  • Sec. 175(3) of the Government of India Act, 1935,
  • Sec. 74 of the Indian Contract Act entitles
  • Article 115 of the old Limitation Act
  • Art. 115 of the old Limitation Act.23.
  • Art. 145 or 120 of the Limitation Act.
  • Sec. 70 of the Indian Contract Act,
  • Art. 56 of the old Limitation Act,
  • Sec. 70 of the Contract Act
  • Sec. 74 of the Contract Act,
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Judges
Acts
  • Sec. 175(3) of the Government of India Act, 1935,
  • Sec. 74 of the Indian Contract Act entitles
  • Article 115 of the old Limitation Act
  • Art. 115 of the old Limitation Act.23.
  • Art. 145 or 120 of the Limitation Act.
  • Sec. 70 of the Indian Contract Act,
  • Art. 56 of the old Limitation Act,
  • Sec. 70 of the Contract Act
  • Sec. 74 of the Contract Act,
Smart Summary

Factual and Procedural Background

The plaintiff-respondent submitted a tender in response to a notice issued by the Executive Engineer, Ganges Canal, Meerut Division, for constructing a Tail Fall V.R.B at Mile 7-0-330 of Jani Escape. The tender was accepted and a formal contract was executed on November 4, 1957. The plaintiff commenced work but was forced to stop due to alleged harassment by the defendant's officers. After a brief resumption, the plaintiff finally stopped work on March 21, 1958, without completing the contract. The defendant completed the remaining work through another agency.

The plaintiff filed suit claiming Rs. 34,780.71 for various items detailed in Schedules A to H appended to the plaint. The trial court decreed the suit partly for Rs. 14,283, covering claims under Schedules B and F, but dismissed claims under other schedules. The defendant (State of U.P) appealed only against the decree relating to Schedule B, while the plaintiff filed a cross-objection concerning Schedules D, F, G, and H.

Legal Issues Presented

  1. Whether the plaintiff was entitled to payment for extra work under Schedule B, specifically for reinforced concrete work (R.C.C) done instead of cement concrete as per the original contract.
  2. Whether the plaintiff was entitled to recover amounts claimed under Schedules D, F, G, and H.
  3. Whether the defendant was justified in deducting Rs. 6,650/- as penalty for delayed performance under Clause 2-B of the contract.
  4. Whether the suit was barred by limitation under the relevant Articles of the old Limitation Act.
  5. Whether the claim for refund of the forfeited security deposit was within the limitation period.

Arguments of the Parties

Appellant's Arguments

  • The defendant contended that the plaintiff did not perform the extra work as R.C.C but only cement concrete, and thus was not entitled to the higher payment claimed under Schedule B.
  • The defendant argued that the plaintiff had not obtained prior permission as required under Clauses 41 and 44 of the Special Conditions of the contract for executing the extra work.
  • The defendant justified the deduction of Rs. 6,650/- from the plaintiff’s bill as a penalty for failure to complete the work within the stipulated time under Clause 2-B of the contract.
  • The defendant contended that the suit was barred by limitation, relying on Article 56 of the old Limitation Act.

