In case of an accident at any solid waste processing or treatment or disposal facility or landfill site, the Officer-in-charge of the facility shall report to the local body in Form-VI and the local body shall review and issue instructions if any, to the in-charge of the facility.
FORM - I
[see rule 15(y) 16(1)(c), 21(3)]
Application for obtaining authorisation under solid waste management rules for processing/recycling/treatment and disposal of solid waste
To,
The Member Secretary,
State Pollution Control Board or Pollution Control Committee,
of..
Sir,
I/We hereby apply for authorisation under the Solid Waste Management Rules, 2016 for processing, recycling, treatment and disposal of solid waste.
| 1. |
Name of the local body/agency appointed by them/operator of facility |
|
| 2. |
Correspondence address Telephone No. Fax No., e-mail: |
|
| 3. |
Nodal Officer & designation(Officer authorised by the local body or agency responsible for operation of processing/treatment or disposal facility) |
|
| 4. |
Authorisation required for setting up and operation of the facility (Please tick mark) |
waste processing recycling treatment disposal at landfill |
| 5. |
Attach copies of the Documents Site clearance (local body) Proof of Environmental Clearance Consent for establishment Agreement between municipal authority and operating agency Investment on the project and expected return |
|
| 6. |
Processing/recycling/treatment of solid waste (i) Total Quantity of waste to be processed per day Quantity of waste to be recycled Quantity of waste to be treated Quantity of waste to be disposed into landfill (ii) Utilisation programme for waste processed (Product utilisation) (iii) Methodology for disposal (attach details) Quantity of leachate Treatment technology for leachate (iv) Measures to be taken for prevention and control of environmental pollution (v) Measures to be taken for safety of workers working in the plant (vi) Details on solid waste processing/recycling/treatment/disposal facility (to be attached) |
|
| 7. |
Disposal of solid waste Number of sites identified Quantity of waste to be disposed per day Details of methodology or criteria followed for site selection (attach) Details of existing site under operation Methodology and operational details of landfilling Measures taken to check environmental pollution |
|
| 8 |
Any other information. |
|
| Date: |
Signature: |
| Place: |
Designation: |
Form-II
[see rule 16(1)(e)]
Format for issue of authorisation
File No.:______________
Dated:_______________
Authorisation No_________
To
Ref: Your application number__________________ dt.___________
The _____________State Pollution Control Board/Pollution Control Committee after examining the proposal hereby authorises___________having administrative office at___________________to set up and operate waste processing/recycling/treatment/disposal facility at__________________________
The authorisation is hereby granted to operate the facility for processing, recycling, treatment and disposal of solid waste.
The authorisation is subject to the terms and conditions stated below and such conditions as may be otherwise specified in these rules and the standards laid down in Schedules I and II under these rules.
The_______________State Pollution Control Board/Pollution Control Committees of the UT may, at any time, revoke any of the conditions applicable under the authorisation and shall communicate the same in writing.
Any violation of the provision of the Solid Waste Management Rules, 2016 will attract the penal provision of the Environment (Protection) Act, 1986 (29 of 1986).
(Member Secretary)
State Pollution Control Board/Pollution Control Committee of the UT
(Signature and designation)
Date:
Place:
Form - III
[see rule 19(6), 24(1)]
Format of annual report to be submitted by the operator of facility to the local body
| 1 |
Name of the City/Town and State |
|
| 2 |
Population |
|
| 3 |
Area in sq. kilometers |
|
| 4 |
Name & Address of the local body Telephone No. Fax No. E-mail: |
|
| 5 |
Name and address of operator of the facility |
|
| 6 |
Name of officer in-charge of the facility Phone No: Fax No: E-mail: |
|
| 7 |
Number of households in the city/town, Number of non-residential premises in the city Number of election/administrative wards in the city/town |
|
| 8 |
Quantity of Solid waste |
|
| |
Estimated Quantity of solid waste generated in the local body area per day in metric tones |
/tpd |
| Quantity of solid waste collected per day |
/tpd |
| |
Per capita waste collected per day |
/gm/day |
| |
Quantity of solid waste processed |
/tpd |
| Quantity of solid waste disposed at landfill |
/tpd |
| 9 |
Status of Solid Waste Management (SWM) service |
|
| Segregation and storage of waste at source |
|
| Whether solid waste is stored at source in domestic/commercial/institutional bins If yes, |
Yes/No |
| Percentage of households practice storage of waste at source in domestic bins |
% |
| Percentage of non-residential premises practice storage of waste at source in commercial/institutional bins |
% |
| Percentage of households dispose of throw solid waste on the streets |
% |
| Percentage of non-residential premises dispose of throw solid waste on the streets |
% |
| Whether solid waste is stored at source in a segregated form |
Yes/No |
| If yes, Percentage of premises segregating the waste at source |
% |
| Door to Door Collection of solid waste |
|
| |
Whether door to door collection (D2D) of solid waste is being done in the city/town |
Yes/No |
| if yes |
| |
Number of wards covered in D2D collection of waste |
|
| |
No. of households covered |
|
| |
No. of non-residential premises including commercial establishments, hotels, restaurants educational institutions/offices etc covered |
|
| |
Percentage of residential and non-residential premises covered in door to door collection through: |
% |
| Motorized vehicle |
% |
| Containerized tricycle/handcart |
% |
| Other device |
|
| |
If not, method of primary collection adopted |
|
| |
Sweeping of streets |
