Uttar Pradesh act 1198 of 2018 : The UTTAR PRADESH ENERGY CONSERVATION BUILDING CODE 2018

Department
  • Department of Additional Energy Sources
Ministry
  • Ministry of Vidhai
Enforcement Date

16 Oct 2012

Uttar Pradesh Shasan Atrikt Urja Shrot Vibhag

In persuance of the provisions of clause (3) of Article 348 of the Constitution the Governor is pleased to order the publication of the

following English translation of notification no 1198@87&Add.Energy Sources Deptt.@2018 Dated July 26 ,2018

NOTIFICATION

NO 1198/87&Add.Energy Sources Deptt.@2018 Dated July 26 ,2018

In exercise of the powers conferred by section 15 of the

Energy Conservation Act 2001 (Central Act No 52 of 2001)the Governor in consultation with the Bureau of Energy Efficiency is pleased to approve the draft of Energy Conservation Building Code- 2018 and to direct that the notification and the procedure of implementation thereof shall be adopted.

The Governor is further pleased to approve that the construction of such government buildings of the State of which designing work has not been completed, which are covered under the perview of Energy Conservation Building Code - 2018 shall be caused to be done in accordance with Energy Conservation Building Code - 2018

By, Order

Alok Kumar Principal Secretary

1

UTTAR PRADESH E N E R G Y CONSERVATION

B U I L D I N G

CODE 2 0 1 8

2

3

1. Purpose The purpose of the Uttar Pradesh Energy Conservation Building Code (Code) is to provide

minimum requirements for the energy-efficient design and construction of buildings in Uttar

Pradesh falling under climatic zone: Composite, using ECBC- 2017. The Code also provides two

additional sets of incremental requirements for buildings to achieve enhanced levels of energy

efficiency that go beyond the minimum requirements.

4

2. Scope

The Code is applicable to buildings or building complexes that meet either of following:

(a) has a connected load of 100 kW or greater; or

(b) has a contract demand of 120 kVA or greater; or

(c) plot area of the building is more than 1000 m2 with minimum 2000 m2 as built-up area (excluding basement)

Buildings intended for private residential purposes are not covered by the Code.

2.1 Energy Efficiency Performance Levels

The code prescribes the following three levels of energy efficiency:

(a) Energy Conservation Building Code Compliant Building (ECBC Building)

ECBC Buildings shall demonstrate compliance by adopting the mandatory and

prescriptive requirements listed under ECBC Compliant Building requirements in §4

to §7, or by following the provisions of the Whole Building Performance (WBP)

Method in §9.

(b) Energy Conservation Building Code Plus Building (ECBC+ Building)

ECBC+ Buildings shall demonstrate compliance by adopting the mandatory and

prescriptive requirements listed under ECBC+ Compliant Building requirements in

§4 to §7, or by following the provisions of the Whole Building Performance (WBP)

Method in §9.

(c) Super Energy Conservation Building Code Building (Super ECBC Building)

Super ECBC Buildings shall demonstrate compliance by adopting the mandatory and

prescriptive requirements listed under Super ECBC Compliant Building requirements

in §4 to §7, or by following the provisions of the Whole Building Performance (WBP)

Method in §9.

2.2 Building Systems

The provisions of this code apply to:

(a) Building envelope,

(b) Mechanical systems and equipment, including heating, ventilating, and air

conditioning, service hot water heating,

(c) Interior and exterior lighting, and

(d) Electrical power and motors, and renewable energy systems.

The provisions of this code do not apply to plug loads, and equipment and parts of

buildings that use energy for manufacturing processes, unless otherwise specified in the

Code.

5

2.3 Precedence

The following codes, programs, and policies will take precedence over the Code in case of conflict:

a) Any policy notified as taking precedence over this Code, or any other rules on safety,

security, health, or environment by Central, State, or Local Government.

b) Bureau of Energy Efficiency’s Standards and Labelling for appliances and Star Rating

Program for buildings, provided both or either are more stringent than the requirements

of this Code.

2.4 Reference Standards

The National Building Code of India 2016 (NBC) is the reference standard for lighting levels,

heating, ventilating, and air conditioning (HVAC), thermal comfort conditions, natural ventilation,

and any other building materials and system design criteria addressed in this Code.

2.5 Building Classification

Any one or more building or part of a building with commercial use is classified as per the

functional requirements of its design, construction, and use. The key classification is as below:

a) Hospitality: Any building in which sleeping accommodation is provided for commercial

purposes, except any building classified under Health Care. Buildings and structures under

Hospitality shall include the following:

i. No-star Hotels – like Lodging-houses, dormitories, no-star hotels/ motels

ii. Resort

iii. Star Hotel

b) Health Care: Any building or part thereof, which is used for purposes such as medical or

other treatment or care of persons suffering from physical or mental illness, disease, or

infirmity; care of infants, convalescents, or aged persons, and for penal or correctional

detention in which the liberty of the inmates is restricted. Health Care buildings ordinarily

provide sleeping accommodation for the occupants. Buildings and structures like

hospitals, sanatoria, out-patient healthcare, laboratories, research establishments, and

test houses are included under this type.

c) Assembly: Any building or part of a building, where number of persons congregate or

gather for amusement, recreation, social, religious, patriotic, civil, travel and similar

purposes. Buildings like theatres or motion picture halls, gathering halls, and transport

buildings like airports, railway stations, bus stations, and underground and elevated mass

rapid transit system are included in this group.

d) Business: Any building or part thereof which is used for transaction of business, for

keeping of accounts and records and similar purposes, professional establishments, and

service facilities. There are two subcategories under Business – Daytime Business and 24-

6

hour Business. Unless otherwise mentioned, Business buildings shall include both

Daytime and 24-hour subcategories.

e) Educational: Any building used for schools, colleges, universities, and other training

institutions for day-care purposes involving assembly for instruction, education, or

recreation for students. If residential accommodation is provided in the schools, colleges,

or universities or coaching/ training institution, that portion of occupancy shall be

classified as a No-star Hotel. Buildings and structures under Educational shall include

following types-

i. Schools

ii. Colleges

iii. Universities

iv. Training Institutions

f) Shopping Complex: Any building or part thereof, which is used as shops, stores, market,

for display and sale of merchandise, either wholesale or retail. Buildings like shopping

malls, stand-alone retails, open gallery malls, super markets, or hyper markets are

included in this type.

g) Mixed-use Building: In a mixed-use building, each commercial part of a building must be

classified separately, and –

i. If a part of the mixed-use building has different classification and is less than 10 %

of the total above grade floor area, the mixed-use building shall show compliance

based on the building sub-classification having higher percentage of above grade

floor area.

ii. If a part of the mixed-use building has different classification and one or more sub-

classification is more than 10 % of the total above grade floor area, the compliance

requirements for each sub-classification, having area more than 10% of above

grade floor area of a mixed-use building shall be determined by the requirements

for the respective building classification in §4 to §7.

Any building which does not fall under any of the categories defined above shall be

classified in a category mentioned above that best describes the function of the building.

7

Note 2-1 Building Typologies for UPECBC 2018

Energy efficiency requirements for the Code were derived after

analysing 16 different non-residential building typologies (shown

below), that in turn are broadly based on building classification in

the National Building Code of India. Spatial layouts, material

specifications, facade characteristics, and occupancy patterns have

an impact on energy efficiency of a building and differ for these typologies. Potential

for reducing energy use with technology and materials thus varies from building type

to type. By analysing this potential, ECBC energy efficiency requirements are now

sensitive to building typologies and, to the extent possible, only requirements that

are feasible have been included.

Hospitality

1. Star Hotel

2. No Star Hotel

3. Resort

Educational

1. College

2. University

3. Institution

4. School

Health Care

1. Hospital

2. Out-patient Healthcare

Shopping Complex

1. Shopping Mall

2. Stand-alone Retails

3. Open Gallery Malls

4. Super Markets

Business

1. Large Office (> 30,000 m2)

2. Medium Office (10,000m2 - 30,000 m2)

3. Small Office (< 10,000 m2)

8

Assembly

1. Multiplex

2. Theatre

3. Building used for Transport Services

3. Compliance and Approach

3.1 General

To comply with the Code, buildings shall

a) have an Energy Performance Index Ratio (EPI Ratio) as defined in §3.1.2 that is less than

or equal to 1 and,

b) meet all mandatory requirements mentioned under §4.2, §5.2 , §6.2, and §7.2.

3.1.1 Energy Performance Index

The Energy Performance Index (EPI) of a building is its annual energy consumption in kilowatt-

hours per square meter of the building. While calculating the EPI of a building, the area of

unconditioned basements shall not be included. EPI can be determined by:

𝐸𝑃𝐼 = 𝐴𝑛𝑛𝑢𝑎𝑙 𝐸𝑛𝑒𝑟𝑔𝑦 𝐶𝑜𝑛𝑠𝑢𝑚𝑝𝑡𝑖𝑜𝑛 (𝑖𝑛 𝑘𝑊ℎ)

𝑇𝑜𝑡𝑎𝑙 𝑏𝑢𝑖𝑙𝑡𝑢𝑝 𝑎𝑟𝑒𝑎 (𝑒𝑥𝑐𝑙𝑢𝑑𝑖𝑛𝑔 𝑢𝑛𝑐𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛𝑒𝑑 𝑏𝑎𝑠𝑒𝑚𝑒𝑛𝑡𝑠)

To comply with the Code, EPI shall be calculated based on one of the following:

a) Prescriptive Method including Building Envelope Trade-off Method (see §3.2.2)

b) Whole Building Performance Method (see §3.2.3)

3.1.2 Determining EPI Ratio

The EPI Ratio of a building is the ratio of the EPI of the Proposed Building to the EPI of the

Standard Building:

𝐸𝑃𝐼 𝑅𝑎𝑡𝑖𝑜 = 𝐸𝑃𝐼 𝑜𝑓 𝑃𝑟𝑜𝑝𝑜𝑠𝑒𝑑 𝐵𝑢𝑖𝑙𝑑𝑖𝑛𝑔

𝐸𝑃𝐼 𝑜𝑓 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐵𝑢𝑖𝑙𝑑𝑖𝑛𝑔

where,

Proposed Building is consistent with the actual design of the building, and complies with all the

mandatory requirements of ECBC.

Standard Building is a standardized building that has the same building floor area, gross wall area

and gross roof area as the Proposed Building, complies with the mandatory requirements §4.2,

9

§5.2, §6.2, and §7.2, and minimally complies with prescriptive requirements of §4.3, §5.3 and

§6.3 for ECBC Buildings.

The EPI of the Proposed Building shall be established through any one of the following two

methods described in §3.2 –

a) Prescriptive Method (see §3.2.2)

b) Whole Building Performance Method (see §3.2.3)

3.1.2.1 EPI Ratio through Prescriptive Method

ECBC Buildings that demonstrate compliance through Prescriptive Method (§3.2.2) shall be

deemed to have an EPI equal to the Standard Building EPI, and therefore an EPI Ratio of 1. ECBC+

Buildings and SuperECBC Buildings that demonstrate compliance through Prescriptive Method

shall be deemed to have an EPI Ratio equal to the EPI Ratios listed in §9.5 under the applicable

building type and climate zone.

3.1.2.2 EPI Ratio through Whole Building Performance Method

The EPI of buildings that demonstrate compliance through Whole Building Performance Method

(§3.2.3) shall be calculated using the compliance path defined in §3.1.1 and detailed in §9. The

EPI Ratio of a building that uses the Whole Building Performance Method to show compliance,

should be less than or equal to the EPI Ratio listed in §9.5 for the applicable building type and

climate zone.

3.1.2.3 EPI Ratio for Core and Shell Buildings

EPI for core and shell buildings shall be calculated for the entire building based on the final design

of the common areas and the relevant mandatory undertaking(s) in the tenant lease agreement

for the leased areas, as per §3.1.2.1 or §3.1.2.2.

3.1.2.4 EPI Ratio for Mixed-use Development

In a mixed-use building, each commercial part of a building must be classified separately, and EPI

Ratio shall be calculated separately for each sub-classification, as per §3.1.2.1 or §3.1.2.2. The

EPI Ratio of a mixed-use Proposed Building shall be calculated based on area-weighted average

method. To calculate the reference maximum design EPI Ratio, listed in Table 9-5 through Table

9-7, applicable for the mixed-use building, each commercial part of mixed-use building shall be

classified separately, and,

a) If a part of the mixed-use building has different classification and is less than 10% of the

total above grade area (AGA), the EPI Ratio of the mixed-use Proposed Building shall be

less than or equal to Maximum Allowed EPI listed in Table 9-5 through Table 9-7, for the

building sub-classification having highest percentage of above grade floor area.

10

b) If a part of the mixed-use building has different classification and is more than 10% of the

total above grade floor area, the EPI of the mixed-use Proposed Building shall be less than

or equal to Maximum Allowed EPI for compliance calculated based on area weighted

average method for all building sub-classifications listed in Table 9-5 through Table 9-7.

Exceptions to the above: Any portion of a mixed-use building classified in a category which does

not fall under the scope of ECBC is exempted from demonstrating compliance.

3.2 Compliance Approaches

Buildings that fall within the scope of the Code as mentioned in §2, shall comply with the Code

by meeting all the mandatory requirements (see §3.2.1) and any of the compliance paths

mentioned in §3.2.2, §3.2.2.1, or §3.2.3.

3.2.1 Mandatory Requirements

Buildings shall comply with all mandatory requirements mentioned under §4.2, §5.2 , §6.2, and

§7.2, irrespective of the compliance path.

3.2.2 Prescriptive Method

A building complies with the Code using the Prescriptive Method if it meets the prescribed

minimum (or maximum) values for envelope components (§4.3), comfort systems and controls

(§5.3, §5.4, §5.5), and lighting and controls (§6.3), in addition to meeting all the mandatory

requirements.

3.2.2.1 Building Envelope Trade-off Method

Building Envelope Trade-off Method may be used in place of the prescriptive criteria of §4.3.1,

§4.3.2 and §4.3.3. A building complies with the Code using the Building Envelope Trade-off

Method if the Envelope Performance Factor (EPF) of the Proposed Building is less than or equal

to the EPF of the Standard Building, calculated as per §4.3.5, in addition to meeting the

prescriptive requirements for comfort systems and controls (§5.3, §5.4), and lighting and controls

(§6.3), and all the mandatory requirements (§4.2, §5.2, §6.2 and §7.2).

3.2.3 Whole Building Performance Method

A building complies with the Code using the Whole Building Performance (WBP) Method when

the estimated annual energy use of the Proposed Design is less than that of the Standard Design,

even though it may not comply with the specific provisions of the prescriptive requirements in

§4 trough §7. The mandatory requirements of §4 through §7 (§4.2, §5.2, §6.2, and §7.2) shall be

met when using the WBP Method.

11

3.3 Compliance Requirements

3.3.1 New Building Compliance

3.3.1.1 Full building Compliance

New buildings with completed fit-outs shall comply with either the provisions of §4 through §7

of this Code or the Whole Building Performance Method of §9.

3.3.1.2 Core and Shell building Compliance

New core and shell building shall demonstrate compliance with ECBC requirements for the

following base building systems in the common areas:

a) Building envelope

b) Thermal comfort systems and controls (only those installed by developer/ owner)

c) Lighting systems and controls (only those installed by developer/ owner)

d) Electrical systems (installed by developer/ owner)

e) Renewable energy systems

Additionally, the tenant lease agreement shall have a legal undertaking clause to ensure interior

fit-outs made by tenant shall be Code compliant. The legal undertaking shall mandate the

relevant energy efficiency compliance requirements for all interior fit-outs within the tenant

leased area, including, but not limited to, §5.2.1, §5.2.2.2, §5.2.2.3, §5.2.3, §6, and §7.2.4.

3.3.2 Additions to Existing Buildings

Where the new connected load demand of the addition plus the existing building exceeds 100

kW or 120 kVA, the additions shall comply with the provisions of §4 through §7. Compliance may

be demonstrated in either of the following ways:

a) The addition shall comply with the applicable requirements, or

b) The addition, together with the entire existing building, shall comply with the

requirements of this Code that shall apply to the entire building, as if it were a new

building.

Exceptions to §3.3.2: When space conditioning is provided by existing systems and equipment,

the existing systems and equipment need not comply with this code. However, any new

equipment installed must comply with specific requirements applicable to that equipment.

3.3.3 Alterations to Existing Buildings

Where the connected load or contract demand of the existing building exceeds 100 kW or 120

kVA respectively, part of a building and its systems that are being altered shall meet the

provisions of §4 through §7.

12

Exception to §3.3.3: When the entire building complies with all of the provisions of §4 through

§7, as if it were a new building.

3.4 Approved Analytical Tools

A building following the whole building performance approach shall show compliance through a

whole building energy simulation software that has been approved by BEE. Compliance to the

daylight requirements of §4.2.3, if calculated through software tools, shall be shown through a

daylighting software approved by BEE. The list of BEE approved software for whole building

energy simulation and daylighting analysis is given in Appendix E.

3.5 Administrative Requirements

Administrative requirements, including but not limited to, permit requirements, enforcement,

interpretations, claims of exemption, approved calculation methods, and rights of appeal are

specified by the authority having jurisdiction.

3.6 Compliance Documents

3.6.1 Compliance Documents

Construction drawings and specifications shall show all pertinent data and features of the

building, equipment, and systems in sufficient detail to permit the authority having jurisdiction

to verify that the building complies with the requirements of this code. Details shall include, but

are not limited to:

a) Building Envelope: opaque construction materials and their thermal properties including

thermal conductivity, specific heat, density along with thickness; fenestration U-factors,

solar heat gain coefficients (SHGC), visible light transmittance (VLT) and building envelope

sealing documentation; overhangs and side fins, building envelope sealing details;

b) Heating, Ventilation, and Air Conditioning: system and equipment types, sizes,

efficiencies, and controls; economizers; variable speed drives; piping insulation; duct

sealing, insulation and location; solar water heating system; requirement for balance

report;

c) Lighting: lighting schedule showing type, number, and wattage of lamps and ballasts;

automatic lighting shutoff, occupancy sensors, and other lighting controls; lamp efficacy

for exterior lamps;

d) Electrical Power: electric schedule showing transformer losses, motor efficiencies, and

power factor correction devices; electric check metering and monitoring system.

e) Renewable energy systems: system peak generation capacity, technical specifications,

solar zone area

13

3.6.2 Supplemental Information

The authority having jurisdiction may require supplemental information necessary to verify

compliance with this code, such as calculations, worksheets, compliance forms, manufacturer’s

literature, or other data.

4. Building Envelope

4.1 General

The building envelope shall comply with the mandatory provisions of §4.2, and the prescriptive

criteria of §4.3.

4.2 Mandatory Requirements

4.2.1 Fenestration

4.2.1.1 U-Factor

U-factors shall be determined for the overall fenestration product (including the sash and frame)

in accordance with ISO-15099 by an accredited independent laboratory, and labeled or certified

by the manufacturer. U-factors for sloped glazing and skylights shall be determined at a slope of

20 degrees above the horizontal. For unrated products, use the default table in Appendix A.

4.2.1.2 Solar Heat Gain Coefficient

SHGC shall be determined for the overall single or multi glazed fenestration product (including

the sash and frame) in accordance with ISO-15099 by an accredited independent laboratory, and

labeled or certified by the manufacturer.

Exceptions to §4.2.1.2:

a) Shading coefficient (SC) of the center of glass alone multiplied by 0.86 is an acceptable

alternate for compliance with the SHGC requirements for the overall fenestration area.

b) Solar heat gain coefficient (SHGC) of the glass alone is an acceptable alternate for

compliance with the SHGC requirements for the overall fenestration product.

4.2.1.3 Visual Light Transmittance

Visual light transmittance (VLT) shall be determined for the fenestration product in accordance

with ISO-15099 by an accredited independent laboratory, and labeled or certified by the

manufacturer. For unrated products, use the default table in Appendix A.

14

4.2.2 Opaque Construction

U-factors shall be calculated for the opaque construction in accordance with ISO-6946. Testing

shall be done in accordance with approved ISO Standard for respective insulation type by an

accredited independent laboratory, and labeled or certified by the manufacturer. For unrated

products, use the default tables in Appendix A.

4.2.3 Daylighting

Above grade floor areas shall meet or exceed the useful daylight illuminance (UDI) area

requirements listed in Table 4-1 for 90% of the potential daylight time in a year. Mixed-use

buildings shall show compliance as per the criteria prescribed in §2.5. Compliance shall be

demonstrated either through daylighting simulation method in §4.2.3.1 or the manual method

in §4.2.3.2. Assembly buildings and other buildings where daylighting will interfere with the

functions or processes of 50% (or more) of the building floor area, are exempted from meeting

the requirements listed in Table 4-1.

Table 4.1: Daylight Requirement

Building Category

Percentage of above grade floor area meeting the UDI

requirement

ECBC ECBC+ SuperECBC

Business,

Educational 40% 50% 60%

No Star Hotel

Star Hotel

Healthcare

30% 40% 50%

Resort 45% 55% 65%

Shopping Complex 10% 15% 20%

Assembly* Exempted

*and other buildings where daylighting will interfere with the functions or processes

of 50% (or more) of the building floor area

15

4.2.3.1 Daylighting Simulation Method

Only BEE approved software shall be used to demonstrate compliance through the daylighting

simulation method. Buildings shall achieve illuminance level between 100 lux and 2,000 lux for

the minimum percentage of floor area prescribed in Table 4-1 for at least 90% of the potential

daylit time. Illuminance levels for all spaces enclosed by permanent internal partitions (opaque,

translucent, or transparent) with height greater or equal to 2 m from the finished floor, shall be

measured as follows:

a) Measurements shall be taken at a work plane height of 0.8 m above the finished floor.

b) The period of analysis shall be fixed for 8 hours per day, anytime between 8:00 AM IST to

5:00 PM IST, resulting in 2,920 hours in total for all building types except for Schools.

Schools shall be analyzed for 7 hours per day, anytime between 7:00 AM IST to 3:00 PM

IST.

c) Available useful daylight across a space shall be measured based on point-by-point grid

values. UDI shall be calculated for at least one point for each square meter of floor area.

d) Fenestration shall be modeled with actual visible light transmission (VLT) as per the details

provided in the material specification sheet.

e) All surrounding natural or man-made daylight obstructions shall be modeled if the

distance between the façade of the building (for which compliance is shown) and

surrounding natural or man-made daylight obstructions is less than or equal to twice the

height of the man-made or natural sunlight obstructers. If the reflectance of the surfaces

is not known, default reflectance of 30% and 0% shall be used for all vertical surfaces of

man-made and natural obstructers respectively.

f) Interior surface reflectance shall be modeled based on the actual material specification.

If material specification is not available, following default values shall be used:

Table 4.2: Default Values for Surface Reflectance

Surface Type Reflectance

Wall or Vertical Internal Surfaces 50%

Ceiling 70%

Floor 20%

Furniture (permanent) 50%

4.2.3.2 Manual Daylighting Compliance Method

This method can be used for demonstrating compliance with daylighting requirements without

simulation. Daylight extent factors (DEF) mentioned in Table 4-3 shall be used for manually

16

calculating percentage of above grade floor area meeting the UDI requirement for 90% of the

potential daylit time in a year.

Table 4.3: Daylight Extent Factors (DEF) for Manually Calculating Daylight Area

Shading Latitude Window

Type

VLT < 0.3 VLT ≥0.3

North South East West North South East West

No

shading

or

PF < 0.4

≥15°N All window

types

2.5 2.0 0.7 0.5 2.8 2.2 1.1 0.7

< 15°N 2.4 2.0 1.3 0.6 1.7 2.2 1.5 0.8

Shading

with PF

≥ 0.4

All

latitudes

All

window

types

without

light shelf

2.8 2.3 1.5 1.1 3.0 2.5 1.8 1.5

Window

with

Light shelf

3.0 2.5 1.8 1.6 3.5 3.0 2.1 1.8

a) To calculate the daylit area:

i. In a direction perpendicular to the fenestration, multiply daylight extent factor (DEF)

by the head height of the fenestration or till an opaque partition higher than head

height of the fenestration, whichever is less.

ii. In the direction parallel to the fenestration, daylit area extends a horizontal dimension

equal to the width of the fenestration plus either 1 meter on each side of the aperture,

or the distance to an opaque partition, or one-half the distance to an adjacent

fenestration, whichever is least.

iii. For skylights, calculate the horizontal dimension in each direction equal to the top

aperture dimension in that direction plus either the floor-to-ceiling height (H) for

skylights, or 1.5 H for monitors, or H or 2H for the sawtooth configuration, or the

distance to the nearest 1 meter or higher opaque partition, or one-half the distance

to an adjacent skylight or vertical glazing, whichever is least.

b) A separate architectural plan shall be prepared with all daylit areas marked on the floor

plans. A summary shall be provided showing compliance as per Table 4-1.

c) Glazed façades, with non-cardinal orientation, shall be categorized under a particular

cardinal direction if its orientation is within ± 45 degrees of that cardinal direction.

d) Any surrounding natural or man-made daylight obstructions shall not be considered in

this method.

17

4.2.4 Building Envelope Sealing

Following areas of the building envelope, of all except naturally ventilated buildings or spaces,

shall be sealed, caulked, gasketed, or weather-stripped:

a) Joints around fenestration, skylights, and door frames

b) Openings between walls and foundations, and between walls and roof, and wall panels

c) Openings at penetrations of utility services through roofs, walls, and floors

d) Site-built fenestration and doors

e) Building assemblies used as ducts or plenums

f) All other openings in the building envelope

g) Exhaust fans shall be fitted with a sealing device such as a self-closing damper

h) Operable fenestration should be constructed to eliminate air leakages from fenestration

frame and shutter frame

18

Note 4-1 Daylight Extent Factor and Useful Daylight Illuminance

Useful Daylight Illuminance (UDI) is defined as the annual

occurrence of daylight between 100 lux to 2,000 lux on a work

plane. This daylight is most useful to occupants, glare free and when

available, eliminates the need for artificial lighting.

Application of UDI and Daylight Extent Factor

A 7,200 m2 four story office building in Delhi is trying to achieve ECBC level

compliance. Building is oriented along east west axis. It has a rectangular layout (60

m x 30 m). Total built up area is distributed evenly across all floors above grade. VLT

of glazing in all orientations is 0.39. Windows have light shelves and external shading

devices with PF ≥ 0.4. Head height of fenestrations is 3.0 m. Length of glazing on the

north and south facing façade is 45 meter and on the east façade, 25 meter.

Table 4-1 lists the minimum daylight area requirements for ECBC Buildings. Row 2 of

the table specifies that all ECBC Buildings other than resorts and shopping malls and,

more than 3 stories above the ground shall have a minimum of 40% of its floor area

exposed to daylight in range of 100 – 2,000 lux for at least 90% of the year.

This office building must then have at least 2,880 m2 (40% of 7,200 m2) of floor area

fulfilling the UDI requirements. Across each floor plate, this area should be then

2,880/ 4 = 720 m2.

Compliance with § 4.2.3 Daylight Requirements can be checked for through two

approaches.

(a) Analysis Through Software

If the whole building performance approach is used, compliance for daylighting

requirements can be checked by analysing the façade and floor plate design in an

analytical software approved by BEE (§ 3.4). The image below, developed through an

approved software, specifies the lux levels and time period of a year during which

lighting levels would be available. With this information, designers can check if the

required minimum area as per § 4.2.3 has the required daylight levels.

19

UDI Analysis with a Daylighting Analysis Software

(b) Manual method

This approach will be suitable for projects adopting the prescriptive compliance

approach. From Table 4-3 determine the daylight extent factor (DEF) for the building.

For a building located in Delhi (latitude > 15 degrees), with glazing of VLT ≥ 0.3,

shading PF ≥0.4 shading and light shelves in windows, DEFs for windows in North =

3.5, in South = 3.0, in East = 2.1, and in West = 1.8. Head height is 3.0 m. There are

no opaque partitions adjacent to the external walls and windows are arranged in a

continuous strip.

Area complying with requirements of should be calculated as follows:

In a direction perpendicular to the fenestration, multiply daylight extent factor (DEF)

by the head height of the fenestration or till an opaque partition higher than head

height of the fenestration, whichever is less. Head height will be considered because

there are no opaque partitions near the external walls.

In the direction parallel to the fenestration, daylit area extends a horizontal

dimension equal to the width of the fenestration plus either 1 meter on each side of

the aperture, or the distance to an opaque partition, or one-half the distance to an

adjacent fenestration, whichever is least. In this case, 1 meter on each side of the

windows at extreme ends of the window strip in each façade will be considered since

there are no opaque partitions adjacent to wall and no opaque area between the

windows.

11:21::

20

Table 4-1-1: Calculation for Daylight Area Meeting UDI Requirement

Orientation DEF

Window/

Fenestration

Width

X m (distance

perpendicular

to

fenestration)

Y m (distance

parallel to

fenestration)

(X x Y m2) Above

ground area

meeting the UDI

requirement for

90% of the time

in a year)

North 3.5 45 m 3.5x3 = 10.5 m (45+2) = 47 m 47 x 10.5 = 493.5

m2

South 3.0 45 m 3.0x3=9.0m (45+2) = 47 m 47 x 9 = 423 m 2

East 2.1 25 m 2.1x3=6.3m (25+2)=27 m 27 x 6.3 = 170 m 2

West 1.8 0 m (service

zone) 0 0 0

Total daylight area per floor meeting UDI requirement during 90% of

the year 1086.5 m2

Total daylight area in the building meeting UDI requirement during

90% of the year

1086.5 x 4 = 4346

m2

4,346 m2 of area will meet the UDI requirements. This is 60.3 % of the total above

grade floor area of 7,200 m2. Thus, the building will comply with UDI requirement.

Daylight area should be indicated in floor plans submitted to code enforcement

authorities. Design guidelines on daylighting stated in NBC (Part 8: Building Services,

Section 1: Lighting and Natural Ventilation, Subsection 4.2: Daylighting) should also

be referred to achieve the ECBC, ECBC+, or SuperECBC requirement.

4.3 Prescriptive Requirements

4.3.1 Roof

Roofs shall comply with the maximum assembly U-factors in Table 4-4 through Table 4-6. The

roof insulation shall be applied externally as part of structural slab and not as a part of false

ceiling.

21

Table 4-4 Roof Assembly U-factor (W/m2.K) Requirements for ECBC Compliant Building

Composite

All building types, except below 0.33

School <10,000 m2 AGA 0.47

Hospitality > 10,000 m2 AGA 0.20

Table 4-5: Roof Assembly U-factor (W/m2.K) Requirements for ECBC+ Compliant Building

Composite

Hospitality

Healthcare

Assembly

0.20

Business

Educational

Shopping Complex

0.26

Table 4-6: Roof Assembly U-factor (W/m2.K) Requirements for SuperECBC Building

Composite

All building types 0.20

4.3.1.1 Vegetated and Cool Roof

All roofs that are not covered by solar photovoltaic, or solar hot water, or any other renewable

energy system, or utilities and services that render it unsuitable for the purpose, shall be either

cool roofs or vegetated roofs.

a) For qualifying as a cool roof, roofs with slopes less than 20° shall have an initial solar

reflectance of no less than 0.60 and an initial emittance no less than 0.90. Solar

reflectance shall be determined in accordance with ASTM E903-96 and emittance shall be

determined in accordance with ASTM E408-71 (RA 1996).

b) For qualifying as a vegetated roof, roof areas shall be covered by living vegetation

4.3.2 Opaque External Wall

Opaque above grade external walls shall comply with the maximum assembly U-factors in Table

4-7 through Table 4-9.

22

Table 4-7 Opaque Assembly Maximum U-factor (W/m2.K) Requirements for an ECBC compliant

Building

Composite

All building types, except below 0.40

No Star Hotel < 10,000 m2 AGA 0.63

Business < 10,000 m2 AGA 0.63

School <10,000 m2 AGA 0.85

Table 4-8: Opaque Assembly Maximum U-factor (W/m2.K) Requirements for ECBC+ Compliant Building

Composite

All building types, except below 0.34

No Star Hotel < 10,000 m2 AGA 0.44

Business < 10,000 m2 AGA 0.44

School < 10,000 m2 AGA 0.63

Table 4-9: Opaque Assembly Maximum U-factor (W/m2.K) Requirements for SuperECBC Building

Composite

All building types 0.22

Exceptions to §4.3.1.1: Opaque external walls of an unconditioned building of No Star Hotel,

Healthcare, and School categories in all climatic zones, except for cold climatic zone, shall have a

maximum assembly U-factor of 0.8 W/m2.K.

4.3.3 Vertical Fenestration

For all climatic zones, vertical fenestration compliance requirements for all three incremental

energy efficiency levels, i.e. ECBC, ECBC+, and SuperECBC, shall comply with the following:

a) Maximum allowable Window Wall Ratio (WWR) is 40% (applicable to buildings showing

compliance using the Prescriptive Method, including Building Envelope Trade-off

Method)

b) Minimum allowable Visual Light Transmittance (VLT) is 0.27

c) Assembly U-factor includes both frame and glass area weighted U-factors

d) Assembly SHGC includes both frame and glass area weighted SHGC

Vertical fenestration shall comply with the maximum Solar Heat Gain Coefficient (SHGC) and U-

factor requirements of Table 4-10. Vertical fenestration on non-cardinal direction, shall be

23

categorized under a particular cardinal direction if its orientation is within ± 22.5° of that cardinal

direction.

Table 4-10: Vertical Fenestration Assembly U-factor and SHGC Requirements for ECBC Buildings

Composite

Maximum U-factor (W/m².K) 3.00

Maximum SHGC Non-North 0.27

Maximum SHGC North

for latitude ≥ 15°N

0.50

Maximum SHGC North

for latitude < 15°N

0.27

See Appendix A for default values of unrated fenestration.