Respondent's Arguments

  • The plaintiff asserted that the extra work under Schedule B was done under oral instructions from the Engineer Incharge, supported by a second drawing (Ex. 2) showing alterations requiring R.C.C instead of cement concrete.
  • The plaintiff argued that the use of steel bars embedded in the concrete qualified the work as reinforced concrete (R.C.C), entitling him to the claimed payment.
  • The plaintiff denied the requirement for written permission for the extra work, relying on oral instructions and the contract provision that work may be directed by the Engineer Incharge.
  • The plaintiff contended that the penalty deduction was unjustified as the defendant did not suffer any damage and had already recovered the cost of completing the unfinished work through a debiting agency.
  • The plaintiff submitted that the suit was within limitation under Articles 115 and 120 of the old Limitation Act, and that the claim for refund of the security deposit was also timely.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
State of West Bengal v. B.K Mondal, A.I.R 1962 S.C 779 Application of Section 70 of the Indian Contract Act to government contracts for payment of benefits received despite absence of formal contract. The Court applied this precedent to hold that the defendant government was liable to pay for extra R.C.C work done under oral instructions, preventing unjust enrichment.
Maula Bux v. Union of India, 1969 2 SCC 554 Limits on forfeiture of security deposits under Section 74 of the Indian Contract Act; forfeiture must be reasonable compensation and not penalty. The Court relied on this precedent to hold that the defendant was not entitled to forfeit the entire security deposit as no damage was suffered, and forfeiture would amount to penalty.
Union of India v. Rampur Distillery and Chemicals Limited, 1973 1 SCC 649 Security deposits taken to ensure due performance cannot be forfeited entirely where no loss is caused by default. The Court followed this precedent to confirm that the plaintiff was entitled to refund of the security deposit deducted by the defendant.
State of U.P v. Suraj Prasad Gupta, F.A No. 351 of 1968 (decided on 3-2-1976) Application of Article 115 of the old Limitation Act to claims for compensation for breach of contract. The Court applied this precedent to hold that the suit was within limitation period under Article 115.
Zila Parishad, Ambala v. Banarsi Dass Kapur, A.I.R 1973 Pun. and Har. 276 Limitation period applicable to suits for return of security deposits is governed by Articles 145 or 120 of the Limitation Act. The Court relied on this precedent to conclude that the plaintiff's claim for refund of security deposit fell under Article 120 and was within time.
Datt Singh v. Srihar Singh, 1955 N.U.C 3551 Suit for return of deposit money is not for compensation for breach; limitation governed by Article 145 or 120. The Court cited this to support the view that the claim for refund of security deposit was governed by the residuary Article 120.

Court's Reasoning and Analysis

The Court analyzed the nature of the extra work claimed under Schedule B, focusing on whether the work was reinforced concrete (R.C.C) or merely cement concrete as contended by the defendant. The Court found that iron bars were embedded in the concrete as directed by the Engineer Incharge, supported by oral testimony and documentary evidence including a second drawing (Ex. 2) showing changes requiring R.C.C. The Court emphasized that the defining characteristic of R.C.C is the embedding of steel bars, not the specific ratio of materials used, rejecting the defendant’s argument that the ratio 1:4:8 with brick ballast disqualified the work as R.C.C.

The Court also rejected the defendant’s contention that prior written permission was necessary for the extra work, holding that oral instructions from the Engineer Incharge and the contract provision allowing work as directed sufficed.

Applying Section 70 of the Indian Contract Act and relying on the Supreme Court precedent in State of West Bengal v. B.K Mondal, the Court held that the defendant could not avoid payment for the extra work done as it had received benefit, preventing unjust enrichment.

Regarding the penalty deduction under Clause 2-B, the Court found that the defendant had already recovered the actual cost of completing the unfinished work and had not suffered damage. Citing Section 74 of the Contract Act and relevant Supreme Court decisions, the Court held that forfeiture of the security deposit as penalty without actual damage was not justified.

On limitation, the Court examined Articles 56, 115, and 120 of the old Limitation Act. It held that Article 56 did not apply because the contract specified payment terms. The Court found the suit was within time under Article 115, which applies to compensation claims for breach of contract, supported by precedent from this Court. For the refund of security deposit, the Court held the claim was governed by the residuary Article 120 with a six-year limitation period, and thus was also timely.

Holding and Implications

The Court DISMISSED the appeal filed by the State of U.P and ALLOWED the plaintiff's cross-objection partly. The decree of the trial court was modified to grant the plaintiff an additional sum of Rs. 6,650/- with interest at 3% per annum from the date of institution of the suit until payment.

The direct effect of this decision is that the plaintiff is entitled to payment for the extra R.C.C work performed under oral instructions and to the refund of the security deposit improperly forfeited by the defendant. The defendant cannot retain the security deposit as penalty without proof of actual damage. The suit was held to be within the limitation period under applicable Articles of the old Limitation Act.

No new legal precedent was established beyond the application and affirmation of existing principles concerning extra work payment, unjust enrichment under Section 70, penalty and compensation under Section 74, and limitation provisions.

    State Of U.P v. Chandra Gupta & Co. .