|
| Length of roads, streets, lanes, bye-lanes in the city that need to be cleaned |
Km |
| Frequency of street sweepings and percentage of population covered |
frequency % of population covered |
Daily |
Alternate days |
Twice a week |
Occasionally |
| Tools used |
|
| Manual sweeping |
% |
| Mechanical sweeping |
% |
| Whether long handle broom used by sanitation workers |
Yes/No |
| Whether each sanitation worker is given handcart/tricycle for collection of waste |
Yes/No |
| Whether handcart/tricycle is containerized |
Yes/No |
| Whether the collection tool synchronizes with collection/waste storage containers utilized |
Yes/No |
| Secondary Waste Storage facilities |
|
| |
No. and type of waste storage depots in the city/town Open waste storage sites Masonry bins Cement concrete cylinder bins Dhalao/covered rooms/space Covered metal/plastic containers Upto 1.1 m3 bins 2 to 5 m3 bins Above 5m3 containers Bin-less city |
No. Capacity in m3 |
| |
Bin/population ratio Ward wise details of waste storage depots (attach): Ward No: Area: Population: No. of bins placed Total volume of bins placed |
|
| |
Total storage capacity of waste storage facilities in cubic meters Total waste actually stored at the waste storage depots daily Give frequency of collection of waste from the depots Number of bins cleared |
Frequency |
No. of bins |
| Daily |
|
| Alternate day |
|
| Twice a week |
|
| Once a week |
|
| Occasionally |
|
| |
Whether storage depots have facility for storage of segregated waste in green, blue and black bins |
Yes/No (if yes, add details) No. of green bins: No. of blue bins: No. of black bins: |
| |
Whether lifting of solid waste from storage depots is manual or mechanical. Give percentage |
(%) of Manual Lifting of SOLID WASTE |
% |
| (%) of Mechanical lifting |
% |
| |
If mechanical - specify the method used |
front-end loaders/Top loaders |
| |
Whether solid waste is lifted from door to door and transported to treatment plant directly in a segregated form |
Yes/No (if yes, specify) |
| |
Waste Transportation per day Type and Number of vehicles used (pl tick or add) |
No. Trips made waste transported |
| |
Animal cart Tractors Non tipping Truck Tipping Truck Dumper Placers Refuse collectors Compactors Others JCB/loader |
| |
Frequency of transportation of waste |
Frequency Daily Alternate day Twice a week Once a week Occasionally |
(%) of waste transported |
| |
Quantity of waste transported each day Percentage of total waste transported daily Waste Treatment Technologies used |
/tpd % |
| |
Whether solid waste is processed |
Yes/No |
| |
If yes, Quantity of waste processed daily Land(s) available with the local body for waste processing (in Hectares) |
/tpd |
| |
Land currently utilized for waste processing Solid waste processing facilities in operation Solid waste processing facilities under construction |
|
| |
Distance of processing facilities from city/town boundary Details of technologies adopted |
|
| |
Composting, |
Qty. raw material processed Qty. final product produced Qty. sold Qty. of residual waste landfilled |
| |
vermi composting Bio-methanation |
Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| |
Refuse Derived Fuel Waste to Energy technology such as incineration, gasification, pyrolysis or any other technology (give detail) |
Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| |
Co-processing |
Qty. raw material processed |
| |
Combustible waste supplied to cement plant |
|
| |
Combustible waste supplied to solid waste based power plants Others Solid waste disposal facilities |
Qty. |
| |
No. of dumpsites sites available with the local body |
|
| |
No. of sanitary landfill sites available with the local body Area of each such sites available for waste disposal Area of land currently used for waste disposal |
|
| |
Distance of dumpsite/landfill facility from city/town |
kms |
| |
Distance from the nearest habitation Distance from water body Distance from state/national highway |
kms kms kms |
| |
Distance from Airport Distance from important religious places or historical monument |
kms kms |
| |
Whether it falls in flood prone area |
Yes/No |
| |
Whether it falls in earthquake fault line area |
Yes/No |
| |
Quantity of waste landfilled each day Whether landfill site is fenced Whether Lighting facility is available on site |
tpd Yes/No Yes/No |
| |
Whether Weigh bridge facility available |
Yes/No |
| |
Vehicles and equipments used at landfill (specify) Manpower deployed at landfill site Whether covering is done on daily basis If not, Frequency of covering the waste deposited at the landfill |
Bulldozer, Compacters etc. available Yes/No (if yes, attach details) Yes/No |
| |
Cover material used |
Yes/No |
| |
Whether adequate covering material is available Provisions for gas venting provided Provision for leachate collection |
Yes/No, (if yes, attach technical data sheet) Yes/No, (if yes, attach technical data sheet) |
| 10 |
Whether an Action Plan has been prepared for improving solid waste management practices in the city |
Yes/No (if Yes attach Action Plan details) |
| 11 |
What separate provisions are made for: Dairy related activities: Slaughter houses waste: C&D waste (construction debris): |
Attach details on Proposals, Steps taken, Yes/No Yes/No Yes/No |
| 12 |
Details of Post Closure Plan |
Attach Plan |
| 13 |
How many slums are identified and whether these are provided with Solid Waste Management facilities: |
Yes/No (if Yes, attach details) |
| 14 |
Give details of manpower deployed for collection including street sweeping, secondary storage, transportation, processing and disposal of waste |
|
| 15 |
Mention briefly, the difficulties being experienced by the local body in complying with provisions of these rules |
|
| 16 |
Mention briefly, if any innovative idea is implemented to tackle a problem related to solid waste, which could be replicated by other local bodies. |
|
Signature of Operator
Dated:
Place:
Form - IV
[see rules 15(za), 24(2)]
Format for annual report on solid waste management to be submitted by the local body
