9. Bidding Process
9.1. For the procurement of transmission services under these guidelines, BPC may at its option either adopt a two-stage process featuring separate Request for Qualification (RFQ) and Request for Proposal (RFP) or adopt a single stage two envelope tender process combining the RFP and RFQ processes. The bid documents shall be prepared in accordance with para 4.1 of these guidelines.
9.2. RFQ or combined RFQ and RFP notice should be published in at least two national newspapers, website of the BPC and the appropriate Government and preferably in trade magazines also, so as to accord it wide publicity. The bidding shall necessarily be by way of International Competitive Bidding (ICB). For the purpose of issue of RFQ minimum conditions to be met by the bidder shall be specified in the RFQ notice.
9.3. BPC shall provide only written interpretation of the tender document to any bidder/participant and the same shall be made available to all other bidders. All parties shall rely solely on written communication and acceptances from the bidders.
9.4. Standard documentation to be provided in the RFQ shall include,
9.4.1.13[Definition of requirements, including:
Brief description of the Project;
Commissioning milestones to be achieved by the bidders;
Qualification requirements to be met by bidders including, minimum net-worth, internal resource generation, etc with necessary proof of the same, as outlined in the bid documents;]
9.4.2.14[The conditions as specified by the Appropriate Commission to be complied with by a person for being eligible to obtain a transmission license shall be necessary conditions for RFQ and will be incorporated in the RFQ by BPC.]
9.4.3.15[* * *]
9.4.4.16[* * *]
9.4.5.17[* * *]
9.4.6.18[* * *]
9.5. RFP shall be issued to all bidders who have qualified at the 19[RFP] stage. BPC may call a pre bid conference with all the developers who have sought documents for RFQ. In case the bidders seek any deviations and BPC finds 20[those] deviations are reasonable, the BPC may agree to deviation. The clarification/revised-bidding document shall be given to all who had sought the 21[RFP] document informing about the deviations and clarifications. Wherever revised bidding documents are issued, the BPC shall provide bidders at least 22[one month] after issue of such documents for submission of bids.
9.6. Standard documentation to be provided by the BPC in the RFP shall include,
9.6.1. Specified target dates/months for commissioning and commercial operations and start of providing the transmission services.
9.6.2.23[Proposed Transmission Service Agreement(TSA). The TSP will enter into a Transmission Service Agreement (TSA) with the concerned utilities. These may include the utilities falling in the region where the load is located, any intervening region and the interregional transmission lines between the regions.
The bid document for the concerned project shall provide a draft of proposed TSA.]
9.6.3.24[Required Period of validity of offer of bidder.]
9.6.4.25[TSA proposed to be entered with the selected bidder. The TSA proposed in the RFP stage may be amended based on the inputs received from bidders during the pre bid conference and it will be made available to all RFP bidders. No further amendments shall be carried out in the TSA.]
9.6.5.26[Bid evaluation methodology to be adopted by the BPC. The bids shall be evaluated based on annual transmission charges for all components covered under the package as quoted by the bidder.]
9.6.6.27[The RFP shall also specify the Discount Factor (DF) that would be used for evaluation of bids.]
9.6.7.28[The RFP will also specify the bid bond as well as the Contract Performance Guarantee that the bidders will have to furnish.]
9.6.8.29[The proposed indemnification agreement between the TSP and the utilities will also be provided along with the RFP. This indemnification will be applicable to both the TSP and the utilities from the zero date as specified in the RFP.]
30[9.6.9. The RFP shall also specify the liquidated damages that would apply in event of delay in start of providing the transmission services.]
31[9.6.10. Other technical, operational and safety criteria to be met by bidder/TSP, including the provisions of the technical standard specified by CEA, IEGC/State Grid Code, relevant orders of the Appropriate Commission, etc., as applicable.]
9.7. Bid submission and evaluation. To ensure competitiveness, the minimum number of qualified bidders will be two.
32[9.8. Bid evaluation committee. The Empowered Committee shall constitute a committee for evaluation of the bids with at least one representative from CEA and not less than two representatives from the concerned Regional Power Committees with at least one representative from every concerned RPC and one independent member. The independent member shall have expertise in financial matter/bid evaluation.]
9.9. The bids shall be opened in public and representatives of bidders shall be allowed to remain present.
9.10. The technical bids shall be 33[examined] to ensure that the bids submitted meet minimum eligibility criteria set out in the 34[bid] documents on all technical evaluation parameters. Only the bids that meet all elements of the minimum technical criteria set out in the RFQ shall be considered for further evaluation on the transmission charges bids.
9.11. The transmission charge bid shall be rejected if it contains any deviation from the 35[bid documents] for submission of the same.
9.12. The bidder who has quoted lowest 36[levelised] transmission charge as per evaluation procedure shall be considered for the award.