(4) If a settlement is reached between the condemning authority and a property or business owner prior to a lawsuit being filed, the property or business owner who settles compensation claims in lieu of condemnation shall be entitled to recover costs in the same manner as provided in s.
73.091 and attorney's fees in the same manner as provided in s.
73.092, more specifically as follows:
(a) Attorney's fees for presuit negotiations under this section regarding the amount of compensation to be paid for the land, severance damages, and improvements must be calculated in the same manner as provided in s.
73.092(1) unless the parties otherwise agree.
(b) If business damages are recovered by the business owner based on the condemning authority accepting the business owner's initial offer or the business owner accepting the condemning authority's initial counteroffer, attorney's fees must be calculated in accordance with s.
73.092(2), (3), (4), and (5) for the attorney's time incurred in presentation of the business owner's good faith offer under paragraph (2)(c). Otherwise, attorney's fees for the award of business damages must be calculated as provided in s.
73.092(1), based on the difference between the final judgment or settlement of business damages and the counteroffer to the business owner's offer by the condemning authority.
(c) Presuit costs must be presented, calculated, and awarded in the same manner as provided in s.
73.091, after submission by the business or property owner to the condemning authority of all appraisal reports, business damage reports, or other work products for which recovery is sought, and upon transfer of title of the real property by closing, upon payment of any amounts due for business damages, or upon final judgment.
(d) If the parties cannot agree on the amount of costs and attorney's fees to be paid by the condemning authority, the business or property owner may file a complaint in the circuit court in the county in which the property is located to recover attorney's fees and costs.
This shall only apply when the action is by the Department of Transportation, county, municipality, board, district, or other public body for the condemnation of a road right-of-way.