    K.C Agrawal, J.:— This is a defendant's appeal from the judgment and decree dated 22-8-1964 passed by the learned Additional Civil Judge, Meerut, decreeing the suit of the plaintiff-respondent partly for a sum of Rs. 14,283/-. The suit was filed by the plaintiff-respondent in the following circumstances.

    2. The Executive Engineer, Ganges Canal, Meerut Division, Meerut, issued a notice dated 13th August, 1957, inviting tenders for constructing a new Tail Fall V.R.B at Mile 7-0-330 of Jani Escape. The tender submitted by the plaintiff-respondent, in pursuance of the aforesaid notice, was accepted on the 19th of August, 1957, and a formal contract in that behalf was, thereafter, executed on November 4, 1957. The plaintiff started the work, but as the officers of the defendant began to harass him, he had to stop it on January 24, 1958. Upon the understanding arrived at, the work was resumed soon thereafter but it was finally again stopped by the plaintiff on March 21, 1958. Admittedly, the plaintiff had not executed the entire work undertaken by him under the contract. It was, thereafter, got done by the defendant through another agency. The plaintiff, however, filed the suit, giving rise to the present appeal, for recovery of a sum of Rs. 34,780.71 Paise. Schedules A to H appended to the plaint give the details of the amount claimed in the plaint. As in the present appeal we are concerned only with the claims under Schedules B, D, F, G and H, we need not mention the facts relating to other Schedules. The claim under Schedule B was for the payment of Rs. 13,770/- regarding reinforced concrete work (briefly stated as R.C.C), which according to the plaintiff was extra work not otherwise provided for in the contract. The total quantity of the work was 1,02000 Cft. The claim has been made @ 35% per Cft., whereas the payment was made only @ 21.50% Cft. The claim under Schedule D was for a sum of Rs. 1,265.08 Paise regarding the amount unduly recovered. Under Schedule F, the plaintiff claimed Rs. 283/- on account of Shuttering that was done by the plaintiff, it had been left and could not be removed due to the position being behind glacie. Schedule G was for the sum of Rs. 2,148/- as the price of the stores which had been supplied by the plaintiff for execution of the work, to the Government. The last item under Schedule H was for the recovery of Rs. 6,650/-, which had been deducted by the defendant from the bill paid on 15-3-1959 by way of penalty. The suit was contested by the State of U.P and it was denied that the plaintiff was enittled to any amount claimed in the plaint. The defendant disputed that the plaintiff had done any extra work as claimed by him in Schedule B. The claims made under other Schedules were also controverted. Admitting that a sum of Rs. 6,650/-. had been deducted out of the amount payable to the plaintiff, the defendant stated in the written statement that as the plaintiff was guilty of having not performed the contract within time the defendant had authority under the contract executed between the plaintiff and the defendant to deduct the amount.

    3. As stated above, the trial court decreed, the suit of the plaintiff for Rs. 14,283/- only. This decree was in respect of the amounts claimed under Schedules B and F. In respect of amounts claimed under other Schedules, the finding given by the court below is that the plaintiff could not prove that he was entitled to it and, therefore, the suit regarding them was liable to be dismissed. Feeling aggrieved by the judgment and decree of the trial court, the State of U.P has filed the present appeal challenging the decree only in respect of Schedule B. The appeal is, accordingly, valued at Rs. 13,770/-. The plaintiff has filed a Cross Objection valuing it at Rs. 10,352/- for the items covered by Schedules D, F, G and H.

    4. We propose to take up the appeal filed by the State of U.P first. As stated above, the claim under Schedule B was in respect of extra work. The details of the extra work have been given in the aforesaid Schedule. The same are as under:

    “Reinforced concrete paid as plain concrete.

    5. This work has been executed under instructions of the Supervising Staff in the following situations:

    (a) Horizontal and vertical reinforcement to connect different layers of 1:4:8 concrete.

    (b) Welded reinforcement net work on Girder piles near the Wall.

    (c) Net work of steel reinforcement in foundations of down stream wing walls where pipe fules have been provided.

    (d) In block foundations.

    (e) In Glacie portion to bind 1:4:8 Cement Concrete with 1:2:3.

    (f) To bind brick work with foundation concrete.”

