AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • section 4(1) of the Land Acquisition Act, 1894 (for short the Act)
  • Section 23(1-A) of the Amended Act 68 of 1984.
  • ARTICLE 226 CONSTITUTION OF INDIA
  • 25):1. Section 50(2) of the L.A Act
  • Order 1, Rule 10, CPC,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • section 4(1) of the Land Acquisition Act, 1894 (for short the Act)
  • Section 23(1-A) of the Amended Act 68 of 1984.
  • ARTICLE 226 CONSTITUTION OF INDIA
  • 25):1. Section 50(2) of the L.A Act
  • Order 1, Rule 10, CPC,
Smart Summary

Structured Summary of the Opinion

Factual and Procedural Background

The Andhra Pradesh State Road Transport Corporation ("the Corporation") filed applications seeking leave to file a review petition, condonation of a delay of 5,509 days in filing the review petition, and to review this Court's judgment dated 24-2-1989 in A.S. No. 1582 of 1982 (single judge). The applications are disposed of together in this order.

Relevant facts (as stated in the opinion):

  • In June 1974 the Corporation placed a requisition to acquire approximately 37.17 acres for a bus station; section 4(1) notification was published on 2-1-1975.
  • Possession was taken on 11-3-1977. Award No.1 of 1979 (dated 25-1-1979) fixed market value for Ac. 2.03 cents at Rs.30,000 per acre. The 2nd respondent-claimant owned Ac.1.74 cents of that land.
  • The claimant sought a reference under Section 18; O.P. No. 140 of 1979 resulted in an award/decree dated 4-2-1982 assessing the market value at Rs.50,000 per acre (enhanced compensation).
  • The Revenue Divisional Officer/Land Acquisition Officer (at the instance of the State/Corporation) filed A.S. No. 1643 of 1982 challenging the award; amounts were deposited in Court on 11-10-1984.
  • This Court dismissed A.S. No. 1643 of 1982 by judgment dated 23-2-1989, upholding the reference Court and commenting on entitlement to additional benefits under the Amended Act and interest provisions subject to Supreme Court decision.
  • The claimant's appeal A.S. No. 1582 of 1982 was heard and allowed in part on 24-2-1989, enhancing compensation to Rs.95,000 per acre and holding the claimant entitled to additional benefits under the Amended Act.
  • The claimant filed execution proceedings for Rs.5,11,906/-. The Revenue Divisional Officer objected that the decree-holder was not entitled to benefits under Section 23(1-A); the Executing Court overruled objections by order dated 13-6-2002. That order became final.
  • The Corporation alleges error in the 24-2-1989 judgment and sought review, contending among other things that the claimant should not have been awarded benefits under the Amended Act and that the claimant suppressed relevant facts; review applications were filed after a long delay.

Legal Issues Presented

  1. Whether leave should be granted to the petitioner-Corporation to file a review petition against this Court's judgment dated 24-2-1989 in A.S. No. 1582 of 1982 after a delay of 5,509 days (i.e., whether the delay should be condoned).
  2. Whether the petitioner-Corporation is entitled, after more than 15 years, to have this Court review and reopen a finally concluded judgment (i.e., whether it may "intrude and wake up" the issue of correctness of the 1989 judgment).
  3. Whether the claimant was incorrectly held entitled to additional benefits (solatium, enhanced interest, etc.) under the Amended Act and whether the decree granting such additional benefits is a nullity and can be challenged at this stage.

