Growth modeling is necessary to calculate whether a particular stand meets stand requirement and is on a trajectory towards these desired future condition basal area target. The appropriate growth model will be based on stand characteristics and will include at a minimum, the following components: The number of trees by diameter class, the percent of conifer and hardwood, and the age of the stand. See board manual section 7.
(i)
Hardwood conversion in the inner zone. When the existing stands in the combined core and inner zone do not meet stand requirements, no harvest is permitted in the inner zone, except in connection with hardwood conversion.
The landowner may elect to convert hardwood-dominated stands in the inner zone to conifer-dominated stands. Harvesting and replanting shall be in accordance with the following limits:
(A) Conversion activities in the
inner zone of any harvest unit are only allowed where all of the following are present:
. Existing stands in the combined core and inner zone do not meet stand requirements (WAC 222-30-021(1)(b) );
. There are fewer than fifty-seven conifer trees per acre eight inches or larger dbh in the conversion area;
. There are fewer than one hundred conifer trees per acre larger than four inches dbh in the conversion area;
. There is evidence (such as conifer stumps, historical photos, or a conifer understory) that the conversion area can be successfully reforested with conifer and support the development of conifer stands;
. The landowner owns five hundred feet upstream and five hundred feet downstream of the harvest unit;
. The core and inner zones contain no stream adjacent parallel roads;
. Riparian areas contiguous to the proposed harvest unit are owned by the landowner proposing to conduct the conversion activities, and meet shade requirements of WAC 222-30-040 or have a seventy-five foot buffer with trees at least forty feet tall on both sides of the stream for five hundred feet upstream and five hundred feet downstream of the proposed harvest unit (or the length of the stream, if less);
. If the landowner has previously converted hardwood-dominated stands, then post-harvest treatments must have been performed to the satisfaction of the department.
(B) In addition to the conditions set forth above, permitted conversion activities in the
inner zone of any harvest unit are limited by the following:
. Each continuous conversion area is not more than five hundred feet in length; two conversion areas will be considered "continuous" unless the no-harvest area separating the two conversion areas is at least half the length of the larger of the two conversion areas.
. Type S and F (Type 1, 2, or 3) Water: Up to fifty percent of the inner zone area of the harvest unit on one side of the stream may be converted provided that:
. The landowner owns the opposite side of the stream and the landowner's riparian area on the opposite bank meets the shade requirements of WAC 222-30-040 or has a seventy-five foot buffer of trees at least forty feet tall or:
. The landowner does not own land on the opposite side of the stream but the riparian area on the opposite bank meets the shade requirements of WAC 222-30-040 or has a seventy-five foot buffer of trees at least forty feet tall.
. Not more than twenty-five percent of the inner zone of the harvest unit on both sides of a Type S or F Water may be converted if the landowner owns both sides.
(C) Where conversion is allowed in the
inner zone, trees within the conversion area may be harvested except that:
. Conifer trees larger than twenty inches dbh shall not be harvested;
. Not more than ten percent of the conifer stems greater than eight inches dbh, exclusive of the conifer noted above, within the conversion area may be harvested; and
. The landowner must exercise reasonable care in the conduct of harvest activities to minimize damage to all residual conifer trees within the conversion area including conifer trees less than eight inches dbh.
(D) Following harvest in conversion areas, the landowner must:
. Reforest the conversion area with conifer tree species suitable to the site in accordance with the requirements of WAC 222-34-010; and
. Conduct post-harvest treatment of the site until the conifer trees necessary to meet acceptable stocking levels in WAC 222-34-010(2) have crowns above the brush or until the conversion area contains a minimum of one hundred fifty conifer trees greater than eight inches dbh per acre.
. Notify the department in writing within three years of the approval of the forest practices application for hardwood conversion, if the hardwood conversion has been completed.
(E)
Tracking hardwood conversion. The purpose of tracking hardwood conversion is to determine if hardwood conversion is resulting in adequate enhancement of riparian functions toward the desired future condition while minimizing the short term impacts on functions. The department will use existing or updated data bases developed in cooperation with the Washington Hardwoods Commission to identify watershed administrative units (WAUs) with a high percentage of hardwood-dominated riparian areas and, thus have the potential for excessive hardwood conversion under these rules. The department will track the rate of conversion of hardwoods in the riparian zone: (1) Through the application process on an annual basis; and (2) at a WAU scale on a biennial basis as per WAC
222-30-120 through the adaptive management process which will develop thresholds of impact for hardwood conversion at the watershed scale.