    6. The plaintiff's case with regard to this item was that under the contract the plaintiff was required to do cement concrete, but as it was ordered by the officers concerned to do R.C.C, it rendered the R.C.C of 10,2000 Cft. The defendant, however, instead of making payment for the R.C.C has paid only for the cement concrete and, therefore, it was entitled to have payment for the R.C.C The dispute under this Schedule is with regard to the work done in the bed glacie portion, enjoining the layers, Wing Walls, in the pipe piling of the foundation, in the to wall by fitting and by making a net work of iron bars. The contract, however, provided not only the drawing Ext. 1, which was given to the plaintiff, but also for the execution of these items by cement concrete. According to the plaintiff, he was subsequently ordered by the Engineer Incharge to do R.C.C instead of cement concrete and, accordingly, the orders were carried out. In support of his case, Jai Prakash, who was the partner of the plaintiff, has appeared as P.W 2. In his statement, he has clearly stated that he was asked by the Engineer Incharge to do these works by the R.C.C instead of cement concrete and the same was, thereafter, done in the ratio of 1:4:8. The plaintiff has also produced Ex. 2 dated 22-2-1958, the second drawing supplied to him. The plaintiff had to execute the work in accordance with this drawing. The second drawing Ex. 2 shows some alterations and changes in the nature of work, i.e, R.C.C In the lower part of the design in Ex. 2, a provision has been made for using of iron bars while this was not shown in the drawing Ex. 1. This change in the drawing itself is significant and establishes that the Engineer Incharge and others concerned subsequently changed their minds and desired the items mentioned in Schedule B to be carried in R.C.C instead of cement concrete.

    7. The defendant in support of its case that the plaintiff did not do R.C.C but only cement concrete, produced S.V Sharma and Kailash Chandra as D.Ws 2 and 3 respectively. S.V Sharma was an Assistant Engineer posted at the site at the relevant time. He has clearly admitted in his statement that he was the Engineer Incharge of this work. According to his statement in examination-in-chief, the work of items of Schedule B was done in plain concrete, and that the same having been done in the ratio of 1:4:8, it could not be considered as R.C.C In his cross-examination, he, however, admitted that some extra work was also done by the plaintiff, and that he did not know if the plaintiff had received payment for the same. On further cross-examination, he had to admit the iron bars were placed horizontally and fixed up vertically. He further showed his ignorance as to whether iron bars were further used in girders. Likewise, he could not deny whether from bars were fitted in the foundation, but this much was admitted by him that at those places where iron bars were fitted they were all done under his instructions. He further admitted that photos were also taken when bars were fixed. These photos had been produced by the plaintiff and have been marked Exts. 7, 8, 10 and 11. The next witness on this question is Kailash Chandra Jain. He was then the Overseer Incharge of the work. Although he has denied that any R.C.C work was done by the plaintiff but he admitted at the same time that the work was done by the plaintiff in the ratio of 1:4:8 in brick ballast. Thereafter, he stated that iron to the quantity of 367.38 C.W.T was used. According to him, R.C.C work was done in the bridge by debitable agency. He, however, could not show from the Measurement Book, which was produced in the court, that this work was got done through debitable agency and not by the plaintiff. He admitted that iron bars were fitted in blocks and sheet piling.

    8. Apart from the oral evidence adduced on its behalf, the defendant has also filed a letter Ex. A-1 dated 5-8-1958 along with a report on the claims of the plaintiff. Item 3 of this report deals with the claim of the plaintiff regarding R.C.C It has been mentioned in this report that although the work had been done by the plaintiff in the ratio of 1:4:8 with ballast, but the same could not be considered as R.C.C The report of the Assistant Engineer was endorsed by-the Executive Engineer, and, thereafter, by the Superintending Engineer.