| CALENDAR YEAR: |
DATE OF SUBMISSION OF REPORT: |
| |
|
| 1 |
Name of the City/Town and State |
|
| 2 |
Population |
|
| 3 |
Area in sq. kilometers |
|
| 4 |
Name & Address of local body Telephone No. Fax No. E-mail: |
|
| 5 |
Name of officer in-charge dealing with solid waste management (SOLID WASTEM) Phone No: Fax No: E-mail: |
|
| 6 |
Number of households in the city/town Number of non-residential premises in the city Number of election/administrative wards in the city/town |
|
| 7 |
Quantity of Solid waste (solid waste) |
|
| |
Estimated Quantity of solid waste generated in the local body area per day in metric tones Quantity of solid waste collected per day |
/tpd /tpd |
| |
Per capita waste collected per day |
/gm/day |
| |
Quantity of solid waste processed Quantity of solid waste disposed at dumpsite/landfill |
/tpd /tpd |
| 8 |
Status of Solid Waste Management service |
|
| |
Segregation and storage of waste at source Whether SOLID WASTE is stored at source in domestic/commercial/institutional bins, If yes, Percentage of households practice storage of waste at source in domestic bins Percentage of non-residential premises practice storage of waste at source in commercial/institutional bins Percentage of households dispose or throw solid waste on the streets Percentage of non-residential premises dispose of throw solid waste on the streets Whether solid waste is stored at source in a segregated form, If yes, Percentage of premises segregating the waste at source |
Yes/No % % % % Yes/No % |
| |
Door to Door Collection of solid waste |
|
| |
Whether door to door collection (D2D) of solid waste is being done in the city/town if yes Number of wards covered in D2D collection of waste |
Yes/No |
| |
No. of households covered No. of non-residential premises including commercial establishments, hotels, restaurants educational institutions/offices etc covered Percentage of residential and non-residential premises covered in door to door collection through: Motorized vehicle Containerized tricycle/handcart Other device |
% % % |
| |
If not, method of primary collection adopted |
|
| |
Sweeping of streets Length of roads, streets, lanes, bye-lanes in the city that need to be cleaned |
km |
| |
Frequency of street sweepings and percentage of population covered |
frequency % of population covered |
Daily |
Alternate days |
Twice a week |
Occasionally |
| |
Tools used Manual sweeping Mechanical sweeping Whether long handle broom used by sanitation workers Whether each sanitation worker is given handcart/tricycle for collection of waste Whether handcart/tricycle is containerized Whether the collection tool synchronizes with collection/waste storage containers utilized |
% % Yes/No Yes/No Yes/No Yes/No |
| |
Secondary Waste Storage facilities No. and type of waste storage depots in the city/town Open waste storage sites Masonry bins Cement concrete cylinder bins Dhalao/covered rooms/space Covered metal/plastic containers Upto 1.1 m3 bins 2 to 5 m3 bins Above 5m3 containers Bin-less city |
No. Capacity in m3 |
| |
Bin/population ratio |
|
| |
Ward wise details of waste storage depots (attach): Ward No: Area: Population: No. of bins placed Total volume of bins placed |
|
| |
Total storage capacity of waste storage facilities in cubic meters Total waste actually stored at the waste storage depots daily |
|
| |
Give frequency of collection of waste from the depots Number of bins cleared |
Frequency Daily |
No. of bins |
| Alternate day |
|
| Twice a week Once a week Occasionally |
| |
Whether storage depots have facility for storage of segregated waste in green, blue and black bins |
Yes/No (if yes, add details) No. of green bins: No. of blue bins: No. of black bins: |
| |
Whether lifting of solid waste from storage depots is manual or mechanical. Give percentage (%) of Manual Lifting of solid waste (%) of Mechanical lifting |
% % |
| |
If mechanical - specify the method used Whether solid waste is lifted from door to door and transported to treatment plant directly in a segregated form Waste transportation per day Type and Number of vehicles used |
front-end loaders/Top loaders |
| Yes/No (if yes, specify) |
| No. Trips made waste transported |
| |
Animal cart Tractors Non tipping Truck Tipping Truck Dumper Placers Refuse collectors Compactors Others JCB/loader |
|
| |
Frequency of transportation of waste |
Frequency Daily Alternate day Twice a week Once a week Occasionally |
(%) of waste transported |
| |
Quantity of waste transported each day |
/tpd |
| |
Percentage of total waste transported daily |
% |
| |
Waste Treatment Technologies used |
|
| |
Whether solid waste is processed |
Yes/No |
| |
If yes, Quantity of waste processed daily Whether treatment is done by local body or through an agency Land(s) available with the local body for waste processing (in Hectares) |
/tpd |
| |
Land currently utilized for waste processing |
|
| |
Solid waste processing facilities in operation |
|
| |
Solid waste processing facilities under construction |
|
| |
Distance of processing facilities from city/town boundary |
|
| |
Details of technologies adopted Composting, |
Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| |
Vermi composting |
Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| |
Bio-methanation |
Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| |
Refuse Derived Fuel Waste to Energy technology such as incineration, gasification, pyrolysis or any other technology (give detail) |
Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled Qty. raw material processed Qty. final product produced Qty. sold Quantity of residual waste landfilled |
| |
Co-processing |
Qty. raw material processed |
| |
Combustible waste supplied to cement plant Combustible waste supplied to solid waste based power plants |
|
| |
Others |
Qty. |
| |
Solid waste disposal facilities No. of dumpsites sites available with the local body |
|
| |
No. of sanitary landfill sites available with the local body |
|
| |