Table 4-11: Vertical Fenestration U-factor and SHGC Requirements for ECBC+ buildings and SuperECBC

buildings

Composite

Maximum U-factor (W/m².K) 2.20

Maximum SHGC Non-North 0.25

Maximum SHGC North for latitude ≥ 15°N 0.50

Maximum SHGC North for latitude < 15°N 0.25

Exceptions to SHGC requirements in Table 4-10 above:

For fenestration with a permanent external projection, including but not limited to overhangs,

side fins, box frame, verandah, balcony, and fixed canopies that provide permanent shading to

the fenestration, the equivalent SHGC for the proposed shaded fenestration may be determined

as less than or equal to the SHGC requirements of Table 4-10. Equivalent SHGC shall be calculated

by following the steps listed below:

a) Projection factor (PF) for the external permanent projection, shall be calculated as per

the applicable shading type listed in §8.2. The range of projection factor for using the SEF

is 0.25≤𝑃𝐹≥1.0. Other shading devices shall be modeled through the Whole Building

Performance Method in §9.

b) A shaded vertical fenestration on a non-cardinal direction, shall be categorized either

under a particular cardinal direction or a primary inter-cardinal direction if its orientation

is within the range of ±22.5 degrees of the cardinal or primary inter-cardinal direction.

c) An equivalent SHGC is calculated by dividing the SHGC of the unshaded fenestration

product with a Shading Equivalent Factor (SEF). SEF shall be determined for each

orientation and shading device type as per Equation 4.1.

24

d) The maximum allowable SHGC is calculated by multiplying the prescriptive SHGC

requirement from Table 4-10 with the SEF.

Equation 4.1: SEF = (C3 x PF3) + (C2 x PF2) + (C1 x PF) + C0

Where,

0.25 ≤ PF ≥ 1.0, and,

C3, C2, C1 and C0 are the coefficient of shading equivalent factor (SEF), listed in Table 4-12 and

Table 4-13.

Table 4-12: Coefficients of Shading Equivalent Factors for Latitudes greater than or equal to 15 ºN

Overhang + Fin Overhang Fin*

Coeffi

cients C3 C2 C1 C0 C3 C2 C1 C0 C3 C2 C1 C0

North -0.03 -0.23 1.09 0.99 -0.02 -0.10 0.43 0.99 0.14 -0.39 0.62 0.99

East 4.49 -6.35 4.70 0.52 -0.05 0.42 0.66 1.02 0.12 -0.35 0.57 0.99

South -4.09 8.14 -0.73 1.32 -1.01 1.91 0.24 1.12 0.53 -1.35 1.48 0.88

West -1.21 3.92 -0.56 1.28 1.52 -2.51 2.30 0.76 0.02 -0.15 0.46 1.01

N-E -0.95 1.50 0.84 1.18 2.19 -3.78 2.62 0.72 -1.64 3.07 -1.05 1.30

S-E 2.67 -4.99 5.68 0.32 -0.93 1.37 0.76 0.99 0.68 -1.47 1.35 0.88

S-W -0.50 1.36 2.45 0.73 -3.23 5.61 -1.56 1.32 1.86 -3.81 2.71 0.69

N-W -6.85 11.7 -3.92 1.89 -0.22 0.19 0.74 1.01 -2.02 2.63 -0.18 1.14

* Coefficients are for side fins on both sides of fenestration. For side fins on only one side, divide

the coefficients mentioned in this table by 2.

Table 4-12: Coefficients of Shading Equivalent Factors for Latitudes less than 15 ºN

Overhang + Fin Overhang Fin*

Coeffi

cients

C3 C2 C1 C0 C3 C2 C1 C0 C3 C2 C1 C0

North -0.09 -0.29 1.41 1.05 -0.05 -0.10 0.54 1.02 0.10 -0.40 0.77 1.01

East -0.55 0.89 1.28 0.97 -0.62 0.88 0.51 1.02 0.15 -0.41 0.56 0.98

South -4.09 6.98 -1.92 1.41 -2.49 4.89 -2.45 1.43 1.57 -3.35 2.62 0.59

West -1.99 3.82 -0.19 1.18 -0.16 0.10 0.89 0.97 0.06 -0.22 0.48 0.99

N-E -1.73 3.45 -0.02 1.23 0.10 -0.55 1.15 0.92 -0.26 0.30 0.48 1.02

S-E -2.06 4.32 -0.96 1.41 -0.60 0.90 0.37 0.94 0.83 -1.42 1.22 0.92

S-W -2.06 4.48 -1.13 1.40 -0.39 0.50 0.60 0.87 1.56 -3.17 2.41 0.73

N-W -0.53 0.72 1.79 0.93 0.10 -0.38 0.96 0.96 0.24 -0.57 0.90 0.97

* Coefficients are for side fins on both sides of fenestration. For side fins on only one side, divide

the coefficients mentioned in this table by 2.

25

e) The maximum allowable SHGC of glazing shall be 0.9.

f) Any surrounding man-made or natural sunlight obstructers shall be considered as a

permanent shading of PF equal to 0.4 if

i. the distance between the vertical fenestration of the building, for which compliance

is shown, and surrounding man-made or natural sunlight obstructers is less than or

equal to twice the height of the surrounding man-made or natural sunlight

obstructers; and

ii. the surrounding man-made or natural sunlight obstructers shade the façade for at

least 80% of the total time that the façade is exposed to direct sun light on a summer

solstice. Compliance shall be shown using a sun path diagram for summer solstice

super-imposed on the building plan.

g) Vertical fenestration, located such that its bottom is more than 2.2 m above the level of

the floor, is exempt from the SHGC requirements in Table 4-10, if the following conditions

are complied with:

i. The Total Effective Aperture for the elevation is less than 0.25, including all

fenestration areas more than 1.0 meter above the floor level; and,

ii. An interior light shelf is provided at the bottom of this fenestration area, with a

projection factor on interior side not less than:

a. for E-W, SE, SW, NE, and NW orientations

b. 0.5 for S orientation, and

c. 0.35 for N orientation when latitude is less than 15°N.

26

Note 4-2 Equivalent SHGC and Projection Factor

A 5,400 m2 two story office building in Delhi is trying to achieve ECBC level

compliance. It has a rectangular layout (90 m x 30 m) with floor to floor height of 4.0

m and floor area is evenly distributed over the two floors. Windows are either east

or west facing and equally distributed on the two floors. The windows are all 1.85 m

in length and 2.165 m in height with an overhang of 0.85 m. Cill level is 1.385 m above

floor level. The overall glazing area is 384 m2. SHGC of the glazing in the East/ West

Fenestration is 0.30; area wighted U-Factor is 3.0 W/m2.K. VLT of the glazing in all

orientation is 0.5. Will the vertical fenestration comply with the ECBC from the

prescriptive approach?

Solution:

Table 4-10 and §4.3.3 lists the U-factor, SHGC and VLT requirements for vertical

fenestration for ECBC compliant buildings. The building is located in Delhi (Latitude:

28070’ N, Longitude: 77010’E), which falls under the composite climate, as per

Appendix B, Table 12.1. To fulfil prescriptive requirements, Window to Wall ratio ≤

40%, SHGC ≤ 0.27, U-factor ≤ 3.0 W/m2.K, and VLT ≥ 0.27.

Total Floor area = 5400 m2

Total wall area = 2 x (2x ((90m x 4m) + (30m x 4m))) = 1,920 m2

Total Fenestration area = 384 m2

Window to Wall Ratio (WWR) = 384/1,920 = 20%

As per the calculations, the building has a WWR of 20%, thus complying with the

requirement for WWR. The U-factor is also less than 3.0 W/m2.K. Similarly the VLT is

0.45, which is greater than the minimum specified value of 0.27, thus complying with

the u-factor and VLT requirement.

Equivalent SHGC Calculation

As the windows have an overhang, this case will fall under the exception, and the

equivalent SHGC value will be calculated as per Equation 4.1, i.e.

SEF = (C3 x PF3) + (C2 x PF2) + (C1 x PF) + C0

Where,

PF = Projection Factor, and,

27

C0, C1, C2, C3 are coefficients of Shading Equivalent Factors (SEF), listed in Table 4-12

and Table 4-13.

First, calculate Projection Factor (PF) for each orientation. Shading Equivalent Factor

coefficients should be from Table 4-12, as the latitude is greater than 15ºN.

SEFEast = (C3 x PF3) + (C2 x PF2) + (C1 x PF) + C0

SEFEast = (-0.05 x (0.345)3) + (0.42 x (0.345)2) + (0.66 x 0.345) + 1.02

SEFEast = 1.296

Therefore, equivalent SHGCEast = 0.3 ÷ 1.296 = 0.23 Hence the vertical fenestration

on the east façade will comply as per prescriptive approach, as the equivalent SHGC

is less than maximum allowed.

Similarly, for the west facade:

SEFWest = (C3 x PF3) + (C2 x PF2) + (C1 x PF) + C0

SEFWest = (1.52 x 0.3453) + (-2.51 x 0.3452) + (2.30 x 0.345) + 0.76

SEFWest = 1.317

Therefore equivalent SHGCWest = 0.3 ÷ 1.317 = 0.23, hence the vertical fenestration

on the west façade will comply using the prescriptive approach, as the equivalent

SHGC is less than maximum allowed.

PF:HIV pr 0.345

28

4.3.3.1 U-factor Exception

Vertical fenestration on all unconditioned buildings or unconditioned spaces may have a

maximum U-factor of 5 W/m2.K provided they comply with all conditions mentioned in Table 4-

14.

Table 4-14: U-factor (W/m2.K) Exemption Requirements for Shaded Building

Building Type Climate

zone

Orientation Maximum

Effective

SHGC

Minimum

VLT

PF

Unconditioned

buildings or

unconditioned

spaces

All except

cold

Non-North for all

latitudes and

North for latitude <15°N

0.27 0.27 ≥ 0.40

North for latitude >15°N 0.27 0.27 0.0

4.3.4 Skylights

Skylights shall comply with the maximum U-factor and maximum SHGC requirements of Table 4-

15. Skylight roof ratio (SRR), defined as the ratio of the total skylight area of the roof, measured

to the outside of the frame, to the gross exterior roof area, is limited to a maximum of 5 % for

ECBC Building, ECBC+ Building, and SuperECBC Building, when using the Prescriptive Method for

compliance.

Table 4-15: Skylight U-factor and SHGC Requirements (U-factor in W/m2.K)

Climate Maximum U-factor Maximum SHGC

All climatic zones 4.25 0.35

Exception to §4.3.4 Skylights in temporary roof coverings or awnings over unconditioned spaces.

4.3.5 Building Envelope Trade-Off Method

The building envelope complies with the code if the Envelope Performance Factor (EPF) of the

Proposed Building is less than the EPF of the Standard Building, where the Standard Building

exactly complies with the prescriptive requirements of building envelope. This method shall not

be used for buildings with WWR>40%. Trade-off is not permitted for skylights. Skylights shall

meet requirements of 4.3.4. The envelope performance factor shall be calculated using the

following equations.

29

Equation 4.2: EPF Total = EPF Roof + EPF Wall + EPF Fenest

𝐸𝑃𝐹𝑅𝑜𝑜𝑓 = 𝑐𝑅𝑜𝑜𝑓 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

𝐸𝑃𝐹𝑊𝑎𝑙𝑙 = 𝑐𝑊𝑎𝑙𝑙,𝑚𝑎𝑠𝑠 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

+ 𝑐𝑊𝑎𝑙𝑙,𝑂𝑡ℎ𝑒𝑟 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡 = 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝑁𝑜𝑟𝑡ℎ ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝑁𝑜𝑟𝑡ℎ ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 + 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝑆𝑜𝑢𝑡ℎ ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝑆𝑜𝑢𝑡ℎ ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 + 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝐸𝑎𝑠𝑡 ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝐸𝑎𝑠𝑡 ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 + 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝑊𝑒𝑠𝑡 ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝑊𝑒𝑠𝑡 ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊

𝑛

𝑊=1

EPFRoof = Envelope performance factor for roofs. Other subscripts include walls and

fenestration.

As, Aw = The area of a specific envelope component referenced by the subscript "s" or for

windows the subscript "w".

SHGCw = The solar heat gain coefficient for windows (w).

SEFw = A multiplier for the window SHGC that depends on the projection factor of an

overhang or side fin.

Us = The U-factor for the envelope component referenced by the subscript "s".

cRoof = A coefficient for the "Roof" class of construction.

Cwall = A coefficient for the "Wall"

C1 Fenes = A coefficient for the "Fenestration U-factor"

C2 Fenes = A coefficient for the "Fenestration SHGC"

Values of "c" are taken from Table 4-16 through Table 4-20 for each class of construction.

30

Table 4-16: Envelope Performance Factor Coefficients – Composite Climate

Daytime Business, Educational,

Shopping Complex

24-hour Business, Hospitality,

Health Care, Assembly

C factor U-factor C factor SHGC C factor U-factor C factor SHGC

Mass Walls 5.39 - 7.91 -

Curtain Walls, Other 7.83 - 10.32 -

Roofs 14.93 - 17.88 -

North Windows 0.33 81.08 -2.83 119.14

South Windows -2.30 221.07 -3.54 294.00

East Windows -1.17 182.64 -3.23 255.91

West Windows -0.74 182.11 -2.85 252.61

4.3.6 Standard Building EPF Calculation

EPF of the Standard Building shall be calculated as follows:

a) The Standard Building shall have the same building floor area, gross wall area and gross

roof area as the Proposed Building. If the building has both 24-hour and daytime

occupancies, the distribution between these shall be the same as the Proposed Design.

b) The U-factor of each envelope component shall be equal to the criteria from §4 for each

class of construction.

c) The SHGC of each window shall be equal to the criteria from §4.3.3.

31

Note 4-3 Building Envelope Trade-off Method

Application of Building Envelope Trade-off method

A 1,000 m2 single story daytime use office building in Ahmedabad is trying to achieve

ECBC level compliance. Each side has a band of windows, without shading. The

materials for the envelope have already been selected, prior to opting for ECBC

compliance. Their thermal properties are: roof assembly U-value= 0.4 W/m².K, external

wall assembly U-value = 0.25 W/m².K, glazing SHGC = 0.25, VLT = 0.27, area weighted

U-value for glazing = 1.8 W/m².K. External walls are mass wall construction type.

Dimensions of the building envelope are as follows:

According to Table 11-1, Appendix B, Ahmedabad falls under the hot and dry climate

zone. To prove compliance through the prescriptive approach, U values, and SHGC must

comply with requirements listed in Table 4-4, Table 4-7, Table 4-10 and VLT and window

to wall ratio with requirements in § 4.3.3 for a 24-hour use building in the hot and dry

climate zone. The table below lists thermal properties of the building envelope

components and the corresponding prescriptive requirements for ECBC complaint

buildings.

Table 4-3-1 Prescriptive Requirements and Proposed Thermal Properties

Prescriptive U-factor

(W/m2.K)

Proposed U-factor

(W/m2.K)

Area

(m2)

Wall 1-North,

South

=< 0.63 0.25 90

Wall 2-East,

West

=< 0.63 0.25 144

Roof =< 0.33 0.4 1000

32

U-factor SHGC VLT U-factor SHGC VLT

Window - South =< 3.0 =< 0.27 =< 0.27 1.8 0.25 0.27 30

Window - North =< 3.0 =< 0.5 =< 0.27 1.8 0.25 0.27 30

Window - East =< 3.0 =< 0.27 =< 0.27 1.8 0.25 0.27 48

Window - West =< 3.3 =< 0.27 =< 0.27 1.8 0.25 0.27 48

U-value of the roof of the proposed building, at 0.4 W/m².K does not fulfil prescriptive

requirements. Similarly, §4.3.3 requires the WWR to be less than 40%. This condition is

fulfilled in the proposed buildings as can be seen in the calculations below.

Total Fenestration Area North, South = 2 x (25 m x 1.2 m) = 60 m2

Wall Area North, South = 2 x (25 m x 3 m) = 150 m2

Total Fenestration Area East, West = 2 x (40 m x 1.2 m) = 96 m2

Total Wall Area East, West = 2 x (40 m x 3 m) = 240 m2

Total Fenestration Area = 156 m2, Total Wall Area = 390 m2

WWR = 156/390= 0.4.

Hence, this building will not be compliant if the prescriptive approach is followed.

Compliance through Building Envelope Trade-off method

Envelope performance factor (EPF) for the Standard Building and Proposed Building

must be compared. As per the Building Envelope Trade-off method, the envelope

performance factor (EPF) shall be calculated using the following equations:

Equation 11.1 EPF Total = EPF Roof + EPF Wall + EPF Fenest

Where,

𝐸𝑃𝐹𝑅𝑜𝑜𝑓 = 𝑐𝑅𝑜𝑜𝑓 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

𝐸𝑃𝐹𝑊𝑎𝑙𝑙 = 𝑐𝑊𝑎𝑙𝑙,𝑚𝑎𝑠𝑠 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

+ 𝑐𝑊𝑎𝑙𝑙,𝑂𝑡ℎ𝑒𝑟 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

33

𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡 = 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝑁𝑜𝑟𝑡ℎ ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝑁𝑜𝑟𝑡ℎ ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 + 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝑆𝑜𝑢𝑡ℎ ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝑆𝑜𝑢𝑡ℎ ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 + 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝐸𝑎𝑠𝑡 ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝐸𝑎𝑠𝑡 ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 + 𝑐1𝐹𝑒𝑛𝑒𝑠𝑡,𝑊𝑒𝑠𝑡 ∑ 𝑈𝑊𝐴𝑊

𝑛

𝑊=1

𝑛

𝑊=1

+ 𝑐2 𝐹𝑒𝑛𝑒𝑠𝑡,𝑊𝑒𝑠𝑡 ∑ 𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊

𝑛

𝑊=1

Standard Building EPF will be derived from U-factors, SHGCs and VLTs of walls, roofs

and fenestration from Table 4-4, Table 4-7, Table 4-10 and § 4.3.3 for a 24-hour use

building in the hot and dry climate zone. Values of C are from 24-hour Office building

in hot and dry climatic zone for each class of construction from Table 4-16. Since There

is no shading for the windows, Mw will not be considered.

Step 1: Calculation of EPF Proposed Building from actual envelope properties

𝐸𝑃𝐹𝑅𝑜𝑜𝑓,𝐴𝑐𝑡𝑢𝑎𝑙 = 𝑐𝑅𝑜𝑜𝑓 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

= 14.82 x 0.40 x 1,000 = 5,928

𝐸𝑃𝐹𝑊𝑎𝑙𝑙,𝐴𝑐𝑡𝑢𝑎𝑙 = 𝑐𝑊𝑎𝑙𝑙,𝑚𝑎𝑠𝑠 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

+ 𝑐𝑊𝑎𝑙𝑙,𝑂𝑡ℎ𝑒𝑟 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

= (6.4 x 0.25 x 90) + (6.4 x 0.25 x 144) = 374.4

𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡 = 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝑁𝑜𝑟𝑡ℎ + 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝑆𝑜𝑢𝑡ℎ + 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝐸𝑎𝑠𝑡 + 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝑊𝑒𝑠𝑡

𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡 = 𝐶1 𝐹𝑒𝑛𝑒𝑠𝑡 ∑ 𝑈𝑊𝐴𝑊 𝑛

𝑊=1 + 𝐶2 𝐹𝑒𝑛𝑒𝑠𝑡 ∑

𝑆𝐻𝐺𝐶𝑊 𝑆𝐸𝐹𝑊

𝐴𝑊 𝑛

𝑊=1

EPF Fenest, North = -0.37 x 1.8 x 30 + 101.66 x 0.25 x 30 = -19.98 + 762.45 = 742.47

EPF Fenest, South = -1.35 x 1.8 x 30 + 252.90 x 0.25 x 30 = -72.9 + 1,896.75 = 1,823.85

EPF Fenest, East = -0.85 x 1.8 x 48 + 219.91 x 0.25 x 48 = - 73.44 + 2,638.9 = 2, 565.46

EPF Fenest, West = -0.80 x 1.8 x 48 + 226.57 x 0.25 x 48 = -69.12 + 2,718.8 = 2,649.7

Therefore,

EPF Fenest =7,781.5

34

EPF Proposed = 5,928 + 374.4 + 7,781.5 = 14,083.9

Step 2: Calculating EPF Standard Building from prescriptive envelope requirements

𝐸𝑃𝐹𝑟𝑜𝑜𝑓,𝐴𝑐𝑡𝑢𝑎𝑙 = 𝑐𝑅𝑜𝑜𝑓 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

= 14.82 x 0.33 x 1000 = 4,890.6

𝐸𝑃𝐹𝑊𝑎𝑙𝑙,𝐴𝑐𝑡𝑢𝑎𝑙 = 𝑐𝑊𝑎𝑙𝑙,𝑚𝑎𝑠𝑠 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

+ 𝑐𝑊𝑎𝑙𝑙,𝑂𝑡ℎ𝑒𝑟 ∑ 𝑈𝑆𝐴𝑆

𝑛

𝑆=1

= (6.4 x 0.63 x 90) + (6.4 x 0.63 x 144) = 362.88 + 580.6 = 943.5

𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡 = 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝑁𝑜𝑟𝑡ℎ + 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝑆𝑜𝑢𝑡ℎ + 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝐸𝑎𝑠𝑡 + 𝐸𝑃𝐹𝐹𝑒𝑛𝑒𝑠𝑡,𝑊𝑒𝑠𝑡

Now,

EPF Fenest, North = -0.37 x 3.3 x 30 + 101.66 x 0.5 x 30 = - 36.63 + 1,524.9 = 1,488.3

EPF Fenest, South = -1.35 x 3.3 x 30 + 252.9 x 0.27 x 30 = -133.7 + 2.048.5 = 1,914.8

EPF Fenest, East = -0.85 x 3.3 x 48 + 219.91 x 0.27 x 48 = -134.64 + 2,850 = 2,715.4

EPF Fenest, West = -0.8 x 3.3 x 48 + 226.57 x 0.27 x 48 = -126.7 + 2,936 = 2,809.6

Therefore,

EPF Fenest =8,928

EPF Baseline = 4,890.6 + 943.5 + 8,928= 14,762.2

Since EPF Baseline > EPF Proposed, therefore the building is compliant with ECBC building

envelope requirements.

35

5. Comfort Systems and Controls

5.1 General

All heating, ventilation, air conditioning equipment and systems, and their controls shall comply

with the mandatory provisions of §5.2 and the prescriptive criteria of §5.3 for the respective

building energy efficiency level.

All service water heating equipment and systems shall comply with the mandatory provisions of

§5.2.

5.2 Mandatory Requirements

5.2.1 Ventilation

a) All habitable spaces shall be ventilated with outdoor air in accordance with the

requirements of §5.2.1 and guidelines specified in the National Building Code 2016 (Part

8: Building Services, Section 1: Lighting and Natural Ventilation, Subsection 5: Ventilation).

b) Ventilated spaces shall be provided with outdoor air using one of the following:

i. Natural ventilation

ii. Mechanical ventilation

iii. Mixed mode ventilation

5.2.1.1 Natural Ventilation Design Requirements

Naturally ventilated buildings or spaces in a mixed-mode ventilated buildings shall:

a) Comply with guidelines provided for natural ventilation in NBC.

b) Have minimum BEE 3-star rated ceiling fans, if provided with ceiling fans.

c) Have exhaust fans complying with minimum efficiency requirements of fans in §5.3, if

provided.

5.2.1.2 Mechanical Ventilation Air Quantity Design Requirements

Buildings that are ventilated using a mechanical ventilation system or spaces in mixed-mode

ventilated buildings that are ventilated with a mechanical system, either completely or in

conjunction with natural ventilation systems, shall:

a) Install mechanical systems that provide outdoor air change rate as per NBC.

b) Have a ventilation system controlled by CO sensors for basement carpark spaces with

total car park space greater than or equal to 600 m2.

36

Note 5-1 Adaptive Thermal Comfort

Human body has the ability to adapt to environmental conditions and

become accustomed to them over time. People accustomed to the

variability of environmental parameters in non-air-conditioned

buildings can live and work through a larger temperature range

without experiencing thermal discomfort. This logic informs the

adaptive thermal comfort model for buildings. Adaptive comfort models offer an

opportunity to reduce energy use as buildings can be operated at more moderate

temperatures. Energy used to maintain stringent comfort conditions through

mechanical equipment can thus be avoided. Operative temperatures for the model

can be calculated using the formulae below.

Naturally Ventilated Buildings

Indoor Operative Temperature = (0.54 x outdoor temperature) + 12.83

Where, indoor operative temperature (°C) is neutral temperature, & outdoor

temperature is the 30-day outdoor running mean air temperature (°C).

The 90 % acceptability range for the India specific adaptive models for naturally

ventilated buildings is ± 2.38 °C.

For example, Indoor Operative Temperature for a naturally ventilated building in Delhi

= (0.54 x 33.0) + 12.83 = 30.68 °C

Mixed Mode Buildings

Indoor Operative Temperature = (0.28 x outdoor temperature) + 17.87

Where indoor operative temperature (°C) is neutral temperature & outdoor

temperature is the 30-day outdoor running mean air temperature (°C).

The 90% acceptability range for the India specific adaptive models for mixed-mode

buildings is ± 3.46°C.

For example, Indoor Operative Temperature for a mixed mode building in Delhi

= (0.28 x 33.0) + 17.87 = 27.1 °C

Air Conditioned Buildings

Indoor Operative Temperature = (0.078 x outdoor temperature) + 23.25

Where indoor operative temperature (°C) is neutral temperature & outdoor

temperature is the 30-day outdoor running mean air temperature (°C).

The 90% acceptability range for the adaptive models for conditioned buildings is

±1.5°C.

For example, Indoor Operative Temperature for an air-conditioned building in Delhi

= (0.078 x 33.0) + 23.25

= 25.8 °C

37

5.2.1.3 Demand Control Ventilation

Mechanical ventilation systems shall have demand control ventilation if they provide outdoor air

greater than 1,500 liters per second, to a space greater than 50 m2, with occupant density

exceeding 40 people per 100 m2 of the space, and are served by one or more of the following

systems:

a) An air side economizer

b) Automatic outdoor modulating control of the outdoor air damper

Exceptions to § 5.2.1.3: Following shall be exempt from installing demand control ventilation

systems:

a) Classrooms in Schools, call centers category under Business

b) Spaces that have processes or operations that generate dust, fumes, mists, vapors, or

gases and are provided with exhaust ventilation, such as indoor operation of internal

combustion engines or areas designated for unvented food service preparation, or beauty

salons

c) Systems with exhaust air energy recovering system

5.2.2 Minimum Space Conditioning Equipment Efficiencies

5.2.2.1 Chillers

a) Chillers shall meet or exceed the minimum efficiency requirements presented in Table 5-

1 through Table 5-2 under ANSI/ AHRI 550/ 590 conditions.

b) The application of air-cooled chiller is allowed in all buildings with cooling load less than

530 kW. For buildings with cooling load equal to or greater than 530 kW, the number of

air-cooled chiller shall be restricted to 33% of the total installed chilled water capacity

unless the authority having jurisdiction mandates the application of air cooled chillers.

c) Minimum efficiency requirements under BEE Standards and Labeling Program for chillers

shall take precedence over the minimum requirements presented in Table 5-1 through

Table 5-2.

d) To show compliance to ECBC, minimum requirement of both COP and IPLV requirement

of ECBC Building shall be met. To show compliance with ECBC+ Building and SuperECBC

Building, minimum requirement of either COP or IPLV of respective efficiency level shall

be met.

38

Table 5-1: Minimum Energy Efficiency Requirements for water cooled Chillers

Chiller Capacity (kWr) ECBC Building ECBC+ Building SuperECBC Building

COP IPLV COP IPLV COP IPLV

<260 4.7 5.8 5.2 6.9 5.8 7.1

≥260 & <530 4.9 5.9 5.8 7.1 6.0 7.9

≥530 & <1,050 5.4 6.5 5.8 7.5 6.3 8.4

≥1,050 & <1,580 5.8 6.8 6.2 8.1 6.5 8.8

≥1,580 6.3 7.0 6.5 8.9 6.7 9.1

Table 5-2: Minimum Energy Efficiency Requirements for air cooled Chillers

Chiller Capacity (kWr) ECBC Building ECBC+ Building SuperECBC Building

COP IPLV COP IPLV COP / IPLV

<260 2.8 3.5 3.0 4.0 NA

≥260 3.0 3.7 3.2 5.0 NA

5.2.2.2 Unitary, Split, Packaged Air-Conditioners

Unitary air-conditioners shall meet or exceed the efficiency requirements given in Table 5-3

through Table 5-5. Window and split air conditioners shall be certified under BEE’s Star Labeling

Program. EER shall be as per IS 8148 for all unitary, split, packaged air conditioners greater than

10 kWr.

Table 5-3: Minimum Requirements for Unitary, Split, Packaged Air Conditioners in ECBC Building

Cooling Capacity (kWr) Water Cooled Air Cooled

≤ 10.5 NA BEE 3 Star

> 10.5 3.3 EER 2.8 EER

Table 5-4: Minimum Requirements for Unitary, Split, Packaged Air Conditioners in ECBC+ Building

Cooling Capacity (kWr) Water Cooled Air Cooled

≤ 10.5 NA BEE 4 Star

> 10.5 3.7 EER 3.2 EER

Table 5-5: Minimum Requirements for Unitary, Split, Packaged Air Conditioners in SuperECBC Building

Cooling Capacity (kWr) Water Cooled Air Cooled

≤ 10.5 NA BEE 5 Star

>10.5 3.9 EER 3.4 EER

39

5.2.2.3 Variable Refrigerant Flow

Variable Refrigerant Flow (VRF) systems shall meet or exceed the efficiency requirements

specified in Table 5-6 as per the ANSI/ AHRI Standard 1230 while the Indian Standard on VRF is

being developed. BEE Standards and Labeling requirements for VRF shall take precedence over

the current minimum requirement.

Table 5-6: Minimum Efficiency Requirements for VRF Air conditioners for ECBC Building*

For Heating or cooling or both

Type Size category

(kWr)

EER IEER

VRF Air Conditioners,

Air cooled

< 40 3.28 4.36

>= 40 and < 70 3.26 4.34

>= 70 3.02 4.07

* The revised EER and IEER values as per Indian Standard for VRF corresponding to

values in this table will supersede as and when the revised standards are published.

5.2.2.4 Air Conditioning and Condensing Units Serving Computer Rooms

Air conditioning and condensing units serving computer rooms shall meet or exceed the energy

efficiency requirements listed in Table 5-7.

Table 5-7: Minimum Efficiency Requirements for Computer Room Air Conditioners

Equipment type Net Sensible

Cooling Capacity a

Minimum SCOP-127 b

Downflow Upflow

All types of computer

room ACs

Air/ Water/ Glycol

All capacity 2.5 2.5

a. Net Sensible cooling capacity = Total gross cooling capacity - latent cooling capacity – Fan

power

b. Sensible Coefficient of Performance (SCOP-127): A ratio calculated by dividing the net

sensible cooling capacity in watts by the total power input in watts (excluding re-heater

and dehumidifier) at conditions defined in ASHRAE Standard 127-2012 Method of Testing

for Rating Computer and Data Processing Room Unitary Air Conditioners)

5.2.3 Controls

To comply with the Code, buildings shall meet the requirements of §5.2.3.1 through §5.2.3.5.

40

5.2.3.1 Timeclock

Mechanical cooling and heating systems in Universities and Training Institutions of all sizes and

all Shopping Complexes with built up area greater than 20,000 m2 shall be controlled by

timeclocks that:

a) Can start and stop the system under different schedules for three different day-types per

week,

b) Are capable of retaining programming and time setting during loss of power for a period

of at least 10 hours, and

c) Include an accessible manual override that allows temporary operation of the system for

up to 2 hours.

Exceptions to §5.2.3.1:

a) Cooling systems less than 17.5 kWr

b) Heating systems less than 5.0 kWr

c) Unitary systems of all capacities

5.2.3.2 Temperature Controls

Mechanical heating and cooling equipment in all buildings shall be installed with controls to

manage the temperature inside the conditioned zones. Each floor or a building block shall be

installed with at least one control to manage the temperature. These controls should meet the

following requirements:

a) Where a unit provides both heating and cooling, controls shall be capable of providing a

temperature dead band of 3.0°C within which the supply of heating and cooling energy

to the zone is shut off or reduced to a minimum.

b) Where separate heating and cooling equipment serve the same temperature zone,

temperature controls shall be interlocked to prevent simultaneous heating and cooling.

c) Separate thermostat control shall be installed in each

i. guest room of Resort and Star Hotel,

ii. room less than 30 m2 in Business,

iii. air-conditioned class room, lecture room, and computer room of Educational,

iv. in-patient and out-patient room of Healthcare

5.2.3.3 Occupancy Controls

Occupancy controls shall be installed to de-energize or to throttle to minimum the ventilation

and/or air conditioning systems when there are no occupants in:

a) Each guest room in a Resort and Star Hotel

b) Each public toilet in a Star Hotel or Business with built up area more than 20,000 m2

41

c) Each conference and meeting room in a Star Hotel or Business

d) Each room of size more than 30 m2 in Educational buildings

5.2.3.4 Fan Controls

Cooling towers in buildings with built up area greater than 20,000 m2, shall have fan controls

based on wet bulb logic, with either:

a) Two speed motors, pony motors, or variable speed drives controlling the fans, or

b) Controls capable of reducing the fan speed to at least two third of installed fan power

5.2.3.5 Dampers

All air supply and exhaust equipment, having a Variable Frequency Drive (VFD), shall have

dampers that automatically close upon:

a) Fan shutdown, or,

b) When spaces served are not in use

c) Backdraft gravity damper is acceptable in the system with design outdoor air of the

system is less than 150 liters per second in all climatic zones except cold climate, provided

backdraft dampers for ventilation air intakes are protected from direct exposure to wind.

d) Dampers are not required in ventilation or exhaust systems serving naturally conditioned

spaces.

e) Dampers are not required in exhaust systems serving kitchen exhaust hoods.

5.2.4 Additional Controls for ECBC+ and SuperECBC Buildings

ECBC+ building shall comply with requirements of § 5.2.4 in addition to complying with

requirements of §5.2.3.

5.2.4.1 Centralized Demand Shed Controls

ECBC+ and SuperECBC Buildings with built up area greater than 20,000 m2 shall have a building

management system. All mechanical cooling and heating systems in ECBC+ and SuperECBC

Buildings with any programmable logic controller (PLC) to the zone level shall have the following

control capabilities to manage centralized demand shed in noncritical zones:

a) Automatic demand shed controls that can implement a centralized demand shed in non-

critical zones during the demand response period on a demand response signal.

b) Controls that can remotely decrease or increase the operating temperature set points by

four degrees or more in all noncritical zones on signal from a centralized control point

c) Controls that can provide an adjustable rate of change for the temperature setup and

reset

The centralized demand shed controls shall have additional capabilities to

42

a) Be disabled by facility operators

b) Be manually controlled from a central point by facility operators to manage heating and

cooling set points

5.2.4.2 Supply Air Temperature Reset

Multi zone mechanical cooling and heating systems in ECBC+ and SuperECBC Buildings shall have

controls that automatically reset the supply-air temperature in response to building loads or to

outdoor air temperature. Controls shall reset the supply air temperature to at least 25% of the

difference between the design supply air temperature and the design room air temperature.