Arguments of the Parties

Petitioner-Corporation's Arguments

  • The Corporation contended this Court erred in enhancing compensation from Rs.50,000 to Rs.95,000 per acre on 24-2-1989 and that, because the appeal by the Land Acquisition Officer had been dismissed, the claimant's appeal should likewise have been dismissed.
  • The Corporation alleged the claimant played fraud by not informing the Court of the dismissal of the appeal preferred by the Land Acquisition Officer, and that if this had been known the claimant's appeal might have been dismissed.
  • The Corporation argued that the award of interest (9% per annum for one year and 15% per annum thereafter) is erroneous because enhanced interest provisions under the Amended Act apply only from the date the Amended Act came into force (not earlier than 30-4-1982), while the acquisition and earlier steps predated that; thus the rate of interest should be modified.
  • Counsel for the petitioner relied on Neyvely Lignite Corpn. Ltd. v. Spl. Tahsildar, AIR 1995 SC 1004, submitting that a beneficiary is a person interested and entitled to participate in enquiry and, if not impleaded, is entitled to come on record and challenge awards even at a later stage.

State / Revenue Divisional Officer / Respondent-side Position (as reflected in the opinion)

  • The Revenue Divisional Officer (RDO) had previously filed a counter in execution proceedings contending that the decree-holder (claimant) was not entitled to the benefits under Section 23(1-A) of the Act; those objections were overruled by the Executing Court on 13-6-2002 and that order became final.
  • The Executing Court rejected the plea that the decree was a nullity; the Revenue Divisional Officer's subsequent Civil Revision Petition (C.R.P. No. 2171 of 2003) was dismissed by this Court on 12-9-2003. The opinion treats these outcomes as indicating that the plea has already been unsuccessfully raised and cannot be revived via the present review application.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
K.S. Paripoornan v. State of Kerala, AIR 1995 SC 1012 Principle that benefits under the Amended Act (such as additional amounts/solatium) are available only in certain cases—text refers to the Supreme Court's holding limiting availability where the award was passed much earlier than the Amended Act coming into force. The Court observed that, according to the averments, the original award was passed before the Amended Act and that Paripoornan suggested claimants may not be entitled to benefits. The opinion treats this authority as supporting the view that claimants may not be entitled to additional benefits where awards predate the Amended Act.
Neyvely Lignite Corpn. Ltd. v. Spl. Tahsildar, AIR 1995 SC 1004 Held that a beneficiary (local authority/company/statutory authority) is a "person interested" under procedural rules and has rights to be heard, be impleaded, adduce evidence, and in certain circumstances to seek leave to appeal if prejudiced. The petitioner relied on this case to argue it (as beneficiary) could be impleaded or could seek leave to challenge enhanced awards even if not originally a party. The Court considered the decision but concluded it did not support the petitioner's position because the petitioner had not availed the remedies envisaged and was aware of appeals and deposits made earlier.
U.P. Awas Evam Vikas Parishad v. Gyan Devi, AIR 1995 SC 724 The Constitution Bench articulated multiple principles (set out in para 25 of that decision), including: right of a local authority to appear and adduce evidence; right to adequate notice; remedy under Article 226; entitlement to be impleaded; right to appeal with leave if prejudicially affected; and that matters finally concluded will not be reopened. The Court relied on the principles listed from this decision to analyze whether the petitioner fell within the situations where it could seek relief after finality. The Court concluded that the petitioner's facts did not fall within the situations contemplated by the decision and therefore that decision did not assist the petitioner.

Court's Reasoning and Analysis

The Court proceeded step-by-step and grounded its analysis in the facts and precedent expressly relied upon in the opinion:

  1. Timeline and knowledge: The Court emphasised the procedural history (notification 1975, award 1979, reference award 4-2-1982, appeals in 1982, judgments in February 1989, deposit of decretal amount on 11-10-1984, execution objections overruled on 13-6-2002). The Court observed that the petitioner did not participate in the reference or earlier appeals and that the petitioner was aware of the State's appeal (A.S. No. 1643 of 1982) and that the petitioner's instance had led to that appeal being filed.
  2. Failure to use available remedies: The Court analysed the remedies available to a beneficiary/local authority (as explained in the cited precedents) — impleadment in reference proceedings, appearing before the Collector or reference Court, invoking Article 226, filing an appeal with leave against an enhanced award, or being impleaded in appeals filed by others — and found that the petitioner did not avail itself of such remedies despite opportunities to do so.
  3. Application of precedents: The Court examined the petitioner's reliance on Neyvely and U.P. Awas Evam Vikas Parishad. It recited the principles that beneficiaries are persons interested and may be entitled to be heard and to seek leave to appeal. However, the Court concluded that those authorities did not assist the petitioner because the petitioner's factual situation differed: it had not been impleaded but had also not sought impleadment or to be made a party, had been aware of the appeals, and had in fact caused an appeal to be filed on behalf of the State and deposited amounts — indicating knowledge and inaction rather than denial of opportunity.
  4. Delay and laches: The Court emphasised that the petitioner sought to reopen a matter that had been finally concluded for about 15½ years. It described the applications as frivolous and speculative, and found it difficult to accept the petitioner's stated ignorance of the prior judgments and execution outcomes, given the petitioner's actions and the timeline (including communications dated 18-7-2002 and deposit of amounts for certified copies on 5-9-2002).
  5. Allegation of fraud: The Court addressed the allegation that the claimant suppressed the dismissal of the State's appeal. The Court found no element of fraud: the appeals were decided by the same Judge on successive days (23-2-1989 and 24-2-1989) in separate judgments; no party asked that the appeals be disposed of together; and the mere sequencing or separate pronouncement did not amount to fraud warranting reopening.
  6. Res judicata / finality and prior proceedings: The Court observed that the same point (that the decree was a nullity or that additional benefits were not payable) had already been raised and rejected in the execution proceedings and in a civil revision petition (C.R.P. No. 2171 of 2003). The Court considered that the execution court and this Court in revisional proceedings had rejected the objection and that the plea could not be revived via the present review application.
  7. Conclusion from analysis: Given the petitioner's inaction over a prolonged period, its awareness of the appeals and deposit of amounts, the distinct precedents which did not, on the facts, entitle the petitioner to reopen the matter now, and the existence of prior rejections of similar pleas, the Court concluded that condonation of delay and leave to file the review petition should be refused.

Holding and Implications

Holding:

THE APPLICATIONS TO CONDONE DELAY AND TO GRANT LEAVE TO FILE THE REVIEW PETITION ARE DISMISSED. Consequently, the review petition itself is dismissed with costs.

Implications:

  • Direct effect on the parties: The petitioner-Corporation's applications seeking condonation of a 5,509-day delay and leave to file a review petition were refused; the review petition was dismissed and ordered to pay the respondent's costs as reflected in the memorandum of costs. The Executing Court's earlier order (13-6-2002) and the subsequent dismissal of the civil revision petition (12-9-2003) remain undisturbed by these proceedings.
  • The Court found no basis to reopen a matter finally concluded in 1989 and treated the petitioner's delay and long inaction as fatal to its application; the decision enforces finality and laches principles in the context of post-acquisition proceedings where remedies were available but not pursued.
  • The opinion does not announce or purport to lay down a new precedent; rather it applies existing Supreme Court authorities and treats prior adjudications and execution proceedings as determinative in the particular facts of this case.

Disposition / Costs

The applications to condone delay and to grant leave to file the review petition were dismissed. The review petition was dismissed with costs.

A brief memorandum of costs is recorded in the opinion (as reproduced in the source):

  • Stamp for Vakalatnama: Rs.5.00
  • Advocate's fees: Not filed / shown as 0.00
  • To be paid by the Petitioner to the Respondent: Rs.5.00

Final line in the source: "Petition dismissed."

    A.P.S.R.T.C, Hyderabad v. Revenue Divisional Officer, L.A.O Kurnool And Another

    B. Sudershan Reddy, J.:— The Andhra Pradesh State Road Transport Corporation (hereinafter referred to as ‘the Corporation’) filed these applications seeking leave of this Court to file a review petition, to condone the delay of 5509 days in filing the review petition and to review the judgment dated 24-2-1989 passed in A.S No. 1582 of 1982 by a learned single Judge of this Court. All these applications are being disposed of by a common order.

