43 CFR 3483.2 : Public Lands: Interior (§ 1.1 To Parts 10011-10099) — (Parts 1000-1599 To Parts 10011-10099) — Regulations Relating To Public Lands (Continued) (Parts 1000-1599 To Parts 10011-10099) — Bureau Of Land Management, Department Of The Interior (Parts 1000-1599 To Parts 9261-9999) — Minerals Management (3000) (§ 3000.0-5 To § 3936.40) — Coal Exploration And Mining Operations Rules (§ 3480.0-1 To § 3487.1) — Diligence Requirements (§ 3483.1 To § 3483.6) — Termination or cancellation for failure to meet diligent development and maintain continued operation.

4 Aug 2016

(a) Any Federal coal lease or LMU which has not achieved diligent development shall be terminated by DOI.

(b) After an LMU has been terminated under the provision of paragraph (a) of this section, any Federal coal lease included in that LMU shall then be subject to the diligent development and continued operation requirements that would have been imposed on that Federal lease by the rules of this part, as if the Federal lease had not been included in the LMU.

(c) Any Federal coal lease on which continued operation is not maintained shall be subject to cancellation.

(d) The DOI may cancel any Federal coal lease or LMU which fails to meet the requirement for submission of a resource recovery and protection plan.

43 CFR 3483.2