Court of Appeal Establishes Principles for Flood Risk Sequential Testing and Cumulative Impacts Assessment in NSIP Applications
Introduction
The Court of Appeal case Substation Action Save East Suffolk Ltd, R (On the Application Of) v Secretary of State for Energy Security and Net Zero & Ors ([2024] EWCA Civ 12) addresses critical issues surrounding the approval process for nationally significant infrastructure projects (NSIPs), specifically offshore wind farms. The appellant, a community-based organization, challenged the refusal of judicial review against development consent orders (DCOs) issued for the East Anglia One North (EA1N) and East Anglia Two (EA2) Offshore Wind Farms. Central to this appeal were concerns about surface water flooding risks and the assessment of cumulative impacts from related infrastructure projects.
The appellant contended that the Secretary of State failed to adequately apply the sequential test for flood risk and neglected the cumulative environmental impacts of additional projects such as the Nautilus and Eurolink interconnectors. The Court of Appeal, however, upheld the lower court's dismissal of the appeal, thereby reinforcing existing legal frameworks governing environmental assessments and planning policies.
Summary of the Judgment
The Court of Appeal reviewed an appeal against Judge Lang's decision to refuse judicial review claims related to the DCOs for EA1N and EA2 Offshore Wind Farms. The appellant raised two primary grounds:
- Flood Risk Assessment: Arguing that the Secretary of State did not properly apply a sequential test to assess and minimize flood risks from surface water.
- Cumulative Impacts: Contending that the assessment failed to consider the cumulative environmental effects of potential future projects connected to the new National Grid substation.
Upon thorough examination, the Court of Appeal found that:
- The sequential test was appropriately applied to address flood risks, focusing primarily on fluvial (river) flooding as per existing policy guidelines.
- Regarding cumulative impacts, the Secretary of State was justified in deferring the assessment of future projects due to insufficient available information, thus not breaching environmental assessment regulations.
Consequently, the appeal was dismissed, upholding the validity of the initial decisions to grant development consents.
Analysis
Precedents Cited
The judgment references several key cases and statutory provisions that underpin the Court's reasoning:
- R (Friends of the Earth Ltd) v Secretary of State for Transport [2021] PTSR 190: Provided a comprehensive account of the Planning Act 2008 provisions, particularly sections 31 and 104 concerning development consent and national policy statements.
- R (Zurich Assurance Ltd (t/a Threadneedle Property Investments)) v North Lincolnshire Council [2012] EWHC 3708 (Admin): Explored the application of the sequential test in planning decisions, though the Court found it inapplicable to the present case’s context.
- Hale Bank Parish Council v Halton Borough Council [2019] EWHC 2677 (Admin): Similar to the Zurich case, it was examined to determine the applicability of sequential testing under varying policy wordings.
- Wathen-Fayed v Secretary of State for Levelling-Up, Housing and Communities [2023] EWHC 92 (Admin): Discussed the discretion of decision-makers in applying flood risk assessments, supporting the view that policy guidelines allow for planning judgment discretion.
- R (Larkfleet Ltd) v South Kesteven District Council [2016] Env. LR. 76: Highlighted that cumulative effects assessments could be deferred if insufficient information is available.
- Pearce v Secretary of State for Business, Energy and Industrial Strategy [2021] EWHC 326 (Admin): Reinforced the principle that decision-makers may defer cumulative impacts assessments when future project information is lacking.
- R (Scarisbrick) v Secretary of State for Communities and Local Government [2017] EWCA Civ 787: Articulated principles for interpreting national planning policies, distinguishing between policy interpretation and planning judgment.
Legal Reasoning
The Court of Appeal meticulously dissected the legal frameworks governing planning decisions, focusing on the Planning Act 2008, the National Policy Statement for Energy (EN-1), the National Planning Policy Framework (NPPF), and the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017.
Sequential Test Application
The sequential test, as outlined in EN-1 and referenced in the NPPF and Planning Practice Guidance (PPG), mandates that new developments be directed towards areas with the lowest flood risk. Specifically, it prioritizes Flood Zone 1 (low risk) before considering Zones 2 (medium risk) and 3 (high risk), only applying the Exception Test when no suitable lower-risk sites are available.
The appellant argued that this test should encompass all sources of flooding, including surface water, necessitating a demonstration of no available lower-risk sites for any flood source. However, the Court clarified that the existing sequential test primarily addresses fluvial flooding, and the policies do not explicitly require a site-by-site demonstration for non-fluvial flood risks. The judge’s interpretation, upheld by the Court, emphasized that while surface water flood risks must be considered, the application allows for planning judgment to assess mitigation measures alongside site selection.