    9. Another circumstance which deserves notice at this place is about the fixation of dowels on the various works mentioned in this Schedule. The case of the plaintiff was that these dowels were used by him in order to cover the R.C.C work which was done on various dates. The case, however, of the defendant was that dowels were fitted because the plaintiff was not doing the work continuously and, therefore, they were fixed for the purposes of protecting the cement concrete work. There is no proof on the record that the dowels had to be used because the plaintiff did not work continuously while laying the concrete. The fact of the use of dowels having not been disputed, it appears to us that they had, in fact, been used by the plaintiff to protect the R.C.C

    10. Having considered the evidence given by the parties on the aforesaid question, we find that iron bars having been used by the plaintiff in the completion of the work mentioned in, Schedule B, the work which the plaintiff did was R.C.C and not cement concrete. Ex. A-1, the contract entered into between the plaintiff and the defendant, also gives the Detailed Specifications and Special Conditions of contract. In paragraph 56 of this contract, the nature of the work of cement concrete has been given. It provides that the concrete shall consist of portland cement fine and coarse aggregate mixed with water in a proportion to be specified by the Engineer Incharge from time to time, whereas this very contract in paragraph 80 deals with reinforcement. Taking into account these two clauses of the contract, it appears to us that the plaintiff having used iron bars in the various items mentioned in Schedule B should be deemed to have done R.C.C.R Greenhalgh in his book “The Practical Builder” at page 294 has given the definition of ‘concrete’ as below:

    “Concrete as a rule is mixture of cement aggregate (such as gravel, crushed stones, and crushed bricks), fine aggregate (such as sand and crushed stones), and suitable binding material (cement).”

    The word ‘reinforced concrete’ has been explained in Encyclopaedia Britannica, 1968 Edition, Vol. VI, at page 264, as:

    “When steel bars are embedded in the concrete the result is called ‘reinforced concrete’…….

    Two fundamental properties permit concrete and steel to work together as a composite material. Their coefficients of a thermal expansion are approximately equal;…….

    Finally, steel bars are used to increase shearing strength and to prevent cracking that would otherwise result from wide temperature changes.”

    11. The definitions given above clearly make out a distinction between the cement concrete and reinforced concrete. It would be found that when steel bars are embedded in the concrete, it becomes reinforced concrete. In the instant case, we have found that steel bars were used by the plaintiff in carrying out the works covered by items of Schedule B. Consequently, the plaintiff having embedded steel bars in the concrete should be held entitled to the payment for R.C.C work. In fact, R.C.C has become one of the many stays of modern construction which is not only economically competitive with the steel frame construction but its advantageous properties have had a radical speed of designs. The submission made by the learned counsel for the State, however, that as the work was done in the ratio of 1:4:8 and that too with brick ballast instead of stone ballast, it could not be considered as R.C.C, does not impress us. The main thing, as stated above, is that steel bars were embeded: in the concrete. This is determinative of the character of the work, and not the ratio. In fact, the concrete specifications differ from work to work. Therefore, simply because the work was not done by the plaintiff in the ratio of 1:2:4 that does not mean that the plaintiff had not done R.C.C and he was not entitled to the payment for the same. In this connection, reference may be made to page 382 of the “Practical Builder”, in which it has been said that there may be various reasons for variation of specification of concrete. Hence, merely because the work was done in the ratio of 1:4:8 and not in the ratio of 1:2:4 would not be a deciding factor. It would be seen that the ratio of cement in the work done by the plaintiff was the same as it would have been done in the ratio of 1:2:4, as urged by the plaintiff's counsel. Cement is the most suitable binding material and is also the most costly component in concrete. As its quantity was not reduced, it cannot be said that simply because the quantity of sand and ballast was changed, that would change the character of the work done by the plaintiff. Hence, we are unable to accept the submission of the counsel for the State that the plaintiff having not done the R.C.C was not entitled to get its price.

    12. Another submission made by the defendant's counsel was that Cls. 41 and 44 of the Special Conditions of the contract required the plaintiff to obtain an order before executing the work, and as the plaintiff did so without obtaining such a permission, he was not entitled to get the price. The submission made cannot be accepted for two reasons. The first reason being that the evidence filed by the plaintiff shows that he had been orally asked to do the R.C.C work. The statement made by Jai Prakash, P.W 2, has already been referred to by me above. There is nothing in his cross examination which could shake his testimony. It shows that he had been orally instructed for the work which is in dispute. Reference may also be made to Condition No. 5 of the Detailed Specifications, which requires that “all work shall be carried out in accordance with the detailed drawing to be supplied or as directed by the Engineer Incharge from time to time.” As the work was done by the plaintiff in accordance with the oral instructions received by him from the Engineer Incharge, therefore, it cannot be said that the plaintiff was not entitled to get the price for R.C.C work. Ext. 2 dated 22-2-1958, the second drawing also shows alterations and changes in the nature of work, i.e, reinforced concrete work. Therefore, this exhibit itself can be treated as an order in writing. Accordingly, the submission of the counsel for the State that as the plaintiff had not obtained any order in writing, he could not get the price for this item, is liable to fail.