    2. That in order to consider as to whether the petitioner-Corporation has made out any case requiring the interference of this Court to review the judgment rendered by this Court after a period of 15 long years, a few relevant facts may have to be noticed.

    3. The petitioner-Corporation some time in June, 1974 placed a requisition with the Revenue Divisional Officer, Kurnool to acquire an extent of Acs. 37.17 cents of land covered by Sy. Nos. 412, 413, 415, 416, 417, 418 and 430 etc., situated at Kallur Village of Kurnool Town for construction of a bus station. The requisition was processed resulting in publication of the notification under section 4(1) of the Land Acquisition Act, 1894 (for short ‘the Act’) in the Official Gazette on 2-1-1975. The possession of the lands was taken as early as on 11-3-1977. The Land Acquisition Officer passed Award No. 1 of 1979 dated 25-1-1979 in respect of Ac. 2.03 cents of land covered by Sy. Nos. 415/2B and 417.A & B etc. fixing the market value at Rs. 30,000/- per acre with attendant benefits as per the Act. The 2nd respondent-claimant is the owner of Ac. 1.74 cents out of the said land admeasuring Ac. 2.03 cents in respect of which the award has been passed by the Land Acquisition Officer.

    4. The respondent-claimant sought for a reference under Section 18 of the Act and it was numbered as O.P No. 140 of 1979 on the file of the II Additional Subordinate Judge, Kurnool. The learned Subordinate Judge vide the award and decree dated 4-2-1982 assessed the market value of the acquired land at Rs. 50,000/- per acre and accordingly granted enhanced compensation.

    5. The Revenue Division Officer/Land Acquisition Officer, Kurnool preferred A.S No. 1643 of 1982 challenging the correctness of the award and decree made in O.P No. 140 of 1979. The amounts were deposited on 11-10-1984 in the Court.

    6. This Court by its judgment dated 23-2-1989 dismissed the appeal in A.S No. 1643 of 1982 upholding the decision of the reference Court. The Court while dismissing the appeal preferred by the Land Acquisition Officer, however, observed that in addition to the market value of the land, the claimant shall be entitled to additional amount calculated at 12% per annum from the date of publication of the notification under Section 4(1) of the Act till the date of award of the Collector, or the date of taking possession of the land whichever is earlier as provided for under Section 23(1-A) of the Amended Act 68 of 1984. This Court also took the view that in addition to the market value of the land, the claimant shall be entitled to solatium of 30% off such market value under Section 23(2) of the Act. That if the compensation is not deposited on or before taking possession of the land, the claimant shall be entitled to interest on such amount at the rate of 9% per annum from the date of taking possession only and if such a compensation or any part thereof is not paid or deposited within a period of one year from the date of taking possession, interest at the rate of 15% per annum shall be paid from the date of expiry of the said period of one year on the amount of compensation or part thereof which has not been paid or deposited as provided under Section 34 of the Act. However, so far as such payment of additional amount, solatium and interest is concerned, the Court observed that the same shall be subject to the decision of the Supreme Court.

    7. The appeal in A.S No. 1582 of 1982 filed by the claimant has come up for hearing before the same learned Judge on 24-2-1989 after the dismissal of the appeal filed by the State against the very same order and decree of the reference Court in O.P No. 140 of 1979. The appeal filed by the claimant was allowed in part enhancing the compensation from that of Rs. 50,000/- per acre to Rs. 95,000/- per acre. It was further held that the claimant shall be entitled to all additional benefits as per the Amended Act.

    8. The claimant pursuant to the judgment and decree in A.S No. 1582 of 1982 dated 24-2-1989 filed an execution petition for realization of the decretal amount of Rs. 5,11,906/- for which the Revenue Divisional Officer filed a counter inter alia contending that the decree holder was not entitled to the benefit under Section 23(1-A) of the Act. The objections were overruled by the Executing Court by order dated 13-6-2002 directing the Land Acquisition Officer to deposit the amount. That order passed by the Civil Court on 13-6-2002 has become final.