Cumulative Impacts Assessment
The appellant contended that the Secretary of State failed to assess the cumulative environmental impacts of additional projects (Nautilus and Eurolink) connected to the substation. The Court upheld the lower court’s decision that the failure was not a legal breach. It reasoned that since these projects were not yet sufficiently defined or approved, a comprehensive cumulative impacts assessment was impractical and therefore lawfully deferred.
The Court reinforced the principle from R (Larkfleet Ltd) v South Kesteven District Council and Pearce v Secretary of State, recognizing that decision-makers have the discretion to defer cumulative assessments when future projects lack requisite detail, ensuring compliance with environmental assessment regulations without necessitating premature or speculative evaluations.
Impact
The judgment has significant implications for future planning and environmental assessments, particularly in the renewable energy sector:
- Clarification of Sequential Test Scope: Reinforces that the sequential test, while comprehensive in addressing flood risks, primarily targets fluvial flooding. Planners retain discretion in managing non-fluvial flood risks through mitigation rather than rigid site exclusion.
- Cumulative Impacts Flexibility: Affirms that cumulative impacts assessments for future or potential projects can be lawfully deferred, provided there is insufficient information to undertake a meaningful assessment. This provides flexibility in planning processes, accommodating the evolving nature of large infrastructure projects.
- Planning Judgment Authority: Upholds the authority of decision-makers to apply planning judgments within the framework of existing policies, emphasizing that not all policy interpretations are subject to legal challenge unless there is clear irrationality or legal misapplication.
- Encouragement of Renewable Energy Projects: By dismissing the appellant’s grounds, the judgment supports the continued development of renewable energy infrastructure, which is critical for national energy security and climate goals.
These principles ensure that while environmental safeguards are maintained, the planning system remains adaptable to complex and interdependent infrastructure projects.
Complex Concepts Simplified
The Sequential Test
The sequential test is a method used in planning to determine the most suitable location for a development project by prioritizing areas with the lowest risk of flooding. It follows a hierarchy:
- First Preference: Areas with low flood risk (Flood Zone 1).
- Second Preference: If no suitable sites are available in Zone 1, areas with moderate flood risk (Flood Zone 2) may be considered.
- Third Preference: Only if no suitable sites exist in Zones 1 or 2, areas with high flood risk (Flood Zone 3) may be used, subject to additional assessments (Exception Test).
This test ensures that development avoids or minimizes flood risks as much as possible, enhancing safety and sustainability.
Cumulative Impacts Assessment
Cumulative impacts refer to the combined environmental effects of multiple projects or developments in a particular area. An assessment evaluates how these projects collectively influence factors like ecology, water management, and community well-being. In this case:
- Existing Projects: Current and approved projects whose impacts have already been assessed.
- Future Projects: Potential or proposed projects that may soon be developed.
The key issue was whether the existing projects (EA1N and EA2) should have included assessments of potential future projects like Nautilus and Eurolink. The Court clarified that if sufficient information about future projects is not available, it is lawful to defer their inclusion in cumulative assessments.
Environmental Impact Assessment (EIA)
An EIA is a process used to evaluate the environmental consequences of proposed projects before they are carried out. It involves:
- Identifying potential environmental impacts.
- Assessing their significance.
- Proposing measures to mitigate adverse effects.
In this judgment, the focus was on whether the environmental information related to future projects was sufficiently robust to require its inclusion in the EIA for EA1N and EA2. The Court found that the provided information was insufficient, justifying its exclusion from the cumulative impacts assessment.
Conclusion
The Court of Appeal's judgment in Substation Action Save East Suffolk Ltd v Secretary of State underscores the balance between stringent environmental safeguards and the practicalities of large-scale infrastructure development. By affirming the appropriate application of the sequential test and allowing flexibility in cumulative impacts assessments, the Court reinforced the importance of planning judgment within established legal frameworks.
This decision is pivotal for future NSIP applications, particularly in the renewable energy sector, as it delineates the boundaries of environmental assessments and planning discretion. Developers and community groups must navigate these frameworks with a clear understanding of policy intentions and judicial interpretations to foster sustainable and resilient development.
Ultimately, the judgment affirms that while environmental considerations are paramount, the planning system accommodates necessary flexibility to respond to evolving project specifics and information availability, ensuring that infrastructure development can proceed in a manner that respects both environmental integrity and national energy objectives.
Comments