    13. Another aspect of the matter which deserves notice at this place is as to whether the plaintiff could recover the amount under Sec. 70 of the Indian Contract Act, despite the fact that no formal, document was executed between the plaintiff and the defendant for the extra work. The term “extras” is generally used in relation to the works which are not expressly or impliedly included in the original contract and, therefore, not included in the original contract price, provided the work is done within the frame work of the original contract. Whether a particular work is extra or not will depend upon the terms and conditions of the contract, its specifications, plans, drawing, nature of the work etc. In the instant case, it cannot be denied that the R.C.C work covered by Schedule B is not expressly primpliedly included in the contract. It is only on account of the oral instructions given by the Engineer Incharge that the said work was done. This work having been thus done within the frame work of the contract is liable to be treated as extra work. Since the defendant has received benefit by this extra work, it is liable to pay for the same. Sec. 70 of the Contract Act is not founded on contract, but embodies the equitable principle of restitution and unjust enrichment. A government is also not outside the operation of Sec. 70, and, therefore, whenever it receives any benefit it is obliged to pay for the same under this section. This controversy came up for decision before the Supreme Court in State of West Bengal v. B.K Mondal A.I.R 1962 S.C 779.. This was a case where a contract as required by Sec. 175(3) of the Government of India Act, 1935, had not been executed between the State Government and B.K Mondal & Sons, having done some work for the State of West Bengal, made a claim for the same. One of the questions which arose for decision before the Supreme Court was whether B.K Mondal & Sons could get the amount under Sec. 70 of the Contract Act as no formal document, as required by Sec. 175(3) of the Government of India Act, 1935, was executed. Answering the aforesaid question, the Supreme Court observed that what Sec. 70 prevents is unjust enrichment and it applies as much to individuals as to corporations and government. In this view of the matter, the government was held liable to pay for the goods delivered to it. The principle laid down by the Supreme Court in this case was followed in subsequent cases by the Supreme Court. Applying the law enunciated in this case, we also find that the defendant having received the benefit is liable to pay for R.C.C to the plaintiff.

    14. Before dealing with the question of limitation, which was urged by the learned counsel for the State, we think it appropriate to deal with the cross-objection filed by the respondent. As stated above, the cross-objection has been filed in respect of Schedules D, F, G and H. The claims with regard to Schedules D, F and G need not detain us long in as much as findings given by the learned Civil Judge on these Schedules appear to us to be correct. Counsel appearing for the respondent attempted to challenge these findings but could not satisfy that the learned Civil Judge committed any error in deciding them against the plaintiff. We have considered the evidence given by the parties on these items, but fail to find any error in the judgment of the court below.

    15. Coming to Schedule H, the claim of the plaintiff was that the defendant had no power to deduct the amount of Rs. 6,650/- from the final bill. The deduction has been attempted to be justified by the defendant on the ground that as the plaintiff did not perform the work within time, the aforesaid sum being 10% of the value of the contract, was liable to be forfeited under Clause 2-B of the contract. The question that arises for determination is as to whether the State could under this clause deduct the amount. The relevant portion of Clause 2-B extracted is as under:

    “Time is the essence of the contract. The contractor shall complete the work within the period specified in the tender……

    If the contractor fails to comply with this condition he shall be liable to pay as compensation an amount equal to one per cent or such smaller amount as the Executive Engineer may decide on the said estimated cost of the whole work for every day that the quantity of work remains incomplete. Provided always that the entire amount of compensation to be paid under the provision of this clause shall not exceed ten per cent on the estimated cost of the work as shown in the tender.”

