(a) In general
The permit program required by section 7502(b)(6) of this title shall provide that permits to construct and operate may be issued if—
(1)
in accordance with regulations issued by the Administrator for the determination of baseline emissions in a manner consistent with the assumptions underlying the applicable implementation plan approved under
section 7410 of this title and this part, the permitting agency determines that—
(A) by the time the source is to commence operation, sufficient offsetting emissions reductions have been obtained, such that total allowable emissions from existing sources in the region, from new or modified sources which are not major emitting facilities, and from the proposed source will be sufficiently less than total emissions from existing sources (as determined in accordance with the regulations under this paragraph) prior to the application for such permit to construct or modify so as to represent (when considered together with the plan provisions required under
section 7502 of this title) reasonable further progress (as defined in
section 7501 of this title); or
(B) in the case of a new or modified major stationary source which is located in a zone (within the nonattainment area) identified by the Administrator, in consultation with the Secretary of Housing and Urban Development, as a zone to which economic development should be targeted, that emissions of such pollutant resulting from the proposed new or modified major stationary source will not cause or contribute to emissions levels which exceed the allowance permitted for such pollutant for such area from new or modified major stationary sources under
section 7502(c) of this title;
(2) the proposed source is required to comply with the lowest achievable emission rate;
(3) the owner or operator of the proposed new or modified source has demonstrated that all major stationary sources owned or operated by such person (or by any entity controlling, controlled by, or under common control with such person) in such State are subject to emission limitations and are in compliance, or on a schedule for compliance, with all applicable emission limitations and standards under this chapter; and
So in original. The word “and” probably should not appear.
(4) the Administrator has not determined that the applicable implementation plan is not being adequately implemented for the nonattainment area in which the proposed source is to be constructed or modified in accordance with the requirements of this part; and
(5) an analysis of alternative sites, sizes, production processes, and environmental control techniques for such proposed source demonstrates that benefits of the proposed source significantly outweigh the environmental and social costs imposed as a result of its location, construction, or modification.
Any emission reductions required as a precondition of the issuance of a permit under paragraph (1) shall be federally enforceable before such permit may be issued.
(e) Rocket engines or motors
The permitting authority of a State shall allow a source to offset by alternative or innovative means emission increases from rocket engine and motor firing, and cleaning related to such firing, at an existing or modified major source that tests rocket engines or motors under the following conditions:
(1) Any modification proposed is solely for the purpose of expanding the testing of rocket engines or motors at an existing source that is permitted to test such engines on November 15, 1990.
(2) The source demonstrates to the satisfaction of the permitting authority of the State that it has used all reasonable means to obtain and utilize offsets, as determined on an annual basis, for the emissions increases beyond allowable levels, that all available offsets are being used, and that sufficient offsets are not available to the source.
(3) The source has obtained a written finding from the Department of Defense, Department of Transportation, National Aeronautics and Space Administration or other appropriate Federal agency, that the testing of rocket motors or engines at the facility is required for a program essential to the national security.
(4) The source will comply with an alternative measure, imposed by the permitting authority, designed to offset any emission increases beyond permitted levels not directly offset by the source. In lieu of imposing any alternative offset measures, the permitting authority may impose an emissions fee to be paid to such authority of a State which shall be an amount no greater than 1.5 times the average cost of stationary source control measures adopted in that area during the previous 3 years. The permitting authority shall utilize the fees in a manner that maximizes the emissions reductions in that area.
References in Text
Section 7502(b) of this title, referred to in subsec. (a), was amended generally by Pub. L. 101–549, title I, § 102(b), Nov. 15, 1990, 104 Stat. 2412, and, as so amended, does not contain a par. (6). See section 7502(c)(5) of this title.
Amendments
1990—Pub. L. 101–549, § 102(c)(1), made technical amendment to section catchline.