Area of each such sites available for waste disposal Area of land currently used for waste disposal |
|
| |
Distance of dumpsite/landfill facility from city/town Distance from the nearest habitation |
kms kms |
| |
Distance from water body Distance from state/national highway Distance from Airport |
kms kms kms |
| |
Distance from important religious places or historical monument |
Kms |
| |
Whether it falls in flood prone area |
Yes/No |
| |
Whether it falls in earthquake fault line area |
Yes/No |
| |
Quantity of waste landfilled each day |
Tpd |
| |
Whether landfill site is fenced |
Yes/No |
| |
Whether Lighting facility is available on site |
Yes/No |
| |
Whether Weigh bridge facility available |
Yes/No |
| |
Vehicles and equipments used at landfill (specify) |
Bulldozer, Compacters etc. available |
| |
Manpower deployed at landfill site |
Yes/No (if yes, attach details) |
| |
Whether covering is done on daily basis |
Yes/No |
| |
If not, Frequency of covering the waste deposited at the landfill Cover material used |
|
| |
Whether adequate covering material is available |
Yes/No |
| |
Provisions for gas venting provided |
Yes/No (if yes, attach technical data sheet) |
| |
Provision for leachate collection |
Yes/No (if yes, attach technical data sheet) |
| 9 |
Whether an Action Plan has been prepared for improving solid waste management practices in the city |
Yes/No (if Yes attach Action Plan details) |
| 10 |
What separate provisions are made for: Dairy related activities: Slaughter houses waste: C&D waste (construction debris): |
Attach details on Proposals, Steps taken, Yes/No Yes/No Yes/No |
| 11 |
Details of Post Closure Plan |
Attach Plan |
| 12 |
How many slums are identified and whether these are provided with Solid Waste Management facilities: |
Yes/No (if Yes, attach details) |
| 13 |
Give details of: Local body's own manpower deployed for collection including street sweeping, secondary storage, transportation, processing and disposal of waste |
|
| 14 |
Give details of: Contractor/concessionaire's manpower deployed for collection including street sweeping, secondary storage, transportation, processing and disposal of waste |
|
| 15 |
Mention briefly, the difficulties being experienced by the local body in complying with provisions of these rules |
|
| 16 |
Mention briefly, if any innovative idea is implemented to tackle a problem related to solid waste, which could be replicated by other local bodies |
|
Signature of CEO/Municipal Commissioner/Executive Officer/Chief Officer
Date:
Place:
Form - V
[see rule 24(3)]
Format of annual report to be submitted by the state pollution control board or pollution control committee committees to the central pollution control board
PART A
To,
The Chairman
Central Pollution Control Board
Parivesh Bhawan, East Arjun Nagar
DELHI- 110 0032
| 1. |
Name of the State/Union territory |
: |
|
| 2. |
Name & address of the State Pollution Control |
: |
|
| 3. |
Number of local bodies responsible for management of solid waste in the State/Union territory under these rules |
: |
|
| 4. |
No. of authorisation application Received |
: |
|
| 5. |
A Summary Statement on progress made by local body in respect of solid waste management |
: |
Please attach as Annexure-I |
| 6. |
A Summary Statement on progress made by local bodies in respect of waste collection, segregation, transportation and disposal |
: |
Please attach as Annexure-II |
| 7. |
A summary statement on progress made by local bodies in respect of implementation of Schedule II |
: |
Please attach as Annexure-III |
| Date: . Place: .. |
Chairman or the Member Secretary State Pollution Control Board/Pollution Control Committee |
PART B
Towns/cities
Total number of towns/cities
Total number of ULBs
Number of class I & class II cities/towns
Authorisation status (names/number)
Number of applications received
Number of authorisations granted
Authorisations under scrutiny
SOLID WASTE Generation status
Solid waste generation in the state (TPD)
collected
treated
landfilled
Compliance to Schedule I of SW Rules (Number/names of towns/capacity)
Good practices in cities/towns
House-to-house collection
Segregation
Storage
Covered transportation
Processing of SW (Number/names of towns/capacity)
Solid Waste processing facilities setup:
| Sl. No. |
Composting |
Vermi-composting |
Biogas |
RDF/Pelletization |
Processing facility operational:
| Sl. No. |
Composting |
Vermi-composting |
Biogas |
RDF/Pelletization |
| |
|
|
|
|
Processing facility under installation/planned:
| Sl. No. |
Composting |
Vermi-composting |
Biogas |
RDF/Pelletisation |
| |
|
|
|
|
Waste-to-Energy Plants: (Number/names of towns/capacity)
| Sl. No. |
Plant Location |
Status of operation |
Power generation (MW) |
Remarks |
Disposal of solid waste (number/names of towns/capacity):
Landfill sites identified
Landfill constructed
Landfill under construction
Landfill in operation
Landfill exhausted
Landfilled capped
Solid Waste Dumpsites (number/names of towns/capacity):
Total number of existing dumpsites
Dumpsites reclaimed/capped
Dumpsites converted to sanitary landfill
Monitoring at Waste processing/Landfills sites
| Sl. No. |
Name of facilities |
Ambient air |
Groundwater |
Leachate quality |
Compost quality |
VOCs |
| 1. |
|
|
|
|
|
|
| 2. |
|
|
|
|
|
|
| 3. |
|
|
|
|
|
|
Status of Action Plan prepared by Municipalities
Total number of municipalities:
Number of Action Plan submitted:
Form - VI
[see rule 25]
Accident Reporting
| 1. |
Date and time of accident |
: |
|
| 2. |
Sequence of events leading to accident |
: |
|
| 3. |
The waste involved in accident |
: |
|
| 4. |
Assessment of the effects of the accidents on human health and the environment |
: |
|
| 5. |
Emergency measures taken |
: |
|
| 6. |
Steps taken to alleviate the effects of accidents |
: |
|
| 7. |
Steps taken to prevent the recurrence of such an accident |
: |
|
| Date: . |
Signature: . |
| Place: .. |
Designation: |
SCHEDULE-I
[see rule 15(w),(zi), 16(1)(b)(e), 16(4)]
Specifications for Sanitary Landfills
(A) Criteria for site selection.