Exception to § 5.2.4.2 : ECBC+ and SuperECBC Buildings in warm humid climate zone.

5.2.4.3 Chilled Water Temperature Reset

Chilled water systems with a design capacity exceeding 350 kWr supplying chilled water to

comfort conditioning systems in ECBC+ and SuperECBC Buildings shall have controls that

automatically reset supply water temperatures by representative building loads (including return

water temperature) or by outdoor air temperature.

Exceptions to § 5.2.4.3: Controls to automatically reset chilled water temperature shall not be

required where the supply temperature reset controls causes improper operation of equipment.

5.2.5 Additional Controls for SuperECBC Buildings

SuperECBC Buildings shall comply with requirements of § 5.2.5 in addition to complying with

requirements of § 5.2.3 and § 5.2.4.

5.2.5.1 Variable Air Volume Fan Control

Fans in Variable Air Volume (VAV) systems in SuperECBC Buildings shall have controls or devices

that will result in fan motor demand of no more than 30% of their design wattage at 50% of

design airflow based on manufacturer’s certified fan data.

5.2.6 Piping and Ductwork

5.2.6.1 Piping Insulation

Piping for heating, space conditioning, and service hot water systems shall meet the insulation

requirements listed in Table 5-8 through Table 5-10. Insulation exposed to weather shall be

protected by aluminum sheet metal, painted canvas, or plastic cover. Cellular foam insulation

shall be protected as above, or be painted with water retardant paint.

Exceptions to § 5.2.6.1:

43

a) Reduction in insulation R value by 0.2 (compared to values in Table 5-8, Table 5-9 and

Table 5-10) to a minimum insulation level of R-0.4 shall be permitted for any pipe located

in partition within a conditioned space or buried.

b) Insulation R value shall be increased by 0.2 over and above the requirement stated in

Table 5-8 through Table 5-10 for any pipe located in a partition outside a building with

direct exposure to weather.

c) Reduction in insulation R value by 0.2 (compared to values in Table 5-8, Table 5-9 and

Table 5-10) to a minimum insulation level of R-0.4 shall be permitted for buildings in

Temperate climate zone.

Table 5-8: Insulation Requirements for Pipes in ECBC Building

Operating Temperature (°C)

Pipe size (mm)

<25 >=40

Insulation R value (m2.K/W)

Heating System

94°C to 121°C 0.9 1.2

60°C to 94°C 0.7 0.7

40°C to 60°C 0.4 0.7

Cooling System

4.5°C to 15°C 0.4 0.7

< 4.5°C 0.9 1.2

Refrigerant Piping (Split systems)

4.5°C to 15°C 0.4 0.7

< 4.5°C 0.9 1.2

Table 5-9: Insulation Requirements for Pipes in ECBC+ Building

Operating Temperature (°C)

Pipe size (mm)

< 40 >= 40

Insulation R value (m2.K/W)

Heating System

94°C to 121°C 1.1 1.3

60°C to 94°C 0.8 0.8

40°C to 60°C 0.5 0.9

Cooling System

4.5°C to 15°C 0.5 0.9

< 4.5°C 1.1 1.3

Refrigerant Piping (Split systems)

4.5°C to 15°C 0.5 0.9

< 4.5°C 1.1 1.3

Table 5-10: Insulation Requirements for Pipes in SuperECBC Building

Pipe size (mm)

44

Operating Temperature (°C)

< 40 >= 40

Insulation R value (m2.K/W)

Heating System

94°C to 121°C 1.5 1.5

60°C to 94°C 1.0 1.3

40°C to 60°C 0.7 1.1

Cooling System

4.5°C to 15°C 0.7 1.2

< 4.5°C 1.5 1.5

Refrigerant Piping (Split systems)

4.5°C to 15°C 0.4 0.7

< 4.5°C 1.5 1.5

5.2.6.2 Ductwork and Plenum Insulation

Ductwork and plenum shall be insulated in accordance with Table 5-11.

Table 5-11: Ductwork Insulation (R value in m2. K/W) Requirements

Duct Location Supply ducts Return ducts

Exterior R -1.4 R -0.6

Unconditioned Space R -0.6 None

Buried R -0.6 None

5.2.7 System Balancing

5.2.7.1 General

System balancing shall be done for systems serving zones with a total conditioned area exceeding

500 m2.

5.2.7.2 Air System Balancing

Air systems shall be balanced in a manner to first minimize throttling losses; then, for fans with

fan system power greater than 0.75 kW, fan speed shall be adjusted to meet design flow

conditions.

5.2.7.3 Hydronic System Balancing

Hydronic systems shall be proportionately balanced in a manner to first minimize throttling

losses; then the pump impeller shall be trimmed or pump speed shall be adjusted to meet design

flow conditions.

45

5.2.8 Condensers

5.2.8.1 Condenser Locations

Condensers shall be located such that the heat sink is free of interference from heat discharge

by devices located in adjoining spaces, and do not interfere with other such systems installed

nearby.

5.2.9 Service Water Heating

5.2.9.1 Solar Water Heating

To comply with the Code, Hotels and Hospitals in all climatic zones and all buildings in cold climate

zone with a hot water system, shall have solar water heating equipment installed to provide for:

a) at least 20% of the total hot water design capacity if above grade floor area of the building

is less than 20,000 m2

b) at least 40% of the total hot water design capacity if above grade floor area of the building

is greater than or equal to 20,000 m2

For compliance with ECBC+ and SuperECBC, Hotels and Hospitals in all climatic zones and all

buildings in cold climate zone with a hot water system, shall have solar water heating equipment

installed to provide at least 40% and 60% respectively of the total hot water design capacity.

Exception to § 5.2.9.1: Systems that use heat recovery to provide the hot water capacity required

as per the efficiency level or building size.

5.2.9.2 Heating Equipment Efficiency

Service water heating equipment shall meet or exceed the performance and minimum efficiency

requirements presented in available Indian Standards

a) Solar water heater shall meet the performance/ minimum efficiency level mentioned in

IS 13129 Part (1&2)

b) Gas Instantaneous water heaters shall meet the performance/ minimum efficiency level

mentioned in IS 15558 with above 80% Fuel utilization efficiency.

c) Electric water heater shall meet the performance/ minimum efficiency level mentioned

in IS 2082.

5.2.9.3 Other Water Heating System

Supplementary heating system shall be designed to maximize the energy efficiency of the system

and shall incorporate the following design features in cascade:

a) Maximum heat recovery from hot discharge system like condensers of air conditioning

units,

46

b) Use of gas fired heaters wherever gas is available, and

c) Electric heater as last resort.

5.2.9.4 Piping Insulation

Piping insulation shall comply with § 5.2.6.1. The entire hot water system including the storage

tanks, pipelines shall be insulated conforming to the relevant IS standards on materials and

applications.

5.2.9.5 Heat Traps

Vertical pipe risers serving storage water heaters and storage tanks not having integral heat traps

and serving a non-recirculating system shall have heat traps on both the inlet and outlet piping.

5.2.9.6 Swimming Pools

All heated pools shall be provided with a vapor retardant pool cover on or at the water surface.

Pools heated to more than 32°C shall have a pool cover with a minimum insulation value of R-

4.1.

Exception to § 5.2.9.6: Pools deriving over 60% of their energy from site-recovered energy or

solar energy source.

5.3 Prescriptive Requirements

Compliance shall be demonstrated with the prescriptive requirements in this section. Supply,

exhaust, and return or relief fans with motor power exceeding 0.37 kW shall meet or exceed the

minimum energy efficiency requirements specified in Table 5-12 through Table 5-14 except the

following need not comply with the requirement

a) Fans in un-ducted air conditioning unit where fan efficiency has already been taken in

account to calculate the efficiency standard of the comfort system.

b) Fans in Health Care buildings having HEPA filters.

c) Fans inbuilt in energy recovery systems that pre-conditions the outdoor air.

Table 5-12: Mechanical and Motor Efficiency Requirements for Fans in ECBC Buildings

System type Fan Type Mechanical Efficiency

Motor Efficiency (As per IS 12615)

Air-handling unit Supply, return and exhaust 60% IE 2

Table 5-13: Mechanical and Motor Efficiency Requirements for Fans in ECBC+ Buildings

System type Fan Type Mechanical Efficiency

Motor Efficiency (As per IS 12615)

47

Air-handling unit Supply, return and exhaust 65% IE 3

Table 5-14: Mechanical and Motor Efficiency Requirements for Fans in SuperECBC Buildings

System type Fan Type Mechanical Efficiency

Motor Efficiency (As per IS 12615)

Air-handling unit Supply, return and exhaust 70% IE 4

5.3.1 Pumps

Chilled and condenser water pumps shall meet or exceed the minimum energy efficiency

requirements specified in Table 5-15 through Table 5-17. Requirements for pumps in district

chiller systems and hot water pumps for space heating are limited to the installed efficiency

requirement of individual pump equipment only. To show compliance, calculate the total

installed pump capacity in kilo watt and achieve the prescribed limits per kilo watt of refrigeration

installed in the building.

Exceptions to § 5.3.1: Pumps used in processes e.g. service hot water, chilled water used for

refrigeration etc.

Table 5-15: Pump Efficiency Requirements for ECBC Building

Equipment ECBC

Chilled Water Pump (Primary and Secondary) 18.2 W/ kWr with VFD on secondary pump

Condenser Water Pump 17.7 W/ kWr

Pump Efficiency (minimum) 70%

Table 5-16: Pump Efficiency Requirements for ECBC+ Building

Equipment ECBC+ Building

Chilled Water Pump (Primary and Secondary) 16.9 W/ kWr with VFD on secondary pump

Condenser Water Pump 16.5 W/ kWr

Pump Efficiency (minimum) 75%

Table 5-17: Pump Efficiency Requirements for SuperECBC Building

Equipment SuperECBC Building

Chilled Water Pump (Primary and Secondary) 14.9 W/ kWr with VFD on secondary pump

Condenser Water Pump 14.6 W/ kWr

Pump Efficiency (minimum) 85%

48

5.3.2 Cooling Towers

Cooling towers shall meet or exceed the minimum efficiency requirements specified in Table 5-

18. ECBC+ and SuperECBC Buildings shall have additional VFD installed in the cooling towers.

Table 5-18: Cooling Tower Efficiency Requirements for ECBC, ECBC+, and SuperECBC Buildings

Equipment type Rating Condition Efficiency

Open circuit cooling

tower Fans

35°C entering water

29°C leaving water

24°C WB outdoor air

0.017 kW/kWr

0.31 kW/ L/s

5.3.3 Economizers

5.3.3.1 Economizer for ECBC, ECBC+, and SuperECBC Building

Each cooling fan system in buildings with built up area greater than 20,000 m2, shall include at

least one of the following:

a) An air economizer capable of modulating outside-air and return-air dampers to supply

50% of the design supply air quantity as outside-air.

b) A water economizer capable of providing 50% of the expected system cooling load at

outside air temperatures of 10°C dry-bulb/7.2°C wet-bulb and below.

Exception to §5.3.3.1:

a) Projects in warm-humid climate zones are exempt.

b) Projects with only daytime occupancy in the hot-dry are exempt.

c) Individual ceiling mounted fan systems is less than 3,200 liters per second exempt.

5.3.3.2 Partial Cooling

Where required by §5.3.3.1 economizers shall be capable of providing partial cooling even when

additional mechanical cooling is required to meet the cooling load.

5.3.3.3 Economizer Controls

Air economizer shall be equipped with controls

a) That allows dampers to be sequenced with the mechanical cooling equipment and not be

controlled by only mixed air temperature.

b) Capable of automatically reducing outdoor air intake to the design minimum outdoor air

quantity when outdoor air intake will no longer reduce cooling energy usage.

49

c) Capable of high-limit shutoff at 24 °C dry bulb temperature.

5.3.3.4 Testing

Air-side economizers shall be tested in the field following the requirements in §12 Appendix C to

ensure proper operation.

Exception to §5.3.3.4: Air economizers installed by the HVAC system equipment manufacturer

and certified to the building department as being factory calibrated and tested per the

procedures in §12.

5.3.4 Variable Flow Hydronic Systems

5.3.4.1 Variable Fluid Flow

HVAC pumping systems having a total pump system power exceeding 7.5 kW shall be designed

for variable fluid flow and shall be capable of reducing pump flow rates to an extent which is

lesser or equal to the limit, where the limit is set by the larger of:

a) 50% of the design flow rate, or

b) the minimum flow required by the equipment manufacturer for proper operation of the

chillers or boilers.

5.3.4.2 Isolation Valves

Water cooled air-conditioning or heat pump units with a circulation pump motor greater than or

equal to 3.7 kW shall have two-way automatic isolation valves on each water cooled air-

conditioning or heat pump unit that are interlocked with the compressor to shut off condenser

water flow when the compressor is not operating.

5.3.4.3 Variable Speed Drives

Chilled water or condenser water systems that must comply with either §5.3.4.1 or §5.3.4.2 and

that have pump motors greater than or equal to 3.7 kW shall be controlled by variable speed

drives.

5.3.5 Boilers

Gas and oil fired boilers shall meet or exceed the minimum efficiency requirements specified in

Table 5-19 and Table 5-20.

Table 5-19: Minimum Efficiency Requirements for Oil and Gas Fired Boilers for ECBC building

Equipment Type Sub Category Size Category Minimum FUE

Boilers, Hot Water Gas or oil fired All capacity 80%

FUE - fuel utilization efficiency

50

Table 5-20: Minimum Efficiency Requirements for Oil and Gas Fired Boilers for ECBC+ and SuperECBC

building

Equipment Type Sub Category Size Category Minimum FUE

Boilers, Hot Water Gas or oil fired All capacity 85%

FUE - fuel utilization efficiency

5.3.6 Energy Recovery

All Hospitality and Healthcare, with systems of capacity greater than 2,100 liters per second and

minimum outdoor air supply of 70% shall have air-to-air heat recovery equipment with minimum

50 % recovery effectiveness

At least 50 % of heat shall be recovered from diesel and gas fired generator sets installed in

Hospitality, Healthcare, and Business buildings with built up area greater than 20,000 m2.

5.4 Total System Efficiency – Alternate Compliance Approach

Buildings may show compliance by optimizing the total system efficiency for the plant side

comfort system instead of the individual equipment mentioned under the prescriptive

requirement. This alternate compliance approach is applicable for central chilled water plant side

system in all building types. The total installed capacity per kilo-watt refrigeration load shall be

less than or equal to maximum threshold requirements as specified in Table 5-21. Equipment

that can be included in central chilled water plant side system for this alternate approach are

chillers, chilled water pumps, condenser water pumps, and cooling tower fan. Compliance check

will be based on annual hourly simulation.

Table 5-21 Minimum System Efficiency* Requirement for ECBC, ECBC+, and SuperECBC Buildings

Water Cooled Chilled Water Plant Maximum Threshold (kW/kWr)

ECBC 0.26

ECBC+ 0.23

SuperECBC 0.20

5.5 Low-energy Comfort Systems

Alternative HVAC systems which have low energy use may be installed in place of (or in

conjunction with) refrigerant-based cooling systems. Such systems shall be deemed to meet the

minimum space conditioning equipment efficiency levels of §5.2.2, but shall comply with all other

applicable mandatory provisions of §5.2 as applicable. The approved list of low energy comfort

systems1 is given below:

1 This is not an all-inclusive list. The updated list of low energy comfort systems is available at BEE website (https://www.beeindia.gov.in/).

51

a) Evaporative cooling

b) Desiccant cooling system

c) Solar air conditioning

d) Tri-generation (waste-to-heat)

e) Radiant cooling system

f) Ground source heat pump

g) Adiabatic cooling system

Buildings with an approved low-energy comfort system installed for more than 50 % of the

cooling and heating requirement of the building shall be deemed equivalent to the ECBC+

building standard prescribed in § 5.2.2.

Buildings having an approved low energy comfort system installed for more than 90 % of the

cooling and heating requirement of the building shall be deemed equivalent to the SuperECBC

building standard prescribed in §5.2.2.

Note 5-2 Thermal Energy Storage Thermal Energy Storage

Thermal storage may be used for limiting maximum demand, by

controlling peak electricity load through reduction of chiller capacity,

and by taking advantage of high system efficiency during low ambient

conditions. Thermal storage would also help in reducing operating

cost by using differential time-of-the day power tariff, where applicable.

The storage media can be ice or water. Water need stratified storage tanks and is

mostly viable with large storage capacity and has an advantage of plant operation at

higher efficiencies but requires larger storage volumes. In case of central plant,

designed with thermal energy storage, its location shall be decided in consultation

with the air conditioning engineer. For roof top installations, structural provision shall

take into account load coming on the building/structure due to the same. For open

area surface installation, horizontal or vertical system options shall be considered and

approach ladders for manholes provided. Buried installation shall take into account

loads due to movement of vehicles above the area.

52

6. Lighting and Controls

6.1 General

Lighting systems and equipment shall comply with the mandatory provisions of § 6.2 and the

prescriptive criteria of § 6.3. The lighting requirements in this section shall apply to:

a) Interior spaces of buildings,

b) Exterior building features, including facades, illuminated roofs, architectural features,

entrances, exits, loading docks, and illuminated canopies, and,

c) Exterior building grounds lighting that is provided through the building's electrical service.

Exceptions to §6.1:

a) Emergency or security lighting that is automatically off during normal building operations.

6.2 Mandatory Requirements

6.2.1 Lighting Control

6.2.1.1 Automatic Lighting Shutoff

a) 90% of interior lighting fittings in building or space of building larger than 300 m2 shall be

equipped with automatic control device.

b) Additionally, occupancy sensors shall be provided in

i. All building types greater than 20,000 m2 BUA, in

a. All habitable spaces less than 30 m2, enclosed by walls or ceiling height partitions.

b. All storage or utility spaces more than 15 m2 in all building types with BUA greater

than 20,000 m2.

c. Public toilets more than 25 m2, controlling at least 80 % of lighting fitted in the

toilet. The lighting fixtures, not controlled by automatic lighting shutoff, shall be

uniformly spread in the area.

ii. In corridors of all Hospitality greater than 20,000 m2 BUA, controlling minimum 70%

and maximum 80% of lighting fitted in the public corridor. The lighting fixtures, not

controlled by automatic lighting shut off, shall be uniformly spread in the area.

iii. In all Business and all conference or meeting rooms.

c) Automatic control device shall function on either:

i. A scheduled basis at specific programmed times. An independent program schedule

shall be provided for areas of no more than 2,500 m2 and not more than one floor,

or,

ii. Occupancy sensors that shall turn off the lighting fixtures within 15 minutes of an

occupant leaving the space. Light fixtures controlled by occupancy sensors shall have

53

a wall-mounted, manual switch capable of turning off lights when the space is

occupied.

Exception to § 6.2.1.1: Lighting systems designed for emergency and firefighting purposes.

6.2.1.2 Space Control

Each space enclosed by ceiling-height partitions shall have at least one control device to

independently control the general lighting within the space. Each control device shall be

activated either manually by an occupant or automatically by sensing an occupant. Each control

device shall

a) control a maximum of 250 m2 for a space less than or equal to 1,000 m2, and a maximum

of 1,000 m2 for a space greater than 1,000 m2.

b) have the capability to override the shutoff control required in § 6.2.1.1 for no more than

2 hours, and

c) be readily accessible and located so the occupants can see the control.

Exception to § 6.2.1.2 (c): The required control device may be remotely installed if required for

reasons of safety or security. A remotely located device shall have a pilot light indicator as part

of or next to the control device and shall be clearly labeled to identify the controlled lighting.

6.2.1.3 Control in Daylight Areas

a) Luminaires, installed within day lighting extent from the window as calculated in § 4.2.3,

shall be equipped with either a manual control device to shut off luminaires, installed

within day lit area, during potential daylit time of a day or automatic control device that:

i. Has a delay of minimum 5 minutes, or,

ii. Can dim or step down to 50% of total power.

b) Overrides to the daylight controls shall not be allowed.

c) For SuperECBC Buildings, Lighting Power Density adjustment factor of 20% shall be

allowed to all spaces with more than 70% of their area under daylight controls.

6.2.1.4 Centralized Controls for ECBC+ and SuperECBC Buildings

ECBC+ and SuperECBC building shall have centralized control system for schedule based

automatic lighting shutoff switches.

6.2.1.5 Exterior Lighting Control

a) Lighting for all exterior applications not exempted in §6.3.5 shall be controlled by a photo

sensor or astronomical time switch that is capable of automatically turning off the

exterior lighting when daylight is available or the lighting is not required.

b) Lighting for all exterior applications, of Schools and Business with built up area greater

than 20,000 m2, shall have lamp efficacy not less than 80 lumens per watt, 90 lumens per

54

watt, and 100 lumens per watt, for ECBC, ECBC+, and SuperECBC Buildings respectively,

unless the luminaire is controlled by a motion sensor or exempt under §6.1.

c) Facade lighting and façade non-emergency signage of Shopping Complexes shall have

separate time switches.

Exemption to §6.2.1.5: Exterior emergency lighting.

6.2.1.6 Additional Control

The following lighting applications shall be equipped with a control device to control such lighting

independently of general lighting:

a) Display/ Accent Lighting. Display or accent lighting greater than 300 m2 area shall have a

separate control device.

b) Hotel Guest Room Lighting. Guest rooms and guest suites in a hotel shall have a master

control device at the main room entry that controls all permanently installed luminaires

and switched receptacles.

c) Task Lighting. Supplemental task lighting including permanently installed under shelf or

under cabinet lighting shall have a control device integral to the luminaires or be

controlled by a wall-mounted control device provided the control device complies with

§6.2.1.2.

d) Nonvisual Lighting. Lighting for nonvisual applications, such as plant growth and food-

warming, shall be equipped with a separate control device.

e) Demonstration Lighting. Lighting equipment that is for sale or for demonstrations in

lighting education shall be equipped with a separate control device accessible only to

authorized personnel.

6.2.2 Exit Signs

Internally-illuminated exit signs shall not exceed 5 Watts per face.

6.3 Prescriptive Requirements

6.3.1 Interior Lighting Power

The installed interior lighting power for a building or a separately metered or permitted portion

of a building shall be calculated in accordance with §6.3.4 and shall not exceed the interior

lighting power allowance determined in accordance with either §6.3.2 or §6.3.3. Tradeoffs of

interior lighting power allowance among portions of the building for which a different method of

calculation has been used are not permitted.

Exception to §6.3: The following lighting equipment and applications shall not be considered

when determining the interior lighting power allowance, nor shall the wattage for such lighting

be included in the installed interior lighting power. However, any such lighting shall not be

55

exempt unless it is an addition to general lighting and is controlled by an independent control

device.

a) Display or accent lighting that is an essential element for the function performed in

galleries, museums, and monuments,

b) Lighting that is integral to equipment or instrumentation and is installed by its

manufacturer,

c) Lighting specifically designed for medical or dental procedures and lighting integral to

medical equipment,

d) Lighting integral to food warming and food preparation equipment,

e) Lighting for plant growth or maintenance,

f) Lighting in spaces specifically designed for use by the visually impaired,

g) Lighting in retail display windows, provided the display area is enclosed by ceiling-height

partitions,

h) Lighting in interior spaces that have been specifically designated as a registered interior

historic landmark,

i) Lighting that is an integral part of advertising or directional signage,

j) Exit signs,

k) Lighting that is for sale or lighting educational demonstration systems,

l) Lighting for theatrical purposes, including performance, stage, and film or video

production, and

m) Athletic playing areas with permanent facilities for television broadcasting.

6.3.2 Building Area Method

Determination of interior lighting power allowance (watts) by the building area method shall be

in accordance with the following:

Determine the allowed lighting power density for each appropriate building area type from Table

6-1 for ECBC Buildings, from Table 6-2 for ECBC+ Buildings and from Table 6-3 for SuperECBC

Buildings.

a) Calculate the gross lighted carpet area for each building area type.

b) The interior lighting power allowance is the sum of the products of the gross lighted floor

area of each building area times the allowed lighting power density for that building area

type.

Table 6-1 Interior Lighting Power for ECBC Buildings – Building Area Method

Building Type LPD (W/m2) Building Area Type LPD (W/m2)

Office Building 9.50 Motion picture theater 9.43

Hospitals 9.70 Museum 10.2

56

Hotels 9.50 Post office 10.5

Shopping Mall 14.1 Religious building 12.0

University and Schools 11.2 Sports arena 9.70

Library 12.2 Transportation 9.20

Dining: bar lounge/leisure 12.2 Warehouse 7.08

Dining: cafeteria/fast food 11.5 Performing arts theater 16.3

Dining: family 10.9 Police station 9.90

Dormitory 9.10 Workshop 14.1

Fire station 9.70 Automotive facility 9.00

Gymnasium 10.0 Convention center 12.5

Manufacturing facility 12.0 Parking garage 3.00

In cases where both a general building area type and a specific building area type

are listed, the specific building area type shall apply.

Table 6-2 Interior Lighting Power for ECBC+ Buildings – Building Area Method

Building Type LPD (W/m2) Building Area Type LPD (W/m2)

Office Building 7.60 Motion picture theater 7.50

Hospitals 7.80 Museum 8.20

Hotels 7.60 Post office 8.40

Shopping Mall 11.3 Religious building 9.60

University and Schools 9.00 Sports arena 7.80

Library 9.80 Transportation 7.40

Dining: bar lounge/leisure 9.80 Warehouse 5.70

Dining: cafeteria/fast food 9.20 Performing arts theater 13.0

Dining: family 8.70 Police station 7.90

Dormitory 7.30 Workshop 11.3

Fire station 7.80 Automotive facility 7.20

Gymnasium 8.00 Convention center 10.0

Manufacturing facility 9.60 Parking garage 2.40

In cases where both a general building area type and a specific building area type

are listed, the specific building area type shall apply.

Table 6-3 Interior Lighting Power for SuperECBC Buildings – Building Area Method

Building Type LPD (W/m2) Building Area Type LPD (W/m2)

Office Building 5.0 Motion picture theater 4.7

Hospitals 4.9 Museum 5.1

57

Hotels 4.8 Post office 5.3

Shopping Mall 7.0 Religious building 6.0

University and Schools 6.0 Sports arena 4.9

Library 6.1 Transportation 4.6

Dining: bar lounge/leisure 6.1 Warehouse 3.5

Dining: cafeteria/fast food 5.8 Performing arts theater 8.2

Dining: family 5.5 Police station 5.0

Dormitory 4.6 Workshop 7.1

Fire station 4.9 Automotive facility 4.5

Gymnasium 5.0 Convention center 6.3

Manufacturing facility 6.0 Parking garage 1.5

In cases where both a general building area type and a specific building area type

are listed, the specific building area type shall apply.

6.3.3 Space Function Method

Determination of interior lighting power allowance (watts) by the space function method shall

be in accordance with the following:

a) Determine the appropriate building type and the allowed lighting power density from

Table 6-4 for ECBC Buildings, Table 6-5 for ECBC+ Buildings and, Table 6-6 for SuperECBC

Buildings. In cases where both a common space type and building specific space type are

listed, building specific space type LPD shall apply.

b) For each space, enclosed by partitions 80% or greater than ceiling height, determine the

gross carpet area by measuring to the face of the partition wall. Include the area of

balconies or other projections. Retail spaces do not have to comply with the 80% partition

height requirements.

c) The interior lighting power allowance is the sum of the lighting power allowances for all

spaces. The lighting power allowance for a space is the product of the gross lighted carpet

area of the space times the allowed lighting power density for that space.

Table 6-4 Interior Lighting Power for ECBC Buildings – Space Function Method

Category LPD (W/m2) Lamp Category LPD (W/m2)

Common Space Types

Restroom 7.70 Stairway 5.50

Storage 6.80 Corridor/Transition 7.10

Conference/ Meeting 11.5 Lobby 9.10

58

Parking Bays (covered/

basement)

2.20 Parking Driveways

(covered/ basement)

3.00

Electrical/Mechanical 7.10 Workshop 17.1

Business

Enclosed 10.0 Open Plan 10.0

Banking Activity Area 12.6 Service/Repair 6.80

Healthcare

Emergency 22.8 Recovery 8.60

Exam/Treatment 13.7 Storage 5.50

Nurses’ Station 9.40 Laundry/Washing 7.50

Operating Room 21.8 Lounge/Recreation 8.00

Patient Room 7.70 Medical Supply 13.7

Pharmacy 10.7 Nursery 5.70

Physical Therapy 9.70 Corridor/Transition 9.10

Radiology/Imaging 9.10

Hospitality

Hotel Dining 9.10 Hotel Lobby 10.9

For Bar Lounge/ Dining 14.1 Motel Dining 9.10

For food preparation 12.1 Motel Guest Rooms 7.70

Hotel Guest Rooms 9.10

Shopping Complex

Mall Concourse 12.8 For Family Dining 10.9

Sales Area 18.3 For food preparation 12.1

Motion Picture Theatre 9.60 Bar Lounge/ Dining 14.1

Educational

Classroom/Lecture 13.7 Card File and Cataloguing 9.10

For Classrooms 13.8 Stacks (Lib) 18.3

Laboratory 15.1 Reading Area (Library) 10.0

Assembly

Dressing Room 9.10 Seating Area - Performing

Arts Theatre

22.6

Exhibit Space - Convention

Centre

14.0 Lobby - Performing Arts

Theatre

21.5

Seating Area - Gymnasium 4.60 Seating Area - Convention

Centre

6.40

Fitness Area - Gymnasium 13.70 Seating Religious Building 16.4

Museum - General Exhibition 16.40 Playing Area - Gymnasium 18.8

Museum - Restoration 18.3

59

Table 6-5 Interior Lighting Power for ECBC+ Buildings – Space Function Method

Category LPD (W/m2) Lamp Category LPD (W/m2)

Common Space Types

Restroom 6.10 Stairway 4.40

Storage 5.40 Corridor/Transition 3.60

Conference/ Meeting 9.20 Lobby 7.30

Parking Bay (covered/

basement)

1.75 Parking Driveways

(covered/ basement)

2.50

Electrical/Mechanical 5.70 Workshop 13.7

Business

Enclosed 8.60 Open Plan 8.60

Banking Activity Area 9.30 Service/Repair 5.50

Healthcare

Emergency 18.2 Recovery 7.00

Exam/Treatment 10.9 Storage 4.40

Nurses’ Station 7.50 Laundry/Washing 6.00

Operating Room 17.5 Lounge/Recreation 6.40

Patient Room 6.10 Medical Supply 10.9

Pharmacy 8.50 Nursery 4.60

Physical Therapy 7.80 Corridor/Transition 7.30

Radiology/Imaging 7.30

Hospitality

Hotel Dining 7.30 Hotel Lobby 8.80

For Bar Lounge/ Dining 11.3 Motel Dining 7.30

For food preparation 12.1 Motel Guest Rooms 6.10

Hotel Guest Rooms 7.30

Shopping Complex

Mall Concourse 10.2 For Family Dining 8.80

Sales Area 14.6 For food preparation 12.1

Motion Picture Theatre 10.3 Bar Lounge/ Dining 11.3

Educational

Classroom/Lecture 10.9 Card File and Cataloguing 7.30

For Classrooms 11.0 Stacks (Library) 14.6

Laboratory 12.1 Reading Area (Library) 9.20

Assembly

Dressing Room 7.30 Seating Area - Performing

Arts Theatre

18.1

Exhibit Space - Convention

Centre

11.2 Lobby - Performing Arts

Theatre

17.2

60

Seating Area - Gymnasium 3.60 Seating Area – Convention

Centre

5.10

Fitness Area - Gymnasium 7.85 Seating Religious Building 13.1

Museum - General Exhibition 11.3 Playing Area - Gymnasium 12.9

Museum - Restoration 11.0

Table 6-6 Interior Lighting Power for SuperECBC Buildings – Space Function Method

Category LPD (W/m2) Lamp Category LPD (W/m2)

Common Space Types

Restrooms 3.80 Stairway 2.70

Storage 3.40 Corridor/Transition 2.30

Conference/ Meeting 5.70 Lobby 4.60

Parking Bays (covered/

basement)

1.10 Driveways (covered/

basement)

1.50

Electrical/Mechanical 3.50 Workshop 8.60

Business

Enclosed 5.40 Open Plan 5.40

Banking Activity Area 5.80 Service/Repair 3.40

Healthcare

Emergency 11.4 Recovery 4.40

Exam/Treatment 6.80 Storage 2.70

Nurses’ Station 5.00 Laundry/Washing 3.80

Operating Room 10.9 Lounge/Recreation 4.60

Patient Room 3.80 Medical Supply 6.80

Pharmacy 5.30 Nursery 2.90

Physical Therapy 4.90 Corridor/Transition 4.60

Radiology/Imaging 4.60

Hospitality

Hotel Dining 4.60 Hotel Lobby 5.50

For Bar Lounge/ Dining 7.00 Motel Dining 4.60

For food preparation 7.50 Motel Guest Rooms 3.80

Hotel Guest Rooms 4.60

Shopping Complex

Mall Concourse 6.40 For Family Dining 5.50

Sales Area 9.20 For food preparation 7.50

Motion Picture Theatre 6.50 Bar Lounge/ Dining 7.00

Educational

Classroom/Lecture 6.80 Card File and Cataloguing 4.60

For Classrooms 6.90 Stacks (Library) 9.20

Laboratory 7.50 Reading Area (Library) 5.70

61

Assembly

Dressing Room 4.60 Seating Area - Performing

Arts Theatre

11.3

Exhibit Space – Convention

Centre

7.00 Lobby - Performing Arts

Theatre

10.8

Seating Area - Gymnasium 3.40 Seating Area – Convention

Centre

3.20

Fitness Area - Gymnasium 3.92 Seating Religious Building 8.20

Museum – General Exhibition 5.65 Playing Area - Gymnasium 6.50

Museum – Restoration 5.50

Note 6-1 Calculating Interior Lighting Power – Space Function Method

A four-story building has retail on the ground floor and offices on the

top three floors. Area is 3,600 m2. Space types and their respective

areas are mentioned below. Steps for calculating interior lighting

power allowance using the space function method for a ECBC

building is described below.