    9. In the review petition filed along with the application seeking leave of this Court, the case of the Corporation is that this Court committed an error in enhancing the compensation from that of Rs. 50,000/- per acre to Rs. 95,000/- per acre. This Court having dismissed the appeal filed by the Land Acquisition Officer ought to have dismissed the appeal filed by the claimant also. The claimant played fraud by not bringing the factum of dismissal of the appeal preferred by the Land Acquisition Officer and had that fact been brought to the notice of the Court, the appeal preferred by the claimant also in all probability would have ended in dismissal. It is also the case of the Corporation that the Court committed an error in awarding interest at 9% per annum for one year and 15% per annum thereafter till the realization of the decretal amount since the enhanced rate of interest is payable from the date of amended act coming into force and not earlier to 30-4-1982. In the instant case, draft declaration was published on 27-11-1975 and an award has come to be passed on 25-1-1979 and the reference Court enhanced the compensation by order and decree dated 4-2-1982 and accordingly the rate of interest is liable to be modified. The sum and substance of the case of the Corporation is that the claimant is not entitled to additional benefits as held by the Supreme Court in K.S Paripoornan v. State of Kerala, AIR 1995 SC 1012. The benefits under the provisions of the Amended Act are available only to the cases pending before the reference Court in respect of acquisition initiated prior to 1982.

    10. The question that falls for consideration is whether leave is to be granted to the petitioner-Corporation by condoning the delay of 5509 days in filing the review petition and whether the petitioner is entitled to intrude and wakeup the issue of correctness of the judgment of this Court rendered in A.S No. 1582 of 1982 dated 24-2-1989 after a long lapse of more than 15 years.

    11. That admittedly, the petitioner did not raise its little finger when the proceedings were pending in the reference Court as well as in this Court. It did not participate in the proceedings. But the case of the Corporation is that it came to know about the proceedings resulting in dismissal of the objections raised by the Revenue Divisional Officer, by the Executing Court on 13-6-2002 only on 18-7-2002 when the Revenue Divisional Officer, Kurnool requested the Corporation to deposit certain amounts towards the expenditure for obtaining the certified copies and to file review petitions in this Court in four matters including this matter. The amounts were accordingly paid to him by the Executive Engineer on 5-9-2002. No steps were taken by the Land Acquisition Officer to challenge the orders passed by the Executing Court dated 13-6-2002. No steps were taken to file review petitions. It is under those circumstances, the Corporation filed these applications.

    12. In our considered opinion, these applications filed by the petitioner-Corporation are not only frivolous but speculative in their nature. Even according to the averments made in the affidavit filed in support of the applications, the entire decretal amount as per the decree in O.P No. 140 of 1979 was already deposited on 11-10-1984 and only the amount to be deposited is towards the additional benefit as per the Amendment Act for which the claimants are not entitled to, in view of the fact that the award passed by the Land Acquisition Officer was much earlier to the Amendment Act coming into force as held by the Supreme Court in Paripoornan's case (AIR 1995 SC 1012) (supra). It is difficult to believe that the petitioner had no knowledge about the dismissal of the appeal filed by the Land Acquisition Officer in A.S No. 1643 of 1982 as well as the order in the appeal preferred by the claimant in A.S No. 1582 of 1982 on 24-2-1989. Even according to the averments made in the affidavit filed by the petitioner, it is stated that on 18-7-2002 itself, the Revenue Divisional Officer addressed a letter to the Corporation duly informing them about the order passed by the reference Court. It is even averred that the Land Acquisition Officer insisted to deposit the amount ordered by the Court in the execution petition as early as on 18-7-2002. In our considered opinion, no relief could be granted to the petitioner to come on record at this stage to review the judgment rendered by this Court as early as on 24-2-1989 i.e to say after about 15½ years.