(i) The department in the business allocation of land assignment shall provide suitable site for setting up of the solid waste processing and treatment facilities and notify such sites.
(ii) The sanitary landfill site shall be planned, designed and developed with proper documentation of construction plan as well as a closure plan-in a phased manner. In case a new landfill facility is being established adjoining an existing landfill site, the closure plan of existing landfill should form a part of the proposal of such new landfill.
(iii) The landfill sites shall be selected to make use of nearby wastes processing facilities. Otherwise, wastes processing facility shall be planned as an integral part of the landfill site.
(iv) Landfill sites shall be set up as per the guidelines of the Ministry of Urban Development, Government of India and Central Pollution Control Board.
(v) The existing landfill sites which are in use for more than five years shall be improved in accordance with the specifications given in this Schedule.
(vi) The landfill site shall be large enough to last for at least 20-25 years and shall develop landfill cells in a phased manner to avoid water logging and misuse.
(vii) The landfill site shall be 100 meter away from river, 200 meter from a pond, 200 meter from Highways, Habitations, Public Parks and water supply wells and 20 km away from Airports or Airbase. However in a special case, landfill site may be set up within a distance of 10 and 20 km away from the Airport/Airbase after obtaining no objection certificate from the civil aviation authority/Air force as the case may be. The Landfill site shall not be permitted within the flood plains as recorded for the last 100 years, zone of coastal regulation, wetland, Critical habitat areas, sensitive eco-fragile areas..
(viii) The sites for landfill and processing and disposal of solid waste shall be incorporated in the Town Planning Department's land-use plans.
(ix) A buffer zone of no development shall be maintained around solid waste processing and disposal facility, exceeding five Tonnes per day of installed capacity. This will be maintained within the total area of the solid waste processing and disposal facility. The buffer zone shall be prescribed on case to case basis by the local body in consultation with concerned State Pollution Control Board.
(x) The biomedical waste shall be disposed of in accordance with the Bio-medical Waste Management Rules, 2016, as amended from time to time. The hazardous waste shall be managed in accordance with the Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016, as amended from time to time. The E-waste shall be managed in accordance with the e-Waste (Management) Rules, 2016 as amended from time to time.
(xi) Temporary storage facility for solid waste shall be established in each landfill site to accommodate the waste in case of non-operation of waste processing and during emergency or natural calamities.
(B) Criteria for development of facilities at the sanitary landfills.
(i) Landfill site shall be fenced or hedged and provided with proper gate to monitor incoming vehicles, to prevent entry of unauthorised persons and stray animals
(ii) The approach and/internal roads shall be concreted or paved so as to avoid generation of dust particles due to vehicular movement and shall be so designed to ensure free movement of vehicles and other machinery.
(iii) The landfill site shall have waste inspection facility to monitor waste brought in for landfilling h, office facility for record keeping and shelter for keeping equipment and machinery including pollution monitoring equipment. The operator of the facility shall maintain record of waste received, processed and disposed.
(iv) Provisions like weigh bridge to measure quantity of waste brought at landfill site, fire protection equipment and other facilities as may be required shall be provided.
(v) Utilities such as drinking water and sanitary facilities (preferably washing/bathing facilities for workers) and lighting arrangements for easy landfill operations during night hours shall be provided.
(vi) Safety provisions including health inspections of workers at landfill sites shall be carried out made.
(vii) Provisions for parking, cleaning, washing of transport vehicles carrying solid waste shall be provided. The wastewater so generated shall be treated to meet the prescribed standards.
(C) Criteria for specifications for land filling operations and closure on completion of land filling.
(i) Waste for land filling shall be compacted in thin layers using heavy compactors to achieve high density of the waste. In high rainfall areas where heavy compactors cannot be used, alternative measures shall be adopted.
(ii) Till the time waste processing facilities for composting or recycling or energy recovery are set up, the waste shall be sent to the sanitary landfill. The landfill cell shall be covered at the end of each working day with minimum 10 cm of soil, inert debris or construction material..
(iii) Prior to the commencement of monsoon season, an intermediate cover of 40-65 cm thickness of soil shall be placed on the landfill with proper compaction and grading to prevent infiltration during monsoon. Proper drainage shall be constructed to divert run-off away from the active cell of the landfill.
