CERC Sets New Precedents in Transmission Tariff Adjustments: PGCIL v. Karnataka Power Transmission

CERC Sets New Precedents in Transmission Tariff Adjustments: PGCIL v. Karnataka Power Transmission

Introduction

The case of Power Grid Corporation of India Ltd. (PGCIL) v. Karnataka Power Transmission Corporation Ltd. And Others, adjudicated by the Central Electricity Regulatory Commission (CERC) on May 7, 2021, marks a significant development in the regulation of electricity transmission tariffs in India. This comprehensive petition was filed by PGCIL seeking truing up of tariffs under the 2014 and 2019 Tariff Regulations for the extension of the Kudankulam APP-Tirunelveli 400 kV Transmission Line.

Summary of the Judgment

The CERC, after meticulous examination of the submissions from both the petitioner (PGCIL) and the respondents (distribution licensees and power departments), granted the truing up of tariffs for the periods 2014-2019 and 2019-2024. The Commission approved the capital costs, additional capital expenditures (ACE), and various other financial components integral to determining the transmission charges. Notably, the Commission addressed specific issues such as the treatment of Return on Equity (RoE), Interest on Loan (IoL), and Operation & Maintenance (O&M) expenses, ensuring adherence to the stipulated regulatory frameworks.

Analysis

Precedents Cited

The judgment extensively references the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations of both 2014 and 2019. These regulations serve as the backbone for tariff determination and ensure that the process remains transparent, fair, and aligned with national standards.

Legal Reasoning

The Commission's decision was anchored in a detailed examination of the financial submissions by PGCIL. Key aspects of the legal reasoning include:

  • Capital Cost Admission: The Commission validated the capital costs submitted by PGCIL, ensuring they were within the approved estimates and compliant with regulatory norms.
  • Return on Equity (RoE): RoE was grossed up based on the Minimum Alternate Tax (MAT) rates, aligning with the provisions of the 2014 and 2019 Tariff Regulations.
  • Operation & Maintenance (O&M) Expenses: The Court clarified the treatment of O&M expenses for the Platform Level Communication Control (PLCC) system, determining that separate O&M expenses for PLCC were not admissible as it is part of the sub-station.
  • Interest on Loan (IoL): IoL was calculated using the weighted average rate of interest, factoring in the actual loan portfolio as stipulated by regulations.
  • Additional Capital Expenditure (ACE): ACE claims were scrutinized and approved based on actual expenditures, reinforcing the importance of substantiated financial claims.

Impact

This judgment has far-reaching implications for the power transmission sector in India:

  • Tariff Determination: Establishes a clear framework for tariff adjustments, ensuring that transmission licensees can recover costs transparently.
  • Financial Compliance: Reinforces the necessity for detailed and accurate financial reporting by transmission companies.
  • Regulatory Clarity: Provides definitive interpretations of complex regulations, such as the treatment of O&M expenses and RoE calculations.
  • Future Litigation: Serves as a precedent for similar petitions, guiding both regulatory bodies and transmission companies in future tariff-related disputes.

Complex Concepts Simplified

Truing Up of Tariff

Truing up refers to the process of adjusting the approved transmission tariffs based on actual costs incurred versus initially projected costs. This ensures that transmission companies are neither overburdened nor undercompensated.

Return on Equity (RoE)

RoE is the profit generated on shareholders' equity. In this context, it is adjusted (grossed up) based on the applicable tax rates to determine the appropriate return that can be factored into tariff calculations.

Interest on Loan (IoL)

IoL represents the interest component of loans taken by transmission companies. It is calculated using the weighted average rate of interest on the company's loan portfolio, ensuring that the cost of borrowing is accurately reflected in the tariffs.

Operation & Maintenance (O&M) Expenses

O&M Expenses cover the costs associated with the day-to-day operations and upkeep of transmission assets. The judgment clarified that certain communication systems (PLCC) integrated within sub-stations should not have separate O&M charges.

Conclusion

The CERC's decision in the Power Grid Corporation of India Ltd. v. Karnataka Power Transmission Corporation Ltd. case underscores the Commission's commitment to balanced and fair tariff determination. By meticulously evaluating PGCIL's claims and addressing intricate regulatory nuances, the Commission has set a robust precedent that will guide future tariff adjustments and regulatory proceedings in the power transmission sector. This judgment not only ensures financial prudence but also fosters transparency and accountability, paving the way for a more efficient and equitable electricity transmission framework in India.

Case Details

Year: 2021
Court: Central Electricity Regulatory Commission

Judge(s)

P.K. PujariChairpersonI.S. Jha, MemberArun Goyal, MemberPravas Kumar Singh, Member

Advocates

Shri S.S. Raju, PGCIL, ;Shri B. Vinodh Kanna, Advocate, TANGEDCO, ;Shri B. Dash, PGCILShri A.K. Verma, PGCILShri Ved Prakash Rastogi, PGCILMs. R. Ramalakshmi, TANGEDCODr. R. Kathiravan, TANGEDCO

Comments