    13. Learned counsel for the petitioner-Corporation relying upon the judgment of the Supreme Court in Neyvely Lignite Corpn. Ltd. v. Spl. Tahsildar, Land Acquisition, Neyvely, AIR 1995 SC 1004 submitted that the petitioner-Corporation being the beneficiary is a person interested and entitled to participate in the enquiry to ensure that only just and proper compensation for the acquired land is paid. It is entitled to canvass the correctness of the award passed by the Land Acquisition Officer as well as the reference Court. The reference Court ought to have impleaded it as a party. Since it was not impleaded as a party, it is entitled to come on record and challenge the decree and judgment of this Court even at this stage.

    14. In Neyvely Lignite Corporation's case (AIR 1995 SC 1004) (supra), notification under Section 4(1) of the Act was published in the year 1975 acquiring a large extent of 5200 acres of land for the purpose of excavating inferior quality of the coal in South Arcot District in the State of Tamil Nadu. The awards were passed in the year 1977-1980 under Section 11 of the Act. Dissatisfied therewith, the claimants sought and secured over 2000 references under Section 18 to the Civil Court. In some of the references, the Civil Court made awards and decrees. In the pending references, Neyvely Lignite Corporation Limited sought to be impleaded as a party respondent to adduce the evidence in fixing a proper compensation. The Civil Court dismissed the applications. The High Court in the revisions by judgment dated 16-2-1987 upheld the order of the Civil Court. In the appeals filed by the State under Section 54 of the Act, the Corporation sought to be impleaded as a party respondent which were turned down holding that the Corporation is not a person interested. The Supreme Court after referring to its earlier decisions held that the beneficiary i.e to say local authority or company or statutory authority “is a person interested to determine just and proper compensation for the acquired land and is an aggrieved person. It flows from it that the beneficiary has the right to be heard by the Collector or the Court. If the compensation is enhanced it is entitled to canvass its correctness by filing an appeal or defend the award of the Collector. If it is not made a party, it is entitled to seek leave of the Court and file the appeal against the enhanced award and decree of the Civil Court under Section 26 or of the judgment and decree under Section 54 or is entitled to file writ petition under Art. 226 and assail its legality or correctness. When the award made under Section 11 of the Collector is vitiated by fraud, collusion or corruption, the beneficiary is entitled to challenge it in the writ petition apart from the settled law that the conduct of the Collector or Civil Judge is amenable to disciplinary enquiry and appropriate action. These are very valuable and salutary rights. Moreover in the language of Order 1, Rule 10, CPC, in the absence of the beneficiary who ultimately is to bear the higher compensation, no complete and effectual determination of binding just and proper compensation to the acquired land would be made. So it is concomitantly a proper party if not a necessary party to the proceedings Under Order 1, Rule 10, CPC. The denial of the right to a person interested is in negation of fair and just procedure offending Art. 14 of the Constitution.”

    (Emphasis is ours)

    15. In U.P Awas Evam Vikas Parishad v. Gyan Devi, AIR 1995 SC 724, a Constitution Bench of the Apex Court having elaborately considered the issue as to the entitlement of local authority or company for whom land is being acquired and its right to appear in the acquisition proceedings before the Collector and the reference Court and adduce evidence, laid down the following principles (para 25):

    1. Section 50(2) of the L.A Act confers on a local authority for whom land is being acquired a right to appear in the acquisition proceedings before the Collector and the reference Court and adduce evidence for the purpose of determining the amount of compensation.

    2. The said right carries with it the right to be given adequate notice by the Collector as well as the reference Court before whom acquisition proceedings are pending on the date on which the matter of determination of compensation will be taken up.

    3. The proviso to Section 50(2) only precludes a local authority from seeking a reference but it does not deprive the local authority which feels aggrieved by the determination of the amount of compensation by the Collector or by the reference Court to invoke the remedy under Article 226 of the Constitution as well as the remedies available under the L.A Act.