For each of the space type, corresponding Lighting Power Density (LPD) values for

Business and Shopping complex building type from Table 6-4 are used. Area is

multiplied with the LPD values to estimate the lighting power allowance for the whole

building. It is 40,055.5 W.

Table 6-1-1 Space Types, Areas and Corresponding LPDs

Space Function LPD (W/ m²) Area (m²) Lighting Power Allowance (W)

Office

Office - enclosed 10.0 720 7,200

Office – open plan 10.0 1,485 14,850

Meeting Rooms 11.5 120 1,380

Lobbies 7.1 93 660

Restrooms 7.7 51 393

Corridors 7.1 125 887.5

62

Electrical/ Mechanical 7.1 14 99

Staircase 5.5 84 462

Total 25,931.5

Retail

General sales area 18.3 669 12,243

Offices – enclosed 10.0 28 280

Restrooms 7.7 9 69

Corridors 7.1 79 561

Active Storage 6.8 93 632

Food preparation 12.1 28 339

Total 14,124

Building Total 40,055.5W

6.3.4 Installed Interior Lighting Power

The installed interior lighting power calculated for compliance with §6.3 shall include all power

used by the luminaires, including lamps, ballasts, current regulators, and control devices except

as specifically exempted in §6.1.

Exception to §6.3.4: If two or more independently operating lighting systems in a space are

controlled to prevent simultaneous user operation, the installed interior lighting power shall be

based solely on the lighting system with the highest power.

6.3.4.1 Luminaire Wattage

Luminaire efficacy shall be 0.7 or above. Luminaire wattage incorporated into the installed

interior lighting power shall be determined in accordance with the following:

a) The wattage of incandescent luminaires with medium base sockets and not containing

permanently installed ballasts shall be the maximum labeled wattage of the luminaires.

b) The wattage of luminaires containing permanently installed ballasts shall be the operating

input wattage of the specified lamp/ballast combination. Operating input wattage can be

either values from manufacturers’ catalogs or values from independent testing laboratory

reports.

63

c) The wattage of all other miscellaneous luminaire types not described in (a) or (b) shall be

the specified wattage of the luminaires.

d) The wattage of lighting track, plug-in busway, and flexible-lighting systems that allow the

addition and/ or relocation of luminaires without altering the wiring of the system shall

be the larger of the specified wattage of the luminaires included in the system or 135

Watt per meter (45 W/ft.). Systems with integral overload protection, such as fuses or

circuit breakers, shall be rated at 100% of the maximum rated load of the limiting device.

6.3.5 Exterior Lighting Power

Connected lighting power of exterior lighting applications shall not exceed the lighting power

limits specified in Table 6-7 for ECBC Buildings, Table 6-8 for ECBC+ Buildings and Table 6-9 for

SuperECBC Buildings. Trade-offs between applications are not permitted.

Table 6-7 Exterior Building Lighting Power for ECBC Buildings

Exterior lighting application Power limits

Building entrance (with canopy) 10 W/m2 of canopied area

Building entrance (w/o canopy) 90 W/ linear m of door width

Building exit 60 W/lin m of door width

Building façade 5.0 W/m2 of vertical facade area

Emergency signs, ATM kiosks, Security areas facade 1.0 W/m2

Driveways and parking (open/ external) 1.6 W/m2

Pedestrian walkways 2.0 W/m2

Stairways 10.0 W/m2

Landscaping 0.5 W/m2

Outdoor sales area 9.0 W/m2

Table 6-8 Exterior Building Lighting Power for ECBC+ Buildings

Exterior lighting application Power limits

Building entrance (with canopy) 8.0 W/m2 of canopied area

Building entrance (w/o canopy) 72 W/ linear m of door width

64

Building exit 48 W/lin m of door width

Building façade 4.0 W/m2 of vertical façade area

Emergency signs, ATM kiosks, Security areas façade 0.8 W/m2

Driveways and parking (open/ external) 1.3 W/m2

Pedestrian walkways 1.6 W/m2

Stairways 8.0 W/m2

Landscaping 0.4 W/m2

Outdoor sales area 7.2 W/m2

Table 6-9 Exterior Building Lighting Power for SuperECBC Buildings

Exterior lighting application Power limits

Building entrance (with canopy) 5.0 W/m2 of canopied area

Building entrance (w/o canopy) 45 W/ linear m of door width

Building exit 30 W/lin m of door width

Building façade 2.5 W/m2 of vertical façade area

Emergency signs, ATM kiosks, Security areas façade 0.5 W/m2

Driveways and parking (open/ external) 0.8 W/m2

Pedestrian walkways 1.0 W/m2

Stairways 5.0 W/m2

Landscaping 0.25 W/m2

Outdoor sales area 4.5 W/m2

65

7. Electrical and Renewable Energy Systems

7.1 General

All electric and renewable energy equipment and systems shall comply with the mandatory

requirements of §7.2.

7.2 Mandatory Requirements

7.2.1 Transformers

7.2.1.1 Maximum Allowable Power Transformer Losses

Power transformers of the proper ratings and design must be selected to satisfy the minimum

acceptable efficiency at 50% and full load rating.

Permissible total loss values shall not exceed

a) 5% of the maximum total loss values mentioned in IS 1180 for oil type transformers in

voltage class above 11 kV but not more than 22 kV

b) 7.5% of the maximum total loss values mentioned in above IS 1180 for oil type

transformers in voltage class above 22 kV and up to and including 33 kV

c) values listed in Table 7.1 for dry type transformers

Table 7-1: Dry Type Transformers

Rating

(kVA)

Impedance

(%)

Max. Total Loss (W)

ECBC Building ECBC+ Building SuperECBC Building

50 % Load 100% Load 50 % Load 100% Load 50 % Load 100% Load

16 4.5 150 480 135 440 120 400

25 4.5 210 695 190 635 175 595

63 4.5 380 1,250 340 1,140 300 1,050

100 4.5 520 1,800 475 1,650 435 1,500

160 4.5 770 2,200 670 1,950 570 1,700

200 4.5 890 2,700 780 2,300 670 2,100

250 4.5 1,050 3,150 980 2,930 920 2,700

66

315 4.5 1,100 3,275 1,025 3,100 955 2,750

400 4.5 1,300 3,875 1,225 3,450 1,150 3,330

500 4.5 1,600 4,750 1,510 4,300 1,430 4,100

630 4.5 2,000 5,855 1,860 5,300 1,745 4,850

1000 5 3,000 9,000 2,790 7,700 2,620 7,000

1250 5 3,600 10,750 3,300 9,200 3,220 8,400

1600 6.25 4,500 13,500 4,200 11,800 3,970 11,300

2000 6.25 5,400 17,000 5,050 15,000 4,790 14,100

2500 6.25 6,500 20,000 6,150 18,500 5,900 17,500

Total loss values given in above table are applicable for thermal classes E, B and F and have

component of load loss at reference temperature according to Clause 17 of IS. An increase of 7%

on total for thermal class H is allowed.

Table 7-2: Permissible Losses for Oil Type Transformers. Total losses for oil type transformers shall

confirm with Indian Standard IS 1180.

Rating

(kVA)

Impedance

(%)

Max. Total Loss (W)

ECBC Building ECBC+ Building SuperECBC Building

50 % Load 100% Load 50 % Load 100% Load 50 % Load 100% Load

16 4.5 150 480 135 440 120 400

25 4.5 210 695 190 635 175 595

63 4.5 380 1250 340 1140 300 1050

100 4.5 520 1800 475 1650 435 1500

160 4.5 770 2200 670 1950 570 1700

200 4.5 890 2700 780 2300 670 2100

250 4.5 1050 3150 980 2930 920 2700

67

315 4.5 1100 3275 1025 3100 955 2750

400 4.5 1300 3875 1225 3450 1150 3330

500 4.5 1600 4750 1510 4300 1430 4100

630 4.5 2000 5855 1860 5300 1745 4850

1000 5 3000 9000 2790 7700 2620 7000

1250 5 3600 10750 3300 9200 3220 8400

1600 6.25 4500 13500 4200 11800 3970 11300

2000 6.25 5400 17000 5050 15000 4790 14100

2500 6.25 6500 20000 6150 18500 5900 17500

Total loss values given in above table are applicable for thermal classes E, B and F and have

component of load loss at reference temperature according to Clause 17 of IS 1180 i.e., average

winding temperature rise as given in Column 2 of Table 8.2 plus 300C. An increase of 7% on total

for thermal class H is allowed.

7.2.1.2 Measurement and Reporting of Transformer Losses

All measurement of losses shall be carried out by using calibrated digital meters of class 0.5 or

better accuracy and certified by the manufacturer. All transformers of capacity of 500 kVA and

above would be equipped with additional metering class current transformers (CTs) and potential

transformers (PTs) additional to requirements of Utilities so that periodic loss monitoring study

may be carried out.

7.2.1.3 Voltage Drop

Voltage drop for feeders shall not exceed 2% at design load. Voltage drop for branch circuit shall

not exceed 3% at design load.

7.2.2 Energy Efficient Motors

Motors shall comply with the following:

a) Three phase induction motors shall conform to Indian Standard (IS) 12615 and shall fulfil

the following efficiency requirements:

i. ECBC Buildings shall have motors of IE 2 (high efficiency) class or a higher class

ii. ECBC+ Buildings shall have IE 3 (premium efficiency) class motors or higher class

iii. SuperECBC Buildings shall have IE 4 (super premium efficiency) class motors

68

b) All permanently wired polyphase motors of 0.375 kW or more serving the building and

expected to operate more than 1,500 hours per year and all permanently wired polyphase

motors of 50kW or more serving the building and expected to operate more than 500

hour per year, shall have a minimum acceptable nominal full load motor efficiency not

less than levels specified in the latest version of IS 12615.

c) Motors of horsepower differing from those listed in the table shall have efficiency greater

than that of the next listed kW motor.

d) Motor horsepower ratings shall not exceed 20% of the calculated maximum load being

served.

e) Motor nameplates shall list the nominal full-load motor efficiencies and the full-load

power factor.

f) Motor users should insist on proper rewinding practices for any rewound motors. If the

proper rewinding practices cannot be assured, the damaged motor should be replaced

with a new, efficient one rather than suffer the significant efficiency penalty associated

with typical rewind practices. Rewinding practices from BEE guideline for energy efficient

motors shall be followed.

g) Certificates shall be obtained and kept on record indicating the motor efficiency.

Whenever a motor is rewound, appropriate measures shall be taken so that the core

characteristics of the motor is not lost due to thermal and mechanical stress during

removal of damaged parts. After rewinding, a new efficiency test shall be performed and

a similar record shall be maintained.

7.2.3 Diesel Generator (DG) Sets

BEE star rated DG sets shall be used in all compliant buildings. DG sets in buildings greater than

20,000 m2 BUA shall have:

a) minimum 3 stars rating in ECBC Buildings

b) minimum 4 stars rating in ECBC+ Buildings

c) minimum 5 stars rating in SuperECBC Buildings

7.2.4 Check-Metering and Monitoring

a) Services exceeding 1000 kVA shall have permanently installed electrical metering to

record demand (kVA), energy (kWh), and total power factor. The metering shall also

display current (in each phase and the neutral), voltage (between phases and between

each phase and neutral), and total harmonic distortion (THD) as a percentage of total

current.

b) Services not exceeding 1000 kVA but over 65 kVA shall have permanently installed electric

metering to record demand (kW), energy (kWh), and total power factor (or kVARh).

69

c) Services not exceeding 65 kVA shall have permanently installed electrical metering to

record energy (kWh).

d) In case of tenant based building, metering should be provided at a location from where

each tenant could attach the services.

Table 7-3: Sub Metering Requirements

120 kVA to 250 kVA Greater than 250 kVA

Minimum requirement for metering of electrical load

Energy kWh Required Required

Demand kVA Required Required

Total power factor Required Required

Minimum requirement for separation of electrical load

HVAC system and components Required Required

Interior and Exterior Lighting * Not required Required

Domestic hot water Not required Required

Plug loads Not required Required

Renewable power source Required Required

Mandatory requirement for building type over the requirement stated above

Shopping Complex Façade lighting Elevator, escalators,

moving walks

Business Data centers

Hospitality Commercial kitchens

* Hotel guestrooms and hospital in patient areas are exempted from the

lighting sub-metering requirements.

7.2.5 Power Factor Correction

All 3 phase shall maintain their power factor at the point of connection as follows:

70

a) 0.97 for ECBC Building

b) 0.98 for ECBC+ building

c) 0.99 for SuperECBC building

7.2.6 Power Distribution Systems

The power cabling shall be sized so that the distribution losses do not exceed

a) 3% of the total power usage in ECBC Buildings

b) 2% of the total power usage in ECBC+ Buildings

c) 1% of total power usage in SuperECBC Buildings

Record of design calculation for the losses shall be maintained. Load calculation shall be

calculated up to the panel level.

7.2.7 Uninterruptible Power Supply (UPS)

In all buildings, UPS shall meet or exceed the energy efficiency requirements listed in Table 7-4.

Any Standards and Labeling program by BEE shall take precedence over requirements listed in

this section.

Table 7-4: Energy Efficiency Requirements for UPS for ECBC, ECBC+, SuperECBC building

UPS Size Energy Efficiency Requirements at 100% Load

kVA< 20 90.2%

20<=kVA <= 100 91.9%

kVA > 100 93.8%

7.2.8 Renewable Energy Systems

All buildings shall have provisions for installation of renewable energy systems in the future on

rooftops or the site.

7.2.8.1 Renewable Energy Generating Zone (REGZ)

a) A dedicated REGZ equivalent to at least 25 % of roof area or area required for generation

of energy equivalent to 1% of total peak demand or connected load of the building,

whichever is less, shall be provided in all buildings.

b) The REGZ shall be free of any obstructions within its boundaries and from shadows cast

by objects adjacent to the zone

c) ECBC+ and SuperECBC building shall fulfil the additional requirements listed in Table 7-5

and Table 7-6 respectively.

71

Exception to § 7.2.8.1: Projects with solar hot water and/ or solar power generation systems.

Table 7-5: Minimum Solar Zone Area/Renewable Energy Generating Zone Requirement for ECBC+

Building

Building Type Minimum Electricity to be Generated

in REGZ

All building types except below Minimum 2% of total electrical load

Star Hotel > 20,000 m²

Resort > 12,500 m2

University > 20,000 m²

Business > 20,000 m²

Minimum 3% of total electricity load

Table 7-6: Minimum Solar Zone Area/Renewable Energy Generating Zone Requirement for SuperECBC

Building

Building Type Minimum Electricity to be Generated in

REGZ

All Building types except below Minimum 4% of total electrical load

Star Hotel > 20,000 m²

Resort > 12,500 m2

University > 20,000 m²

Business > 20,000 m²

Minimum 6% of total electrical load

7.2.8.2 Main Electrical Service Panel

Minimum rating shall be displayed on the main electrical service panel. Space shall be reserved

for the installation of a double pole circuit breaker for a future solar electric installation.

7.2.8.3 Demarcation on Documents

The following shall be indicated in design and construction documents:

a) Location for inverters and metering equipment,

b) Pathway for routing of conduit from the REGZ to the point of interconnection with the

electrical service,

c) Routing of plumbing from the REGZ to the water-heating system and,

d) Structural design loads for roof dead and live load.

72

8. Definitions, Abbreviations, and Acronyms

8.1 General

Certain terms, abbreviations, and acronyms are defined in this section for the purposes of this

code. These definitions are applicable to all sections of this code. Terms that are not defined shall

have their ordinarily accepted meanings within the context in which they are used.

8.2 Definitions

A

Above grade area (AGA): AGA is the cumulative floor area of all the floor levels of a

building that are above the ground level. Ground level shall be as defined in building site

plan. A floor level is above grade if one-third of the total external surface area of only the

said floor level is above the ground level.

Accredited independent laboratory: testing laboratory not affiliated with producer or

consumer of goods or products tested at the laboratory and accredited by national or

international organizations for technical competence

Addition: an extension or increase in floor area or height of a building outside of the

existing building envelope.

Air conditioning and condensing units serving computer rooms: air conditioning

equipment that provides cooling by maintaining space temperature and humidity within

a narrow range. Major application is in data centers where dissipating heat generated by

equipment takes precedence over comfort cooling for occupants.

Alteration: any change, rearrangement, replacement, or addition to a building or its

systems and equipment; any modification in construction or building equipment.

Area weighted average (AWA) method: AWA method is based on the concept of

weighted arithmetic mean where instead of each data point contributing equally to the

final mean; each data point contributes more “weight” than others based on the size of

the area the said data point is applicable to. To calculate the area weighted average mean,

a summation of each data point multiplied with its respective area is divided with the

total area. 𝑨𝑾𝑨=Σ(𝑫𝒂𝒕𝒂 𝒑𝒐𝒊𝒏𝒕 𝑿 𝒂𝒓𝒆𝒂)/𝑻𝒐𝒕𝒂𝒍 𝒂𝒓𝒆𝒂

Astronomical time switch: an automatic time switch that makes an adjustment for the

length of the day as it varies over the year.

Authority having jurisdiction: the agency or agent responsible for enforcing this

Standard.

73

B

Balancing, air system: adjusting airflow rates through air distribution system devices,

such as fans and diffusers, by manually adjusting the position of dampers, splitters vanes,

extractors, etc., or by using automatic control devices, such as constant air volume or

variable air volume boxes.

Balancing, hydronic system: adjusting water flow rates through hydronic distribution

system devices, such as pumps and coils, by manually adjusting the position valves, or by

using automatic control devices, such as automatic flow control valves.

Ballast: a device used in conjunction with an electric-discharge lamp to cause the lamp to

start and operate under proper circuit conditions of voltage, current, waveform,

electrode heat, etc.

Standard Design: a computer model of a hypothetical building, based on actual building

design, that fulfils all the mandatory requirements and minimally complies with the

prescriptive requirements of ECBC.

Boiler: a self-contained low-pressure appliance for supplying steam or hot water

Building or building complex or complex: a structure wholly or partially enclosed within

exterior walls, or within exterior and party walls, and a roof, affording shelter to persons,

animals, or property. Building complex means a building or group of buildings constructed

in a contiguous area for business, commercial, institutional, healthcare, hospitality

purposes or assembly buildings under the single ownership of individuals or group of

individuals or under the name of a co-operative group society or on lease and sold as

shops or office space or space for other commercial purposes, having a connected load

of 100 kW or contract demand of 120 kVA and above.

Building, base: includes building structure, building envelope, common areas, circulation

areas, parking, basements, services area, plant room and its supporting areas and, open

project site area.

Building, core and shell: buildings where the developer or owner will only provide the

base building and its services.

Building, existing: a building or portion thereof that was previously occupied or approved

for occupancy by the authority having jurisdiction.

Building envelope: the exterior plus the semi-exterior portions of a building. For the

purposes of determining building envelope requirements, the classifications are defined

as follows:

74

a) Building envelope, exterior: the elements of a building that separate conditioned

spaces from the exterior

b) Building envelope, semi-exterior: the elements of a building that separate

conditioned space from unconditioned space or that enclose semi-heated spaces

through which thermal energy may be transferred to or from the exterior, or to or

from unconditioned spaces, or to or from conditioned spaces

Building grounds lighting: lighting provided through a building’s electrical service for

parking lot, site, roadway, pedestrian pathway, loading dock, and security applications

Building material: any element of the building envelope through which heat flows and

that heat is included in the component U-factor calculations other than air films and

insulation

Built up area (BUA): Sum of the covered areas of all floors of a building, other than the

roof, and areas covered by external walls and parapet on these floors.

24-hour Business Building: Business building operated and occupied for more than 12

hours on each weekday. Intensity of occupancy may vary.

C

Cardinal direction: cardinal directions or cardinal points are the four main directional

points of a compass: north, south, east, and west which are also known by the first letters:

N, S, E, and W.

Carpet area: net area measured between external walls, from the inner faces of walls.

Thickness of internal or partition walls is excluded.

Centralized control: single hardware/ software for observing and controlling operations

of a group of equipment and devices with similar or different functions

Circuit breaker: a safety device that automatically stops flow of current in electrical

circuits. It protects the circuit from current surge.

Class of construction: classification that determines the construction materials for the

building envelope, roof, wall, floor, slab-on-grade floor, opaque door, vertical

fenestration, skylight

Daylight window: fenestration 2.2 meter above floor level, with an interior light shelf at

bottom of this fenestration

Coefficient of Performance (COP) – cooling: the ratio of the rate of heat removal to the

rate of energy input, in consistent units, for a complete refrigerating system or some

specific portion of that system under designated operating conditions

75

Coefficient of Performance (COP) – heating: the ratio of the rate of heat delivered to the

rate of energy input, in consistent units, for a complete heat pump system, including the

compressor and, if applicable, auxiliary heat, under designated operating conditions.

Common area: areas within a building that are available for use by all tenants in a building

(i.e. lobbies, corridors, restrooms, etc.)

Commercial building: a building or a part of building or building complex which are used

or intended to be used for commercial purposes and classified as per the time of the day

the building is operational and sub classified, as per the functional requirements of its

design, construction, and use as per following details:

a) Group I – 24 hours building covering Type A Hospitality, Type B Health Care and

Type C Assembly and,

b) Group II – Regular building covering Type D Business, Type E Educational and Type

F Shopping Complexes.

Compliance documents: the forms specified in ECBC Rules and Regulations to record and

check compliance with these rules. These include but are not limited to EPI Ratio

Compliance Report, Building Envelope Compliance Form, Mechanical Systems

Compliance Form and Permit Checklist, Lighting System Compliance Form and Permit

Checklist and certificates from Certified Energy Auditor for existing or proposed buildings.

Connected load: the sum of the rated wattage of all equipment, appliances and devices

to be installed in the building or part of building or building complexes, in terms of

kilowatt (kW) that will be allocated to all applicants for electric power consumption in

respect of the proposed building or building complexes on their completion.

Contract demand: the maximum demand in kilowatt (kW) or kilo Volt Ampere (kVA)

(within a consumer’s sanctioned load) agreed to be supplied by the electricity provider or

utility in the agreement executed between the user and the utility or electricity provider.

Construction documents: drawings or documents, containing information pertaining to

building construction processes and approvals, building materials and equipment

specification, architectural details etc. required by the authority having jurisdiction.

Controls or control device: manually operated or automatic device or software to

regulate the operation of building equipment

Cool roof: roof with top layer of material that has high solar reflectance and high thermal

emittance properties. Cool roof surfaces are characterized by light colors so that heat can

be rejected back to the environment.

76

Cumulative design EPI: energy performance index for a building having two or more

different functional uses and calculated based on the area weighted average (AWA)

method

D

Daylight area: the daylight illuminated floor area under horizontal fenestration (skylight) or

adjacent to vertical fenestration (window), described as follows:

a) Horizontal Fenestration: the area under a skylight, monitor, or sawtooth configuration

with an effective aperture greater than 0.001 (0.1%). The daylight area is calculated

as the horizontal dimension in each direction equal to the top aperture dimension in

that direction plus either the floor-to-ceiling height (H) for skylights, or 1.5 H for

monitors, or H or 2H for the sawtooth configuration, or the distance to the nearest 1

meter or higher opaque partition, or one-half the distance to an adjacent skylight or

vertical glazing, whichever is least, as shown in the plan and section figures below.

D-Hm .... .7 1251‘ka

77

b) Vertical Fenestration: the floor area adjacent to side apertures (vertical fenestration

in walls) with an effective aperture greater than 0.06 (6%). The daylight area extends

into the space perpendicular to the side aperture a distance equal to daylight

extension factor (DEF) multiplied by the head height of the side aperture or till higher

opaque partition, whichever is less. In the direction parallel to the window, the

daylight area extends a horizontal dimension equal to the width of the window plus

either 1 meter on each side of the aperture, or the distance to an opaque partition,

or one-half the distance to an adjacent skylight or window, whichever is least.

“mum... mmmm

78

Daylight Extension Factor (DEF): factor to manually calculate the daylight area on floor

plates. It is to be multiplied by the head height of windows. It is dependent on orientation

and glazing VLT, shading devices adjacent to it and building location.

Daytime Business Building: Business building operated typically only during daytime on

weekdays upto 12 hours each day.

Deadband: the range of values within which a sensed variable can vary without initiating a

change in the controlled process.

Demand: maximum rate of electricity (kW) consumption recorded for a building or facility

during a selected time frame.

Demand control ventilation (DCV): a ventilation system capability that provides automatic

reduction of outdoor air intake below design rates when the actual occupancy of spaces

served by the system is less than design occupancy

Design capacity: output capacity of a mechanical or electrical system or equipment at design

conditions

Design conditions: specified indoor environmental conditions, such as temperature, humidity

and light intensity, required to be produced and maintained by a system and under which the

system must operate

Distribution system: network or system comprising controlling devices or equipment and

distribution channels (cables, coils, ducts, pipes etc.) for delivery of electrical power or,

cooled or heated water or air in buildings

Door: all operable opening areas, that are not more than one half glass, in the building

envelope, including swinging and roll-up doors, fire doors, and access hatches. For the

purposes of determining building envelope requirements, the door types are defined as

follows:

a) Door, non-swinging: roll-up sliding, and all other doors that are not swinging doors.

b) Door, swinging: all operable opaque panels with hinges on one side and opaque

revolving doors.

Door area: total area of the door measured using the rough opening and including the door

slab and the frame.

79

E

Economizer, air: a duct and damper arrangement with automatic controls that allow a

cooling system to supply outdoor air to reduce or eliminate the need for mechanical

cooling during mild or cold weather

Economizer, water: a system by which the supply air of a cooling system is cooled

indirectly with water that is itself cooled by heat or mass transfer to the environment

without the use of mechanical cooling

ECBC Building: a building that complies with the mandatory requirements of §4 to §7 and

also complies either with the prescriptive requirements stated under the ECBC Building

categories of §4 to §7, or, with the whole building performance compliance method of

§9.

ECBC+ Building: a building that complies with the mandatory requirements of §4 to §7

and also complies either with the prescriptive requirements stated under the ECBC+

Building categories of §4 to §7, or, with the whole building performance compliance

method of §9. This is a voluntary level of compliance with ECBC.

Effective aperture: Visible Light Transmittance x window-to-wall Ratio. (EA = VLT x WWR)

Effective aperture, horizontal fenestration: a measure of the amount of daylight that

enters a space through horizontal fenestration (skylights). It is the ratio of the skylight

area times the visible light transmission divided by the gross roof area above the daylight

area. See also daylight area.

Effective aperture, vertical fenestration: a measure of the amount of daylight that enters

a space through vertical fenestration. It is the ratio of the daylight window area times its

visible light transmission plus half the vision glass area times its visible light transmission

and the sum is divided by the gross wall area. Daylight window area is located 2.2 m or

more above the floor and vision window area is located above 1 m but below 2.2 m. The

window area, for the purposes of determining effective aperture shall not include

windows located in light wells when the angle of obstruction ( ) of objects obscuring the

sky dome is greater than 70o, measured from the horizontal, nor shall it include window

area located below a height of 1 m. See also daylight area.

80

Efficacy: the lumens produced by a lamp plus ballast system divided by the total watts of

input power (including the ballast), expressed in lumens per watt

Efficiency: performance at a specified rating condition

Efficiency, thermal: ratio of work output to heat input

Efficiency, combustion: efficiency with which fuel is burned during the combustion

process in equipment

Emittance: the ratio of the radiant heat flux emitted by a specimen to that emitted by a

blackbody at the same temperature and under the same conditions

Energy: power derived from renewable or non-renewable resources to provide heating,

cooling and light to a building or operate any building equipment and appliances. It has

various forms such as thermal (heat), mechanical (work), electrical, and chemical that may

be transformed from one into another. Customary unit of measurement is watts (W)

Energy Conservation Building Code (ECBC): the Energy Conservation Building Code as

updated from time to time by the Bureau and displayed on its website

(www.beeindia.gov.in).

Energy Efficiency Ratio (EER): the ratio of net cooling capacity in kW to total rate of

electric input in watts under design operating conditions

Energy recovery system: equipment to recover energy from building or space exhaust air

and use it to treat (pre-heat or pre-cool) outdoor air taken inside the building or space by

ventilation systems

Envelope Performance Factor (EPF): value for the building envelope performance

compliance option calculated using the procedures specified in 4.3.5 and 4.3.6. For the

purposes of determining building envelope requirements the classifications are defined

as follows:

a) Standard Building EPF: envelope performance factor calculated for the Standard

Building using prescriptive requirements for walls, vertical fenestrations and roofs

81

b) Proposed Building EPF: the building envelope performance factor for the Proposed

Building using proposed values for walls, vertical fenestrations and roofs

Energy Performance Index (EPI): of a building means its annual energy consumption in

kilowatt-hours per square meter of the area of the building which shall be calculated in

the existing or proposed building as per the formula below, =annual energy consumption

in kWhtotal built−up area (excluding storage area and the parking in the basement) in m2.

EPI Ratio: of a building means the ratio of the EPI of the Proposed Building to the EPI of

the Standard Building.

Equipment: mechanical, electrical or static devices for operating a building, including but

not limited to those required for providing cooling, heating, ventilation, lighting, service

hot water, vertical circulation

Equipment, existing: equipment previously installed in an existing building

Equivalent SHGC: SHGC for a fenestration with a permanent external shading projection.

It is calculated using the Projection Factor (PF) of the permanent external shading

projection and Shading Equivalent Factor (SEF) listed in §4.3.1.

Exemption: any exception allowed to compliance with ECBC requirements

F

Fan system power: sum of the nominal power demand (nameplate W or HP) of motors

of all fans that are required to operate at design conditions to supply air from the heating

or cooling source to the conditioned space(s) and return it to the point where is can be

exhausted to outside the building.

Fenestration: all areas (including the frames) in the building envelope that let in light,

including windows, plastic panels, clerestories, skylights, glass doors that are more than

one-half glass, and glass block walls.

a) Skylight: a fenestration surface having a slope of less than 60 degrees from the

horizontal plane. Other fenestration, even if mounted on the roof of a building, is

considered vertical fenestration.

b) Vertical fenestration: all fenestration other than skylights. Trombe wall

assemblies, where glazing is installed within 300 mm of a mass wall, are

considered walls, not fenestration.

Fenestration area: total area of the fenestration measured using the rough opening and

including the glazing, sash, and frame. For doors where the glazed vision area is less than

50% of the door area, the fenestration area is the glazed vision area. For all other doors,

the fenestration area is the door area.

82

Finished floor level: level of floor achieved after finishing materials have been added to

the subfloor or rough floor or concrete floor slab.

Fossil fuel: fuel derived from a hydrocarbon deposit such as petroleum, coal, or natural

gas derived from living matter of a previous geologic time.

Fuel: a material that may be used to produce heat or generate power by combustion

Fuel utilization efficiency (FUE): a thermal efficiency measure of combustion equipment

like furnaces, boilers, and water heaters

G

Gathering hall (Type of Assembly): any building, its lobbies, rooms and other spaces

connected thereto, primarily intended for assembly of people, but which has no theatrical

stage or permanent theatrical and/or cinematographic accessories and has gathering

space for greater or equal to 100 persons, for example, stand-alone dance halls, stand-

alone night clubs, halls for incidental picture shows, dramatic, theatrical or educational

presentation, lectures or other similar purposes having no theatrical stage except a raised

platform and used without permanent seating arrangement; art galleries, community

halls, marriage halls, places of worship, museums, stand-alone lecture halls, passenger

terminals and heritage and archeological monuments, pool and billiard parlors, bowling

alleys, community halls, courtrooms, gymnasiums, indoor swimming pools, indoor tennis

court, any indoor stadium for sports and culture, auditoriums

Grade: finished ground level adjoining a building at all exterior walls

Guest room: any room or rooms used or intended to be used by a guest for sleeping

purposes

H

Habitable spaces: space in a building or structure intended or used for working, meeting,

living, sleeping, eating, or cooking. Bathrooms, water closet compartments, closets, halls,

storage or utility space, and similar areas are not considered habitable spaces.

Heat capacity: amount of heat necessary to raise the temperature of a given mass by 1°C.

Numerically, the heat capacity per unit area of surface (W/m2.K) is the sum of the

products of the mass per unit area of each individual material in the roof, wall, or floor

surface multiplied by its individual specific heat.

Hospitals and sanatoria (Healthcare): Any building or a group of buildings under single

management, which is used for housing persons suffering from physical limitations

because of health or age and those incapable of self-preservation, for example, any

hospitals, infirmaries, sanatoria and nursing homes.

83

HVAC system: equipment, distribution systems, and terminal devices that provide, either

collectively or individually, the processes of heating, ventilating, or air conditioning to a

building or parts of a building.

Hyper Markets (Type F of Shopping Complex): large retail establishments that are a

combination of supermarket and department stores. They are considered as a one-stop

shop for all needs of the customer.

I

Infiltration: uncontrolled inward air leakage through cracks and crevices in external

surfaces of buildings, around windows and doors due to pressure differences across these

caused by factors such as wind or indoor and outside temperature differences (stack

effect), and imbalance between supply and exhaust air systems

Installed interior lighting power: power in watts of all permanently installed general,

task, and furniture lighting systems and luminaires

Integrated part-load value (IPLV): weighted average efficiency of chillers measured when

they are operating at part load conditions (less than design or 100% conditions). It is more

realistic measurement of chiller efficiency during its operational life.

K

Kilovolt-ampere (kVA): where the term “kilovolt-ampere” (kVA) is used in this Code, it is

the product of the line current (amperes) times the nominal system voltage (kilovolts)

times 1.732 for three-phase currents. For single-phase applications, kVA is the product of

the line current (amperes) times the nominal system voltage (kilovolts).

Kilowatt (kW): the basic unit of electric power, equal to 1000 W.

L

Labeled: equipment or materials to which a symbol or other identifying mark has been

attached by the manufacturer indicating compliance with specified standard or

performance in a specified manner.

Lamp: a generic term for man-made light source often called bulb or tube

Lighted floor area, gross: gross area of lighted floor spaces

Lighting, emergency: battery backed lighting that provides illumination only when there

is a power outage and general lighting luminaries are unable to function.

Lighting, general: lighting that provides a substantially uniform level of illumination

throughout an area. General lighting shall not include decorative lighting or lighting that

84

provides a dissimilar level of illumination to serve a specialized application or feature

within such area.

Lighting system: a group of luminaires circuited or controlled to perform a specific

function.