    16. It appears from the Conditions of the Contract that the defendant at the time of making the payment for the work done under the contract had deducted a sum of Rs. 6,650/- from the amount payable to him, in exercise of the power given by Clause 1. The amount deducted was kept by it by way of security. As stated above, the deduction was justified by the State Government on the ground that the plaintiff having not done the work within time and having left the same unfinished, was liable to forfeiture. The submission made by the counsel for the respondent was that as the defendant had debited the plaintiff with the actual cost which was spent in getting the remaining work done, therefore, it was not entitled to forfeit the amount of security left with it. The submission is well founded. The State of U.P having deducted the excess amount which it had to pay to the debiting agency for getting the unfinished work done and completed, it is not entitled to forfeit the security deposit as it would result in conferring double benefit to the State.

    17. Sri Radha Krishna, counsel appearing for the plaintiff, urged that as no damage was suffered by the State Government it could not forfeit the security deposit made by the plaintiff. Reference was made by him in this connection to Sec. 74 of the Contract Act, which reads as under:

    “When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual, damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.”

    18. The submission made on behalf of the respondent was disputed by the learned counsel appearing for the State on the ground that the security deposit having been taken from the respondent in order to ensure the due performance of the contract and the respondent having defaulted the entire amount was liable to be forfeited.

    19. After having heard counsel for the parties, we are inclined to accept the submission advanced on behalf of the respondent. Sec. 74 of the Indian Contract Act entitles a person to get reasonable compensation and does not entitle him to realise anything by way of penalty. If a contract is not duly performed but still no damage is suffered on account of non-performance, the promisee would not be entitled to get damages.

    20. A similar question regarding the right of the Union of India to forfeit the security came up for consideration before the Supreme Court in Maula Bux v. Union Of India† . 1969 2 SCC 554. In that case, Maula Bux had entered into a contract with the Government of India for the supply of certain goods and had deposited certain amount of security for the due performance of the contract. It was stipulated in the contract that the amount of security was to stand forfeited in case the appellant neglected to perform his part of the contract. On Maula Bux committing default in the supply, the government did not only rescind the contract but also forfeit the security deposit. Holding that a case of forfeiture of earnest money was different from forfeiture of security deposit for due performance of the contract, the Supreme Court held that under Sec. 74 only reasonable amount can be forfeited if a contract is not performed. But, where under the terms of the contract the party in breach has undertaken to pay a sum of money or to forfeit a sum of money which he has already paid to the party complaining of a breach of contract, the undertaking is of the nature of penalty. It further held that the amount deposited by way of security for guaranteeing the due performance of the contract could not be regarded as earnest money. Applying the law to the facts of the present case, we find that as the defendant, admittedly, did not suffer any damage it was not entitled to forfeit the security deposit, in as much as forfeiture of security would amount to imposition of penalty. This case was followed by the Supreme Court in Union of India v. Rampur Distillery and Chemicals Limited 1973 1 SCC 649. It was held in this case that the party to a contract taking security deposit from the other party to ensure due performance of the contract is not entitled to forfeit the security deposit on the ground of default, when no loss is caused to him in consequence of such default. We, accordingly, find that the learned Civil Judge was not right in holding that the forfeiture of security by the defendant in the instant case was justified. We, therefore, hold that the plaintiff is entitled to get a decree for the sum of Rs. 6,650/- under this head.

    21. The only other question which remains to be decided is about limitation. Counsel for the State urged, that the period of limitation applicable to the reliefs sought for by the plaintiff was Art. 56 of the old Limitation Act, whereas counsel for the respondent submitted that as there are no specific articles in the said Act providing for the reliefs claimed in the suit, the residuary Art. 120 would apply. He also, in the alternative, relied on Article 115 of the old Limitation Act and submitted that even if this Article is applied, the suit is within time. These three Articles of the old Limitation Act are quoted below:

    Art. 56. For the price of work done by the plaintiff for the defendant at his request, where no time has been fixed for payment. Three Years. When the work is done. Art. 115. For compensation for the breach of any contract, express or implied, not in writing registered and not herein specially provided for. Three Years. When the contract is broken, or (where there are successive breaches) when the breach in respect of which the suit is instituted occurs, or where the breach is continuing, when it ceases. Art. 120. Suit for which no period of limitation is provided elsewhere in this Schedule. Six Years. When the right to sue accrues.