    4. In the event of denial of the right conferred by Section 50(2) on account of failure of the Collector to serve notice of the acquisition proceedings the local authority can invoke the jurisdiction of the High Court under Article 226 of the Constitution.

    5. Even when notice has been served on the local authority the remedy under Article 226 of the Constitution would be available to the local authority on grounds on which judicial review is permissible under Article 226.

    6. The local authority is a proper party in the proceedings before the reference Court and is entitled to be impleaded as a party in those proceedings wherein it can defend the determination of the amount of compensation by the Collector and oppose enhancement of the said amount and also adduce evidence in that regard.

    7. In the event of enhancement of the amount of compensation by the reference Court if the Government does not file an appeal the local authority can file an appeal against the award in the High Court after obtaining leave of the Court.

    8. In an appeal by the person having an interest in land seeking enhancement of the amount of compensation awarded by the reference Court the local authority should be impleaded as a party and is entitled to be served notice of the said appeal. This would apply to an appeal in the High Court as well as in this Court.

    9. Since a company for whom land is being acquired has the same right as a local authority under Section 50(2), whatever has been said with regard to a local authority would apply to a company too.

    10. The matters which stand finally concluded will, however, not be reopened.

    16. In the case on hand, we are required to notice that admittedly the petitioner herein was not impleaded as a party respondent in the reference by the reference Court. No notice as such has been issued by the reference Court to the petitioner nor the petitioner filed any application seeking its impleadment as a party respondent so as to enable it to adduce any evidence in the matter.

    17. The question that falls for consideration is whether the matter, which stood, finally concluded is required to be reopened at the instance of the petitioner at this stage?

    18. That as held by the apex Court in U.P Awas Evam's case (AIR 1995 SC 724) (supra), the local authority for whose benefit the land is acquired has a right to appear and adduce its evidence and that right is independent of the right that is available to the local authority to appear and adduce evidence before the Collector. The local authority has a right to be impleaded as a party in the proceedings before the reference Court. The local authority is necessary for the decision of the question involved in the proceedings before the reference Court and it is a proper party in the proceedings. That at any rate, in the instant case, no application has been filed by the petitioner to implead itself in the reference.

    19. The Supreme Court while adverting to the question whether the local authority for whose benefit the lands have been acquired is entitled to file an appeal with the leave of the Court challenging the correctness of the Award passed by the reference Court observed: (AIR 1995 SC 724, Para 23)

    “In case the amount of compensation has been enhanced by the Court and no appeal is filed by the Government the local authority if adversely affected by such enhancement may file an appeal with the leave of the Court. This right of the local authority does not depend on its being impleaded as a party in the proceedings before the reference Court. Even if the local authority is not impleaded as a party before the reference Court it can file an appeal against the award of the reference Court in the High Court after obtaining leave if it is prejudicially affected by the award. In case the Government files an appeal against the enhancement, of the award the local authority is entitled to support the said appeal and get itself impleaded as a party”.

    20. In the instant case, admittedly the appeal in A.S No. 1643 of 1982 was preferred by the Land Acquisition Officer at the instance of the petitioner-Corporation. That even, before stay orders were granted the total amount in full satisfaction of the decree dated 4-2-1982 was deposited by the Corporation on 11-10-1984. That makes it clear that Corporation was not only aware of filing the appeal by the State but the appeal itself was filed at the instance of the Corporation. The Corporation made no effort to support the appeal preferred by the State and got itself impleaded as a party. No doubt, in the appeal preferred by the claimant seeking further enhancement of the amount of compensation, the Corporation was not impleaded as a party. But the Corporation also did not make any effort to come on record.

    21. In our considered opinion, the judgment rendered by the Supreme Court in U.P Awas Evam's case (AIR 1995 SC 724) (supra) in no manner supports the case of the petitioner. The petitioner's case does not fall under any of the situations envisaged and the principles laid down in the said decision.