Lighting power allowance:

a) Interior lighting power allowance: the maximum lighting power in watts allowed

for the interior of a building

b) Exterior lighting power allowance: the maximum lighting power in watts allowed

for the exterior of a building

Lighting Power Density (LPD): maximum lighting power per unit area of a space as per its

function or building as per its classification.

Low energy comfort systems: space conditioning or ventilation systems that are less

energy intensive then vapor compression based space condition systems. These primarily

employ alternate heat transfer methods or materials (adiabatic cooling, radiation,

desiccant, etc.), or renewable sources of energy (solar energy, geo-thermal) so that

minimal electrical energy input is required to deliver heating or cooling to spaces.

Luminaires: a complete lighting unit consisting of a lamp or lamps together with the

housing designed to distribute the light, position and protect the lamps, and connect the

lamps to the power supply.

Luminous Efficacy (LE): total luminous flux (visible light) emitted from a lamp or lamp/

ballast combination divided by input power, expressed in lumens per Watt.

M

Man-made daylight obstruction: any permanent man-made object (equipment, adjacent

building) that obstructs sunlight or solar radiation from falling on a portion or whole of a

building’s external surface at any point of time during a year is called as a man-made

sunlight obstructer.

Manual (non-automatic): requiring personal intervention for control. Non-automatic

does not necessarily imply a manual controller, only that personal intervention is

necessary.

Manufacturing processes: processes through which raw material is converted into

finished goods for commercial sale using machines, labor, chemical or biological

processes, etc.

Manufacturer: company or person or group of persons who produce and assemble goods

or purchases goods manufactured by a third party in accordance with their specifications.

85

Mean temperature: average of the minimum daily temperature and maximum daily

temperature.

Mechanical cooling: reducing the temperature of a gas or liquid by using vapor

compression, absorption, and desiccant dehumidification combined with evaporative

cooling, or another energy-driven thermodynamic cycle. Indirect or direct evaporative

cooling alone is not considered mechanical cooling.

Metering: practice of installing meters in buildings to acquire data for energy

consumption and other operational characteristics of individual equipment or several

equipment grouped on basis of their function (lighting, appliances, chillers, etc.).

Metering is done in buildings to monitor their energy performance.

Mixed mode air-conditioned building: building in which natural ventilation is employed

as the primary mode of ventilating the building, and air conditioning is deployed as and

when required.

Mixed use development: a single building or a group of buildings used for a combination

of residential, commercial, business, educational, hospitality and assembly purposes

N

National Building Code 2016 (NBC): model building code that provides guidelines for

design and construction of buildings. In this code, National Building Code 2016 refers to

the latest version by the Bureau of Indian Standards.

Natural daylight obstruction: any natural object, like tree, hill, etc., that obstructs

sunlight from falling on part or whole of a building’s external surface at any point of time

during a year and casts a shadow on the building surface.

Naturally ventilated building: a building that does not use mechanical equipment to

supply air to and exhaust air from indoor spaces. It is primarily ventilated by drawing and

expelling air through operable openings in the building envelope.

Non-cardinal directions: any direction which is not a cardinal direction, i.e. perfect north,

south, east, or west, is termed as non-cardinal direction.

No Star hotel (Type of Hospitality): any building or group of buildings under the same

management, in which separate sleeping accommodation on commercial basis, with or

without dining facilities or cooking facilities, is provided for individuals. This includes

lodging rooms, inns, clubs, motels, no star hotel and guest houses and excludes residential

apartments rented on a lease agreement of 4 months or more. These shall also include

any building in which group sleeping accommodation is provided, with or without dining

facilities for persons who are not members of the same family, in one room or a series of

86

adjoining rooms under joint occupancy and single management, for example, school and

college dormitories, students, and other hostels and military barracks.

O

Occupant sensor: a device that detects the presence or absence of people within an area

and causes lighting, equipment, or appliances to be dimmed, or switched on or off

accordingly.

Opaque assembly or opaque construction: surface of the building roof or walls other

than fenestration and building service openings such as vents and grills.

Opaque external wall: external wall composed of materials which are not transparent or

translucent, usually contains the structural part of the building, and supports the glazed

façade. This type may be composed of one or more materials, and can accommodate

various physical processes at a time, as the insulation and thermal inertia.

Open Gallery Mall (Type of Shopping Complex): a large retail complex containing a

variety of stores and often restaurants and other business establishments housed in a

series of connected or adjacent buildings or in a single large building. The circulation area

and atrium of the open gallery mall is an unconditioned space and is open to sky.

Orientation: the direction a building facade faces, i.e., the direction of a vector

perpendicular to and pointing away from the surface of the facade. For vertical

fenestration, the two categories are north-oriented and all other.

Outdoor (outside) air: air taken from the outside the building and has not been previously

circulated through the building.

Out-patient Healthcare (Type of Healthcare): any building or a group of buildings under

single management, which is used only for treating persons requiring treatment or

diagnosis of disease but not requiring overnight or longer accommodation in the building

during treatment or diagnosis.

Overcurrent: any current in excess of the rated current of the equipment of the ampacity

of the conductor. It may result from overload, short circuit, or ground fault.

Owner: a person, group of persons, company, trust, institute, Registered Body, state or

central Government and its attached or sub-ordinate departments, undertakings and like

agencies or organization in whose name the property stands registered in the revenue

records for the construction of a building or building complex

P

Party wall: a firewall on an interior lot line used or adapted for joint service between two

buildings.

87

Permanently installed: equipment that is fixed in place and is not portable or movable.

Plenum: a compartment or chamber to which one or more ducts are connected, that

forms a part of the air distribution system, and that is not used for occupancy or storage.

Plug loads: energy used by products that are powered by means of an AC plug. This term

excludes building energy that is attributed to major end uses specified in § 5, § 6, § 7 (like

HVAC, lighting, water heating, etc.).

Pool: any structure, basin, or tank containing an artificial body of water for swimming,

diving, or recreational bathing. The terms include, but no limited to, swimming pool,

whirlpool, spa, hot tub.

Potential daylit time: amount of time in a day when there is daylight to light a space

adequately without using artificial lighting. Potential daylit time is fixed for 8 hours per

day i.e. from 09:00 AM to 5:00 PM local time, resulting 2920 hours in total for all building

types except for Type E-1 - Educational, which shall be analyzed for 7 hours per day i.e.

from 08:00 AM to 3:00 PM local time.

Primary inter-cardinal direction: any of the four points of the compass, midway between

the cardinal points; northeast, southeast, southwest, or northwest are called primary

inter-cardinal direction.

Process load: building loads resulting from the consumption or release of energy due to

industrial processes or processes other than those for providing space conditioning,

lighting, ventilation, or service hot water heating.

Projection factor, overhang: the ratio of the horizontal depth of the external shading

projection to the sum of the height of the fenestration and the distance from the top of

the fenestration to the bottom of the farthest point of the external shading projection, in

consistent units.

88

Projection factor, side fin: the ratio of the horizontal depth of the external shading

projection to the distance from the window jamb to the farthest point of the external

shading projection, in consistent units.

Projection Factor, overhang and side fin: average of ratio projection factor for overhang

only and projection factor of side fin only.

Proposed Building: is consistent with the actual design of the building and complies with

all the mandatory requirements of ECBC.

Proposed Design: a computer model of the proposed building, consistent with its actual

design, which complies with all the mandatory requirements of ECBC.

R

R-value (thermal resistance): the reciprocal of the time rate of heat flow through a unit

area induced by a unit temperature difference between two defined surfaces of material

or construction under steady-state conditions. Units of R value are m2.K /W.

Readily accessible: capable of being reached quickly for operation, renewal, or

inspections without requiring those to whom ready access is requisite to climb over or

remove obstacles or to resort to portable ladders, chairs, etc. In public facilities,

accessibility may be limited to certified personnel through locking covers or by placing

equipment in locked rooms.

Recirculating system: a domestic or service hot water distribution system that includes a

close circulation circuit designed to maintain usage temperatures in hot water pipes near

terminal devices (e.g., lavatory faucets, shower heads) in order to reduce the time

required to obtain hot water when the terminal device valve is opened. The motive force

for circulation is either natural (due to water density variations with temperature) or

mechanical (recirculation pump).

Reflectance: ratio of the light or radiation reflected by a surface to the light or radiation

incident upon it.

Renewable Energy Generating Zone: a contiguous or semi-contiguous area, either on

rooftop or elsewhere within site boundary, dedicated for installation of renewable energy

systems.

Resort (Type of Hospitality): commercial establishments that provide relaxation and

recreation over and above the accommodation, meals and other basic amnesties. The

characteristics of resort are as below –

i. Includes 1 or more recreation(s) facility like spa, swimming pool, or any sport;

ii. Is located in the midst of natural and picturesque surroundings outside the city;

89

iii. Comprises of 2 or more blocks of buildings within the same site less than or equal

to 3 floors (including the ground floor).

Reset: automatic adjustment of the controller set point to a higher or lower value.

Roof: the upper portion of the building envelope, including opaque areas and

fenestration, that is horizontal or tilted at an angle of less than 60° from horizontal. This

includes podium roof as well which are exposed to direct sun rays.

Roof area, gross: the area of the roof measured from the exterior faces of walls or from

the centerline of party walls

S

Selectivity ratio of a glass: ratio between light transmission and solar factor of glass.

Service: the equipment for delivering energy from the supply or distribution system to

the premises served.

Service water heating equipment: equipment for heating water for domestic or

commercial purposes other than space heating and process requirements.

Set point: the desired temperature (°C) of the heated or cooled space that must be

maintained by mechanical heating or cooling equipment.

Shading Coefficient (SC): Measure of thermal performance of glazing. It is the ratio of

solar heat gain through glazing due to solar radiation at normal incidence to that occurring

through 3 mm thick clear, double-strength glass. Shading coefficient, as used herein, does

not include interior, exterior, or integral shading devices.

Shading Equivalent Factor: coefficient for calculating effective SHGC of fenestrations

shaded by overhangs or side fins.

Shopping Mall (Shopping Complex): a large retail complex containing a variety of stores

and often restaurants and other business establishments housed in a series of connected

or adjacent buildings or in a single large building. The circulation area and atrium of the

mall is an enclosed space covered completely by a permanent or temporary structure.

Simulation program: software in which virtual building models can be developed to

simulate the energy performance of building systems.

Single-zone system: an HVAC system serving a single HVAC zone.

Site-recovered energy: waste energy recovered at the building site that is used to offset

consumption of purchased fuel or electrical energy supplies.

90

Slab-on-grade floor: floor slab of the building that is in contact with ground and that is

either above grade or is less than or equal to 300 mm below the final elevation of the

nearest exterior grade.

Soft water: water that is free from dissolved salts of metals such as calcium, iron, or

magnesium, which form insoluble deposits on surfaces. These deposits appear as scale in

boilers or soap curds in bathtubs and laundry equipment.

Solar energy source: source of thermal, chemical, or electrical energy derived from

direction conversion of incident solar radiation at the building site.

Solar Heat Gain Coefficient (SHGC): the ratio of the solar heat gain entering the space

through the fenestration area to the incident solar radiation. Solar heat gain includes

directly transmitted solar heat and absorbed solar radiation, which is then reradiated,

conducted, or convected into the space.

Space: an enclosed area within a building. The classifications of spaces are as follows for

purpose of determining building envelope requirements:

a) Conditioned space: a cooled space, heated space, or directly conditioned space.

b) Semi-heated space: an enclosed space within a building that is heated by a heating

system whose output capacity is greater or equal to 10.7 W/m2 but is not a

conditioned space.

c) Non-conditioned space: an enclosed space within a building that is not

conditioned space or a semi-heated space. Crawlspaces, attics, and parking

garages with natural or mechanical ventilation are not considered enclosed

spaces.

Star Hotels/motels (Star Hotel): any building or group of buildings under single

management and accredited as a starred hotel by the Hotel and Restaurant Approval and

Classification Committee, Ministry of Tourism, in which sleeping accommodation, with or

without dining facilities is provided.

Stand-alone Retail (Shopping Complex): a large retail store owned or sublet to a single

management which may offer customers a variety of products under self-branding or

products of different brands. The single management shall have a complete ownership of

all the spaces of the building and no space within the building is further sold or sublet to

a different management.

Standard Building: a building that minimally complies with all the mandatory and

prescriptive requirements of Energy Conservation Building Code and has same floor area,

gross wall area, and gross roof area of the Proposed Building.

91

Standard Design: a computer model of a hypothetical building, based on actual building

design, that fulfils all the mandatory requirements and minimally complies with the

prescriptive requirements of ECBC, as described in the Whole Building Performance

method.

Story: portion of a building that is between one finished floor level and the next higher

finished floor level or building roof. Basement and cellar shall not be considered a story.

Summer Solar Insolation: measure of solar radiation energy received on a given surface

area from the month of March to October within the same calendar year. Units of

measurement are watts per square meter (W/m²) or kilowatt-hours per square meter per

day (kW×h/ (m²×day)) (or hours/day).

SuperECBC Building: a building that complies with the mandatory requirements of §4 to

§7 and also complies either with the prescriptive requirements stated under the

SuperECBC Building categories of §4 to §7, or, with the whole building performance

compliance method of §9. This is a voluntary level of compliance with ECBC.

Super Market (Shopping Complex): supermarkets are large self-service grocery stores

that offer customers a variety of foods and household supplies. The merchandise is

organized into an organized aisle format, where each aisle has only similar goods placed

together.

System: a combination of equipment and auxiliary devices (e.g., controls, accessories,

interconnecting means, and terminal elements) by which energy is transformed so it

performs a specific function such as HVAC, service water heating, or lighting.

System Efficiency: the system efficiency is the ratio of annual kWh electricity

consumption of equipment of water cooled chilled water plant (i.e. chillers, chilled and

condenser water pumps, cooling tower) to chiller thermal kWh used in a building.

System, existing: a system or systems previously installed in an existing building.

T

Tenant lease agreement: The formal legal document entered into between a Landlord

and a Tenant to reflect the terms of the negotiations between them; that is, the lease

terms have been negotiated and agreed upon, and the agreement has been reduced to

writing. It constitutes the entire agreement between the parties and sets forth their basic

legal rights.

Tenant leased area: area of a building that is leased to tenant(s) as per the tenant lease

agreement. Terminal device: a device through which heated or cooled air is supplied to a

space to maintain its temperature. It usually contains dampers and heating and cooling

92

coils. Or a device by which energy form a system is finally delivered. e.g., registers,

diffusers, lighting fixtures, faucets, etc.

Theater or motion picture hall (Type of Assembly): any building primarily meant for

theatrical or operatic performances and which has a stage, proscenium curtain, fixed or

portable scenery or scenery loft, lights, mechanical appliances or other theatrical

accessories and equipment for example, theaters, motion picture houses, auditoria,

concert halls, television and radio studios admitting an audience and which are provided

with fixed seats.

Thermal block: a collection of one or more HVAC zones grouped together for simulation

purposes. Spaces need not be contiguous to be combined within a single thermal block.

Thermal comfort conditions: conditions that influence thermal comfort of occupants.

Environmental conditions that influence thermal comfort air and radiant temperature,

humidity, and air speed.

Thermostat: device containing a temperature sensor used to automatically maintain

temperature at a desirable fixed or adjustable set point in a space.

Tinted: (as applied to fenestration) bronze, green, or grey coloring that is integral with

the glazing material. Tinting does not include surface applied films such as reflective

coatings, applied either in the field or during the manufacturing process.

Transformer: a piece of electrical equipment used to convert electric power from one

voltage to another voltage.

Transformer losses: electrical losses in a transformer that reduces its efficiency.

Transport Buildings (Assembly): any building or structure used for the purpose of

transportation and transit like airports, railway stations, bus stations, and underground

and elevated mass rapid transit system example, underground or elevated railways.

U

Unconditioned buildings: building in which more than 90% of spaces are unconditioned

spaces.

Unconditioned space: mechanically or naturally ventilated space that is not cooled or

heated by mechanical equipment.

Universities and all others coaching/ training institutions (Educational): a building or a

group of buildings, under single management, used for imparting education to students

numbering more than 100 or public or private training institution built to provide training/

coaching etc.

93

Useful Daylight Illuminance: percentage of annual daytime hours that a given point on a

work plane height of 0.8 m above finished floor level receives daylight between 100 lux

to 2,000 lux.

U-factor (Thermal Transmittance): heat transmission in unit time through unit area of a

material or construction and the boundary air films, induced by unit temperature

difference between the environments on each side. Unit of U value is W/m2.K.

V

Variable Air Volume (VAV) system: HVAC system that controls the dry-bulb temperature

within a space by varying the volumetric flow of heated or cooled air supplied to the space

Vegetative roofs: also known as green roofs, they are thin layers of living vegetation

installed on top of conventional flat or sloping roofs.

Ventilation: the process of supplying or removing air by natural or mechanical means to

or from any space. Such air is not required to have been conditioned.

Vision Windows: windows or area of large windows that are primarily for both daylight

and exterior views. Typically, their placement in the wall is between 1 meter and 2.2

meter above the floor level.

W

Wall: that portion of the building envelope, including opaque area and fenestration, that

is vertical or tilted at an angle of 60° from horizontal or greater. This includes above- and

below-grade walls, between floor spandrels, peripheral edges of floors, and foundation

walls.

a) Wall, above grade: a wall that is not below grade

b) Wall, below grade: that portion of a wall in the building envelope that is entirely

below the finish grade and in contact with the ground

Wall area, gross: the overall area off a wall including openings such as windows and doors

measured horizontally from outside surface to outside service and measured vertically

from the top of the floor to the top of the roof. If roof insulation is installed at the ceiling

level rather than the roof, then the vertical measurement is made to the top of the ceiling.

The gross wall area includes the area between the ceiling and the floor for multi-story

buildings.

94

Water heater: vessel in which water is heated and withdrawn for use external to the

system.

Z

Zone, HVAC: a space or group of spaces within a building with heating and cooling

requirements that are sufficiently similar so that desired conditions (e.g., temperature)

can be maintained throughout using a single sensor (e.g., thermostat or temperature

sensor).

8.3 SI to IP Conversion Factors

SI Unit IP Unit

1 cmh 1.7 cfm

1 Pa 0.0040 inch of water gauge

1m 3.28 ft

1m 39.37 in

1mm 0.039 in

1 l/s 2.12 cfm

1 m2 10.76 ft2

1 W/m2 10.76 W/ ft2

1 W/ lin m 3.28 W/ ft

1 W/m4.K 5.678 Btu/ h-ft2-°F

1 W/ l-s-1 0.063 W/ gpm

1 m2.K/W 0.1761 ft2-h-°F/ Btu

1 °C ((°C x 9/5) + 32) °F

1 kWr 0.284 TR

1 kW 1.34 hp

1 kW 3412.142 Btu/hr

n mm v". m ‘ ‘ mm m w M M

95

8.4 Abbreviations and Acronyms

AFUE Annual fuel utilization efficiency

AHRI Air-conditioning, Heating and Refrigeration

Institute

ANSI American National Standards Institute

ARI Air-Conditioning and Refrigeration Institute

ASHRAE American Society of Heating, Refrigerating and

Air-Conditioning Engineers

ASTM American Society for Testing and Materials

BIS Bureau of Indian Standards

Btu British thermal unit

Btu/h British thermal units per hour

Btu/h-ft2-°F British thermal units per hour per square foot

per degree Fahrenheit

BUA Built up area

C Celsius

cmh cubic meter per hour

cm centimeter

COP coefficient of performance

DEF daylight extent factor

EER energy efficiency ratio

EPI energy performance index

F Fahrenheit

ft foot

h hour

h-ft2-°F/Btu hour per square foot per degree Fahrenheit per

British thermal unit

h-m2-°C/W hour per square meter per degree Celsius per

Watt

hp horsepower

HVAC heating, ventilation, and air conditioning

I-P inch-pound

in. inch

IPLV integrated part-load value

IS Indian Standard

ISO International Organization for Standardization

kVA kilovolt-ampere

96

kW Kilowatt of electricity

kWr kilowatt of refrigeration

kWh kilowatt-hour

l/s liter per second

LE luminous efficacy

lin linear

lin ft linear foot

lin m linear meter

lm lumens

Lm/W lumens per watt

LPD lighting power density

m meter

mm millimeter

m2 square meter

m2.K/W square meter Kelvin per watt

NBC National Building Code 2016

Pa pascal

PF projection factor

R R-value (thermal resistance)

SC shading coefficient

SEF Shading equivalent factor

SHGC solar heat gain coefficient

TR tons of refrigeration

UPS uninterruptible power supply

VAV variable air volume

VLT visible light transmission

W watt

W/ l-s-1 watt per litre per second

W/m2 watts per square meter

W/m2.K watts per square meter per Kelvin

W/m2 watts per hour per square meter

W/m.K watts per lineal meter per Kelvin

Wh watthour

97

9. Whole Building Performance Method

9.1 General

9.1.1 Scope

The Whole Building Performance Method is an alternative to the Prescriptive Method compliance

path contained in §4 through §7 of this Code. It applies to all building types covered by the Code

as mentioned in §2.5.

9.1.2 Compliance

A building complies with the Code using the Whole Building Performance (WBP) Method, when

the estimated EPI Ratio is equal to or less than 1, even though it may not comply with the specific

provisions of the prescriptive requirements in §4 trough §7. The mandatory requirements of §4

through §7 (§4.2, §5.2, §6.2, and §7.2) shall be met when using the WBP Method.

9.1.3 Annual Energy Use

Annual energy use for the purposes of the WBP Method shall be calculated in kilowatt-hours

(kWh) of electricity use per year per unit area. Energy sources other than electricity that are used

in the building shall be converted to kWh of electric energy at the rate of 0.75 kWh per megajoule.

Note: The annual energy use calculation as per the Whole Building Performance Method is not a

prediction of the actual energy use of the building once it gets operational. Actual energy

performance of a building depends on a number of factors like weather, occupant behaviour,

equipment performance and maintenance, among others, which are not covered by this Code.

9.1.4 Trade-offs Limited to Building Permit

The WBP Method may be used for building permit applications that include less than the whole

building; however, any design parameters that are not part of the building permit application

shall be identical for both the Proposed Design and the Standard Design. Future improvements

to the building shall comply with both the mandatory and prescriptive requirements of

concurrent code.

9.1.5 Documentation Requirements

Compliance shall be documented and compliance forms shall be submitted to the authority

having jurisdiction. The information submitted shall include, at a minimum, the following:

a) Summary describing the results of the analysis, including the annual energy use for the

Proposed Design and the Standard Design, and software used.

b) Brief description of the project with location, number of stories, space types, conditioned

and unconditioned areas, hours of operation.

98

c) List of the energy-related building features of the Proposed Design. This list shall also

document features different from the Standard Design.

d) List showing compliance with the mandatory requirements of this code.

e) The input and output report(s) from the simulation program including a breakdown of

energy usage by at least the following components: lights, internal equipment loads,

service water heating equipment, space heating equipment, space cooling and heat

rejection equipment, fans, and other HVAC equipment (such as pumps). The output

reports shall also show the number of hours any loads are not met by the HVAC system

for both the Proposed Design and Standard Design.

f) Explanation of any significant modelling assumptions made.

g) Explanation of any error messages noted in the simulation program output.

h) Building floor plans, building elevations, and site plan.

9.2 Mandatory Requirements

All requirements of §4.2, §5.2, §6.2, and §7.2 shall be met. These sections contain the mandatory

provisions of the Code and are prerequisites for demonstrating compliance using the WBP

Method.

9.3 Simulation Requirements

9.3.1 Energy Simulation Program

The simulation software shall be a computer-based program for the analysis of energy

consumption in buildings and be approved by the authority having jurisdiction. The simulation

program shall, at a minimum, have the ability to model the following:

a) Energy flows on an hourly basis for all 8,760 hours of the year,

b) Hourly variations in occupancy, lighting power, miscellaneous equipment power,

thermostat set points, and HVAC system operation, defined separately for each day of the

week and holidays,

c) Thermal mass effects,

d) Ten or more thermal zones,

e) Part-load and temperature dependent performance of heating and cooling equipment,

f) Air-side and water-side economizers with integrated control.

In addition to the above, the simulation tool shall be able to produce hourly reports of energy

use by energy source and shall have the capability to performing design load calculations to

determine required HVAC equipment capacities, air, and water flow rates in accordance with §5

for both the proposed and Standard building designs.

99

The simulation program shall be tested according to ASHRAE Standard 140 Method of Test for

the Evaluation of Building Energy Analysis Computer Programs (ANSI approved) and the results

shall be furnished by the software provider.

9.3.2 Climate Data

The simulation program shall use hourly values of climatic data, such as temperature and

humidity, from representative climatic data for the city in which the Proposed Design is to be

located. For cities or urban regions with several climate data entries, and for locations where

weather data are not available, the designer shall select available weather data that best

represent the climate at the construction site.

9.3.3 Compliance Calculations

The Proposed Design and Standard Design shall be calculated using the following:

a) Same simulation program,

b) Same weather data, and

c) Identical building operation assumptions (thermostat set points, schedules, equipment

and occupant loads, etc.) unless an exception is allowed by this Code or the authority

having jurisdiction for a given category.

9.4 Calculating Energy Consumption of Proposed Design and Standard Design

9.4.1 Energy Simulation Model

The simulation model for calculating the Proposed Design and the Standard Design shall be

developed in accordance with the requirements in Table 9-1. The Standard Design is based on

the mandatory and prescriptive requirements of the ECBC compliant building. The Standard

Design will be the same for all compliance levels (ECBC, ECBC+, Super ECBC).

9.4.2 HVAC Systems

The HVAC system type and related performance parameters for the Standard Design shall be

determined from Table 9-2 and the following rules:

a) Other components: Components and parameters not listed in Table 9-2 or otherwise

specifically addressed in this subsection shall be identical to those in the Proposed Design.

Exception to § 9.4.2(a): Where there are specific requirements in §5.2.2, the component

efficiency in the Standard Design shall be adjusted to the lowest efficiency level allowed

by the requirement for that component type.

b) All HVAC and service water heating equipment in the Standard Design shall be modeled

at the minimum efficiency levels, both part load and full load, in accordance with §5.2.2.

100

c) Where efficiency ratings, such as EER and COP, include fan energy, the descriptor shall be

broken down into its components so that supply fan energy can be modeled separately.

d) Minimum outdoor air ventilation rates shall be the same for both the Standard Design

and the Proposed Design except for conditions specified in §9.4.2.1.

e) The equipment capacities for the Standard Design shall be sized proportionally to the

capacities in the Proposed Design based on sizing runs; i.e., the ratio between the

capacities used in the annual simulations and the capacities determined by the sizing runs

shall be the same for both the Proposed Design and Standard Design.

f) Unmet load hours for the Proposed Design shall not differ from unmet load hours for the

Standard Design by more than 50 hours. Maximum number of unmet hours shall not

exceed 300 for either case.

Table 9-1 Modelling Requirements for Calculating Proposed and Standard Design

Case Proposed Design Standard Design

1. Design Model

a) The simulation model of the Proposed Design shall be consistent with the design documents, including proper accounting of fenestration and opaque envelope types and area; interior lighting power and controls; HVAC system types, sizes, and controls; and service water heating systems and controls.

b) When the whole building performance method is applied to buildings in which energy-related features have not been designed yet (e.g., a lighting system), those yet-to-be-designed features shall be described in the Proposed Design so that they minimally comply with applicable mandatory and prescriptive requirements of §4.2, §5.2 , §6.2, and §7.2 and §4.3, §5.3, and §6.3 respectively.

The Standard Design shall be developed by modifying the Proposed Design as described in this table. Unless specified in this table, all building systems and equipment shall be modeled identically in the Standard Design and Proposed Design.

2. Space Use Classification

The building type or space type classifications shall be chosen in accordance with §2.5. More than one building type category may be used in a building if it is a mixed-use facility.

Same as Proposed Design.

3. Schedules

Operational schedules (hourly variations in occupancy, lighting power, equipment

Same as Proposed Design.

101

power, HVAC equipment operation, etc.) suitable for the building and/or space type shall be modeled for showing compliance. Schedules must be modeled as per §9.6. In case a schedule for an occupancy type is missing in §9.6, appropriate schedule may be used. Temperature and humidity schedules and set points shall be identical in the Standard and Proposed Designs. Temperature control/ thermostat throttling ranges shall also be modeled identically in both the Designs

Exception: Schedules may be allowed to differ between the Standard and Proposed models wherever it is necessary to model nonstandard efficiency measures and/ or measures which can be best approximated by a change in schedule. Measures that may warrant a change in operating schedules include but are not limited to automatic controls for lighting, natural ventilation, demand controlled ventilation systems, controls for service water heating load reduction. Schedule change is not allowed for manual controls under any category. This is subject to approval by the authority having jurisdiction.

4. Building Envelope

All components of the building envelope in the Proposed Design shall be modeled as shown on architectural drawings or as installed for existing building envelopes. Exceptions: The following building elements are permitted to differ from architectural drawings. a) Any envelope assembly that covers

less than 5% of the total area of that assembly type (e.g., exterior walls) need not be separately described. If not separately described, the area of an envelope assembly must be added to the area of the adjacent assembly of that same type.

b) Exterior surfaces whose azimuth orientation and tilt differ by no more than 45 degrees and are otherwise the same may be described as either a single surface or by using multipliers.

The Standard Design shall have identical conditioned floor area and identical exterior dimensions and orientations as the Proposed Design, except as noted in (a), (b), (c), and (d) below. a) Orientation. The Standard

Design performance shall be generated by simulating the building with its actual orientation and again after rotating the entire building 90, 180, 270 degrees, then averaging the results. The building shall be modeled so that it does not shade itself.

b) Opaque assemblies such as roof, floors, doors, and walls shall be modeled as

102

c) For exterior roofs, other than roofs with ventilated attics, the reflectance and emittance of the roof surface shall be modeled in accordance with §4.3.1.1.

d) Manually operated fenestration shading devices such as blinds or shades shall not be modeled. Permanent shading devices such as fins, overhangs, and light shelves shall be modeled.

e) The exterior roof surface shall be modeled using the solar reflectance in accordance with ASTM E903-96 and thermal emittance determined in accordance with ASTM E408-71. Where cool roof is proposed, emittance and reflectance shall be modeled as per ASTM E408-71 and ASTM E903-96 respectively. Where cool roof is not proposed, the exterior roof surface shall be modeled with a reflectance of 0.3 and a thermal emittance of 0.9.

having the same heat capacity as the Proposed Design but with the maximum U-factor allowed in §4.3.1 and §4.3.1.1.

c) Fenestration. Fenestration areas shall equal that in the Proposed Design or 40% of gross above grade wall area, whichever is smaller, and shall be distributed on each face in the same proportions as in the Proposed Design No shading projections are to be modeled; fenestration shall be assumed to be flush with the exterior wall or roof. Manually operated fenestration shading devices such as blinds or shades shall not be modeled. Fenestration U- factor shall be the maximum allowed for the climate, and the solar heat gain coefficient shall be the maximum allowed for the climate and orientation.

d) Roof Solar Reflectance and Thermal Emittance: The exterior roof surfaces shall be modeled using a solar reflectance of 0.6 and a thermal emittance of 0.9.

5. Lighting

Lighting power in the Proposed Design shall be determined as follows: Where a complete lighting system exists, the actual lighting power shall be used in the model. Where a lighting system has been designed, lighting power shall be determined in accordance with either §6.3.4.

Lighting power in the Standard Design shall be determined using the same categorization procedure (building area or space function) and categories as the Proposed Design with lighting power set equal to the maximum allowed for the

103

Where no lighting exists, or is specified, lighting power shall be determined in accordance with the §6.3.2 or §6.3.3 for the appropriate building type. Lighting system power shall include all lighting system components shown or provided for on plans (including lamps, ballasts, task fixtures, and furniture- mounted fixtures). Lighting power for parking garages and building facades shall be modeled. Minimum Lighting controls, as per the ECBC requirements of §6.2.1, shall be modeled in the Proposed case. Automatic daylighting controls shall be modeled directly in the software or through schedule adjustments determined by a separate daylight analysis approved by the authority having jurisdiction. Other automatic lighting controls shall be modeled directly in the software by adjusting the lighting power as per Table 9-4.

corresponding method and category in either §6.3.2 or §6.3.3. Power for fixtures not included in the lighting power density calculation shall be modeled identically in the Proposed Design and Standard Design. Lighting controls shall be as per the ECBC requirements of §6.2.1.

6. HVAC Thermal Zones

HVAC Zones Designed: Where HVAC zones are defined on design drawings, each HVAC zone shall be modeled as a separate thermal block. Exception: Identical zones (similar occupancy and usage, similar internal loads, similar set points and type of HVAC system, glazed exterior walls face the same orientation or vary by less than 45°) may be combined for simplicity. HVAC Zones Not Designed: Where HVAC zones are not defined on design drawings, HVAC zones shall be defined based on similar occupancy and usage, similar internal loads, similar set points and type of HVAC system, glazed exterior walls that face the same orientation or vary by less than 45° in combination with the following rules:

Same as Proposed Design

104

Perimeter Core Zoning: Separate thermal block shall be modeled for perimeter and core spaces. Perimeter spaces are defined as spaces located within 5 meters of an exterior or semi exterior wall. Core spaces are defined as spaces located greater than 5 meters of an exterior or semi exterior wall. Separate thermal blocks shall be modeled for floors in contact with ground and for floors which have a ceiling/roof exposure to the ambient.

7. HVAC Systems

The HVAC system type and all related performance parameters, such as equipment capacities and efficiencies, in the Proposed Design shall be determined as follows: a) Where a complete HVAC system exists,

the model shall reflect the actual system type using actual component capacities and efficiencies.

b) Where an HVAC system has been designed, the HVAC model shall be consistent with design documents. Mechanical equipment efficiencies shall be adjusted from actual design conditions to the rating conditions specified in §5, if required by the simulation model.

c) Where no heating system has been specified, the heating system shall be assumed to be electric. The system characteristics shall be identical to the system modeled in the Standard Design.

d) Where no cooling system has been specified, the cooling system and its characteristics shall be identical to the system modeled in the Standard Design.

The HVAC system type shall be as per Table 9-2 and related performance parameters for the Standard Design shall be determined from requirements of §9.4.2. Equipment performance shall meet the requirements of §5 for code compliant building.

8. Service Hot Water

The service hot water system type and all related performance parameters, such as equipment capacities and efficiencies, in

The service water heating system shall be of the same type as the Proposed Design.

