48 CFR 11.502 : Federal Acquisition Regulations System (Section 1.000 To Parts 9906-9999) — Federal Acquisition Regulation (Parts 1 - 99) (Section 1.000 To Parts 54-99) — Acquisition Planning (Parts 5 - 12) (Section 5.000 To Section 12.603) — Describing Agency Needs (Section 11.000 To Section 11.801) — Liquidated Damages (Section 11.500 To Section 11.503) — Procedures.

31 Dec 2014

(a) Include the applicable liquidated damages clause and liquidated damages rates in solicitations when the contract will contain liquidated damages provisions.

(b) Construction contracts with liquidated damages provisions must describe the rate(s) of liquidated damages assessed per day of delay. The rate(s) should include the estimated daily cost of Government inspection and superintendence. The rate(s) should also include an amount for other expected expenses associated with delayed completion such as—

(1) Renting substitute property; or

(2) Paying additional allowance for living quarters.