    22. The legal remedies that are available to a local authority for whose benefit the lands have been acquired, if it feels aggrieved by the determination of the amount of compensation by the Collector or the reference Court are (a) to challenge the determination of the amount of compensation by the Collector by invoking the remedy under Article 226 of the Constitution of India. But in cases where the local authority has failed to appear in spite of service of notice, local authority can have no cause or grievance. It is a different matter altogether if the award is assailed on the grounds of mala fides or perversity and (b) by preferring appeal with the leave of the Court against the award of the reference Court. It can even get impleaded as a party in the appeal preferred by the State at its instance. It can come on record in the appeal filed in the High Court against the award of the reference Court by the person having an interest in the matter.

    23. The case of the petitioner in the instant case does not fall in any one of those categories. Being fully aware of the appeal preferred by the State, the petitioner did not come on record. Obviously, it is also aware of the appeal preferred by the claimant and yet had not chosen to come on record. It could have impleaded itself as a party respondent. Non-impleadment of the local authority in the appeal preferred by the person having interest in the land does not render the judgment and decree of this Court void. The local authority should be impleaded as a party in the appeal preferred by the claimant and it is entitled to be served the notice in the said appeal so that it can defend the award of the reference Court and oppose the enhancement of compensation before the High Court. Non-impleadment of the local authority in the appeal preferred by the claimant per se does not render the appeal proceedings void. The only requirement is that this Court should allow when an application is filed by the local authority to come on record so that it can oppose any further enhancement of the compensation.

    24. The petitioner having not availed any such legal remedies that were available to it in law and having slept over the matter ever since the land was acquired for its benefit in the year 1974, had chosen to file the present applications seeking reopening of a finally concluded matter, which in our considered opinion is not only misconceived but untenable and unsustainable in law. It woke up from its deep slumber after a period of 15 years when the matter stood finally concluded vide the judgment of this Court in A.S No. 1582 of 1982 dated 24-2-1989.

    25. However, it was contended that the respondent claimant while advancing arguments in A.S No. 1582 of 1982 filed by him suppressed the factum of dismissal of A.S No. 1643 of 1982 on 23-2-1989 and therefore, the judgment in A.S No. 1582 of 1982 dated 24-2-1989 is vitiated by fraud. There is no element of fraud involved as such. The appeals were disposed of by the same learned Judge of this Court vide two separate judgments rendered on 23-2-1989 and 24-2-1989 respectively. That even if both the appeals were heard together, this Court could have as well dismissed the appeal preferred by the State and allowed the appeal filed by the claimant. It is true that it would have been desirable and proper that the appeals were disposed of together. But the fact remains that none of the parties requested the Court to dispose of both the appeals together. On that count, it cannot be said that the judgment is vitiated by any fraud. It is easy to level allegations of fraud but difficult to establish and sustain the plea.

    26. However, the learned counsel contended that the decree of this Court as regards additional benefits as per the provisions of the Amended Act is nullity and can be raised at any stage even in the execution proceedings. It is brought on record that the Land Acquisition Officer resisted the execution petition raising more or less similar objections. However, the Executing Court rejected the objections and allowed the execution petition by its order dated 13-6-2002. That as against the said order which is common in its nature, the Revenue Divisional Officer filed C.R.P No. 2171 of 2003 in this Court and the same was dismissed by this Court vide order dated 12-9-2003. We cannot go into the correctness of the Order passed in the civil revision petition by this Court. The plea that the decree is a nullity had already been raised in the Executing Court unsuccessfully and the same plea cannot be permitted to be raised once again in these proceedings.

    27. For the aforesaid reasons, we are not inclined to condone the delay of 5509 days in filing the review petition and grant any leave to file the review petition. In the result, the application to condone the delay as well as to grant leave to file the review petition shall stand dismissed. Consequently, the review petition also shall stand dismissed with costs.

    Memorandum of costs Respondent's Costs Rs. Ps. Stamp for Vakalatnama 5 00 Advocate's fees. Not filed 0 00 To be paid by the Petitioner to the Respondent 5 00