105

the Proposed Design shall be determined as follows: a) Where a complete service hot water

system exists, the model shall reflect the actual system type using actual component capacities and efficiencies.

b) Where a service hot water system has been designed, the service hot water model shall be consistent with design documents.

c) Where no service hot water system exists, or is specified, no service hot water heating shall be modeled.

For residential facilities, hotels and hospitals the Standard Design shall have a solar hot water system capable of meeting 20% of the hot water demand. Systems shall meet the efficiency requirements of §5.2.9.2, the pipe insulation requirements of §5.2.9.4 and incorporate heat traps in accordance with §5.2.9.5.

9. Miscellaneous Loads

Receptacle, motor, and process loads shall be modeled and estimated based on the building type or space type category. These loads shall be included in simulations of the building and shall be included when calculating the Standard Design and Proposed Design. All end-use load components within and associated with the building shall be modeled, unless specifically excluded by this Table, but not limited to, exhaust fans, parking garage ventilation fans, exterior building lighting, swimming pool heaters and pumps, elevators and escalators, refrigeration equipment, and cooking equipment.

Receptacle, motor and process loads shall be modeled the same as the Proposed Design.

10. Modelling Limitations to the Simulation Program

If the simulation program cannot model a component or system included in the Proposed Design, one of the following methods shall be used with the approval of the authority having jurisdiction: a) Ignore the component if the energy

impact on the trade-offs being considered is not significant.

b) Model the component substituting a thermodynamically similar component model.

c) Model the HVAC system components or systems using the HVAC system of the Standard Design in accordance with Section 6 of this table.

Same as Proposed Design.

106

d) Whichever method is selected, the component shall be modeled identically for both the Proposed Design and Standard Design models.

Table 9-2 HVAC Systems Map for Standard Design

Hotel/Motel,

Hospital Patient

Rooms, Hotel

Guest Rooms,

Resorts, Villas,

Sleeping Quarters

in Mixed-use

Buildings, Schools,

Classrooms/Lecture

Rooms1

Buildings with

Less than or

Equal to

12,500 m² of

Conditioned

Area

Buildings with

More than

12,500 m² of

Conditioned

Area

Data Centre/

Server/Computer

Rooms

Name System A System B System C System D

System Type2 Split AC VRF : Variable

Refrigerant

Flow

VAV: Central

cooling plant

with variable

volume AHU

for each zone

Computer Room

air conditioners

Fan Control Constant Volume Constant

volume

Variable

volume

Constant volume

Cooling Type Direct expansion

with air cooled

condenser

Direct

expansion with

air cooled

condenser

Chilled Water

with water

cooled

condenser

Direct expansion

with air cooled

condenser

Heating Type 1. Heat Pump:

Where no heating

system has been

specified or where

an electric heating

system has been

1. Heat Pump:

Where no

heating system

has been

specified or

where an

electric heating

system has

1. Electric

resistance:

Where no

heating system

has been

specified or

where an

electric heating

NA

107

specified in the

Proposed Design

2. Fossil Fuel Boiler:

Where a heating

system exists and a

fossil fuel hot water

boiler has been

specified in the

Proposed Design

been specified

in the

Proposed

Design

2. Fossil Fuel

Boiler: Where a

heating system

exists and a

fossil fuel hot

water boiler

has been

specified in the

Proposed

Design

system has

been specified

in the

Proposed

Design

2. Fossil Fuel

Boiler: Where a

heating system

exists and a

fossil fuel hot

water boiler

has been

specified in the

Proposed

Design

Notes:

1. Buildings of the listed occupancy types or spaces in Mixed-use Buildings with the listed

occupancy types.

2. Where attributes make a building eligible for more than one system type; use the

predominant condition to determine the Standard Design system type provided the non-

predominant conditions apply to less than 1,000 m2 of conditioned floor area. Use additional

system type for non-predominant conditions if those conditions apply to more than 1,000 m2

of conditioned floor area.

Use additional system type for any space which has a substantial difference in peak loads and/

or operational hours compared to the predominant space type. Such spaces may include but

are not limited to computer/ server rooms, retail areas in residential, or office buildings.

9.4.2.1 Minimum Outdoor air rates:

Minimum outdoor air rates shall be identical for both the Standard Design and Proposed Design,

except

a) when modeling demand controlled ventilation (DCV) in the Proposed Design (DCV is not

required in the Standard Design as per §5.2.1.4)

b) when the Proposed Design has a minimum ventilation flow higher than the minimum

required by the applicable code, the Standard Design shall be modeled as per the

108

minimum ventilation rate required by the applicable code and the Proposed Design shall

be modeled as per actual design (higher than Standard Design)

9.4.2.2 Fan Schedules

Supply and return fans shall operate continuously whenever the spaces are occupied and shall

be cycled to meet heating and cooling loads during unoccupied hours.

9.4.2.3 Fan Power

a) For Systems Types A, B and D,

Pfan = cmh x .51

Where Pfan = Standard Design fan power in watts

cmh = Standard Design supply airflow rate auto-sized by the simulation software

b) For System Type C

Fan power shall be modeled as per power and efficiency limits specified in Table 5-12

using a static pressure of 622 Pa or the design static pressure, whichever is higher. The

simulation software shall automatically calculate the Standard Design fan power based

on the above inputs.

9.4.2.4 Design Airflow Rates

Design airflow rates for the Standard Design shall be sized based on a supply air to room air

temperature difference of 11 °C. The Proposed Design airflow rates shall be as per design.

9.4.2.5 Economizers (airside and waterside)

Airside economizers shall be modeled in the Standard Design as per the requirements of §5.3.3.

Exception to §9.4.2.5: Airside economizer shall not be modeled for Standard Design HVAC System

Type A.

9.4.2.6 Energy Recovery

Energy recovery shall be modeled in the Standard Design as per the requirements of §5.3.

9.4.2.7 Chilled Water Design Supply Temperatures

Chilled water design supply temperature shall be modeled at 6.7° C and return temperature at

13.3° C.

9.4.2.8 Chillers

Only electric chillers shall be modeled in the Standard Design for System C. Chillers shall meet

the minimum efficiency requirements indicated in Table 5-1 and Table 5-2. Chillers in the

Standard Design shall be selected as per Table 9-3 below:

109

Table 9-3: Modeling Requirements for Calculating Proposed and Standard Design

Peak Building Cooling Load (kWr) Chiller Type

< 1,055 1 Water Cooled Screw Chiller

1,055 to 2,110 2 Water Cooled Screw Chillers

> 2,110 2 Water Cooled Centrifugal Chillers

minimum, equally sized such that no Chiller

is greater than 2,813 kWr

Exception to above: Air cooled chillers are allowed to be modeled in the Standard Design if the

Proposed Design has air cooled chillers. If the proposed building has a mix of air and water cooled

chillers, then the Standard Design shall be modeled with a mix of air and water cooled chillers in

the same proportion as in the Proposed Design. However, this exception applies only for

minimum ECBC compliance. Air cooled chillers shall not be modeled in the Standard Design when

demonstrating compliance with ECBC+ and SuperECBC Building requirements.

9.4.2.9 Chilled Water Pumps

Chilled and condenser water pumps for the Standard Design shall be modeled as per power and

efficiency limits specified in Table 5-15.

Standard Design chilled water pumps shall be modeled as primary-secondary with variable

secondary flow.

9.4.2.10 Cooling Tower

Standard Design cooling tower shall be modeled as an open circuit axial flow tower with power

and efficiency as per Table 5-18. The fans shall be modeled as two speed.

Condenser water design supply temperature shall be 29.4°C or 5.6°C approach to wet bulb

temperature, whichever is lower, with a design temperature rise of 5.6°C.

9.4.2.11 Boiler

Standard Design boilers shall be modeled as natural draft boilers and shall use the same fuel as

the Proposed Design. Boiler efficiency shall be modeled as per Table 5-19.

9.4.2.12 Hot Water Design Supply Temperatures

Hot water design supply temperature shall be modeled at 82°C and return temperature at 54°C.

9.4.2.13 Hot Water Pumps

The Standard Design hot water pumps shall be modeled with a minimum efficiency of 70% and a

pump power of 300 W/l-s-1.

110

Standard Design hot water pumps shall be modeled as primary-secondary with variable

secondary flow.

9.4.2.14 Campus/ District Cooling Systems

All district cooling plants shall be assumed to be on grid electricity, unless otherwise specified

and supported through pertinent documents. New district plants shall comply with the

mandatory requirements of ECBC irrespective of who owns and/or operates the district plant.

Projects may choose either option A or option B given below for modelling campus/district

cooling systems.

Option A

The cooling source shall be modeled as purchased chilled water in both the Standard Design and

Proposed Design. For the Standard Design, Table 9-2 HVAC Systems Map, shall be modified as

follows:

a) For System Type C; purchased chilled water shall be modeled as the cooling source.

b) System Types A and B shall be replaced with a two-pipe fan coil system with purchased

chilled water as the cooling source.

The chilled water/thermal energy consumption simulated by the software shall be converted to

units of kWh and added to the overall building energy consumption. The following conversion

factors shall be used to convert chilled water/thermal energy consumption to units of kWh.

1 ton hour = 0.85 kWh

1 MBtu = 1,000,000 Btu = 293 kWh

Option B

The Standard Design shall be modeled as per Table 9-2 HVAC Systems Map.

For the Proposed Design, model a virtual onsite chilled water plant with Chiller, Pumps and

cooling towers modeled at minimum efficiency levels as per §9.4.2.7 to §9.4.2.10. Airside/ low

side capacities shall be modeled as per design and the plant capacities shall be auto-sized by the

software.

Table 9-4: Power Adjustment Factors for Automatic Lighting Controls

Automatic Control Device Daytime occupancy and area

< 300 m2

All Others

Programmable Timing Control 10% 0%

Occupancy Sensor 10% 10%

Occupancy Sensor and

Programmable Timing Control

15% 10%

111

9.4.3 Compliance Thresholds for ECBC compliant, ECBC+ and SuperECBC Buildings

For buildings to qualify as ECBC+ and SuperECBC Buildings, the WBP Method shall be followed

for the Standard Design as detailed above. The Proposed Design for ECBC+ and SuperECBC

Buildings shall meet the mandatory provisions of §4.2, §5.2, §6.2, and §7.2.

The EPI Ratio for ECBC+ and SuperECBC Buildings shall be equal to or less than the EPI Ratios

listed under the applicable climate zone in Table 9-5 through Table 9-9 of §9.5.

9.5 Maximum Allowed EPI Ratios

Table 9-5: Maximum Allowed EPI Ratios for Building in Composite Climate

Building Type Composite

ECBC ECBC+ SuperECBC

Hotel (No Star and Star) 1 0.91 0.81

Resort 1 0.88 0.76

Hospital 1 0.85 0.77

Outpatient 1 0.85 0.75

Assembly 1 0.86 0.77

Office (Regular Use) 1 0.86 0.78

Office (24 Hours) 1 0.88 0.76

Schools and University 1 0.77 0.66

Open Gallery Mall 1 0.85 0.76

Shopping Mall 1 0.86 0.74

Supermarket 1 0.81 0.70

Strip retail 1 0.82 0.68

112

9.6 Schedules

Table 9-10: Schedules for Business Buildings

Business

Time Period

Occupancy

Schedule

Lighting

Schedule

Equipment

Schedule

Elevator

Schedule

D a

y ti

m e

B u

si n

e ss

2 4

H o

u r

B u

si n

e ss

D a

y ti

m e

B u

si n

e ss

2 4

H o

u r

B u

si n

e ss

D a

y ti

m e

B u

si n

e ss

2 4

H o

u r

B u

si n

e ss

D a

y ti

m e

B u

si n

e ss

2 4

H o

u r

B u

si n

e ss

00:00-01:00 0.00 0.90 0.05 0.90 0.00 0.95 0.05 0.55

01:00-02:00 0.00 0.90 0.05 0.90 0.00 0.95 0.05 0.25

02:00-03:00 0.00 0.90 0.05 0.90 0.00 0.95 0.05 0.25

03:00-04:00 0.00 0.90 0.05 0.90 0.00 0.95 0.05 0.15

04:00-05:00 0.00 0.50 0.05 0.50 0.00 0.00 0.05 0.35

05:00-06:00 0.00 0.20 0.05 0.05 0.00 0.00 0.05 0.50

06:00-07:00 0.00 0.10 0.10 0.05 0.00 0.00 0.20 0.20

07:00-08:00 0.10 0.10 0.30 0.90 0.00 0.95 0.40 0.40

08:00-09:00 0.20 0.90 0.90 0.90 0.10 0.95 0.80 0.80

09:00-10:00 0.95 0.90 0.90 0.90 0.90 0.95 0.80 0.80

10:00-11:00 0.95 0.90 0.90 0.90 0.90 0.95 0.55 0.55

11:00-12:00 0.95 0.90 0.90 0.90 0.90 0.95 0.35 0.35

12:00-13:00 0.95 0.90 0.90 0.90 0.90 0.95 0.25 0.25

13:00-14:00 0.50 0.20 0.50 0.50 0.80 0.20 0.95 0.95

14:00-15:00 0.95 0.90 0.90 0.90 0.90 0.95 0.95 0.95

15:00-16:00 0.95 0.90 0.90 0.90 0.90 0.95 0.35 0.35

16:00-17:00 0.95 0.90 0.90 0.90 0.90 0.95 0.15 0.35

17:00-18:00 0.95 0.90 0.95 0.90 0.90 0.95 0.75 0.70

18:00-19:00 0.30 0.90 0.50 0.90 0.50 0.20 0.95 0.95

19:00-20:00 0.10 0.20 0.30 0.90 0.10 0.95 0.50 0.50

20:00-21:00 0.10 0.90 0.30 0.90 0.10 0.95 0.30 0.35

21:00-22:00 0.10 0.90 0.20 0.90 0.00 0.95 0.20 0.25

22:00-23:00 0.00 0.90 0.10 0.90 0.00 0.95 0.05 0.25

23:00-24:00 0.00 0.90 0.05 0.90 0.00 0.20 0.05 0.55

113

Table 9-11 Schedules for Assembly Buildings

Assembly

Time Period O

cc u

p a

n cy

S ch

e d

u le

Li g

h ti

n g

S

ch e

d u

le

E q

u ip

m e

n t

S ch

e d

u le

E le

v a

to r

S ch

e d

u le

H V

A C

F a

n

S ch

e d

u le

(O

n /O

ff )

E xt

e rn

a l

Li g

h ti

n g

S ch

e d

u le

B a

se m

e n

t

V e

n ti

la ti

o n

B a

se m

e n

t Li

g h

ti n

g

00:00-01:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.80

01:00-02:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

02:00-03:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

03:00-04:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

04:00-05:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

05:00-06:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

06:00-07:00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.10

07:00-08:00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.10

08:00-09:00 0.20 0.40 0.30 0.20 0 0.00 1.00 0.80

09:00-10:00 0.20 0.75 0.50 0.50 1 0.00 1.00 0.80

10:00-11:00 0.20 0.95 0.95 0.50 1 0.00 1.00 0.80

11:00-12:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

12:00-13:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

13:00-14:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

14:00-15:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

15:00-16:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

16:00-17:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

17:00-18:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

18:00-19:00 0.50 0.95 0.50 0.50 1 0.80 1.00 0.80

19:00-20:00 0.20 0.40 0.30 0.40 1 0.80 1.00 0.80

20:00-21:00 0.20 0.40 0.30 0.20 0 0.80 1.00 0.80

21:00-22:00 0.20 0.40 0.30 0.20 0 0.80 1.00 0.80

22:00-23:00 0.10 0.10 0.00 0.00 0 0.80 1.00 0.80

23:00-24:00 0.10 0.10 0.00 0.00 0 0.80 0.00 0.80

114

Table 9-12 Schedules for Business - Office Buildings

Business – Office

Time Period

HVAC Fan

Schedule (On/Off)

External

Lighting

Schedule

Basement

Ventilation Basement Lighting

D a

y ti

m e

B u

si n

e ss

2 4

H o

u rs

B u

si n

e ss

7 D

a y

s/

w e

e k

D a

y ti

m e

B u

si n

e ss

2 4

H o

u rs

B u

si n

e ss

D a

y ti

m e

B u

si n

e ss

2 4

H o

u rs

B u

si n

e ss

00:00-01 00 0 1 0.80 0.00 1.00 0.05 1.00

01:00-02:00 0 1 0.80 0.00 1.00 0.05 1.00

02:00-03:00 0 1 0.80 0.00 1.00 0.05 1.00

03:00-04:00 0 1 0.80 0.00 1.00 0.05 1.00

04:00-05:00 0 1 0.80 0.00 1.00 0.05 1.00

05:00-06:00 0 1 0.80 0.00 1.00 0.05 1.00

06:00-07:00 0 1 0.00 0.00 1.00 0.05 1.00

07:00-08:00 1 1 0.00 0.00 1.00 0.05 1.00

08:00-09:00 1 1 0.00 1.00 1.00 1.00 1.00

09:00-10:00 1 1 0.00 1.00 1.00 1.00 1.00

10:00-11:00 1 1 0.00 1.00 1.00 1.00 1.00

11:00-12:00 1 1 0.00 1.00 1.00 1.00 1.00

12:00-13:00 1 1 0.00 1.00 1.00 1.00 1.00

13:00-14:00 1 1 0.00 1.00 1.00 1.00 1.00

14:00-15:00 1 1 0.00 1.00 1.00 1.00 1.00

15:00-16:00 1 1 0.00 1.00 1.00 1.00 1.00

16:00-17:00 1 1 0.00 1.00 1.00 1.00 1.00

17:00-18:00 1 1 0.00 1.00 1.00 1.00 1.00

18:00-19:00 1 1 0.80 1.00 1.00 1.00 1.00

19:00-20:00 1 1 0.80 1.00 1.00 1.00 1.00

20:00-21:00 1 1 0.80 1.00 1.00 1.00 1.00

21:00-22:00 1 1 0.80 0.00 1.00 0.05 1.00

22:00-23:00 0 1 0.80 0.00 1.00 0.05 1.00

23:00-24:00 0 1 0.80 0.00 1.00 0.05 1.00

115

Table 9-13 Schedules for Educational - School Buildings (A)

Educational - School

Time Period

Occupancy Schedule Lighting Schedule Equipment Schedule

Student

Zone

Back

Office

Student

Zone

Back

Office

Student

Zone

Back

Office

5 Days/

week

5 Days/

week

5 Days/

week

5 Days/

week

5 Days/

week

5 Days/

week

00:00-01:00 0.00 0.00 0.00 0.00 0.00 0.00

01:00-02:00 0.00 0.00 0.00 0.00 0.00 0.00

02:00-03:00 0.00 0.00 0.00 0.00 0.00 0.00

03:00-04:00 0.00 0.00 0.00 0.00 0.00 0.00

04:00-05:00 0.00 0.00 0.00 0.00 0.00 0.00

05:00-06:00 0.00 0.00 0.00 0.00 0.00 0.00

06:00-07:00 0.00 0.00 0.00 0.20 0.00 0.00

07:00-08:00 0.70 0.00 0.90 0.70 0.35 0.35

08:00-09:00 0.90 0.90 0.90 0.90 0.95 0.95

09:00-10:00 0.90 0.90 0.90 0.90 0.95 0.95

10:00-11:00 0.90 0.90 0.90 0.90 0.95 0.95

11:00-12:00 0.20 0.90 0.20 0.90 0.20 0.95

12:00-13:00 0.90 0.90 0.90 0.90 0.95 0.95

13:00-14:00 0.90 0.20 0.90 0.30 0.95 0.40

14:00-15:00 0.00 0.90 0.00 0.90 0.00 0.95

15:00-16:00 0.00 0.90 0.00 0.90 0.00 0.95

16:00-17:00 0.00 0.90 0.00 0.90 0.00 0.95

17:00-18:00 0.00 0.50 0.00 0.30 0.00 0.25

18:00-19:00 0.00 0.00 0.00 0.10 0.00 0.00

19:00-20:00 0.00 0.00 0.00 0.00 0.00 0.00

20:00-21:00 0.00 0.00 0.00 0.00 0.00 0.00

21:00-22:00 0.00 0.00 0.00 0.00 0.00 0.00

22:00-23:00 0.00 0.00 0.00 0.00 0.00 0.00

23:00-24:00 0.00 0.00 0.00 0.00 0.00 0.00

116

Schedules for Educational - School Buildings (B)

Educational - School

Time Period

Elevator Schedule

HVAC Fan Schedule (On/Off) External

Lighting Schedule

Basement Ventilation

Basement Lighting Student

Area

Back

Office

7 Days/ week

5 Days/ week

5 Days/ week

7 Days/ week

7 Days/ week

7 Days/ week

00:00-01:00 0.00 0.00 0.00 0.00 0.00 0.00

01:00-02:00 0.00 0.00 0.00 0.00 0.00 0.00

02:00-03:00 0.00 0.00 0.00 0.00 0.00 0.00

03:00-04:00 0.00 0.00 0.00 0.00 0.00 0.00

04:00-05:00 0.00 0.00 0.00 0.00 0.00 0.00

05:00-06:00 0.00 0.00 0.00 0.00 0.00 0.00

06:00-07:00 0.00 0.00 0.00 0.20 0.00 0.00

07:00-08:00 0.70 0.00 0.90 0.70 0.35 0.35

08:00-09:00 0.90 0.90 0.90 0.90 0.95 0.95

09:00-10:00 0.90 0.90 0.90 0.90 0.95 0.95

10:00-11:00 0.90 0.90 0.90 0.90 0.95 0.95

11:00-12:00 0.20 0.90 0.20 0.90 0.20 0.95

12:00-13:00 0.90 0.90 0.90 0.90 0.95 0.95

13:00-14:00 0.90 0.20 0.90 0.30 0.95 0.40

14:00-15:00 0.00 0.90 0.00 0.90 0.00 0.95

15:00-16:00 0.00 0.90 0.00 0.90 0.00 0.95

16:00-17:00 0.00 0.90 0.00 0.90 0.00 0.95

17:00-18:00 0.00 0.50 0.00 0.30 0.00 0.25

18:00-19:00 0.00 0.00 0.00 0.10 0.00 0.00

19:00-20:00 0.00 0.00 0.00 0.00 0.00 0.00

20:00-21:00 0.00 0.00 0.00 0.00 0.00 0.00

21:00-22:00 0.00 0.00 0.00 0.00 0.00 0.00

22:00-23:00 0.00 0.00 0.00 0.00 0.00 0.00

23:00-24:00 0.00 0.00 0.00 0.00 0.00 0.00

117

Table 9-14: Schedules for Educational - University Buildings (A)

Educational – University

Time Period

Occupancy Schedule Lighting Schedule Equipment Schedule

S tu

d e

n t

Z o

n e

B a

ck

O ff

ic e

Li b

ra ry

&

C o

m p

u te

r C

e n

tr e

S tu

d e

n t

Z o

n e

B a

ck

O ff

ic e

Li b

ra ry

&

C o

m p

u te

r

C e

n tr

e

S tu

d e

n t

Z o

n e

B a

ck

O ff

ic e

Li b

ra ry

&

C o

m p

u te

r C

e n

te r

5 D

a y

s/

W e

e k

5 D

a y

s/

W e

e k

7 D

a y

s/

w e

e k

5 D

a y

s/

w e

e k

5 D

a y

s/

w e

e k

7 D

a y

s/

w e

e k

5 D

a y

s/

w e

e k

5 D

a y

s/

W e

e k

7 D

a y

s/

w e

e k

00:00-01:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

01:00-02:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

02:00-03:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

03:00-04:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

04:00-05:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

05:00-06:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

06:00-07:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.10

07:00-08:00 0.40 0.00 0.00 0.90 0.00 0.00 0.35 0.35 0.10

08:00-09:00 0.90 0.90 0.30 0.90 0.90 0.90 0.95 0.95 0.70

09:00-10:00 0.90 0.90 0.40 0.90 0.90 0.90 0.95 0.95 0.70

10:00-11:00 0.90 0.90 0.50 0.90 0.90 0.90 0.95 0.95 0.70

11:00-12:00 0.90 0.90 0.50 0.90 0.90 0.90 0.95 0.95 0.70

12:00-13:00 0.90 0.90 0.50 0.90 0.90 0.90 0.95 0.95 0.70

13:00-14:00 0.10 0.20 0.20 0.60 0.30 0.20 0.20 0.40 0.70

14:00-15:00 0.90 0.90 0.50 0.90 0.90 0.90 0.95 0.95 0.70

15:00-16:00 0.90 0.90 0.50 0.90 0.90 0.90 0.95 0.95 0.70

16:00-17:00 0.90 0.90 0.50 0.90 0.90 0.90 0.95 0.95 0.70

17:00-18:00 0.40 0.00 0.50 0.90 0.50 0.90 0.95 0.10 0.80

18:00-19:00 0.00 0.00 0.60 0.00 0.00 0.90 0.00 0.10 0.80

19:00-20:00 0.00 0.00 0.60 0.00 0.00 0.90 0.00 0.10 0.80

20:00-21:00 0.00 0.00 0.60 0.00 0.00 0.90 0.00 0.10 0.80

21:00-22:00 0.00 0.00 0.60 0.00 0.00 0.90 0.00 0.10 0.80

22:00-23:00 0.00 0.00 0.60 0.00 0.00 0.90 0.00 0.10 0.80

23:00-24:00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.00

118

Schedules for Educational - University Buildings (B)

University

Time Period

Elevator Schedule HVAC Fan Schedule (On/Off)

E xt

e rn

a l

Li g

h ti

n g

S ch

e d

u le

B

a se

m e

n t

V e

n ti

la ti

o n

B a

se m

e n

t

Li g

h ti

n g

Li b

ra ry

&

C o

m p

.

C e

n tr

e

S tu

d e

n t

a n

d B

a ck

o ff

ic e

S tu

d e

n t

A re

a

B a

ck

O ff

ic e

Li b

ra ry

&

C o

m p

.

C e

n tr

e

7 days/ week 7 days/

Week

5 days/

week

5 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

Week

00:00-01:00 0.00 0.00 0 0 0 0.80 0.00 0.05

01:00-02:00 0.00 0.00 0 0 0 0.80 0.00 0.05

02:00-03:00 0.00 0.00 0 0 0 0.80 0.00 0.05

03:00-04:00 0.00 0.00 0 0 0 0.80 0.00 0.05

04:00-05:00 0.00 0.00 0 0 0 0.80 0.00 0.05

05:00-06:00 0.00 0.00 0 0 0 0.80 0.00 0.05

06:00-07:00 0.00 0.05 0 0 0 0.00 0.00 0.05

07:00-08:00 0.00 0.25 1 1 1 0.00 0.00 0.05

08:00-09:00 0.50 0.85 1 1 1 0.00 1.00 1.00

09:00-10:00 0.50 0.25 1 1 1 0.00 1.00 1.00

10:00-11:00 0.30 0.25 1 1 1 0.00 1.00 1.00

11:00-12:00 0.20 0.25 1 1 1 0.00 1.00 1.00

12:00-13:00 0.20 0.25 1 1 1 0.00 1.00 1.00

13:00-14:00 0.40 0.90 1 1 1 0.00 1.00 1.00

14:00-15:00 0.30 0.60 1 1 1 0.00 1.00 1.00

15:00-16:00 0.30 0.25 1 1 1 0.00 1.00 1.00

16:00-17:00 0.30 0.25 1 1 1 0.00 1.00 1.00

17:00-18:00 0.50 0.90 1 0 1 0.00 1.00 1.00

18:00-19:00 0.50 0.15 0 0 1 0.80 1.00 1.00

19:00-20:00 0.50 0.05 0 0 1 0.80 1.00 1.00

20:00-21:00 0.50 0.00 0 0 1 0.80 0.00 0.50

21:00-22:00 0.50 0.00 0 0 1 0.80 0.00 0.05

22:00-23:00 0.50 0.00 0 0 1 0.80 0.00 0.05

23:00-24:00 0.00 0.00 0 0 0 0.80 0.00 0.05

119

Table 9-15 Schedules for Healthcare - Hospital Buildings (A)

Healthcare – Hospital

Time Period

Occupancy Schedule Lighting Schedule In

P a

ti e

n t

& I

C U

P u

b li

c S

p a

ce s

O P

D &

O

ff ic

e s

D ia

g n

o st

ic ,

e m

e rg

e n

cy

& O

T

P u

b li

c S

p a

ce s

In P

a ti

e n

t &

I C

U

D ia

g n

o st

ic ,

e m

e rg

e n

cy ,

& O

T

O P

D &

O

ff ic

e s

7 days/

week

7 days/

week

6 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

Week

6 days/

week

00:00-01:00 0.90 0.00 0.00 0.50 0.10 0.10 0.50 0.05

01:00-02:00 0.90 0.00 0.00 0.40 0.10 0.10 0.50 0.05

02:00-03:00 0.90 0.00 0.00 0.40 0.10 0.10 0.50 0.05

03:00-04:00 0.90 0.00 0.00 0.40 0.10 0.10 0.50 0.05

04:00-05:00 0.90 0.00 0.00 0.40 0.10 0.10 0.50 0.05

05:00-06:00 0.90 0.00 0.00 0.40 0.10 0.10 0.50 0.05

06:00-07:00 0.90 0.00 0.00 0.50 0.10 0.10 0.50 0.10

07:00-08:00 0.90 0.10 0.10 0.70 0.50 0.20 0.50 0.30

08:00-09:00 0.90 0.50 0.30 0.70 0.90 0.20 0.90 0.90

09:00-10:00 0.90 0.95 0.90 0.95 0.90 0.20 0.90 0.90

10:00-11:00 0.90 0.95 0.90 0.95 0.90 0.20 0.90 0.90

11:00-12:00 0.90 0.95 0.50 0.95 0.90 0.20 0.90 0.90

12:00-13:00 0.90 0.95 0.20 0.95 0.90 0.20 0.90 0.90

13:00-14:00 0.90 0.95 0.50 0.95 0.90 0.20 0.90 0.50

14:00-15:00 0.90 0.95 0.90 0.95 0.90 0.20 0.90 0.90

15:00-16:00 0.90 0.95 0.90 0.95 0.90 0.20 0.90 0.90

16:00-17:00 0.90 0.95 0.90 0.95 0.30 0.20 0.90 0.90

17:00-18:00 0.90 0.70 0.90 0.95 0.30 0.70 0.90 0.90

18:00-19:00 0.90 0.50 0.50 0.95 0.30 0.90 0.90 0.50

19:00-20:00 0.90 0.30 0.50 0.95 0.30 0.90 0.90 0.50

20:00-21:00 0.90 0.10 0.50 0.70 0.30 0.90 0.50 0.30

21:00-22:00 0.90 0.00 0.10 0.70 0.30 0.90 0.50 0.20

22:00-23:00 0.90 0.00 0.00 0.50 0.30 0.70 0.50 0.10

23:00-24:00 0.90 0.00 0.00 0.50 0.10 0.10 0.50 0.05

120

Schedules for Healthcare - Hospital Buildings (B)

Healthcare - Hospital

Time Period

Equipment Schedule Elevator Schedule

In Patient &

ICU

Diagnostic,

emergency,

& OT

OPD &

Offices Elevator

7 days/

week

7 days/

week

7 days/

Week

7 days/

week

00-01 Hrs 0.40 0.00 0.00 0.20

01-02 Hrs 0.40 0.00 0.00 0.20

02-03 Hrs 0.40 0.00 0.00 0.20

03-04 Hrs 0.40 0.00 0.00 0.20

04-05 Hrs 0.40 0.00 0.00 0.20

05-06 Hrs 0.40 0.00 0.00 0.20

06-07 Hrs 0.40 0.00 0.00 0.20

07-08 Hrs 0.70 0.70 0.70 0.50

08-09 Hrs 0.90 0.90 0.90 0.75

09-10 Hrs 0.90 0.90 0.90 1.00

10-11 Hrs 0.90 0.90 0.90 1.00

11-12 Hrs 0.90 0.90 0.90 1.00

12-13 Hrs 0.90 0.90 0.90 0.75

13-14 Hrs 0.90 0.90 0.90 1.00

14-15 Hrs 0.90 0.90 0.90 1.00

15-16 Hrs 0.90 0.90 0.90 1.00

16-17 Hrs 0.60 0.60 0.90 1.00

17-18 Hrs 0.60 0.60 0.90 1.00

18-19 Hrs 0.60 0.60 0.60 0.50

19-20 Hrs 0.60 0.60 0.60 0.50

20-21 Hrs 0.60 0.60 0.60 0.50

21-22 Hrs 0.60 0.00 0.00 0.30

22-23 Hrs 0.60 0.00 0.00 0.20

23-00 Hrs 0.40 0.00 0.00 0.20

121

Schedules for Healthcare - Hospital Buildings (C)

Healthcare – Hospital

Time Period

HVAC Fan Schedule (On/Off)

E xt

e rn

a l

Li g

h ti

n g

S ch

e d

u le

Service Hot

Water

B a

se m

e n

t

V e

n ti

la ti

o n

B a

se m

e n

t

Li g

h ti

n g

P u

b li

c

S p

a ce

s

B e

d s

&

IC U

D ia

g n

,

e m

e rg

, &

O T

O

P D

&

O ff

ic e

s

B u

il d

in g

S u

m m

e r

B u

il d

in g

W in

te rs

7 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

week

7 days/

week

00:00-01:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

01:00-02:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

02:00-03:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

03:00-04:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

04:00-05:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

05:00-06:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

06:00-07:00 0 1 1 0 0.00 0.00 0.30 0.50 0.50

07:00-08:00 1 1 1 0 0.00 0.00 0.20 0.50 0.50

08:00-09:00 1 1 1 1 0.00 0.20 0.60 1.00 1.00

09:00-10:00 1 1 1 1 0.00 0.30 0.60 1.00 1.00

10:00-11:00 1 1 1 1 0.00 0.30 0.80 1.00 1.00

11:00-12:00 1 1 1 1 0.00 0.30 0.80 1.00 1.00

12:00-13:00 1 1 1 1 0.00 0.25 0.70 1.00 1.00

13:00-14:00 1 1 1 1 0.00 0.25 0.80 1.00 1.00

14:00-15:00 1 1 1 1 0.00 0.25 0.80 1.00 1.00

15:00-16:00 1 1 1 1 0.00 0.25 0.70 1.00 1.00

16:00-17:00 1 1 1 1 0.00 0.25 0.70 1.00 1.00

17:00-18:00 1 1 1 1 0.00 0.10 0.50 1.00 1.00

18:00-19:00 1 1 1 1 1.00 0.00 0.35 1.00 1.00

19:00-20:00 1 1 1 1 1.00 0.00 0.35 1.00 1.00

20:00-21:00 1 1 1 1 1.00 0.00 0.35 1.00 1.00

21:00-22:00 1 1 1 0 1.00 0.00 0.30 0.50 0.50

22:00-23:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

23:00-24:00 0 1 1 0 1.00 0.00 0.30 0.50 0.50

122

Table 9-16 Schedules for Healthcare – Out-patient Healthcare Buildings (A)