(iv) After completion of landfill, a final cover shall be designed to minimise infiltration and erosion. The final cover shall meet the following specifications, namely:
(a) The final cover shall have a barrier soil layer comprising of 60 cm of clay or amended soil with permeability coefficient less than 1 10-7 cm/sec.
(b) On top of the barrier soil layer, there shall be a drainage layer of 15 cm.
(c) On top of the drainage layer, there shall be a vegetative layer of 45 cm to support natural plant growth and to minimise erosion.
(D) Criteria for pollution prevention. In order to prevent pollution from landfill operations, the following provisions shall be made, namely:
(i) The storm water drain shall be designed and constructed in such a way that the surface runoff water is diverted from the landfilling site and leachates from solid waste locations do not get mixed with the surface runoff water. Provisions for diversion of storm water discharge drains shall be made to minimise leachate generation and prevent pollution of surface water and also for avoiding flooding and creation of marshy conditions.
(ii) Non-permeable lining system at the base and walls of waste disposal area. For landfill receiving residues of waste processing facilities or mixed waste or waste having contamination of hazardous materials (such as aerosols, bleaches, polishes, batteries, waste oils, paint products and pesticides) shall have liner of composite barrier of 1.5 mm thick high density polyethylene (HDPE) geo-membrane or geo-synthetic liners, or equivalent, overlying 90 cm of soil (clay or amended soil) having permeability coefficient not greater than 1 10-7 cm/sec. The highest level of water table shall be at least two meter below the base of clay or amended soil barrier layer provided at the bottom of landfills.
(iii) Provisions for management of leachates including its collection and treatment shall be made. The treated leachate shall be recycled or utilized as permitted, otherwise shall be released into the sewerage line, after meeting the standards specified in Schedule-II.. In no case, leachate shall be released into open environment.
(iv) Arrangement shall be made to prevent leachate runoff from landfill area entering any drain, stream, river, lake or pond. In case of mixing of runoff water with leachate or solid waste, the entire mixed water shall be treated by the concern authority.
(E) Criteria for water quality monitoring.
(i) Before establishing any landfill site, baseline data of ground water quality in the area shall be collected and kept in record for future reference. The ground water quality within 50 meter of the periphery of landfill site shall be periodically monitored covering different seasons in a year that is, summer, monsoon and post-monsoon period to ensure that the ground water is not contaminated.
(ii) Usage of groundwater in and around landfill sites for any purpose (including drinking and irrigation) shall be considered only after ensuring its quality. The following specifications for drinking water quality shall apply for monitoring purpose, namely:
| S. No. |
Parameters |
IS 10500:2012, Edition 2.2(2003-09) Desirable limit (mg/1 except for pH) |
| (1) |
(2) |
(3) |
| |
Arsenic |
0.01 |
| |
Cadmium |
0.01 |
| |
Chromium(as Cr6+) |
0.05 |
| |
Copper |
0.05 |
| |
Cyanide |
0.05 |
| |
Lead |
0.05 |
| |
Mercury |
0.001 |
| |
Nickel |
- |
| |
Nitrate as NO3 |
45.0 |
| |
pH |
6.5-8.5 |
| |
Iron |
0.3 |
| |
Total hardness (as CaCO3) |
300.0 |
| |
Chlorides |
250 |
| |
Dissolved solids |
500 |
| |
Phenolic compounds (as C6H5OH) |
0.001 |
| |
Zinc |
5.0 |
| |
Sulphate (as SO4) |
200 |
(F) Criteria for ambient air quality monitoring.
(i) Landfill gas control system including gas collection system shall be installed at landfill site to minimize odour, prevent off-site migration of gases, to protect vegetation planted on the rehabilitated landfill surface. For enhancing landfill gas recovery, use of geomembranes in cover systems along with gas collection wells should be considered.
(ii) The concentration of methane gas generated at landfill site shall not exceed 25 per cent of the lower explosive limit (LEL).
(iii) The landfill gas from the collection facility at a landfill site shall be utilized for either direct thermal applications or power generation, as per viability. Otherwise, landfill gas shall be burnt (flared) and shall not be allowed to escape directly to the atmosphere or for illegal tapping. Passive venting shall be allowed in case if its utilisation or flaring is not possible.
(iv) Ambient air quality at the landfill site and at the vicinity shall be regularly monitored. Ambient air quality shall meet the standards prescribed by the Central Pollution Control Board for Industrial area.
G. Criteria for plantation at landfill Site. A vegetative cover shall be provided over the completed site in accordance with the following specifications, namely:
(a) Locally adopted non-edible perennial plants that are resistant to drought and extreme temperatures shall be planted;
(b) The selection of plants should be of such variety that their roots do not penetrate more than 30 cms. This condition shall apply till the landfill is stabilized;
(c) Selected plants shall have ability to thrive on low-nutrient soil with minimum nutrient addition;
(d) Plantation to be made in sufficient density to minimise soil erosion.
(e) Green belts shall be developed all around the boundary of the landfill in consultation with State Pollution Control Boards or Pollution Control Committees.
H. Criteria for post-care of landfill site. (1) The post-closure care of landfill site shall be conducted for at least fifteen years and long term monitoring or care plan shall consist of the following, namely:
(a) Maintaining the integrity and effectiveness of final cover, making repairs and preventing run-on and run-off from eroding or otherwise damaging the final cover;
(b) Monitoring leachate collection system in accordance with the requirement;
(c) Monitoring of ground water in and around landfill;
(d) Maintaining and operating the landfill gas collection system to meet the standards.
