Central Electricity Regulatory Commission Rules on Non-Applicability of Force Majeure in BPTA Relinquishment Charges: GMR Chhattisgarh Energy Limited vs. Power Grid Corporation of India

Central Electricity Regulatory Commission Rules on Non-Applicability of Force Majeure in BPTA Relinquishment Charges: GMR Chhattisgarh Energy Limited vs. Power Grid Corporation of India

Introduction

The case of GMR Chhattisgarh Energy Limited (GCEL) v. Power Grid Corporation Of India Limited And Another was adjudicated by the Central Electricity Regulatory Commission (CERC) on February 5, 2020. GCEL, a coal-based thermal power producer under the Electricity Act, 2003, sought the relinquishment of its Long Term Access (LTA) rights under a Bulk Power Transfer Agreement (BPTA) dated March 31, 2010. The core of the dispute revolved around GCEL's claim of force majeure due to unforeseen circumstances affecting its ability to execute Long Term Power Purchase Agreements (PPAs), thereby seeking exemption from relinquishment charges imposed by the Central Transmission Utility (CTU).

Summary of the Judgment

CERC examined whether GCEL's inability to secure long-term PPAs constituted a force majeure event under Clause 9 of the BPTA, thereby exempting it from paying relinquishment charges as per Regulation 18 of the Connectivity Regulations, 2009. The Commission concluded that the force majeure clause was intended to cover temporary disruptions and did not encompass the entire spectrum of obligations under the BPTA, particularly the payment of relinquishment charges. Consequently, CERC upheld the CTU's position, mandating GCEL to honor its financial obligations related to the relinquishment of the LTA despite the reported impediments.

Analysis

Precedents Cited

The judgment referenced several pivotal cases to contextualize the application of force majeure within contractual and regulatory frameworks:

  • Bharathidasan University & Anr. vs. All-India Council for Technical Education & Ors. [(2001) 8 SCC 676]: This Supreme Court case clarified the scope of regulatory charges and their statutory backing, emphasizing that only charges explicitly sanctioned by the Act can be imposed by regulatory bodies.
  • Damodar Valley Corporation vs. CERC & Ors. (Appeal Nos. 271, 272, 273, 275 of 2006 & 8 of 2007): The Appellate Tribunal for Electricity reiterated that force majeure clauses should not be manipulated to evade contractual obligations that are clearly delineated within statutory regulations.
  • Other cases like Aryan MP Power Generation Pvt. Ltd. vs. PGCIL and Navbharat Power Pvt. Ltd. vs. PGCIL were cited to illustrate previous interpretations of Clause 9 of the BPTA, reinforcing the notion that it offers temporary relief rather than a loophole for permanent exemption from financial obligations.

Legal Reasoning

The Commission meticulously dissected the contractual clauses within the BPTA alongside the overarching Connectivity Regulations:

  • Clause 9 of the BPTA: Intended to provide temporary relief from obligations in the face of force majeure events like war, natural disasters, or sudden legal changes. The Commission interpreted this clause as non-applicable to financial obligations like relinquishment charges, which are governed by separate regulatory provisions.
  • Regulation 18 of the Connectivity Regulations: Clearly outlines the mechanism and compensation structure for relinquishment of LTA rights. It mandates that relinquishing LTA rights incurs charges based on stranded capacity, irrespective of purported force majeure events.
  • The Court emphasized that the force majeure clause was not an omnibus clause that could override all other contractual obligations, especially those codified in statutory regulations. The inherent nature of the BPTA as a contractual agreement under the aegis of the Electricity Act rendered regulatory provisions paramount.

Furthermore, the Commission highlighted that GCEL's inability to secure PPAs did not fall within the defined scope of force majeure. Instead, it was attributed to market conditions and competition, which are not calamities but rather operational challenges.

Impact

This judgment reinforces the primacy of statutory regulations over individual contractual clauses in the energy sector. It serves as a precedent for regulatory bodies and stakeholders in energy transactions, underscoring that:

  • Contractual Clauses vs. Regulatory Framework: Even if a contract contains a force majeure clause, regulatory provisions that explicitly govern certain aspects (like relinquishment charges) take precedence.
  • Obligation to Pay Relinquishment Charges: Generators cannot evade financial responsibilities stipulated under Connectivity Regulations by invoking force majeure unless such exemptions are explicitly provided within the regulatory framework.
  • Clarity in Contracts: Parties must recognize the boundaries of contractual agreements and the overarching regulatory environment to ensure compliance and avoid unexpected liabilities.

Future cases involving LTA relinquishments will likely cite this judgment to affirm the non-applicability of broad force majeure claims in bypassing regulatory financial obligations.

Complex Concepts Simplified

For better understanding, here are explanations of some complex legal terms and concepts used in the judgment:

  • Bulk Power Transfer Agreement (BPTA): A contractual agreement between a power generator and a transmission utility outlining the terms for transferring bulk power over transmission lines.
  • Long Term Access (LTA): A right granted to power generators allowing them uninterrupted access to the transmission system for a specified period, enabling the evacuation of produced power.
  • Relinquishment Charges: Fees imposed on power generators when they choose to surrender their LTA rights before the contract's expiration, compensating for the stranded capacity.
  • Force Majeure: A contractual clause that frees both parties from liability or obligation when an extraordinary event or circumstance beyond their control occurs, making performance inadvisable or impossible.
  • Connectivity Regulations, 2009: Regulatory guidelines issued by CERC governing the granting of connectivity and open access to the interstate transmission system for power generators.

Conclusion

The CERC's ruling in GMR Chhattisgarh Energy Limited vs. Power Grid Corporation Of India Limited And Another establishes a critical precedent in the energy sector's regulatory landscape. By affirming that force majeure clauses within contractual agreements like the BPTA do not supersede statutory regulations concerning financial obligations, the Commission ensures that regulatory frameworks maintain their intended authority and efficacy. This decision not only upholds the integrity of regulatory provisions but also delineates the boundaries within which contractual clauses operate, safeguarding the interests of both transmission utilities and power generators.

Stakeholders in the energy industry must now navigate their contractual agreements with a clear understanding of the supremacy of regulatory mandates, ensuring compliance and mitigating potential liabilities arising from misconstrued contractual clauses.

Case Details

Year: 2020
Court: Central Electricity Regulatory Commission

Judge(s)

P.K. PujariChairpersonDr. M.K. Iyer, MemberI.S. Jha, Member

Advocates

Shri Sanjay Sen, Senior Advocate, GCELShri Hemant Singh, Advocate, GCELShri Lakshyajit Singh, Advocate, GCELMs. Suparna Srivastava, Advocate, PGCILMs. Nehul Sharma, Advocate, PGCILDr. V.N. Paranjape, PGCILMs. Jyoti Prasad, PGCIL

Comments