Healthcare – Out-patient Healthcare

Time Period

Occupancy Schedule Lighting Schedule Equipment

Schedule

Lo b

b y

D ia

g n

o st

ic

&

E m

e rg

e n

cy

O P

D &

B

a ck

O ff

ic e

D ia

g n

o st

ic

&

E m

e rg

e n

cy

O P

D &

B a

ck O

ff ic

e

D ia

g n

o st

ic

&

E m

e rg

e n

cy

O P

D &

B

a ck

O ff

ic e

6 days/

week

6 days/

Week

6 days/

week

6 days/

Week

6 days/

week

6 days/

week

6 days/

week

00:00-01:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

01:00-02:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

02:00-03:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

03:00-04:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

04:00-05:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

05:00-06:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

06:00-07:00 0.00 0.20 0.20 0.10 0.10 0.00 0.00

07:00-08:00 0.10 0.20 0.20 0.50 0.30 0.50 0.00

08:00-09:00 0.50 0.30 0.20 0.90 0.90 0.95 0.95

09:00-10:00 0.80 0.90 0.90 0.90 0.90 0.95 0.95

10:00-11:00 0.80 0.90 0.90 0.90 0.90 0.95 0.95

11:00-12:00 0.80 0.90 0.90 0.90 0.90 0.95 0.95

12:00-13:00 0.80 0.90 0.50 0.90 0.90 0.95 0.95

13:00-14:00 0.80 0.90 0.20 0.90 0.50 0.95 0.95

14:00-15:00 0.80 0.90 0.50 0.90 0.90 0.95 0.95

15:00-16:00 0.80 0.90 0.90 0.90 0.90 0.95 0.95

16:00-17:00 0.80 0.90 0.90 0.90 0.90 0.95 0.95

17:00-18:00 0.80 0.90 0.90 0.90 0.95 0.95 0.95

18:00-19:00 0.80 0.90 0.50 0.90 0.95 0.95 0.95

19:00-20:00 0.80 0.90 0.50 0.90 0.30 0.95 0.95

20:00-21:00 0.20 0.65 0.20 0.90 0.30 0.80 0.80

21:00-22:00 0.20 0.20 0.20 0.50 0.20 0.00 0.00

22:00-23:00 0.00 0.00 0.00 0.30 0.00 0.00 0.00

23:00-24:00 0.00 0.00 0.00 0.10 0.00 0.00 0.00

123

Schedules for Healthcare – Out-patient Healthcare Buildings (B)

Healthcare - Out-patient Healthcare

Time Period

Elevator

Schedule

HVAC Fan

Schedule

(On/Off)

External

Lighting

Schedule

Service Hot Water

(SHW) Basement

Ventilation

Basement

Lighting

All Spaces Building

Summer

Building

Winters

6 days/

week

6 days/

week

7 Days/

week

6 days/

week

6 days/

week

6 days/

week

6 days/

week

00:00-01:00 0.05 0 0.20 0.00 0.00 0.00 0.00

01:00-02:00 0.05 0 0.20 0.00 0.00 0.00 0.00

02:00-03:00 0.05 0 0.20 0.00 0.00 0.00 0.00

03:00-04:00 0.05 0 0.20 0.00 0.00 0.00 0.00

04:00-05:00 0.05 0 0.20 0.00 0.00 0.00 0.00

05:00-06:00 0.05 0 0.20 0.00 0.00 0.00 0.00

06:00-07:00 0.05 0 0.00 0.00 0.00 0.00 0.00

07:00-08:00 0.50 0 0.00 0.00 0.20 0.00 0.00

08:00-09:00 0.75 1 0.00 0.20 0.60 1.00 1.00

09:00-10:00 1.00 1 0.00 0.30 0.60 1.00 1.00

10:00-11:00 1.00 1 0.00 0.30 0.80 1.00 1.00

11:00-12:00 1.00 1 0.00 0.30 0.80 1.00 1.00

12:00-13:00 0.75 1 0.00 0.25 0.70 1.00 1.00

13:00-14:00 1.00 1 0.00 0.25 0.80 1.00 1.00

14:00-15:00 1.00 1 0.00 0.25 0.80 1.00 1.00

15:00-16:00 1.00 1 0.00 0.25 0.70 1.00 1.00

16:00-17:00 1.00 1 0.00 0.25 0.70 1.00 1.00

17:00-18:00 1.00 1 0.00 0.10 0.50 1.00 1.00

18:00-19:00 0.50 1 0.50 0.01 0.20 1.00 1.00

19:00-20:00 0.50 1 0.50 0.01 0.20 1.00 1.00

20:00-21:00 0.50 1 0.50 0.01 0.20 1.00 1.00

21:00-22:00 0.30 0 0.50 0.01 0.10 1.00 1.00

22:00-23:00 0.05 0 0.20 0.01 0.01 0.00 0.00

23:00-24:00 0.05 0 0.20 0.01 0.01 0.00 0.00

124

Table 9-17 Schedules for Hospitality Buildings (A)

Hospitality

Time Period

Occupancy Schedule

Guest Room Lobby Special Zones Restaurant W

e e

k

D a

y s

W e

e k e

n

d s

W e

e k

D a

y s

W e

e k e

n

d s

W e

e k

D a

y s

W e

e k e

n

d s

W e

e k

D a

y s

W e

e k e

n

d s

00:00-01:00 0.65 0.90 0.10 0.10 0.00 0.00 0.00 0.00

01:00-02:00 0.65 0.90 0.10 0.10 0.00 0.00 0.00 0.00

02:00-03:00 0.65 0.90 0.10 0.10 0.00 0.00 0.00 0.00

03:00-04:00 0.65 0.90 0.10 0.10 0.00 0.00 0.00 0.00

04:00-05:00 0.65 0.90 0.10 0.10 0.00 0.00 0.00 0.00

05:00-06:00 0.65 0.90 0.10 0.10 0.20 0.50 0.00 0.00

06:00-07:00 0.50 0.70 0.20 0.20 0.40 0.70 0.30 0.50

07:00-08:00 0.50 0.70 0.30 0.40 0.40 0.70 0.50 0.80

08:00-09:00 0.30 0.50 0.40 0.70 0.40 0.70 0.50 0.80

09:00-10:00 0.15 0.30 0.40 0.70 0.40 0.70 0.50 0.80

10:00-11:00 0.15 0.20 0.40 0.70 0.40 0.70 0.50 0.80

11:00-12:00 0.15 0.20 0.40 0.70 0.20 0.30 0.00 0.00

12:00-13:00 0.15 0.20 0.40 0.70 0.20 0.30 0.00 0.00

13:00-14:00 0.15 0.20 0.20 0.20 0.20 0.30 0.50 0.50

14:00-15:00 0.15 0.20 0.20 0.20 0.20 0.30 0.50 0.80

15:00-16:00 0.15 0.20 0.20 0.20 0.40 0.70 0.00 0.80

16:00-17:00 0.15 0.20 0.20 0.20 0.40 0.70 0.30 0.30

17:00-18:00 0.30 0.30 0.40 0.40 0.40 0.70 0.30 0.30

18:00-19:00 0.50 0.50 0.40 0.40 0.40 0.70 0.00 0.00

19:00-20:00 0.50 0.70 0.40 0.40 0.40 0.70 0.30 0.50

20:00-21:00 0.65 0.70 0.30 0.30 0.00 0.00 0.50 0.90

21:00-22:00 0.65 0.90 0.20 0.20 0.00 0.00 0.50 0.90

22:00-23:00 0.65 0.90 0.10 0.10 0.00 0.00 0.50 0.90

23:00-24:00 0.65 0.90 0.10 0.10 0.00 0.00 0.50 0.90

125

Schedules for Hospitality Buildings (B)

Hospitality

Time Period

Occupancy Schedule Lighting Schedule

B a

ck

o ff

ic e

C o

n fe

re n

ce /

B a

n q

u e

t R

o o

m s

K it

ch e

n

P u

b li

c

S p

a ce

s

G u

e st

R o

o m

s

W e

e k

D a

y s

W e

e k e

n

d s

7 D

a y

s/

w e

e k

7 D

a y

s/

w e

e k

W e

e k

D a

y s

W e

e k e

n

d s

W e

e k

D a

y s

W e

e k e

n

d s

00:00-01:00 0.20 0.20 0.00 0.00 0.20 0.20 0.20 0.30

01:00-02:00 0.20 0.20 0.00 0.00 0.15 0.20 0.20 0.25

02:00-03:00 0.20 0.20 0.00 0.00 0.10 0.10 0.10 0.10

03:00-04:00 0.20 0.20 0.00 0.00 0.10 0.10 0.10 0.10

04:00-05:00 0.20 0.20 0.00 0.00 0.10 0.10 0.10 0.10

05:00-06:00 0.20 0.20 0.00 0.00 0.20 0.10 0.20 0.10

06:00-07:00 0.20 0.20 0.00 0.50 0.40 0.30 0.45 0.40

07:00-08:00 0.20 0.20 0.00 0.80 0.50 0.30 0.55 0.40

08:00-09:00 0.20 0.20 0.20 0.80 0.40 0.40 0.45 0.55

09:00-10:00 0.95 0.50 0.50 0.50 0.20 0.40 0.20 0.20

10:00-11:00 0.95 0.50 0.90 0.50 0.20 0.40 0.20 0.20

11:00-12:00 0.95 0.50 0.90 0.80 0.20 0.40 0.20 0.20

12:00-13:00 0.95 0.50 0.90 0.80 0.20 0.40 0.20 0.20

13:00-14:00 0.50 0.30 0.90 0.80 0.20 0.40 0.20 0.20

14:00-15:00 0.95 0.50 0.90 0.50 0.20 0.40 0.20 0.20

15:00-16:00 0.95 0.50 0.90 0.50 0.20 0.40 0.20 0.20

16:00-17:00 0.95 0.50 0.90 0.50 0.20 0.40 0.20 0.20

17:00-18:00 0.95 0.50 0.50 0.80 0.25 0.40 0.30 0.30

18:00-19:00 0.30 0.30 0.20 0.80 0.60 0.60 0.70 0.85

19:00-20:00 0.20 0.20 0.20 0.80 0.80 0.70 0.90 1.00

20:00-21:00 0.20 0.20 0.00 0.80 0.90 0.70 1.00 1.00

21:00-22:00 0.20 0.20 0.00 0.80 0.80 0.70 0.90 1.00

22:00-23:00 0.20 0.20 0.00 0.50 0.60 0.60 0.70 0.85

23:00-24:00 0.20 0.20 0.00 0.50 0.30 0.30 0.30 0.40

126

Schedules for Hospitality Buildings (C)

Hospitality

Time Period

Lighting Schedule Equipment Schedule

B a

ck

O ff

ic e

K it

ch e

n

P u

b li

c

S p

a ce

s

G u

e st

R o

o m

s

B a

ck

O ff

ic e

K it

ch e

n

W e

e k

D a

y s

W e

e k e

n

d s

7 D

a y

s/

w e

e k

7 D

a y

s/

w e

e k

W e

e k

D a

y s

W e

e k e

n

d s

W e

e k

D a

y s

W e

e k e

n

d s

7 D

a y

s/

w e

e k

00:00-01:00 0.05 0.05 0.50 0.30 0.20 0.20 0.05 0.05 0.30

01:00-02:00 0.05 0.05 0.05 0.20 0.20 0.20 0.05 0.05 0.10

02:00-03:00 0.05 0.05 0.05 0.20 0.20 0.20 0.05 0.05 0.10

03:00-04:00 0.05 0.05 0.05 0.20 0.20 0.20 0.05 0.05 0.10

04:00-05:00 0.05 0.05 0.05 0.20 0.20 0.20 0.05 0.05 0.10

05:00-06:00 0.05 0.05 0.05 0.30 0.20 0.20 0.05 0.05 0.10

06:00-07:00 0.10 0.10 0.10 0.50 0.30 0.30 0.05 0.05 0.30

07:00-08:00 0.30 0.30 0.30 0.50 0.40 0.60 0.10 0.10 0.30

08:00-09:00 0.90 0.60 0.90 0.50 0.70 0.90 0.30 0.30 0.30

09:00-10:00 0.90 0.60 0.90 0.50 0.20 0.20 0.95 0.70 0.30

10:00-11:00 0.90 0.60 0.90 0.35 0.20 0.20 0.95 0.70 0.30

11:00-12:00 0.90 0.60 0.90 0.35 0.20 0.20 0.95 0.70 0.30

12:00-13:00 0.90 0.60 0.90 0.35 0.20 0.20 0.95 0.70 0.30

13:00-14:00 0.50 0.50 0.50 0.35 0.20 0.20 0.50 0.70 0.30

14:00-15:00 0.90 0.60 0.90 0.35 0.20 0.20 0.95 0.70 0.30

15:00-16:00 0.90 0.60 0.90 0.35 0.20 0.20 0.95 0.70 0.30

16:00-17:00 0.90 0.60 0.90 0.35 0.20 0.20 0.95 0.70 0.30

17:00-18:00 0.95 0.60 0.95 0.35 0.30 0.30 0.95 0.70 0.30

18:00-19:00 0.50 0.50 0.95 0.70 0.50 0.50 0.30 0.30 0.30

19:00-20:00 0.30 0.30 0.95 0.90 0.50 0.50 0.10 0.10 0.30

20:00-21:00 0.30 0.30 0.95 0.90 0.50 0.70 0.10 0.10 0.30

21:00-22:00 0.20 0.20 0.95 0.90 0.70 0.70 0.10 0.10 0.30

22:00-23:00 0.10 0.10 0.95 0.70 0.40 0.40 0.05 0.05 0.30

23:00-24:00 0.05 0.05 0.95 0.40 0.20 0.20 0.05 0.05 0.30

127

Schedules for Hospitality Buildings (D)

Hospitality

Time Period

Elevator Schedule

HVAC Fan Schedule (On/Off)

Public

Spaces Guest Room Back office

Week Days Weekends 7 Days/

week Week Days Weekends

7 Days/

week

00:00-01:00 0.10 0.10 0 1 1 0

01:00-02:00 0.10 0.10 0 1 1 0

02:00-03:00 0.10 0.10 0 1 1 0

03:00-04:00 0.10 0.10 0 1 1 0

04:00-05:00 0.10 0.10 0 1 1 0

05:00-06:00 0.20 0.20 0 1 1 0

06:00-07:00 0.40 0.50 0 1 1 0

07:00-08:00 0.50 0.60 1 1 1 0

08:00-09:00 0.50 0.60 1 1 1 1

09:00-10:00 0.35 0.40 1 1 1 1

10:00-11:00 0.15 0.20 1 1 1 1

11:00-12:00 0.15 0.20 1 1 1 1

12:00-13:00 0.15 0.20 1 1 1 1

13:00-14:00 0.15 0.20 1 1 1 1

14:00-15:00 0.15 0.20 1 1 1 1

15:00-16:00 0.15 0.20 1 1 1 1

16:00-17:00 0.35 0.40 1 1 1 1

17:00-18:00 0.50 0.60 1 1 1 1

18:00-19:00 0.50 0.60 1 1 1 1

19:00-20:00 0.50 0.60 1 1 1 0

20:00-21:00 0.50 0.60 1 1 1 0

21:00-22:00 0.30 0.40 1 1 1 0

22:00-23:00 0.20 0.30 1 1 1 0

23:00-24:00 0.10 0.10 1 1 1 0

128

Schedules for Hospitality Buildings (E)

Hospitality

Time Period

External

Lighting

Schedule

Service Hot Water (SHW) Basement

Ventilation

Basement

Lighting Guest rooms Laundry

7 Days/

week Week Days Weekends

7 Days/

week

7 Days/

week

7 Days/

week

00:00-01:00 1.00 0.01 0.01 0.00 0.50 0.50

01:00-02:00 1.00 0.01 0.01 0.00 0.50 0.50

02:00-03:00 1.00 0.01 0.01 0.00 0.50 0.50

03:00-04:00 1.00 0.01 0.01 0.00 0.50 0.50

04:00-05:00 1.00 0.01 0.01 0.00 0.50 0.50

05:00-06:00 1.00 0.01 0.01 0.00 0.50 0.50

06:00-07:00 0.00 0.50 0.70 0.00 0.50 0.50

07:00-08:00 0.00 0.50 0.70 0.00 0.50 0.50

08:00-09:00 0.00 0.30 0.50 1.00 1.00 1.00

09:00-10:00 0.00 0.15 0.30 1.00 1.00 1.00

10:00-11:00 0.00 0.15 0.20 1.00 1.00 1.00

11:00-12:00 0.00 0.15 0.20 1.00 1.00 1.00

12:00-13:00 0.00 0.15 0.20 1.00 1.00 1.00

13:00-14:00 0.00 0.15 0.20 1.00 1.00 1.00

14:00-15:00 0.00 0.15 0.20 1.00 1.00 1.00

15:00-16:00 0.00 0.15 0.20 1.00 1.00 1.00

16:00-17:00 0.00 0.15 0.20 0.00 1.00 1.00

17:00-18:00 0.00 0.30 0.30 0.00 1.00 1.00

18:00-19:00 1.00 0.50 0.50 0.00 1.00 1.00

19:00-20:00 1.00 0.50 0.70 0.00 1.00 1.00

20:00-21:00 1.00 0.65 0.70 0.00 1.00 1.00

21:00-22:00 1.00 0.65 0.90 0.00 0.50 0.50

22:00-23:00 1.00 0.01 0.01 0.00 0.50 0.50

23:00-24:00 1.00 0.01 0.01 0.00 0.50 0.50

129

Table 9-18 Schedules for Shopping Complexes Buildings (A)

Shopping Complex

Time Period

Occupancy Schedule Lighting Schedule

Retail Corridors & Atrium Special Zone Retail Corridors

& Atrium

Special

Zone

Weekday Week

end Weekday Weekend

Week

day

Week

end

7 Days/

week

7 Days/

week

7 Days/

week

00:00-01:00 0.00 0.00 0.00 0.10 0.00 0.00 0.05 0.05 0.05

01:00-02:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

02:00-03:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

03:00-04:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

04:00-05:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

05:00-06:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

06:00-07:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

07:00-08:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

08:00-09:00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.05 0.05

09:00-10:00 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20

10:00-11:00 0.40 0.40 0.40 0.40 0.20 0.20 0.50 0.50 0.40

11:00-12:00 0.60 0.60 0.60 0.60 0.30 0.50 0.95 0.50 0.60

12:00-13:00 0.60 0.70 0.60 0.70 0.50 0.70 0.95 0.50 0.60

13:00-14:00 0.60 0.90 0.60 0.90 0.50 0.70 0.95 0.50 0.60

14:00-15:00 0.70 0.90 0.70 0.90 0.50 0.70 0.95 0.50 0.60

15:00-16:00 0.70 0.90 0.70 0.90 0.50 0.80 0.95 0.50 0.40

16:00-17:00 0.70 0.90 0.70 0.90 0.50 0.80 0.95 0.70 0.40

17:00-18:00 0.70 0.90 0.70 0.90 0.50 0.80 0.95 0.95 0.40

18:00-19:00 0.90 0.95 0.90 0.95 0.60 0.95 0.95 0.95 0.80

19:00-20:00 0.90 0.95 0.90 0.95 0.60 0.95 0.95 0.95 0.80

20:00-21:00 0.90 0.95 0.90 0.95 0.60 0.95 0.95 0.95 0.80

21:00-22:00 0.00 0.00 0.40 0.40 0.60 0.95 0.05 0.50 0.80

22:00-23:00 0.00 0.00 0.30 0.30 0.60 0.95 0.05 0.30 0.80

23:00-24:00 0.00 0.00 0.10 0.10 0.30 0.95 0.05 0.30 0.80

130

Schedules for Shopping Complexes Buildings (B)

Shopping Complex

Time Period

Equipment Schedule Elevator Schedule

Retail Special Zone

7 Days/ week 7 Days/ week Weekdays Weekends

00:00-01:00 0.05 0.05 0.20 0.20

01:00-02:00 0.05 0.05 0.05 0.20

02:00-03:00 0.05 0.05 0.05 0.05

03:00-04:00 0.05 0.05 0.05 0.05

04:00-05:00 0.05 0.05 0.05 0.05

05:00-06:00 0.05 0.05 0.05 0.05

06:00-07:00 0.05 0.05 0.05 0.05

07:00-08:00 0.05 0.05 0.10 0.10

08:00-09:00 0.05 0.50 0.10 0.10

09:00-10:00 0.05 0.50 0.20 0.20

10:00-11:00 0.90 0.90 0.40 0.40

11:00-12:00 0.90 0.90 0.70 0.70

12:00-13:00 0.90 0.90 0.70 0.80

13:00-14:00 0.90 0.90 0.70 0.95

14:00-15:00 0.90 0.90 0.70 0.95

15:00-16:00 0.90 0.90 0.70 0.95

16:00-17:00 0.90 0.90 0.70 0.95

17:00-18:00 0.90 0.90 0.80 0.95

18:00-19:00 0.90 0.90 0.80 0.95

19:00-20:00 0.90 0.90 0.80 0.95

20:00-21:00 0.50 0.90 0.80 0.95

21:00-22:00 0.05 0.90 0.80 0.80

22:00-23:00 0.05 0.90 0.50 0.60

23:00-24:00 0.05 0.90 0.30 0.40

131

Schedules for Shopping Complexes Buildings (C)

Shopping Complex

Time Period

HVAC Fan Schedule (On/Off) External

Lighting

Schedule

Basement

Ventilation

Basement

Lighting Retail Corridors &

Atrium

Special

Zones

7 Days/

week

7 Days/

week

7 Days/

week

7 Days/

week

7 Days/

week

7 Days/

week

00:00-01:00 0 0 0 1.00 1.00 1.00

01:00-02:00 0 0 0 0.50 0.00 0.05

02:00-03:00 0 0 0 0.50 0.00 0.05

03:00-04:00 0 0 0 0.50 0.00 0.05

04:00-05:00 0 0 0 0.50 0.00 0.05

05:00-06:00 0 0 0 0.50 0.00 0.05

06:00-07:00 0 0 0 0.00 0.00 0.05

07:00-08:00 0 0 0 0.00 0.00 0.05

08:00-09:00 0 0 0 0.00 0.00 0.05

09:00-10:00 0 1 1 0.00 1.00 1.00

10:00-11:00 1 1 1 0.00 1.00 1.00

11:00-12:00 1 1 1 0.00 1.00 1.00

12:00-13:00 1 1 1 0.00 1.00 1.00

13:00-14:00 1 1 1 0.00 1.00 1.00

14:00-15:00 1 1 1 0.00 1.00 1.00

15:00-16:00 1 1 1 0.00 1.00 1.00

16:00-17:00 1 1 1 0.00 1.00 1.00

17:00-18:00 1 1 1 0.00 1.00 1.00

18:00-19:00 1 1 1 1.00 1.00 1.00

19:00-20:00 1 1 1 1.00 1.00 1.00

20:00-21:00 1 1 1 1.00 1.00 1.00

21:00-22:00 0 1 1 1.00 1.00 1.00

22:00-23:00 0 1 1 1.00 1.00 1.00

23:00-24:00 0 1 1 1.00 1.00 1.00

132

Table 9-19 Schedules for Shopping Complex- Strip Retail & Supermall Buildings (A)

Strip Retail & Supermall

Time Period

Occupancy Schedule Lighting

Schedule

Equipment

Schedule Elevator Schedule

Retail & Circulation All Spaces All Spaces

Weekdays Weekends 7 Days/

week

7 Days/

week Weekdays Weekends

00:00-01:00 0.00 0.00 0.05 0.05 0.00 0.00

01:00-02:00 0.00 0.00 0.05 0.05 0.00 0.00

02:00-03:00 0.00 0.00 0.05 0.05 0.00 0.00

03:00-04:00 0.00 0.00 0.05 0.05 0.00 0.00

04:00-05:00 0.00 0.00 0.05 0.05 0.00 0.00

05:00-06:00 0.00 0.00 0.05 0.05 0.00 0.00

06:00-07:00 0.00 0.00 0.05 0.05 0.00 0.00

07:00-08:00 0.00 0.00 0.05 0.05 0.10 0.10

08:00-09:00 0.00 0.00 0.05 0.05 0.10 0.10

09:00-10:00 0.20 0.20 0.20 0.05 0.20 0.20

10:00-11:00 0.40 0.40 0.50 0.90 0.40 0.40

11:00-12:00 0.60 0.60 0.95 0.90 0.70 0.70

12:00-13:00 0.60 0.70 0.95 0.90 0.70 0.80

13:00-14:00 0.60 0.90 0.95 0.90 0.70 0.95

14:00-15:00 0.70 0.90 0.95 0.90 0.70 0.95

15:00-16:00 0.70 0.90 0.95 0.90 0.70 0.95

16:00-17:00 0.70 0.90 0.95 0.90 0.70 0.95

17:00-18:00 0.70 0.90 0.95 0.90 0.80 0.95

18:00-19:00 0.90 0.95 0.95 0.90 0.80 0.95

19:00-20:00 0.90 0.95 0.95 0.90 0.80 0.95

20:00-21:00 0.90 0.95 0.95 0.50 0.80 0.95

21:00-22:00 0.00 0.00 0.05 0.05 0.00 0.00

22:00-23:00 0.00 0.00 0.05 0.05 0.00 0.00

23:00-24:00 0.00 0.00 0.05 0.05 0.00 0.00

133

Table 9-20 Schedules for Shopping Complex- Strip Retail & Supermall Buildings (A)

Strip Retail & Supermall

Time Period

HVAC Fan

Schedule

(On/Off)

External Lighting

Schedule

Basement

Ventilation

Basement

Lighting

7 Days/ week 7 Days/ week 7 Days/ week 7 Days/ week

00:00-01:00 0 0.20 0.00 0.05

01:00-02:00 0 0.20 0.00 0.05

02:00-03:00 0 0.20 0.00 0.05

03:00-04:00 0 0.20 0.00 0.05

04:00-05:00 0 0.20 0.00 0.05

05:00-06:00 0 0.20 0.00 0.05

06:00-07:00 0 0.00 0.00 0.05

07:00-08:00 0 0.00 0.00 0.05

08:00-09:00 0 0.00 0.00 0.05

09:00-10:00 1 0.00 1.00 1.00

10:00-11:00 1 0.00 1.00 1.00

11:00-12:00 1 0.00 1.00 1.00

12:00-13:00 1 0.00 1.00 1.00

13:00-14:00 1 0.00 1.00 1.00

14:00-15:00 1 0.00 1.00 1.00

15:00-16:00 1 0.00 1.00 1.00

16:00-17:00 1 0.00 1.00 1.00

17:00-18:00 1 0.00 1.00 1.00

18:00-19:00 1 1.00 1.00 1.00

19:00-20:00 1 1.00 1.00 1.00

20:00-21:00 1 1.00 1.00 1.00

21:00-22:00 0 1.00 0.20 0.50

22:00-23:00 0 0.20 0.00 0.05

23:00-24:00 0 0.20 0.00 0.05

134

Table 9-21 Schedules for Assembly Buildings

Assembly

Time Period

Occupan

cy

Schedule

Lighting

Schedule

Equipme

nt

Schedule

Elevator

Schedule

HVAC

Fan

Schedule

(On/Off)

External

Lighting

Schedule

Basemen

t

Ventilati

on

Basemen

t Lighting

00:00-01:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.80

01:00-02:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

02:00-03:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

03:00-04:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

04:00-05:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

05:00-06:00 0.00 0.00 0.00 0.00 0 0.80 0.00 0.10

06:00-07:00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.10

07:00-08:00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.10

08:00-09:00 0.20 0.40 0.30 0.20 0 0.00 1.00 0.80

09:00-10:00 0.20 0.75 0.50 0.50 1 0.00 1.00 0.80

10:00-11:00 0.20 0.95 0.95 0.50 1 0.00 1.00 0.80

11:00-12:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

12:00-13:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

13:00-14:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

14:00-15:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

15:00-16:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

16:00-17:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

17:00-18:00 0.80 0.95 0.95 0.50 1 0.00 1.00 0.80

18:00-19:00 0.50 0.95 0.50 0.50 1 0.80 1.00 0.80

19:00-20:00 0.20 0.40 0.30 0.40 1 0.80 1.00 0.80

20:00-21:00 0.20 0.40 0.30 0.20 0 0.80 1.00 0.80

21:00-22:00 0.20 0.40 0.30 0.20 0 0.80 1.00 0.80

22:00-23:00 0.10 0.10 0.00 0.00 0 0.80 1.00 0.80

23:00-24:00 0.10 0.10 0.00 0.00 0 0.80 0.00 0.80

135

Table 9-22 Schedules for Business - Office Buildings

Business – Office

Time Period

HVAC Fan Schedule (On/Off)

External Lighting

Schedule Basement Ventilation Basement Lighting

D a

y ti

m e

B u

si n

e ss

2 4

H o

u r

B u

si n

e ss

7 D

a y

s/

w e

e k

D a

y ti

m e

B

u si

n e

ss

2 4

H o

u r

B u

si n

e ss

D a

y ti

m e

B

u si

n e

ss

2 4

H o

u r

B u

si n

e ss

00:00-01:00 0 1 0.80 0.00 1.00 0.05 1.00

01:00-02:00 0 1 0.80 0.00 1.00 0.05 1.00

02:00-03:00 0 1 0.80 0.00 1.00 0.05 1.00

03:00-04:00 0 1 0.80 0.00 1.00 0.05 1.00

04:00-05:00 0 1 0.80 0.00 1.00 0.05 1.00

05:00-06:00 0 1 0.80 0.00 1.00 0.05 1.00

06:00-07:00 0 1 0.00 0.00 1.00 0.05 1.00

07:00-08:00 1 1 0.00 0.00 1.00 0.05 1.00

08:00-09:00 1 1 0.00 1.00 1.00 1.00 1.00

09:00-10:00 1 1 0.00 1.00 1.00 1.00 1.00

10:00-11:00 1 1 0.00 1.00 1.00 1.00 1.00

11:00-12:00 1 1 0.00 1.00 1.00 1.00 1.00

12:00-13:00 1 1 0.00 1.00 1.00 1.00 1.00

13:00-14:00 1 1 0.00 1.00 1.00 1.00 1.00

14:00-15:00 1 1 0.00 1.00 1.00 1.00 1.00

15:00-16:00 1 1 0.00 1.00 1.00 1.00 1.00

16:00-17:00 1 1 0.00 1.00 1.00 1.00 1.00

17:00-18:00 1 1 0.00 1.00 1.00 1.00 1.00

18:00-19:00 1 1 0.80 1.00 1.00 1.00 1.00

19:00-20:00 1 1 0.80 1.00 1.00 1.00 1.00

20:00-21:00 1 1 0.80 1.00 1.00 1.00 1.00

21:00-22:00 1 1 0.80 0.00 1.00 0.05 1.00

22:00-23:00 0 1 0.80 0.00 1.00 0.05 1.00

23:00-24:00 0 1 0.80 0.00 1.00 0.05 1.00

136

10. Appendix A: Default Values for Typical Constructions

10.1 Procedure for Determining Fenestration Product U-factor and Solar Heat

Gain Coefficient

§ 4.2.1.1 and § 4.2.1.2 require that U-factors and solar heat gain coefficients (SHGC) be

determined for the overall fenestration product (including the sash and frame) in accordance

with ISO 15099. The building envelope trade-off option in § 4.3.5 requires the use of visible light

transmittance (VLT).

In several cases, ISO 15099 suggests that individual national standards will need to be more

specific and in other cases the ISO document gives users the choice of two options. This section

clarifies these specific issues as they are to be implemented for this code:

a) § 4.1 of ISO 15099: For calculating the overall U-factor, ISO 15099 offers a choice between

the linear thermal transmittance (4.1.2) and the area weighted method (4.1.3). The area

weighted method (4.1.3) shall be used.

b) § 4.2.2 of ISO 15099: Frame and divider SHGC’s shall be calculated in accordance with §

4.2.2. The alternate approach in § 8.6 shall not be used.

c) § 6.4 of ISO 15099 refers the issue of material properties to national standards. Material

conductivities and emissivity shall be determined in accordance with Indian standards.

d) § 7 of ISO 15099 on shading systems is currently excluded.

e) § 8.2 of ISO 15099 addresses environmental conditions. The following are defined for

India:

For U-factor calculations:

Tin = 24 ºC

Tout = 32 ºC

V = 3.35 m/s

Trm, out=Tout

Trm,in=Tin

Is = 0 W/m2

For SHGC calculations:

Tin = 24 ºC

Tout = 32 ºC

137

V = 2.75 m/s

Trm,out = Tout

Trm,in = Tin

Is = 783 W/m2

f) § 8.3 of ISO 15099 addresses convective film coefficients on the interior and exterior of

the window product. In § 8.3.1 of ISO 15099, simulations shall use the heat transfer

coefficient based on the center of glass temperature and the entire window height; this

film coefficient shall be used on all indoor surfaces, including frame sections. In § 8.3.2 of

ISO 15099, the formula from this section shall be applied to all outdoor exposed surfaces.

g) § 8.4.2 of ISO 15099 presents two possible approaches for incorporating the impacts of

self-viewing surfaces on interior radiative heat transfer calculations. Products shall use

the method in § 8.4.2.1 of ISO 15099 (Two-Dimensional Element to Element View Factor

Based Radiation Heat Transfer Calculation). The alternate approach in § 8.4.3 of ISO 15099

shall not be used.

10.2 Default U-factors and Solar Heat Gain Coefficients for Unrated Fenestration Products All fenestration with U-factors, SHGC, or visible light transmittance determined, certified, and

labeled in accordance ISO 15099 shall be assigned those values.

10.2.1 Unrated Vertical Fenestration.

Unlabeled vertical fenestration, both operable and fixed, shall be assigned the U-factors,

SHGCs, and visible light transmittances in Table 10.2.1.

