Save Roscam Peninsula CLG v An Bord Pleanala & Ors: Clarifying Costs in Environmental Judicial Reviews

Save Roscam Peninsula CLG v An Bord Pleanala & Ors: Clarifying Costs in Environmental Judicial Reviews

Introduction

The case of Save Roscam Peninsula CLG & Ors v An Bord Pleanala & Ors ([2022] IEHC 202) adjudicated by the High Court of Ireland on April 8, 2022, represents a significant development in the realm of environmental judicial reviews and the complexities surrounding cost protection under the Planning and Development Act 2000 (as amended). This case primarily centered around the applicants—Save Roscam Peninsula CLG, Sophie Cacciaguidi-Fahy, Martin Fahy, and Philip Harkin—challenging the decision of An Bord Pleanala to approve a Strategic Housing Development (SHD) in Rosshill, Galway. A pivotal issue in this case was whether the applicants were entitled to protective costs under Section 50B of the Planning and Development Act 2000, particularly in light of the Aarhus Convention's provisions on access to justice.

Summary of the Judgment

Justice Humphreys delivered a comprehensive judgment addressing multiple grounds of challenge against the decision of An Bord Pleanala. The court meticulously examined each ground, focusing extensively on whether the applicants warranted protective costs. The crux of the decision hinged on interpreting Section 50B of the Planning and Development Act 2000 and its applicability concerning the Aarhus Convention's stipulations on not-prohibitively-expensive costs in environmental cases.

The court concluded that Section 50B and the 2011 Act did not apply to the disputed grounds presented by the applicants. Consequently, the applicants were not entitled to protective costs under these statutory provisions. However, the judgment delved deeper into EU law questions, particularly those arising from the Aarhus Convention, leading to the decision to refer several pertinent questions to the Court of Justice of the European Union (CJEU) for clarification. The judgment underscored uncertainties in current legal frameworks regarding cost protections in environmental judicial reviews, suggesting a need for comprehensive legal clarification at higher judicial levels.

Analysis

Precedents Cited

The judgment extensively referenced previous cases to navigate the complexities surrounding cost protection:

  • Shannon v. McGuinness [1997] IEHC 54
  • Lennon v. Cork City Council [2006] IEHC 438
  • Milebush Properties Limited v. Tameside Metropolitan Borough Council [2011] EWCA Civ. 270
  • Heather Hill Management Company CLG v. An Bord Pleanála [2021] IECA 259
  • Enniskerry v. An Bord Pleanála [2022] IEHC 6

These precedents collectively highlight the evolving landscape of cost protection in environmental litigation. Notably, Enniskerry was directly relevant, involving similar questions about the scope of protective costs under the Aarhus Convention. The judgment also reflected on the North East Pylon Pressure Campaign Limited v. An Bord Pleanála (Case C-470/16), which underscored the interpretative obligations of national courts in aligning with EU environmental objectives.

Impact

The judgment holds substantial implications for future environmental litigation in Ireland:

  • Clarification of Cost Protection: By referring key questions to the CJEU, the judgment signals a forthcoming alignment (or necessary recalibration) of national law with EU environmental directives, particularly concerning cost protections for applicants.
  • Guidance for Future Cases: The detailed analysis provides a framework for practitioners to assess the applicability of Section 50B and related statutes in environmental judicial reviews.
  • Influence on Legislative Reforms: Anticipated clarity from the CJEU may catalyze legislative amendments to better integrate EU obligations, enhancing access to justice in environmental matters.
  • Precedential Value: As one of the high-profile cases addressing the intersection of national planning laws and EU environmental directives, it serves as a pivotal reference for subsequent judgments.

Additionally, the willingness of the court to engage with the CJEU underscores the judiciary's commitment to upholding EU standards, potentially fostering a more predictable and equitable legal environment for environmental governance.

Complex Concepts Simplified

Section 50B of the Planning and Development Act 2000

Section 50B governs the awarding of costs in judicial review proceedings related to planning and development. It outlines scenarios where applicants can be shielded from bearing legal costs if they are unsuccessful, promoting access to justice by reducing financial barriers.

Aarhus Convention

The Aarhus Convention is an international treaty granting the public rights regarding access to information, public participation, and access to justice in environmental matters. Article 9 specifically ensures that legal procedures are accessible and not prohibitively expensive, aligning national laws with these principles.

Not-Prohibitively-Expensive Rule

This principle, derived from the Aarhus Convention, dictates that legal costs in environmental cases should not deter individuals or organizations from seeking justice. It often translates into rules that either limit the costs an applicant may incur or provide full cost protection.

Refer Questions to the CJEU

When national courts face ambiguous or complex interpretations of EU law, they may refer specific questions to the Court of Justice of the European Union (CJEU) for authoritative clarification, ensuring uniform application across member states.

Conclusion

The judgment in Save Roscam Peninsula CLG v An Bord Pleanala & Ors marks a critical juncture in Irish environmental law, particularly concerning the financial accessibility of judicial reviews. By dissecting the applicability of Section 50B and aligning it with the Aarhus Convention's mandates, the High Court highlighted existing ambiguities and the necessity for cohesive legal interpretations. The proactive referral of seven questions to the CJEU underscores a judicial commitment to harmonizing national practices with overarching EU directives, paving the way for more transparent and equitable access to justice in environmental matters.

Moving forward, stakeholders in environmental litigation will keenly await the CJEU's clarifications, which are poised to significantly influence procedural norms and cost considerations. This judgment not only resolves specific disputes but also sets the stage for broader legal reforms, fostering a more robust framework for environmental governance and public participation in Ireland.