New Precedent on the “Storm-in-Progress” Rule and Contractual Indemnification in Slip-and-Fall Cases

New Precedent on the “Storm-in-Progress” Rule and Contractual Indemnification in Slip-and-Fall Cases

Introduction

This commentary analyses the recent decision in Diane Venza v. Catholic Charities of the Diocese of Rockville Centre, Roman Catholic Church of Saint Sylvester, and Property Pro Landscaping Design, Inc. (2025 N.Y. Slip Op. 899) rendered by the Supreme Court of New York, Second Department. The case arises from a slip-and-fall accident in January 2015 in the parking lot of St. Sylvester in Medford, where the plaintiff, Diane Venza, alleged personal injuries. The litigation involved multiple parties with varying interests: the primary plaintiff, defendant third-party plaintiffs (including the Church and Catholic Charities) and a third-party defendant (Property Pro) contracted for snow removal services. Central to the dispute were the issues concerning premises liability under the “storm-in-progress” rule and the interpretation of a contractual hold harmless (indemnification) agreement between the Church and Property Pro.

This commentary provides a comprehensive overview of the judgment’s background, its summary findings, an in-depth analysis on the cited precedents, legal reasoning, the potentially far-reaching impacts on future cases, and clarifies key legal concepts for enhanced understanding.

Summary of the Judgment

The Court assessed motions for summary judgment brought by two parties: the defendant third-party plaintiff, St. Sylvester, and the third-party defendant, Property Pro. The central issue was whether these parties met their initial (prima facie) burden to demonstrate that they were not liable for the plaintiff’s injuries due to either the presence of an ongoing storm that created a temporary slippery condition or the terms of the contractual hold harmless agreement.

The Court found:

  • Neither St. Sylvester nor Property Pro established a prima facie entitlement to judgment under the storm-in-progress rule because the evidence did not conclusively show that the ice was a direct result of an active storm rather than residual accumulations from previous snowfall.
  • Similarly, both parties failed to demonstrate, as a matter of law, that the contractual indemnification clause provided sufficient protection or that the timing of Property Pro's performance absolved them from potential liability.

Consequently, the Court affirmed the lower court’s decision denying summary judgment on the disputed branches, though it directed one bill of costs payable to the plaintiff by both St. Sylvester and Property Pro.

Analysis

Precedents Cited

The judgment relies on several key precedents that have shaped the current understanding of premises liability and contractual indemnification:

  • Canciani v. Stop & Shop Supermarket Co., LLC: This case established that a property owner can only be held liable for slip-and-fall accidents when it either creates the dangerous condition or had actual/constructive notice thereof. The Court uses this principle as the starting point for evaluating the defendant’s burden in showing that they neither created the hazardous condition nor were aware (either actually or constructively) of it.
  • Cerar v. Jefferson Valley Mall L.P.: This decision underscores that, in premises liability cases, a summary judgment motion must demonstrate that the dangerous condition resulted from an ongoing storm, thus excluding events due to residual conditions. The Court applied this reasoning and found that the evidence did not clearly establish that the plaintiff’s fall was due to active weather conditions.
  • Pennino v. Brooklyn Kings Plaza, LLC: This precedent clarifies that property owners are generally not liable for slippery conditions that occur during an ongoing storm or immediately thereafter, reaffirming the parameters of the storm-in-progress defense.
  • Cardona v. City of New York, Stukes v. New York City Housing Authority, and Taormina-Fucci v. 100-02 Rockaway Blvd. 26, LLC: These cases further outline evidentiary requirements for demonstrating that an active weather event, rather than preceding conditions, caused the hazardous ice.
  • Zapototsky v. Ascape Landscape & Constr. Corp. and Cedillo v. Nautilus Realty Ltd. Partnership: These decisions illustrate the necessity for clarity in holding a party to a contractual indemnification promise. They stress that indemnification rights must be clearly supported by the language and structure of the contractual agreement.
  • Better Living Now, Inc. v. Image Too, Inc. and HAINES v. CITY OF NEW YORK: These cases provide guidance on interpreting contract durations, especially with respect to hold harmless agreements in ongoing service contexts where an express term fixing duration is absent.