Pub. L. 101–549, § 102(c)(2), (8), designated existing provisions as subsec. (a), inserted heading, and substituted “(1) shall be federally enforceable” for “(1)(A) shall be legally binding” in last sentence.
Subsec. (a)(1). Pub. L. 101–549, § 102(c)(3), inserted at beginning “in accordance with regulations issued by the Administrator for the determination of baseline emissions in a manner consistent with the assumptions underlying the applicable implementation plan approved under section 7410 of this title and this part,”.
Subsec. (a)(1)(A). Pub. L. 101–549, § 102(c)(4), inserted “sufficient offsetting emissions reductions have been obtained, such that” after “to commence operation,” and substituted “(as determined in accordance with the regulations under this paragraph)” for “allowed under the applicable implementation plan”.
Subsec. (a)(1)(B). Pub. L. 101–549, § 102(c)(5), inserted at beginning “in the case of a new or modified major stationary source which is located in a zone (within the nonattainment area) identified by the Administrator, in consultation with the Secretary of Housing and Urban Development, as a zone to which economic development should be targeted,” and substituted “7502(c)” for “7502(b)”.
Subsec. (a)(4). Pub. L. 101–549, § 102(c)(6), inserted at beginning “the Administrator has not determined that”, substituted “not being adequately implemented” for “being carried out”, and substituted “; and” for period at end.
Subsec. (a)(5). Pub. L. 101–549, § 102(c)(7), added par. (5).
Subsec. (b). Pub. L. 101–549, § 102(c)(9), added subsec. (b).
Subsecs. (c) to (e). Pub. L. 101–549, § 102(c)(10), added subsecs. (c) to (e).
1977—Par. (1)(A). Pub. L. 95–190, § 14(a)(57), inserted “or modified” after “from new” and “applicable” before “implementation plan”, and substituted “source” for “facility” wherever appearing.
Par. (4). Pub. L. 95–190, § 14(a)(58), added par. (4).
Failure To Attain National Primary Ambient Air Quality Standards Under Clean Air Act
Pub. L. 100–202, § 101(f) [title II], Dec. 22, 1987, 101 Stat. 1329–187, 1329–199, provided that:
“No restriction or prohibition on construction, permitting, or funding under sections 110(a)(2)(I), 173(4), 176(a), 176(b), or 316 of the Clean Air Act [sections 7410(a)(2)(I), 7503(4), 7506(a), (b), 7616 of this title] shall be imposed or take effect during the period prior to August 31, 1988, by reason of (1) the failure of any nonattainment area to attain the national primary ambient air quality standard under the Clean Air Act [this chapter] for photochemical oxidants (ozone) or carbon monoxide (or both) by December 31, 1987, (2) the failure of any State to adopt and submit to the Administrator of the Environmental Protection Agency an implementation plan that meets the requirements of part D of title I of such Act [this part] and provides for attainment of such standards by December 31, 1987, (3) the failure of any State or designated local government to implement the applicable implementation plan, or (4) any combination of the foregoing. During such period and consistent with the preceding sentence, the issuance of a permit (including required offsets) under section 173 of such Act [this section] for the construction or modification of a source in a nonattainment area shall not be denied solely or partially by reason of the reference contained in section 171(l) of such Act [
section 7501(1) of this title] to the applicable date established in section 172(a) [
section 7502(a) of this title]. This subsection [probably means the first 3 sentences of this note] shall not apply to any restriction or prohibition in effect under sections 110(a)(2)(I), 173(4), 176(a), 176(b), or 316 of such Act prior to the enactment of this section [Dec. 22, 1987]. Prior to August 31, 1988, the Administrator of the Environmental Protection Agency shall evaluate air quality data and make determinations with respect to which areas throughout the nation have attained, or failed to attain, either or both of the national primary ambient air quality standards referred to in subsection (a) [probably means the first 3 sentences of this note] and shall take appropriate steps to designate those areas failing to attain either or both of such standards as nonattainment areas within the meaning of part D of title I of the Clean Air Act.”