Table 10-1 Defaults for Unrated Vertical Fenestration (Overall Assembly including the Sash and Frame) Frame Type Glazing Type U-Factor (W/m2.K)

All frame types Single Glazing 7.1

Wood, vinyl, or fiberglass frame or metal frame with thermal break

Double Glazing

3.4

Metal and other frame type Double Glazing 5.1

10.2.2 Unrated Sloped Glazing and Skylights

Unrated sloped glazing and skylights, both operable and fixed, shall be assigned the SHGCs and

visible light transmittances in Table 10-1. To determine the default U-factor for unrated sloped

138

glazing and skylights without a curb, multiply the values in Table 10-1 by 1.2. To determine the

default U-factor for unrated skylights on a curb, multiply the values in Table 10-1 by 1.6.

1 0.3 Typical Roof Constructions

For calculating the overall U-factor of a typical roof construction, the U-factors from the typical

wall construction type and effective U-factor for insulation shall be combined according to the

following equation:

1 0.4 Typical Wall Constructions

For calculating the overall U-factor of a typical wall construction, the U-factors from the typical

wall construction type and effective U-factor for insulation shall be combined according to the

following equation:

UTaralKaof : 1 1 7 + UTWwalej UTylmeIerIarian where UTolalRoof Total U-factor of the roof with insulation UTypical Roof U-factor of the roof UTypical Insulation U-factor of the effective insulation

where UTotalWall UTypical Wall UTypical Insulation U Tam] Wu] I 1 1 + UTWimIWaI U TyipcaIImulnnon Total U-factor of the wall with insulation U-factor of the wall U-factor of the effective insulation

139

Table 10-2 Typical Thermal Properties of Common Building and Insulating Materials2

Name Form Density kg/m³

Thermal Conductivi ty W/(mK)

Specific Heat MJ/m³K

Acrylic Sheet Board 1145 0.2174 1.5839

Armor Insulation 270 0.0678 0.1578

Asbestos Cement Board

Board 1404 0.4709 0.7218

Asbestos Sheet - Shera

Board 1377 0.5128 1.2043

Autoclaved Aerat3ed Concrete Block (AAC)

Block 642 0.1839 0.794

Bamboo Wood 913 0.1959 0.6351

Brass Metal 8500 106.48 11.1164

Calcium Silicate Board

Board 1016 0.281 0.8637

Composite Marble Stone 3146 2.44 2.1398

Cement Board Board 1340 0.4384 0.8113

Cement Bonded Particle Board

Board 1251 0.3275 1.1948

Ceramic Fiber Blanket

Insulation 128 0.0491 0.1093

Cement Fiber Board Board 1276 0.388 0.8973

Cement Plaster 278 1.208 0.9719

Cement Powder Powder 1070 0.1137 0.7943

Ceramic Blue Tile Tile 2707 1.372 1.2082

Ceramic Frit Glass Glass 2520 0.6882 0.7859

Ceramic Tile - Bathroom

Tile 2549 0.8018 1.6168

Ceramic Tile Tile 2700 1.5996 1.1438

Chile Wood Wood 362 0.1422 0.4102

Chitodio Stone 3209 3.7512 2.1223

Clay Tile Tile 2531 0.6323 1.4253 2 Thermo-Physical-Optical Property Database of Construction Materials, U.S.- India Joint Center for Building Energy Research and Development (CBERD) and Ministry of New and Renewable Energy (MNRE).

3 This is not an all-inclusive list. The database of thermal properties of building materials is available at

BEE website (https://www.beeindia.gov.in/).

140

Name Form Density kg/m³

Thermal Conductivity W/(mK)

Specific Heat MJ/m³K

Float Glass/ Clear Glass

Glass 2477 1.0522 1.9654

Concrete Block 25/50

Block 2427 1.3957 0.4751

Concrete Block 30/60

Block 2349 1.4107 0.7013

Corian Board 1750 1.012 2.0921

Crystal White Tile Tile 2390 1.5094 1.9427

Dholpuri Stone Stone 2262 3.084 1.583

Mineralized Water Water 1000 0.6134 3.8165

Engineered Wood Floor Tiles

Tile 571 0.2527 1.423

Extruded Polystyrene XPS

Insulation 30 0.0321 0.0374

Fiber Reinforced Plastic (FRP )

Board 1183 0.2252 1.693

Fire Brick Brick 2049 1.2729 1.2887

Floor Board Board 954 0.2654 1.1423

Foam Cement Block Block 581 0.1588 0.5359

Ghana Teak Wood Wood 529 0.2062 0.5769

Glasswool Insulation 49 0.0351 0.0339

Black Fine Granite Stone 3535 2.4351 2.2511

Black Coarse Granite Stone 3473 2.5433 2.1996

Green Marble Stone 2650 2.372 2.5275

Green Rockwool Insulation 96 0.045 0.1089

Gypsum Board Board 623 0.2527 0.6033

Gypsum Powder Powder 588 0.202 1.1918

Gypsum Powder from Board

Powder 542 0.1033 0.626

Italian Black Granite Stone 2911 2.3636 2.2349

Italian Marble Stone 2630 2.7752 2.1869

Jaisalmer Yellow Stone

Stone 3006 2.7447 2.0954

141

Name Form Density kg/m³

Thermal Conductivity W/(mK)

Specific Heat MJ/m³K

Jalore Stone 2982 3.4412 1.9617

Kota Stone Stone 3102 3.0229 2.0732

Laminated Particle Board

Board 656 0.1841 1.2621

Lime Powder Powder 607 0.1286 0.7078

Mangalore Roof Tile Tile - Roof 2531 0.6051 1.2809

Ambaji Marble Stone 3128 2.8108 2.1943

Medium Density Fiberboard (MDF)

Board 133 0.2045 0.961

Melamine Fiberboard Board 807 0.2459 0.6509

Mild Steel (MS) Metal 7823 44.117 4.1896

Mineral Fiber - Celling Board 364 0.071 0.3222

Mineral Fiber - Plain Board 773 0.2739 0.6427

Oak Laminated Floor Tiles

Tile 949 0.2652 1.3389

Concrete Paver Tiles Tile 2210 1.7248 1.3413

Paver Tile Tile 2612 1.4763 1.2737

Plain & Prelaminated Particle Board

Board 902 0.271 0.974

Plaster of Paris (POP) Powder

Powder 1000 0.1353 0.9526

Plywood Board 697 0.221 0.7258

Polyisocyanurate (PIR)

Insulation 40 0.0364 0.0685

Polymer (Anisotropic) Plastic 1743 0.5027 1.6968

Polyurethane Foam (PUF)

Insulation 40 0.0372 0.0704

POP Board Board 1080 0.4994 1.2167

Porcelain Tile Tile 2827 1.5331 1.6259

Pumice Square - Bronze Tile

Tile 2327 0.9907 0.4382

Quartz Stone 2359 3.7603 1.8277

Rajnagar Marble Stone 3332 5.6405 2.777

142

Name Form Density kg/m³

Thermal Conductivity W/(mK)

Specific Heat MJ/m³K

Rigid Polyurethane (40 Kg/m3)

Insulation 40 0.0269 0.0766

Rigid Polyurethane Insulation 25 0.0384 0.0763

Rockwool Insulation 64 0.0461 0.0904

Rubber - Foam Insulation 89 0.0561 0.1486

Rubber Wood Wood 472 0.1679 0.5034

Saag Wood Wood 959 0.2886 1.0258

Sand Powder 1600 0.3075 1.1343

Sandstone Stone 2530 3.0097 1.5957

Serpentine Green Granite

Stone 3068 2.1363 2.4484

Soft Board Board 274 0.0943 0.2753

Soft Board-High Density

Board 353 0.0983 0.2621

Stainless Steel (SS) Metal 7950 13.5633 3.6351

Steam Beech Wood Wood 241 0.2331 0.5512

Straw Board Board 760 0.2237 0.7098

Teak Wood Wood 665 0.2369 0.8412

Tempered Glass Glass 2500 1.0493 1.9227

Tinted Glass Glass 2500 1.0428 1.8904

Udaipur Brown Marble

Stone 3197 2.921 2.2184

V-Board Board 1191 0.2977 0.8245

Veneered Particle Board

Board 788 0.2363 0.7075

Vitrified Tile Tile 2719 1.4786 1.8049

Resource Efficient Bricks (REB)

Brick 1520 0.6314 0.9951

Wood Wood 802 0.2652 0.8715

Wood Pattern Chitodio

Stone 3126 3.4258 2.2852

143

11. Appendix B: Climate Zone Map of Uttar Pradesh

144

Table 11-1 Climate Zone for Major Indian Cities

City Climate Type City Climate Type

Ahmedabad Hot & Dry Kurnool Warm & Humid

Allahabad Composite Leh Cold

Amritsar Composite Lucknow Composite

Aurangabad Hot & Dry Ludhiana Composite

Bangalore Temperate Chennai Warm & Humid

Barmer Hot & Dry Manali Cold

Belgaum Warm & Humid Mangalore Warm & Humid

Bhagalpur Warm & Humid Mumbai Warm & Humid

Bhopal Composite Nagpur Composite

Bhubaneshwar Warm & Humid Nellore Warm & Humid

Bikaner Hot & Dry New Delhi Composite

Chandigarh Composite Panjim Warm & Humid

Chitradurga Warm & Humid Patna Composite

Dehradun Composite Pune Warm & Humid

Dibrugarh Warm & Humid Raipur Composite

Guwahati Warm & Humid Rajkot Composite

Gorakhpur Composite Ramgundam Warm & Humid

Gwalior Composite Ranchi Composite

Hissar Composite Ratnagiri Warm & Humid

Hyderabad Composite Raxaul Warm & Humid

Imphal Warm & Humid Saharanpur Composite

Indore Composite Shillong Cold

Jabalpur Composite Sholapur Hot & Dry

Jagdelpur Warm & Humid Srinagar Cold

Jaipur Composite Sundernagar Cold

Jaisalmer Hot & Dry Surat Hot & Dry

Jalandhar Composite Tezpur Warm & Humid

Jamnagar Warm & Humid Tiruchirappalli Warm & Humid

Jodhpur Hot & Dry Trivandrum Warm & Humid

Jorhat Warm & Humid Tuticorin Warm & Humid

Kochi Warm & Humid Udhagamandalam Cold

Kolkata Warm & Humid Vadodara Hot & Dry

Kota Hot & Dry Veraval Warm & Humid

Kullu Cold Vishakhapatnam Warm & Humid

145

Table 11-2 Climate Zone for District of Uttar Pradesh

District Climate

Zone Latitude Longitude District

Climate

Zone Latitude Longitude

Agra Composite 28˚40’N 76˚02’E Jyotiba Phule

Nagar Composite 28˚50’N 78˚23’E

Aligarh

Composite 25˚55’N 76˚15’E Kannauj Composite 27˚03’N 79˚56’E

Allahabad Composite 25˚25’N 81˚58’E Kanpur Dehat Composite 26˚28’N 80˚20’E

Ambedkar

Nagar

Composite 26˚23’N 82˚42’E Kanpur Nagar Composite 26˚28’N 80˚20’E

Auraiya Composite 26˚28’N 79˚33’E Kanshi Ram

Nagar Composite 28˚02’N 79˚45’E

Azamgarh

Composite 26˚05’N 83˚13’E Kaushambi Composite 25˚53’N 81˚38’E

Badaun

Composite 28˚02’N 79˚17’E Kushinagar Composite 26˚45’N 83˚24’E

Bagpat Composite 28˚57’N 77˚13’E Lakhimpurkh

eri Composite 27˚60’N 80˚34’E

Bahraich

Composite 27˚38’N 81˚37’E Lalitpur Composite 24˚11’N 78˚10’E

Balia

Composite 25˚46’N 84˚12’E Lucknow Composite 26˚50’N 81˚0’E

Balrampur Composite 27˚30’N 82˚20’E Mahamaya

Nagar Composite 27˚64’N 78˚11’E

Banda

Composite 25˚30’N 80˚26’E Maharajganj Composite 26˚07’N 84˚29’E

Barabanki

Composite 26˚55’N 81˚12’E Mahoba Composite 25˚5’N 79˚55’E

Bareily

Composite 28˚22’N 79˚27’E Mainpuri Composite 27˚18’N 79˚04’E

Basti

Composite 26˚52’N 82˚55’E Mathura Composite 27˚30’N 77˚40’E

Bijnor

Composite 29˚27’N 78˚11’E Mau Composite 25˚56’N 83˚33’E

Bulandshar

Composite 28˚28’N 77˚51’E Meerut Composite 29˚01’N 77˚42’E

Chandauli

Composite 28˚27’N 78˚49’E Mirzapur Composite 25˚10’N 82˚34’E

Chitrakoot

Composite 24˚48’N 80˚58’E Moradabad Composite 28˚50’N 78˚50’E

Deoria Composite 23˚24’N 79˚40’E Muzaffarnaga

r Composite 29˚26’N 77˚50’E

Etah Composite 27˚35’N 78˚40’E Pilibhit Composite 28˚40’N 79˚50’E

Etawah Composite 26˚48’N 79˚06’E Pratapgarh Composite 25˚56’N 81˚59’E

146

Faizabad

Composite 26˚45’N 82˚10’E RaeBareli Composite 26˚18’N 81˚20’E

Farrukhabad

Composite 26˚46’N 79˚43’E Rampur Composite 28˚50’N 79˚05’E

Fatehpur

Composite 25˚56’N 81˚13’E Saharanpur Composite 29˚58’N 77˚33’E

Firozabad Composite 27˚10’N 78˚25’E Santkabirnaga

r Nagar Composite 26˚47’N 81˚30’E

GautamBud

h Nagar

Composite 26˚47’N 81˚30’E SantRavidas

Nagar Composite 25˚22’N 82˚28’E

Ghaziabad

Composite 28˚42’N 77˚26’E Shahjahanpur Composite 27˚35’N 79˚37’E

Ghazipur

Composite 25˚38’N 83˚35’E Shravasti Composite 27˚35’N 79˚37’E

Gonda Composite 27˚09’N 81˚58’E Siddharthnaga

r Composite 27˚07’N 82˚01’E

Gorakhpur

Composite 26˚47’N 83˚23’E Sitapur Composite 27˚38’N 80˚45’E

Hamirpur

Composite 31˚41’N 76˚31’E Sonbhadra Composite 24˚22’N 83˚25’E

Hardoi

Composite 27˚26’N 80˚06’E Sultanpur Composite 31˚12’N 75˚11’E

Jalaun

Composite 26˚08’N 79˚25’E Unnao Composite 26˚35’N 80˚30’E

Jaunpur

District Composite 25˚46’N 82˚4’E Varanasi Composite 25˚22’N 83˚0’E

Jhansi

Composite 25˚30’N 78˚36’E

147

12. Appendix C: Air-Side Economizer Acceptance Procedures 12.1 Construction Inspection Prior to Performance Testing, verify and document the following:

(a) System controls are wired correctly to ensure economizer is fully integrated (i.e. economizer

will operate when mechanical cooling is enabled).

(b) Economizer lockout control sensor location is adequate (open to air but not exposed to

direct sunlight nor in an enclosure; away from sources of building exhaust; at least 8 meters

away from cooling towers).

(c) System is provided with barometric relief, relief fan or return fan to control building

pressure.

12.2 Equipment Testing Step 1: Simulate a cooling load and enable the economizer by adjusting the lockout control set

point. Verify and document the following:

(a) Economizer damper modulates opens to 100% outside air.

(b) Return air damper modulates closed and is completely closed when economizer

damper is 100% open.

(c) Economizer damper is 100% open before mechanical cooling is enabled.

(d) Relief fan or return fan (if applicable) is operating or barometric relief dampers freely

swing open.

Step 2: Continue from Step 1 and disable the economizer by adjusting the lockout control set

point. Verify and document the following:

(a) Economizer damper closes to minimum ventilation position.

(b) Return air damper opens to at or near 100%.

(c) Relief fan (if applicable) shuts off or barometric relief dampers close. Return fan (if

applicable) may still operate even when economizer is disabled.

148

13. Appendix D: Compliance Forms Envelope Summary

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms

Project Info Project Address Date

For Building Department Use

Project Built-up Area [m2]

Project Above-grade Area [m2]

Project Conditioned Area [m2]

Applicant Name and Address

Project Climatic Zone

Building

Classification

Hospitality

Business

Health Care

Educational

Assembly

Shopping Complex

Project Description

New Building

Addition

Alteration

Self-occupied

Core and Shell

Mixed-Use

Compliance is sought for

Energy efficiency level

ECBC Compliant

ECBC+ Compliant

SuperECBC Compliant

EPI Ratio

Compliance Prescriptive Method Whole Building Performance Building Trade-off Method

Approach Method Envelope Compliance

Building Envelope

Vertical Fenestration

Area Calculation

Total Vertical

Fenestration Area

(rough opening)

/ Gross Exterior

Wall Area

X 100 = % Window to Wall

Ratio (WWR)

X 100 =

Skylight Area

Calculation

Total Skylight Area / Gross Exterior times (rough opening) Wall Area 100 equal % Skylight to roof ratio (SRR)

÷ X 100 =

149

Daylighting Summary % above-grade floor area meeting the UDI

requirement for 90% of the potential daylit time in a year

Fenestration

Vertical Maximum U-factor Maximum SHGC (or SC) Minimum VLT Overhang / Side fins / Box Frame Projection (yes or no)

If yes, enter Projection Factor for each

orientation and effective SHGC

Skylight Maximum U-factor

Maximum SHGC (or SC)

Opaque Assembly Wall (Minimum

Insulation U-factor)

Roof (Minimum

Insulation U-factor)

Cool Roof

Solar Reflectance Emittance

Wall Assembly Material R-value Assembly U-Factor

150

Envelope Checklist

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms

Project

Address

Applicability Code

Section Component Information Required Location

on Plans

Building

Department Notes

Y e s

N o

N /A

Mandatory Provisions (Section 4.2)

4.2.1 Fenestration rating

4.2.1.1 U-factor Specify reference standard

4.2.1.2 SHGC Specify reference standard

4.2.2 Opaque U-factors Specify reference standard

4.2.3 Daylighting Specify simulation approach or prescriptive

4.2.4

Building envelope sealing

Indicate sealing, caulking, gasketing, and Weather stripping

Prescriptive Compliance Option (Section 4.3)

4.2.5 Roofs Specify implemented U factor

4.2.6 Opaque External Wall

Specify implemented U factor

4.3.1 Vertical fenestration

(1) Indicate U-factors on fenestration schedule. Indicate if values are rated or default. If values are default, then specify frame type, glazing layers, gap width, low-e. (2) Indicate SHGC or SC on fenestration schedule. Indicate if values are rated or default. (3) Indicate VLT of fenestration schedule. Indicate if values are rated or default. (4) Indicate if overhangs or side fins or box- frame projection are used for compliance purposes. If so, provide projection factor calculation and equivalent SHGC calculation

4.3.2 fenestration U factor exemption

Specify if applicable, specify unconditioned space percentage, and specify incorporated specifications

4.3.2 Skylights (1) Indicate U-factors on fenestration schedule. Indicate if values are rated or default. If values are default, then specify frame type, glazing layers, gap width, low-e. (2) Indicate SHGC or SC on fenestration schedule. Indicate if values are rated or default.

4.3.3.1 Vegetative cool roof Specify the solar reflectance, emittance, and Reference standards

Building Envelope Trade-Off Option (Section 4.3.4)

Provide calculations

151

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms

Project Info Project Address: Date

For Building Department

Use

Project Built-up Area [sq.m]:

Project Above-grade Area [sq.m]:

Project Conditioned Area [sq.m]:

Applicant Name and Address:

Project Climatic Zone:

Project Description Briefly described

comfort system type

and features.

Natural ventilation, mechanical Ventilation, Low energy comfort system, heating and

cooling mechanical equipment. percentage area distribution for the installed system, and

related information

Compliance Option System efficiency Prescriptive Method Whole Building Performance Method

Equipment Schedules The following information is required to be incorporated with the mechanical equipment schedules on the plans. For projects without plans, fill in the required information below.

Cooling Equipment Schedule Equip.

ID

Brand Name

Model No. Capacity

kW Testing

Standards OSA CFM

or Economizer?

COP IPLV

Location

Comfort System and Control Summary

152

Heating Equipment Schedule

Equip. ID

Brand Name

Model No.

Capacity

kW Testing

Standards OSA CFM

or

Economizer?

Input kW

Output kW

Efficiency

Fan Equipment Schedule

Equipment

ID Brand Name Model No. Testing

Standards SP Efficiency Flow

Control Location of Service

153

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms

Project

Address

Date

The following information is necessary to check a building permit application for compliance with the mechanical requirements in the Energy

Conservation Building Code.

Applicability Code Component Information Required Location on Building Department Notes

Section

Plans

Y e

s

N o

N /A

Comfort Systems and Control

Mandatory Provisions (Section 5.2) 5.2.1 Ventilation Indicate all habitable spaces are ventilated with outdoor air in accordance

with § 5.2.1 and guidelines specified in NBC 5.2.2 Minimum Space Conditioning Provide equipment schedule with type, capacity, efficiency

Equipment Efficiencies 5.2.3 Controls 5.2.3.1 Timeclock Indicate thermostat with night setback, 3 different day types per week, and

2-hour manual override, capable of retaining programming and time setting during loss of power for a period of at least 10 hours

5.2.3.2 Temperature Controls Indicate temperature control with 3°C deadband minimum if the system provides both heating and cooling.

Indicate thermostats are interlocked to prevent simultaneous heating and cooling, where separate heating and cooling systems are there

Indicate separate thermostat control for space types mentioned in § 5.2.3.2.(c)

5.2.2.3 Occupancy Controls Indicate occupancy controls for space types mentioned in § 5.2.3.3

5.2.2.4 Fan Controls Indicate two-speed motor, pony motor, or variable speed drive to control the fans and controls shall be capable to reduce the fan speed to at least two third of installed fan power

5.2.2.5 Dampers Indicate all air supply and exhaust equipment’s having VFD shall have dampers that automatically close upon the situations

mentioned in § 5.2.3.5 5.2.4 Additional Controls for ECBC+

Building

5.2.4.1 Centralized Demand Shed Controls

Indicate the building has a Building Management System, with all Mechanical cooling and heating systems having PLC to the zone level shall

have the control capabilities mentioned in § 5.2.4.1 5.2.4.2 Supply Air temperature reset Indicate multi zone mechanical cooling and heating systems shall have controls

to automatically reset supply air temperature in response to building loads or outdoor air temperature by at least 25% of the difference between design supply air temperature and the design room air temperature.

5.2.4.3 Chilled Water Temperature Indicate chilled water systems exceeding 350 kW shall have controls to automatically reset supply water temperatures by representative building loads or by outdoor air temperature

5.2.5 Additional controls for SuperECBC Building

Indicate that the mechanical systems comply with § 5.2.4 and § 5.2.5

Comfort System & Controls Checklist

154

5.2.5.1 Variable Air Volume Fan Control Indicate Fans in VAV systems shall have controls or devices to limit fan motor demand as per § 5.2.5.1

5.2.6 Piping & ductwork Indicate sealing, caulking, gasketing, and weather stripping

5.2.6.1 Piping insulation Indicate R-value of Insulation

5.2.6.2 Ductwork and Plenum insulation Indicate R-value of Insulation

5.2.7 System Balancing Show written balance report for HVAC systems serving zones with a total conditioned area exceeding 500 m2

5.2.8 Condensers Indicate location of condenser and source of water used for condenser

5.2.9 Service Hot Water Heating

5.2.9.1 Solar Water Heating Indicate all Hotels and hospitals have solar water heating equipment installed for hot water design capacity as per § 5.2.9.1

5.2.9.2 Heating Equipment Efficiency Indicate service water heating equipment shall meet the performance and efficiency as per § 5.2.9.2

5.2.9.3 Supplementary Water Heating System

Indicate supplementary heating system is designed in consideration with § 5.2.9.3

5.2.9.4 Piping Insulation Indicate the Piping insulation is compliant with § 5.2.6.1.

5.2.9.5 Heat Traps Indicate vertical pipe risers serving water heaters and storage tanks are as per § 5.2.9.5

5.2.9.6 Swimming Pools Indicate the heated pools are provided with a vapor retardant pool cover on the water surface and temperature control and minimum insulation value as per § 5.2.9.6

Prescriptive Compliance Option (Section 5.3)

5.3.1 Fans Indicate fan type, motor efficiency and mechanical efficiency

5.3.2 Pumps Indicate pump type (Primary, secondary, and condenser), its total installed capacity and efficiency

5.3.3 Cooling Towers Indicate cooling tower type and installed capacity

5.3.4 Air-Economizer (ECBC/ECBC+/SuperECBC)

Indicate air economizer is capable of modulating outside-air and return-air dampers to supply 50% of design supply air quantity as outside-air for respective building type.

5.3.4 Water-economizer (ECBC/ECBC+/SuperECBC)

Indicate water economizer is capable of providing 50% of the expected system cooling load at outside air temperatures of 10°C dry-bulb/7.2°C wet-bulb and below, if the designed building is a respective building type.

5.3.4.3 Partial Cooling Indicate where required by § 5.3.4 economizers shall be capable of providing partial cooling even when additional mechanical cooling is required to meet the cooling load.

5.3.4.4 Controls Indicate air economizers are equipped with controls as specified in § 5.3.4.4

5.3.9 Testing Indicate air-side economizers have been tested as per the requirement specified

5.3.5 Variable Flow Hydronic Systems

5.3.5.1 Variable Fluid Flow Indicate design flow rate of HVAC pumping system

5.3.5.2 Isolation Valves Indicate water cooled air-conditioning have two-way automatic isolation valves and pump motors greater than or equal to 3.7 kW is controlled by variable speed drives

155

5.3.5.3 Variable Speed Drives Indicate Chilled water or condenser water systems comply with either § 5.3.5.1 or § 5.3.5.2

5.3.5.4 Heat Recovery Indicate for all Hospitality and Healthcare, heat recovery effectiveness, and efficiency of oil and gas fired boilers

5.4 System Efficiency-Alternate Compliance approach

Attach simulation report

5.5 Low Energy Comfort Systems Indicate system type and list the exemption claimed

156

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms

Project Info Project Address: Date

For Building Department Use

Project Built-up Area (m2):

Project Above-grade area (m2):

Project Conditioned Area (m2):

Applicant Name and Address:

Project Climatic Zone:

Compliance Option Space by Space method Whole Building Method

Maximum Allowed Lighting Power (Interior, Section 6.3.2 or 6.3.3)

Location (Floor/room no.)

Occupancy Description

Allowed

Watts per m2 **

Area in m2

Allowed x Area

** Document all exceptions Total Allowed Watts

Proposed Lighting Power (Interior)

Location (floor/room no.)

Fixture Description Number of Fixtures

Watts/

Fixtur

e

Watts Proposed

Total Proposed Watts may not exceed Total Allowed Watts for Interior Total Proposed Watts

Maximum Allowed Lighting Wattage (Exterior, Section 6.3.5)

Location Description

Allowed Watts per m2

or per lm

Area in m2 (or lm for

perimeter)

Allowed Watts

x m2 (or x lm)

Total Allowed Watts

Proposed Lighting Wattage (Exterior)

Location Fixture Description Number of Fixtures

Watts/ Fixture

Watts Proposed

Total Proposed Watts may not exceed Total Allowed Watts for Exterior Total Proposed Watts

Lighting and Controls Summary

157

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms

Project

Address

Date

The following information is necessary to check a building permit application for compliance with the lighting requirements

in the Energy Conservation Building Code 2018.

Applicability Code

Section

Component Information Required Location

on Plans

Building Department Notes

Y e s

N o

N /A

Lighting and Controls

Mandatory Provisions (Section 6.2)

6.2.1 Lighting Controls

6.2.1.1 Automatic shutoff

Indicate automatic shutoff locations or occupancy sensors

6.2.1.2 Space control Provide schedule with type, indicate locations

6.2.1.3 Daylit Zones Provide manual or automatic control device schedule with type and features, indicate locations

6.2.1.4 Centralized Controls_ECBC+ and SuperECBC Buildings

Provide centralized control system schedule with type and features, indicate locations

6.2.1.5 Ext. lighting control

Indicate photosensor or astronomical time switch

6.2.1.6 Additional control

Provide schedule with type, indicate locations

6.2.3 Exit Signs Indicate wattage per face of Exit signs

Prescriptive Interior Lighting Power Compliance Option (Section 6.3)

6.3 LPD complaince Indicate whether project is complying with the Building Area Method (6.3.2) or the Space Function Method (6.3.3)

6.3.2 Building area method

Provide lighting schedule with wattage of lamp and ballast and number of fixtures. Document all exceptions.

6.3.3 Space function method

Provide lighting schedule with wattage of lamp and ballast and number of fixtures. Document all exceptions.

6.3.4 Luminaire wattage

Indicate the wattage of installed luminaires on the floor plan. In case of luminaires containing permanently installed ballasts, the operating input wattage has to be provided, either from manufacturer’s catalogs or values from independent testing laboratory reports.

Prescriptive Exterior Lighting Power Compliance Option (Section 6.3.5)

6.4 External light allowance

Provide lighting schedule with wattage of lamp and ballast and number of fixtures. Document all exceptions.

Lighting and Controls Checklist

158

Uttar Pradesh Energy Conservation Building Code 2018 Compliance Forms Project

Address

Date

The following information is necessary to check a building permit application for compliance with the Electrical and

Renewable Energy requirements in the Uttar Pradesh Energy Conservation Building Code 2018.

Applicability Code

Section

Component Information Required Location

on Plans

Building Department Notes

Y e s

N o

N /A

Electrical and Renewable Energy System

Mandatory Provisions (Section 7.2)

7.2.1 Transformers

7.2.1.1 Maximum Allowable Power Transformer Losses

Power transformers of the proper ratings and design must be selected to satisfy the minimum acceptable efficiency at 50% and full load rating.

7.2.1.2 Measurement and Reporting of Transformer Losses

All measurement of losses shall be carried out by using calibrated digital meters of class 0.5 or better accuracy and certified by the manufacturer.

All the transformers of capacity of 500 kVA and above would be equipped with additional metering class current transformers (CTs) and potential transformers (PTs) additional to requirements of Utilities

7.2.1.3 Voltage Drop Voltage drop for feeders shall not exceed 2% at design load. Voltage drop for branch circuit shall not exceed 3% at design load.

7.2.2 Energy Efficient Motors

Motors shall comply with the point (a) to (g) mention in this section of the code

7.2.3 Diesel Generator (DG) Sets

BEE star rated DG sets shall be used in all compliant buildings. DG sets in buildings greater than 20,000 m² BUA shall have 3 to 5 star rating for different levels of ECBC Buildings

7.2.4 Check- Metering and Monitoring

comply with the point (a) to (d) mention in this section of the code

7.2.5 Power Factor Correction

All 3 phase shall maintain their power factor at the point of connection as 0.97 or 0.98 or 0.99 for different levels of ECBC Buildings

7.2.6 Power Distribution Systems

The power cabling shall be sized so that the distribution losses do not exceed 3% or 2% or 1% of the total power usage in different levels of ECBC Buildings

7.2.7 Uninterruptibl e Power Supply (UPS)

In all buildings, UPS shall meet or exceed the energy efficiency requirements listed in Table 7-4. Any Standards and Labeling program by BEE shall take precedence over requirements listed in this section.

7.2.8 Renewable Energy Systems

Electrical & Renewable Energy Checklist

159

7.2.8.1 Renewable Energy Generating Zone (REGZ)

comply with the point (a) to (c) mention in this section of the code

7.2.8.2 Main Electrical

Service Panel

Minimum rating shall be displayed on the main electrical service panel. Space shall be reserved for the installation of a double pole circuit breaker for a future solar electric installation.

7.2.8.3 Demarcation on Documents

The points shall be indicated in design and construction documents mentioned in (a) to (d) in this section.

160

Whole Building Compliance:

Whole Building Performance Method Compliance Form

Uttar Pradesh Energy Conservation Building Code 2018 WBP Compliance Form

Project Info Project Address Date

For Building Department Use

Project Built-up Area [m2]

Project Above-grade Area [m2]

Project Conditioned Area [m2]

Applicant Name and Address

Project Climatic Zone

Building

Classification

Hospitality

Business

Health Care

Educational

Assembly

Shopping Complex

Project Description

New Building

Addition

Alteration

Self-occupied

Core and Shell

Mixed-Use

Compliance is sought for

Energy efficiency level

ECBC Compliant

ECBC+ Compliant

SuperECBC Compliant

EPI Ratio

The following information is necessary to check a building permit application for compliance with the Whole Building

Performance Method requirements in the Uttar Pradesh Energy Conservation Building Code 2018.

Applicability Code

Section

Component Information Required Location

on Plans

Building Department Notes

Y e s

N o

N /A

Whole Building Performance Method

9.1 General

9.1.2 Compliance As per specified in the code

9.1.3 Annual Energy Use As per specified in the code

9.1.4 Tradeoff Limited to Building Permit

As per specified in the code

9.1.5 Documentation Requirements

As per specified in the code

9.2 Mandatory Provisions

161

4 Building Envelope

4.2 Mandatory Requirement As per specified in the code

5 Comfort System and Controls

5.2 Mandatory Requirement As per specified in the code

6 Lighting and Controls

6.2 Mandatory Requirement As per specified in the code

7 Electrical & Renewable Energy System

7.2 Mandatory Requirement As per specified in the code

9.3 Simulation Requirements

As per specified in the code, Bureau of Energy Efficiency Approved Software for Demonstrating Compliance with ECBC in Table 14-1

9.4 WBP Compliance Report As per UPECBC Section 9.0

162

14. Appendix E: BEE approved list of software to show compliance4

Table 14-1 Bureau of Energy Efficiency Approved Software for Demonstrating Compliance

with ECBC

Analysis Software

Whole Building Performance Method AECOsim

Design Builder

DOE2

Energy Plus

eQUEST

HAP

IDA-ICE

IES-VE

OpenStudio

Simergy

Trace700

TRNSYS

Visual DOE

Daylighting AGI32(Licaso)

Daysim

Design Builder

DIVA

Groundhog

IES-VE

OpenStudio

RadianceRhino-Grasshopper with Daylighting

Plugins

Sefaira

Sensor Placement + Optimization Tool (SPOT)

4This is not an all-inclusive list. The current list of approved software is available at BEE website

(https://www.beeindia.gov.in/).

SECTIONS