(2) Use of closed landfill sites after fifteen years of post-closure monitoring can be considered for human settlement or otherwise only after ensuring that gaseous emission and leachate quality analysis complies with the specified standards and the soil stability is ensured.
I. Criteria for special provisions for hilly areas. Cities and towns located on hills shall have location-specific methods evolved for final disposal of solid waste by the local body with the approval of the concerned State Pollution Control Board or the Pollution Control Committee. The local body shall set up processing facilities for utilisation of biodegradable organic waste. The non-biodegradable recyclable materials shall be stored and sent for recycling periodically. The inert and non-biodegradable waste shall be used for building roads or filling-up of appropriate areas on hills. In case of constraints in finding adequate land in hilly areas, waste not suitable for road-laying or filling up shall be disposed of in regional landfills in plain areas.
J. Closure and Rehabilitation of Old Dumps- Solid waste dumps which have reached their full capacity or those which will not receive additional waste after setting up of new and properly designed landfills should be closed and rehabilitated by examining the following options:
(i) Reduction of waste by bio mining and waste processing followed by placement of residues in new landfills or capping as in (ii) below.
(i). Capping with solid waste cover or solid waste cover enhanced with geomembrane to enable collection and flaring/utilisation of greenhouse gases.
(iii) Capping as in (ii) above with additional measures (in alluvial and other coarse grained soils) such as cut-off walls and extraction wells for pumping and treating contaminated ground water.
(iv) Any other method suitable for reducing environmental impact to acceptable level.
SCHEDULE II
[see rule 16(1), (b), (e), 16(4)]
Standards of processing and treatment of solid waste
A. Standards for composting. The waste processing facilities shall include composting as one of the technologies for processing of bio degradable waste. In order to prevent pollution from compost plant, the following shall be complied with namely:
(a) The incoming organic waste at site shall be stored properly prior to further processing. To the extent possible, the waste storage area should be covered. If, such storage is done in an open area, it shall be provided with impermeable base with facility for collection of leachate and surface water run-off into lined drains leading to a leachate treatment and disposal facility;
(b) Necessary precaution shall be taken to minimise nuisance of odour, flies, rodents, bird menace and fire hazard;
(c) In case of breakdown or maintenance of plant, waste intake shall be stopped and arrangements be worked out for diversion of waste to the temporary processing site or temporary landfill sites which will be again reprocessed when plant is in order;
(d) Pre-process and post-process rejects shall be removed from the processing facility on regular basis and shall not be allowed to pile at the site. Recyclables shall be routed through appropriate vendors. The non-recyclable high calorific fractions to be segregated and sent to waste to energy or for RDF production, co-processing in cement plants or to thermal power plants. Only rejects from all processes shall be sent for sanitary landfill site(s).
(e) The windrow area shall be provided with impermeable base. Such a base shall be made of concrete or compacted clay of 50 cm thick having permeability coefficient less than 10-7 cm/sec. The base shall be provided with 1 to 2 per cent slope and circled by lined drains for collection of leachate or surface run-off;
(f) Ambient air quality monitoring shall be regularly carried out. Odurnuisance at down-wind direction on the boundary of processing plant shall also be checked regularly.
(g) Leachate shall be re-circulated in compost plant for moisture maintenance.
(h) The end product compost shall meet the standards prescribed under Fertilizer Control Order notified from time to time.
(i) In order to ensure safe application of compost, the following specifications for compost quality shall be met, namely:
| Parameters |
Organic Compost (FCO 2009) |
Phosphate Rich Organic Manure (FCO 2013) |
| (1) |
(2) |
(3) |
| Arsenic (mg/Kg) |
10.00 |
10.00 |
| Cadmium (mg/Kg) |
5.00 |
5.00 |
| Chromium (mg/Kg) |
50.00 |
50.00 |
| Copper (mg/Kg) |
300.00 |
300.00 |
| Lead (mg/Kg) |
100.00 |
100.00 |
| Mercury (mg/Kg) |
0.15 |
0.15 |
| Nickel (mg/Kg) |
50.00 |
50.00 |
| Zinc (mg/Kg) |
1000.00 |
1000.00 |
| C/N ratio |
<20 |
Less than 20:1 |
| pH |
6.5-7.5 |
(1:5 solution) maximum 6.7 |
| Moisture, percent by weight, maximum |
15.0-25.0 |
25.0 |
| Bulk density (g/cm3) |
<1.0 |
Less than 1.6 |
| Total Organic Carbon, per cent by weight, minimum |
12.0 |
7.9 |
| Total Nitrogen (as N), per cent by weight, minimum |
0.8 |
0.4 |
| Total Phosphate (as P205) percent by weight, minimum |
0.4 |
10.4 |
| Total Potassium (as K20), percent by weight, minimum |
0.4 |
- |
| Colour |
Dark brown to black |
- |
| Odour |
Absence of foul Odor |
- |
| Particle size |
Minimum 90% material should pass through 4.0 mm IS sieve |
Minimum 90% material should pass through 4.0 mm IS sieve |
| Conductivity (as dsm-1), not more than |
4.0 |
8.2 |
* Compost (final product) exceeding the above stated concentration limits shall not be used for food crops. However, it may be utilized for purposes other than growing food crops.
