be subject to a strict and restrictive construction.

    In the present case the object of the acquisition was to provide housing accommodation for people living in slums. That object could not be said to be diverted where instead of settling the slum dwellers alone there, some other persons who were equally in need, of better housing accommodation were provided with house sites in the scheme area. In Parshottam Jethalal v. Secretary of State(2), a certain land was acquired for a particular scheme which was later on abandoned and therefore a revised scheme was introduced. It was held that the scheme remained essentially the same. Broomfield, J., observed thus:

    “The Land Acquisition Act postulates a public purpose as to the existence of which the Government is the Judge I will assume for the sake of argument without admitting or deciding that the public purpose must remain substantially the same throughout the proceedings. That was so in the present case. The Act nowhere postulates identity in the scheme by means of which the public object is to be carried out. All that is legally necessary is that the lands which it is intended to acquire for a public purpose should be notified under S. 4 and then under S. 6, Land Acquisition Act. That has been done.”

    We are unable to accept the contention that is urged on behalf of the appellant that the grant of house sites in the scheme area to members of the low and middle income groups amounted to a diversion of the original object of the scheme. The original notification no doubt stated that the purpose of the Government in acquiring the property was to provide house sites for housing the slum dwellers in Kanniappanagar and also slum dwellers in the other parts of the city. The expression “slum dweller” though in popular parlance has acquired some special meaning, namely, those who are economically and socially backward and who huddle themselves together in dwellings in unhealthy surroundings, the term as such has no such technical meaning. The word “slum” in its true import means “a street or alloy situate in a crowded district of a town or city and inhabited by people of low class or by the poor.” It may be that in some cases the slum area may be a thickly populated one and of a squalid and wretched character, but essentially the word slum is of wide import including within it a crowded place in a city inhabited by the poor. Actually wherever there is scarcity of accommodation, one not unoften finds, that several of the persons belonging to the low and middle income groups, have of necessity to take up their abodes in very crowded parts of the locality which can be said to be no better than slums. There is nothing very wrong to regard them, as slum dwellers in a sense. The notification in question being one intended for a beneficent purpose must receive a liberal construction. It will therefore include within the object of providing accommodation for persons belonging to the low and middle income groups as well.

    There has, therefore, been no diversion of the purpose on the part of the Housing Board in allotting house sites to persons belonging to the member of those groups.

    The contention appears to be wrong even factually. In the counter affidavit filed by the Special Deputy Collector for Land Acquisition, it has been stated that almost all the residents of Kanniappanagar have come to take up their residence in the scheme locality. In view of this also, we are of the opinion that there is no substance in the contention that there has been a diversion of the original purpose on the part of the Housing Board proceeding to grant house sites to persons belonging to the lower and middle income groups in the city.

    Mr. Arunachalam next contended that the learned Judge should have struck out the entire notification instead of confining his direction to that under S. 17(4) alone for the reason that what remained will not be in accordance with the provisions of the statute. The learned Judge has held, and on that point there is no dispute on the part of the Government, that the portion of the notification dispensing with the provisions of S. 5-A was invalid. That portion is separable from the rest of the notification. There is authority to show that in a similar situation, that is, where the original notification is a single one containing within itself a notification under S. 4(1) and also an order under S. 17(4) dispensing with the provisions of S. 5-A, the invalidity of the latter part will not vitiate the validity of the former one i.e, that part of the notification which came under S. 4(1). Vide Ramabrahmam v. State of Andhra Pradesh, Madhavi Ammal v. Revenue Divisional Officer, Kozhikode and Naga Mills Tea Co. v. State of Assam(3).

    The argument before us did not proceed on any theory of inseverability. What was said was that the striking out of that part of the notification which related to the obligation under S. 5-A severable it might be left behind it, a notification under S. 4(1) which could not in any sense be said to be in accordance with the statute, and that, therefore, the former notification should also be struck down. The contention is elaborated thus: Under S. 5 A any person interested in any land which has been notified under S. 4 and Sub-S. (1) may, within thirty days after the issue of the notification, object to the acquisition of the land. The right, so to object, is a statutory one given to the individual to be exercised within thirty days of the notification. A proper notification under S. 4(1) should, therefore, enable the individual concerned to file his objections under S. 5-A within thirty days from the date of publication of such notification. In the present case by reason of the Government Order under S. 17(4) which was part of the original notification, S. 5-A was expressly dispensed with. In other words the person aggrieved had no right to state his objections in the manner provided for under that section. If three years after the notification the urgency part of it alone were to be struck down, it was argued, the person aggrieved would have no right to put forward his objections as more than thirty days had already elapsed from the date of the original notification under S. 4(1). In other words, it was contended that in order that the statutory rights given to the owner of the land under S. 5-A might be effective, it would be necessary that there should be a fresh notification under S. 4(1) after which alone the owner will have an opportunity within thirty days thereof to file his objections. If on the contrary, the part of the notification under S. 4(1) was retained, the benefit conferred under S. 5-A could become illusory.

    The learned Special Government Pleader did not accept this contention; he argued that the filing of the objections under S. 5-A could be made within thirty days after the substance of the notification has been published by the Collector and it need not necessarily be within thirty days of the actual publication of the notification under S. 4(1). The former could be done even now. In the view we are taking of the case, it Is unnecessary to consider this contention. It must be observed that this objection to partial striking out of the notification was not raised before the learned Judge. Indeed no objection to the acquisition or even as to the invalidity of chat part of the notification regarding the applicability of S. 17(4) was taken by the appellant all these years. It is practically conceded that the original purpose for which the land was acquired is a public one.

    Generally speaking, the kinds of objections that would be available to an owner of the land whose land is proposed to be acquired under S. 5-A will be those mentioned in Board's Standing Order 90, R. 9, namely:

    1. that the purpose for which the land is acquired is not a bona fide public purpose; (2) that the particular land notified is not the best adopted to the purpose intended or that its area is greater than what is actually required for the purpose; and (3) that the acquisition of the land or any land in the locality is not desirable or expedient.

    So far as the the first of the three categories of objections is concerned, there is no denial that the purpose of the acquisition was a bona fide public one. The other two objections available to the owner of the land can be heard at any stage. The Government have now intimated their willingness to hear the objections of the appellant on those matters. As pointed out by the learned Judge, we have no reason to think that any representation in that behalf by the appellant will not be fairly and reasonably considered by the authorities concerned. The Government have always the power to abandon an acquisition in relation to any part of the land. If the Government are satisfied with the reasons advanced, against the acquisition even at this stage, they have the power to and can abandon the acquisition. There can, therefore, be no substantial grievance on the part of the appellant that an opportunity was not given to him under S. 5-A for filing his objections within thirty days of the original notification. Apart from that consideration, it may also be noticed that if the Court were to hold that the notification under S. 4(1) should be reissued with an opportunity to the appellant to file his objections, it would create further complications in regard to the validity of the title acquired by the various persons who had already obtained house sites under the scheme and who had perhaps built houses thereon. Having regard to the circumstances of the case, we consider that there is no case for exercising the discretionary power of this Court under Art. 226 of the Constitution to quash the entirety of the notification. The notification under S. 4(1) of the Act will, therefore, stand. The Government will, however, hear and dispose of all relevant objections which might be put forward by the appellant within any time to be specified by them. The appeal fails and is dismissed. There will be no order as to costs.