CERC Clarifies Truing Up Procedures and Capital Expenditure Allocation in Transmission Tariff Determination

CERC Clarifies Truing Up Procedures and Capital Expenditure Allocation in Transmission Tariff Determination

Introduction

In the case of Power Grid Corporation Of India Ltd. v. Karnataka Power Transmission Corporation Ltd. And Others (S), adjudicated by the Central Electricity Regulatory Commission (CERC) on June 1, 2020, the Petitioner sought truing up of capital expenditure and determination of tariffs for specific transmission assets under the 2014 and 2019 CERC Tariff Regulations. The core issues revolved around the accurate adjustment of capital costs, treatment of additional capital expenditure (ACE), depreciation methodologies, and the allocation of capital spares in the tariff determination process.

Summary of the Judgment

The CERC analyzed the Petitioner's claims for truing up capital expenditure from April 1, 2014, to March 31, 2019, and determined the tariffs for the subsequent period up to March 31, 2024. Key determinations included:

  • Approval of the trued-up Transmission Tariff for both periods as per the respective regulations.
  • Allowance of additional capitalization beyond the initially approved amount, subject to regulatory provisions.
  • Rejection of the Petitioner's attempt to reallocate capital expenditure towards IT equipment, maintaining the original depreciation methodology.
  • Clarification on the handling of Initial Spares in compliance with the Appellate Tribunal for Electricity (APTEL) directives.

Analysis

Precedents Cited

The judgment extensively referenced the Appellate Tribunal for Electricity (APTEL) decision in Appeal No. 74 of 2017, which delineated the treatment of Initial Spares based on project cost percentages. This precedent was pivotal in guiding the CERC's stance on capital expenditure allocation, ensuring compliance with established regulatory interpretations.

Legal Reasoning

The CERC's legal reasoning hinged on strict adherence to the frameworks set by the 2014 and 2019 Tariff Regulations. The Commission emphasized that truing up exercises are confined to verifying and adjusting previously admitted capital expenditures without permitting new allocations or reapportionments. Specifically:

  • Capital Expenditure Allocation: The Petitioner’s attempt to allocate a portion of capital expenditure to IT equipment during the truing up process was impermissible. The CERC underscored that such allocations should have been addressed in prior petitions and not retroactively applied during tariff adjustments.
  • Depreciation Methodology: Adhering to Regulation 27 of the 2014 Tariff Regulations, the Commission maintained the original depreciation rates and methodologies, rejecting the Petitioner's proposal to alter depreciation for IT equipment.
  • Additional Capital Expenditure (ACE): The CERC permitted ACE claims within the regulated limits, recognizing unforeseen liabilities and compensations, thereby ensuring that the transmission licensee could recover necessary expenditures without overreaching.
  • Initial Spares Treatment: In line with APTEL's judgment, Initial Spares were accurately calculated as a percentage of the project cost, preventing the Petitioner's over-claiming and ensuring regulatory consistency.

Impact

This judgment reinforces the necessity for transmission entities to strictly follow regulatory protocols when claiming capital expenditures and determining tariffs. Future cases will likely reference this decision to uphold the integrity of the truing up process and prevent arbitrary reallocation of capital costs. Additionally, the clear stance on depreciation ensures uniformity in financial reporting and tariff calculations across the sector.

Complex Concepts Simplified

Truing Up of Capital Expenditure

Truing up involves adjusting the initially estimated capital expenditures based on actual costs incurred. This ensures that tariffs reflect real financial inputs rather than projections.

Additional Capital Expenditure (ACE)

ACE refers to expenditures beyond the initially approved capital costs, often arising from unforeseen obligations like compensations or compliance with new regulations.

Initial Spares

Initial Spares are essential spare parts required at the inception of a project to ensure its smooth operation. Their cost is typically a percentage of the total project cost, as directed by regulatory precedents.

Depreciation

Depreciation is the systematic reduction in the recorded cost of fixed assets over their useful life. It reflects asset wear and tear, obsolescence, or usage.

Conclusion

The CERC's decision in Power Grid Corporation Of India Ltd. v. Karnataka Power Transmission Corporation Ltd. And Others (S) underscores the commission's commitment to maintaining regulatory precision in tariff determination processes. By adhering to established regulations and precedents, the CERC ensures transparency, fairness, and financial prudence within the electricity transmission sector. This judgment serves as a crucial reference point for future tariff petitions, emphasizing the importance of meticulous capital expenditure management and compliance with regulatory frameworks.

Case Details

Year: 2020
Court: Central Electricity Regulatory Commission

Judge(s)

P.K. PujariChairpersonI.S. Jha, Member

Advocates

Shri S.S. Raju, PGCIL, Shri Zafrul Hasan, PGCIL, Ms. Anshul Garg, PGCIL, Shri V.K. Singh, PGCIL and Shri Amit K. Jain, PGCIL, Advocate, ;None, Advocate,

Comments