Extension of Commissioning Deadline in Renewable Energy Projects: Wind Four Renergy Pvt Ltd vs CERC

Extension of Commissioning Deadline in Renewable Energy Projects

Wind Four Renergy Pvt Limited v. Central Electricity Regulatory Commission (CERC) & Ors.

Court: Appellate Tribunal For Electricity

Date: January 11, 2022

Introduction

The case of Wind Four Renergy Private Limited vs. Central Electricity Regulatory Commission (CERC) & Others addresses critical issues pertaining to the commissioning deadlines of renewable energy projects, specifically within the wind energy sector. The appellant, Wind Four Renergy Pvt Ltd, challenged the decisions made by CERC and other respondents regarding the extension of the Scheduled Commercial Operation Date (SCOD) for their 50 MW wind power project in Kutch, Gujarat.

The key issues revolved around the denial of an extension for the commissioning deadline, the resultant termination of the Power Purchase Agreement (PPA) by Power Trading Company India Limited (PTC), and the subsequent encashment of the Performance Bank Guarantee (PBG). The appellant contended that the delays in commissioning were beyond their control and sought relief for the same.

Summary of the Judgment

The Appellate Tribunal for Electricity, after a comprehensive review, allowed the appeal filed by Wind Four Renergy Pvt Ltd. The Tribunal found that the delay in commissioning the wind power project was not attributable to the appellant but resulted from the Central Electricity Regulatory Commission's (CERC) inaction in granting the necessary extensions in a timely manner.

Consequently, the Tribunal modified the impugned order of CERC by condoning the period of delay of 132 days from the date of the Tribunal's judgment, thereby extending the SCOD accordingly. Additionally, the Tribunal set aside the termination of the PPA and the encashment of the PBG by PTC, directing them to refund the equivalent amount to the appellant and mandate the furnishing of a fresh PBG.

Analysis

Precedents Cited

The respondents referenced the Halliburton Offshore Services Inc v. Vedanta Limited & Ors. as well as the Maharashtra State Electricity Distribution Company Limited v. Maharashtra Electricity Regulatory Commission and Others judgments. These cases were leveraged to argue against grant of extensions based on delays not caused by force majeure events like the COVID-19 pandemic. However, the Tribunal found these references insufficient in addressing the unique circumstances of the appellant's case, particularly the CERC's delayed actions.

Impact

This judgment sets a significant precedent for renewable energy projects in India, particularly concerning the responsibilities of regulatory bodies in facilitating project timelines. It underscores the imperative for bodies like CERC and SECI to act diligently and promptly in processing extension requests to avoid unfairly penalizing project developers for delays beyond their control.

Additionally, the decision restores the appellant’s confidence and provides a framework for addressing similar grievances, ensuring that project timelines are managed equitably, thereby fostering a more conducive environment for renewable energy investments.

Complex Concepts Simplified

Scheduled Commercial Operation Date (SCOD)

The SCOD is the date by which a power project is expected to commence commercial operations and start generating electricity for sale under a Power Purchase Agreement (PPA).

Performance Bank Guarantee (PBG)

A PBG is a financial instrument provided by the project developer to assure the buyer (in this case, PTC) that the developer will fulfill its contractual obligations. If the developer fails to do so, the buyer can encash the PBG as compensation.

Request for Selection (RfS)

RfS refers to the process initiated by regulatory bodies like SECI to invite bids from developers for setting up renewable energy projects. It outlines the terms, conditions, and requirements for project proposals.

Conclusion

The Tribunal's decision in Wind Four Renergy Pvt Limited vs. CERC & Ors. serves as a landmark ruling that emphasizes the accountability of regulatory bodies in the timely processing of extension requests for renewable energy projects. By recognizing the appellant's lack of control over the delays and rectifying the CERC's inaction, the Tribunal reinforced the principles of fairness and due diligence in the regulatory framework governing renewable energy.

This judgment not only provides relief to Wind Four Renergy Pvt Ltd but also instills a sense of reliability and trust among stakeholders in the renewable energy sector. It ensures that project developers are protected against arbitrary delays and that their efforts to comply with project timelines are duly acknowledged and facilitated by regulatory authorities.

Case Details

Year: 2022
Court: Appellate Tribunal For Electricity

Judge(s)

RKG & SKS

Comments