Legal Reasoning

The Court’s legal reasoning pivots on the concept of the party’s initial, or prima facie, burden when seeking summary judgment in premises liability and indemnification actions. For the storm-in-progress rule:

  • The defendants were required to prove that the dangerous condition (ice) was directly the result of an ongoing storm. However, the evidence (deposition transcripts and other materials) suggested that the ice was likely a result of an accumulation from snowfall two days earlier rather than from an immediate storm.
  • Even if temporary weather provided some support, the fact that residual conditions played an important role undermined the storm defense.

In regard to contractual indemnification:

  • The Court evaluated the hold harmless agreement between St. Sylvester and Property Pro. Although the agreement promised indemnification, the absence of an express term fixing the duration required the Court to assess the surrounding circumstances and the parties’ intent.
  • The Court noted that given Property Pro continued providing snow removal services, it was reasonable for the indemnification terms to extend through the period of service. However, the evidence did not conclusively demonstrate that the dangerous condition developed after the completion of Property Pro’s obligations, thus creating triable issues.

Impact on Future Cases and Legal Practice

The decision has several significant implications:

  • Clarification of the Storm Defense: The judgment solidifies that defendants invoking the storm-in-progress rule must conclusively establish that conditions causing a slip-and-fall arise solely from an active storm. Residual hazards from earlier weather events remain within the realm of potential liability.
  • Contract Interpretation in Indemnification: Future disputes involving hold harmless agreements will benefit from the Court’s approach in examining the intent and express terms (or lack thereof) within such contracts. Parties are encouraged to draft more precise terms regarding duration and scope to avoid ambiguity.
  • Evidentiary Standards: This case reiterates the high evidentiary threshold necessary to meet the prima facie burden on summary judgment motions in premises liability cases, influencing how parties approach fact-gathering and depositions in similar disputes.

Complex Concepts Simplified

Prima Facie Burden: This is the initial obligation on the moving party (in this case, St. Sylvester and Property Pro) to present evidence that, if uncontradicted, would justify granting summary judgment. Essentially, they must show that there is no genuine dispute of material fact to decide the case in their favor.

Storm-in-Progress Rule: The rule provides a defense in premises liability cases by allowing property owners to argue that injuries were caused by an active storm rather than negligent maintenance. However, the evidence must clearly indicate that the hazardous condition resulted directly from the storm’s ongoing effects.

Contractual Indemnification: This concept involves a party’s promise in a contract to protect another party from certain losses or damages. The court’s analysis emphasized the need for clear contractual language and reflected on how the lack of explicit duration terms can result in disputes over whether the indemnification obligation remains in effect during periods of service or after its completion.

Conclusion

The Supreme Court's decision in this matter provides a decisive ruling on two interrelated legal issues in the context of premises liability and contractual indemnification. Firstly, the Court reaffirmed that to successfully invoke the storm-in-progress defense, a defendant must conclusively demonstrate that the dangerous conditions were a direct and uninterrupted result of an active storm rather than a residual effect from earlier weather events. Secondly, the decision sheds light on the interpretation of hold harmless agreements, highlighting the importance of clear, unambiguous contractual terms, particularly regarding the duration of indemnification coverage.

Overall, the judgment is significant both for its impact on future slip-and-fall cases and for its guidance on drafting and enforcing contractual indemnification provisions. By setting a high evidentiary bar for summary judgment in these matters, the Court ensures that triable factual issues receive thorough consideration, thereby protecting the interests of injured parties while clarifying the limits of liability for property owners and service providers.

Case Details

Year: 2025
Court: Supreme Court of New York, Second Department

Judge(s)

Cheryl E. ChambersMark C. Dillon

Attorney(S)

Patrick F. Adams, P.C., Great River, NY (Joseph M. Nador of counsel), for defendant third-party plaintiff appellant-respondent. Smith Sovik Kendrick & Sugnet, P.C., Uniondale, NY (Kenneth T. Boyd of counsel), for third-party defendant respondent-appellant. Rosenberg & Gluck, LLP, Holtsville, NY (Erin M. Hargis of counsel), for respondent.

Comments