CERC Establishes Liability for Transmission Tariff Truing Up Amid Downstream Delays

CERC Establishes Liability for Transmission Tariff Truing Up Amid Downstream Delays

Introduction

In the landmark case of Power Grid Corporation of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Ltd., the Central Electricity Regulatory Commission (CERC) addressed critical issues pertaining to the truing up of transmission tariffs for the 2014-2019 period and the determination of tariffs for the 2019-2024 period. The primary parties involved were Power Grid Corporation of India Limited (the Petitioner) and various distribution licensees, power departments, and transmission licensees (the Respondents), notably including BSES Rajdhani Power Limited and Himachal Pradesh Power Transmission Corporation Limited (HPPTCL).

The core matters revolved around tariff adjustments for specific transmission assets within the augmentation of transformers in the Northern Region. Discrepancies in the scheduled Commercial Operation Date (COD) and subsequent time overruns were pivotal in adjudicating the responsibilities for transmission charges during periods of downstream system delays.

Summary of the Judgment

CERC meticulously examined the petitioner’s petitions regarding the truing up and determination of transmission tariffs for the designated periods. Major findings include:

  • Adjustment of Scheduled COD for certain assets to align with others, rectifying inconsistencies in previous orders.
  • Allocation of transmission charges for assets where downstream transmission systems under HPPTCL and PSTCL were not commissioned, thereby holding these entities liable for the charges during the delay period.
  • Approval of various components of the annual fixed charges, including depreciation, interest on loans, return on equity (RoE), operation & maintenance (O&M) expenses, and interest on working capital (IWC).
  • Rejection of repetitive contentions raised by BSES Rajdhani Power Limited (BRPL), emphasizing the finality of previous CERC findings.
  • Explicit direction for the Petitioner to recover reimbursement of filing fees and publication expenses from the beneficiaries.

The judgment underscores CERC's commitment to regulatory compliance and fair distribution of financial liabilities among stakeholders, particularly in instances of project delays beyond the petitioner's control.

Analysis

Precedents Cited

The judgment references several key precedents influencing CERC’s decision:

  • Patran Transmission Company Limited v. Power System Operation Corporation Limited: Highlighted the necessity of contractual agreements for liability assignments in transmission charges.
  • NPCIL v. CERC (Appeal No. 332/2016): Addressed the implications of lacking contractual arrangements between parties regarding transmission charges.
  • Appeal No. 74 of 2017: Clarified norms around Initial Spares and their capitalization based on overall project costs.

These precedents collectively reinforced the importance of clear contractual obligations and regulated financial distributions in the energy sector, shaping CERC’s adjudication in this case.

Legal Reasoning

CERC employed a detailed legal framework to reach its decision:

  • Regulatory Compliance: Adhered strictly to the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations of both 2014 and 2019.
  • Equitable Allocation: Determined that delays in downstream system commissioning were beyond the petitioner’s control, thus relieving the petitioner from undue financial burdens and assigning liability to HPPTCL and PSTCL.
  • Prudence Check: Ensured all capital costs, including adjustments for cost overruns, discounts for time delays, and allowances for permissible excesses, were within approved norms.
  • Finality of Previous Orders: Established that repetitive contentions by BRPL had been conclusively addressed in prior petitions, reinforcing the finality of CERC’s decisions.

The Commission’s reasoning was methodical, emphasizing fairness and regulatory adherence, particularly in financial allocations related to project delays.

Impact

This judgment has significant implications for the energy sector:

  • Clarity on Liability: Establishes a clear precedent that transmission licensees are liable for charges when downstream systems are delayed, ensuring equitable financial responsibility.
  • Regulatory Compliance: Reinforces the importance of adhering to detailed regulatory frameworks in tariff determinations and adjustments.
  • Financial Planning: Encourages transmission companies to account for potential delays and associated financial liabilities in their project planning and stakeholder agreements.
  • Judicial Efficiency: Demonstrates CERC’s commitment to resolving recurring issues conclusively, reducing the frequency of repetitive petitions.

Future cases involving tariff disputes and project delays will undoubtedly reference this judgment, shaping regulatory approaches and financial accountability in the sector.

Complex Concepts Simplified

Truing Up

Truing up refers to the process of adjusting previously approved tariffs to reflect actual costs incurred, ensuring that financial allocations are accurate and justifiable.

Commercial Operation Date (COD)

The Commercial Operation Date (COD) is the date when a power project becomes operational and starts delivering electricity to the grid. It marks the commencement of tariff coverage.

Additional Capital Expenditure (ACE)

Additional Capital Expenditure (ACE) encompasses the unforeseen costs or expenses arising during the construction of a project. This can include cost overruns, additional materials, or delays requiring extra funding.

Return on Equity (RoE)

Return on Equity (RoE) is the financial ratio that measures the profitability relative to shareholders' equity. It indicates how effectively a company is using its equity base to generate profits.

Weighted Average Rate of Depreciation (WAROD)

Weighted Average Rate of Depreciation (WAROD) is the average rate at which an asset loses value over its useful life, weighted by the cost of different components within the asset.

Conclusion

The CERC’s judgment in Power Grid Corporation of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Ltd. serves as a pivotal reference for managing transmission tariff disputes, particularly concerning obligations arising from project delays. By precisely allocating financial responsibilities and adhering to regulatory standards, CERC fosters a fair and transparent energy sector. This decision not only mitigates undue financial strain on transmitters but also ensures that beneficiaries are not unjustly burdened, thereby balancing the interests of all stakeholders involved.

Moving forward, entities within the energy sector must meticulously plan and adhere to regulatory frameworks to avoid financial discrepancies and ensure smooth operational timelines. The judgment reinforces the necessity for clear contractual agreements and proactive financial management, setting a robust precedent for future regulatory practices.

Case Details

Year: 2022
Court: Central Electricity Regulatory Commission

Judge(s)

P.K. PujariChairpersonI.S. Jha, MemberArun Goyal, MemberP.K. Singh, Member

Advocates

Shri Ved Prakash Rastogi, PGCIL ;Ms. Nikita Choukse, Advocate, HPPTCL ;Shri S. S. Raju, PGCILShri D.K. Biswal, PGCILShri A.K. Verma, PGCIL

Comments