    22. Article 56, quoted above, will show that it prescribes a period of three years for a suit for the price of work done by the plaintiff for the defendant at his request, where no time has been fixed for payment. In this eventuality, the period of limitation starts running from the date when he work is done. In the instant case, however, we find that Clause 7 of the Conditions of Contract provides for payment on intermediate certificate to be regarded as advances. Under this limitation clause, a contractor is entitled to receive a monthly payment proportionate to the part thereof than approved for such purpose by the Engineer Incharge. Similarly, a provision for final payment has also been made in Clause 6. Accordingly, as the contract provides for the time when the payment is to be made, Art. 56 of the old Limitation Act would not be applicable to the claim for the extra work. The other Articles which were relied upon by the plaintiff were Arts. 120 and 115 of the said Act. Art. 115 will apply to a claim of compensation for breach of any contract, express or implied. The period of limitation in such cases is three years and it commences to run when the contract is broken. Although it was vehemently urged by Sri Radha Krishna that the correct Article applicable to the claim for the extra work was Art. 120, but as we find that even applying Art. 115, the suit of the plaintiff is within time, we do not think it necessary to examine the question as to whether Art. 120 applies. The facts of the case, stated above, would show that the claim of the plaintiff was rejected by the State of U.P on 15-3-1959, whereas the suit was filed by the plaintiff on 16-5-1962. The plaintiff having given two months' notice to the State of U.P was entitled to the exclusion of this period of two months, and as 15th of May, 1962, was a public holiday, the plaintiff could, therefore, file the suit on 16-5-1962. Accordingly, the suit filed by the plaintiff on the aforesaid date was within time. This view of ours is supported by a decision of a Division Bench of this Court in State of U.P v. Suraj Prasad Gupta F.A No. 351 of 1968, decided on 3-2-1976.. In this case also it was held that to a claim like the present, the applicable is that provided by Art. 115 of the old Limitation Act.

    23. There remains to consider the question as to whether the claim made by the plaintiff for the refund of the security deposit forfeited by the State was within time. The real question in this case is about the character of the deposit made by the plaintiff as a contractor. The amount was deposited as security for, the performance of the contract. The question of limitation as to the refund of security amount came up for consideration before a Division Bench of the Punjab and Haryana High Court in (Zila Parishad, Ambala…Defendant v. Banarsi Dass Kapur Plaintiff…. A.I.R 1973 Pun. and Har. 276.). The Bench observed that a suit for return of security deposit is not for compensation for the breach of any contract, the deposit remains a deposit whether the depositor has a right to deduct anything therefrom or not. Thus, the suit would be governed either by Art. 145 or 120 of the Limitation Act. In Datt Singh v. Srihar Singh 1955 N.U.C 3551., a learned Single Judge also was required to consider a similar controversy. The commentator has digested the observations made by the learned Judge made in the following terms:

    “The claim for a return of the deposit money cannot by any stretch of the language of Art. 115 be considered as a suit for compensation for breach of any contract. When an employee makes a deposit for due performance of the duties, the deposit is in the nature of a trust and the proper Article in such a case is Art. 145 which provides for a greater period of limitation than Art. 120. Even if Art. 145 is not applied, there is no escape from the conclusion that the other Article applicable to a case of this type is Art. 120.”

    24. For the reasons given above, we find that a suit relating to a deposit would fall under the residuary Art. 120 of the Act. The period provided under this Article is six years. Applying this period, we find that the suit is within time and, therefore, the claim of the plaintiff for the refund of the security deposit cannot be defeated on the ground of limitation.

    25. For these reasons, the appeal is dismissed with costs. The Cross Objection is allowed partly. Accordingly, the decree of the court below is modified, and the suit stands decreed for a further sum of Rs. 6,650/- with interest @ 3 per cent per annum from the date of institution of the suit till its payment.

    26. In view of the divided success of the parties in the Cross Objection, we direct them to bear their own costs.

    27. Appeal dismissed.