B. Standards for treated leachates. The disposal of treated leachates shall meet the following standards, namely:
| S. No |
Parameter |
Standards (Mode of Disposal) |
| Inland surface water |
Public sewers |
Land disposal |
| (1) |
(2) |
(3) |
(4) |
(5) |
| 1. |
Suspended solids, mg/1, max |
100 |
600 |
200 |
| 2. |
Dissolved solids (inorganic) mg/1, max. |
2100 |
2100 |
2100 |
| 3 |
pH value |
5.5 to 9.0 |
5.5 to 9.0 |
5.5 to 9.0 |
| 4 |
Ammonical nitrogen (as N), mg/1, max. |
50 |
50 |
- |
| 5 |
Total Kjeldahl nitrogen (as N), mg/1, max. |
100 |
- |
- |
| 6 |
Biochemical oxygen demand (3 days at 270 C) max.(mg/1) |
30 |
350 |
100 |
| 7 |
Chemical oxygen demand, mg/1, max. |
250 |
- |
- |
| 8 |
Arsenic (as As), mg/1, max |
0.2 |
0.2 |
0.2 |
| 9 |
Mercury (as Hg), mg/1, max |
0.01 |
0.01 |
- |
| 10 |
Lead (as Pb), mg/1, max |
0.1 |
1.0 |
- |
| 11 |
Cadmium (as Cd), mg/1, max |
2.0 |
1.0 |
- |
| 12 |
Total Chromium (as Cr), mg/1, max. |
2.0 |
2.0 |
- |
| 13 |
Copper (as Cu), mg/1, max. |
3.0 |
3.0 |
- |
| 14 |
Zinc (as Zn), mg/1, max. |
5.0 |
15 |
- |
| 15 |
Nickel (as Ni), mg/1, max |
3.0 |
3.0 |
- |
| 16 |
Cyanide (as CN), mg/1, max. |
0.2 |
2.0 |
0.2 |
| 17 |
Chloride (as Cl), mg/1, max. |
1000 |
1000 |
600 |
| 18 |
Fluoride (as F), mg/1, max |
2.0 |
1.5 |
- |
| 19 |
Phenolic compounds (as C6H5OH) mg/1, max. |
1.0 |
5.0 |
- |
Note: While discharging treated leachates into inland surface waters, quantity of leachates being discharged and the quantity of dilution water available in the receiving water body shall be given due consideration.
C. Standards for incineration: The Emission from incinerators/thermal technologies in Solid Waste treatment/disposal facility shall meet the following standards, namely:
| Parameter |
Emission standard |
| (1) |
(2) |
(3) |
| Particulates |
50 mg/Nm3 |
Standard refers to half hourly average value |
| HCl |
50 mg/Nm3 |
Standard refers to half hourly average value |
| SO2 |
200 mg/Nm3 |
Standard refers to half hourly average value |
| CO |
100 mg/Nm3 50 mg/Nm3 |
Standard refers to half hourly average value Standard refers to daily average value |
| Total Organic Carbon |
20 mg/Nm3 |
Standard refers to half hourly average value |
| HF |
4 mg/Nm3 |
Standard refers to half hourly average value |
| NOx (NO and NO2 expressed as NO2) |
400 mg/Nm3 |
Standard refers to half hourly average value |
| Total dioxins and furans |
0.1 ng TEQ/Nm3 |
Standard refers to 6-8 hours sampling. Please refer guidelines for 17 concerned congeners for toxic equivalence values to arrive at total toxic equivalence. |
| Cd + Th + their compounds |
0.05 mg/Nm3 |
Standard refers to sampling time anywhere between 30 minutes and 8 hours. |
| Hg and its compounds |
0.05 mg/Nm3 |
Standard refers to sampling time anywhere between 30 minutes and 8 hours. |
| Sb + As + Pb + Cr + Co + Cu + Mn + Ni + V + their compounds |
0.5 mg/Nm3 |
Standard refers to sampling time anywhere between 30 minutes and 8 hours. |
| Note. All values corrected to 11% oxygen on a dry basis. |
Note:
(a) Suitably designed pollution control devices shall be installed or retrofitted with the incinerator to achieve the above emission limits..
(b) Waste to be incinerated shall not be chemically treated with any chlorinated disinfectants.
(c) Incineration of chlorinated plastics shall be phased out within two years.
(d) if the concentation of toxic metals in incineration ash exceeds the limits specified in the Hazardous Waste (Management, Handling and Trans boundary Movement) Rules, 2008, as amended from time to time, the ash shall be sent to the hazardous waste treatment, storage and disposal facility.
(e) Only low sulphur fuel like LDO, LSHS, Diesel, bio-mass, coal, LNG, CNG, RDF and bio-gas shall be used as fuel in the incinerator.
(f) The CO2 concentration in tail gas shall not be more than 7%.
(g) All the facilities in twin chamber incinerators shall be designed to achieve a minimum temperature of 9500C in secondary combustion chamber and with a gas residence time in secondary combustion chamber not less than 2(two) seconds.
(h) Incineration plants shall be operated (combustion chambers) with such temperature, retention time and turbulence, as to achieve total Organic Carbon (TOC) content in the slag and bottom ash less than 3%, or the loss on ignition is less than 5% of the dry weight.
(i) Odour from sites shall be managed as per guidelines of CPCB issued from time to time