(a) Qualifying conduit hydropower facilities
(1) A qualifying conduit hydropower facility shall not be required to be licensed under this subchapter.
(2)
(A) Any person, State, or municipality proposing to construct a qualifying conduit hydropower facility shall file with the Commission a notice of intent to construct such facility. The notice shall include sufficient information to demonstrate that the facility meets the qualifying criteria.
(B)
Not later than 15 days after receipt of a notice of intent filed under subparagraph (A), the Commission shall—
(i) make an initial determination as to whether the facility meets the qualifying criteria; and
(ii) if the Commission makes an initial determination, pursuant to clause (i), that the facility meets the qualifying criteria, publish public notice of the notice of intent filed under subparagraph (A).
(C)
If, not later than 45 days after the date of publication of the public notice described in subparagraph (B)(ii)—
(i) an entity contests whether the facility meets the qualifying criteria, the Commission shall promptly issue a written determination as to whether the facility meets such criteria; or
(ii) no entity contests whether the facility meets the qualifying criteria, the facility shall be deemed to meet such criteria.
(3)
For purposes of this section:
(A) The term “conduit” means any tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.
(B) The term “qualifying conduit hydropower facility” means a facility (not including any dam or other impoundment) that is determined or deemed under paragraph (2)(C) to meet the qualifying criteria.
(C)
The term “qualifying criteria” means, with respect to a facility—
(i) the facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit;
(ii) the facility has an installed capacity that does not exceed 5 megawatts; and
(iii) on or before August 9, 2013, the facility is not licensed under, or exempted from the license requirements contained in, this subchapter.
References in Text
The Fish and Wildlife Coordination Act, referred to in subsec. (c), is act Mar. 10, 1934, ch. 55, 48 Stat. 401, as amended, which is classified generally to sections 661 to 666c of this title. For complete classification of this Act to the Code, see Short Title note set out under section 661 of this title and Tables.
Prior Provisions
A prior section 30 of act June 10, 1920, was classified to section 791 of this title, prior to repeal by act Aug. 26, 1935, ch. 687, title II, § 212, 49 Stat. 847.
Amendments
2013—Subsecs. (a), (b). Pub. L. 113–23, § 4(a)(1), added subsecs. (a) and (b) and struck out former subsecs. (a) and (b) which authorized the Commission to grant exemptions from the requirements of this subchapter for certain hydroelectric facilities and prohibited the granting of exemptions to facilities with certain capacities.
Subsec. (c). Pub. L. 113–23, § 4(a)(2), substituted “subsection (b)” for “subsection (a)” in introductory provisions.
Subsec. (d). Pub. L. 113–23, § 4(a)(3), substituted “subsection (b)” for “subsection (a)”.
1986—Subsec. (b). Pub. L. 99–495, § 7(a), inserted provision setting the maximum installation capacity for exemptions under subsec. (a) at 40 megawatts in the case of a facility constructed, operated, and maintained by an agency or instrumentality of a State or local government solely for water supply for municipal purposes.
Subsec. (c). Pub. L. 99–495, § 7(b), which directed the insertion of “National Marine Fisheries Service” after “the Fish and Wildlife Service” in both places such term appears, was executed by inserting “National Marine Fisheries Service” after “the United States Fish and Wildlife Service” and “the Fish and Wildlife Service”, as the probable intent of Congress.
Subsec. (e). Pub. L. 99–495, § 7(c), added subsec. (e).
Effective Date of 1986 Amendment
Amendment by Pub. L. 99–495 effective with respect to each license, permit, or exemption issued under this chapter after Oct. 16, 1986, see section 18 of Pub. L. 99–495, set out as a note under section 797 of this title.
Application of Subsection (c)
Pub. L. 99–495, § 8(c), Oct. 16, 1986, 100 Stat. 1251, provided that:
“Nothing in this Act [see Short Title of 1986 Amendment note set out under
section 791a of this title] shall affect the application of section 30(c) of the Federal Power Act [