D. THE COMMISSION'S FINAL ORDERS The participating parties and the Commission's staff filed comments addressing the hearing examiner's report. VEPCO and the Commission's staff agreed with the hearing examiner's findings and recommendations.5F6 The County and the Conservancy challenged the hearing examiner's report on numerous grounds. Their primary arguments, however, addressed the underground construction of the Aspen-Golden transmission lines. The County and the Conservancy requested that the Commission reject the hearing examiner's findings and recommendations and order VEPCO to construct a portion of the Aspen-Golden transmission lines underground. Alternatively, the Conservancy requested that the Commission impose additional conditions to mitigate the visual impacts of the overhead Aspen-Golden transmission lines.6F7
The Commission granted VEPCO's applications and issued CPCNs for the Aspen- Golden and Apollo-Twin Creeks Projects, adopting the hearing examiner's findings and recommendations. In its order addressing the Aspen-Golden Project, the Commission expressly endorsed the hearing examiner's extensive analysis of the feasibility of underground construction 6Ghiorzi also filed comments supporting the hearing examiner's report, asserting that the recommended overhead route imposed the least impact on private property. 7Specifically, the Conservancy requested that the Commission order VEPCO to: (1) refrain from collocating other utility lines within the right of way approved for the Aspen-Golden Project, (2) install and maintain vegetation to reduce the visual impact of the Aspen-Golden transmission lines and other associated structures, and (3) only utilize the amount of approved right of way that was necessary for the implementation of the Aspen-Golden Project. The Conservancy also requested that the Commission keep the record open in the Aspen-Golden case to facilitate the enforcement of these conditions. The County did not join the Conservancy's request.
12
and the UHP. The Commission did not impose the additional conditions requested by the Conservancy. These appeals followed.
II. ANALYSIS
The appellants challenge the Commission's judgments on several grounds. First, the appellants contend that the Commission failed to verify certain information establishing the need for the Aspen-Golden Project. Next, the appellants argue that the Commission erred by determining that the underground construction of a portion of the Aspen-Golden transmission lines was not feasible. The appellants maintain that the Commission erroneously rejected the UHP, in part because the Commission impermissibly required the appellants to present a fully developed proposal sufficient to justify the issuance of a CPCN.
The appellants claim that the Commission erred by permitting the overhead construction of the Aspen-Golden transmission lines along VEPCO's proposed Route 1AA, asserting that the construction of overhead transmission lines along the proposed route would interfere with the Belmont Scenic Viewshed Easement and violate the County's comprehensive plan. Moreover, the appellants contend that the overhead construction of the transmission lines would not minimize adverse impacts to scenic, cultural, historic, and environmental assets along Route 1AA. The Conservancy also claims that the Commission erred by failing to impose additional conditions to reduce the visual impacts of the overhead transmission lines. Finally, the appellants challenge the Commission's approval of the Apollo-Twin Creeks Project. Noting the proposed collocation of the Apollo-Twin Creeks and Aspen-Golden transmission lines, the appellants argue that the CPCN for the Apollo-Twin Creeks Project should have included provisions to accommodate the underground construction of the Aspen- Golden transmission lines.
13
A. THE STANDARD OF REVIEW
"The Constitution of Virginia and statutes enacted by the General Assembly give the Commission 'broad, general and extensive powers' in regulating public utilities." BASF Corp. v. State Corp. Comm'n, 289 Va. 375, 391 (2015) (quoting Office of the Att'y Gen. v. State Corp. Comm'n, 288 Va. 183, 190 (2014)). The Commission's decisions are "entitled to the respect due judgments of a tribunal informed by experience," id. (quoting Appalachian Voices v. State Corp. Comm'n, 277 Va. 509, 516 (2009)), and they come to the Court with a "presumption of correctness," West Virginia v. State Corp. Comm'n, 304 Va. 148, 160 (2025). We are "neither at liberty to substitute [our] judgment in matters within the province of the Commission nor to overrule the Commission's finding[s] of fact unless we can say its determination is contrary to the evidence or without evidence to support it." Appalachian Power Co. v. State Corp. Comm'n, 301 Va. 257, 292 (2022) (quoting Board of Supervisors v. Appalachian Power Co., 216 Va. 93, 105 (1975)). While we review the Commission's conclusions of law de novo, "we will not disturb the Commission's analysis when it is 'based upon the application of correct principles of law.'" BASF Corp., 289 Va. at 391 (quoting Appalachian Voices, 277 Va. at 516).
B. THE VERIFICATION OF THE LOAD FLOW MODELING, CONTINGENCY
ANALYSES, AND RELIABILITY NEEDS SUPPORTING THE ASPEN-GOLDEN
PROJECT
Before issuing a CPCN for the construction of a new electrical transmission line of 138 kV or more, the Commission must initially determine whether the new transmission line is needed. See Code § 56-46.1(B). "In making the determinations about need, corridor or route, and method of installation, the Commission shall verify the applicant's load flow modeling,
14
contingency analyses, and reliability needs presented to justify the new line and its proposed method of installation." Id.
The appellants contend that the Commission failed to verify the load flow modeling, contingency analyses, and reliability needs presented to justify the overhead construction of the Aspen-Golden transmission lines. This argument, however, is not supported by the record. In their report to the Commission, the Commission's staff expressly confirmed that they verified the data establishing the need for the Aspen-Golden Project. The report explained that the Commission's staff verified the power flow models provided by PJM and confirmed that the identified violations of NERC reliability standards would occur without the Aspen-Golden Project. Furthermore, the report explained that the Commission's staff verified that the Aspen- Golden Project would resolve the identified violations. Neither the County nor the Conservancy challenged the verification of this data when they cross-examined the witness sponsoring the section of the staff report addressing this issue.
As to the method of installation, the Commission's staff concluded that the Aspen- Golden transmission lines should be constructed overhead along Route 1AA. Although the Commission's staff investigated the underground construction of the Aspen-Golden lines, they rejected underground construction for numerous reasons, including "timing, cost, and constructability." Given the substantial engineering challenges presented by underground construction, the Commission's staff concluded that underground transmission lines were unlikely to be constructed before the identified violations of NERC reliability standards and the resulting thermal overloads occurred in the summer of 2028. Under these circumstances, the Commission's staff determined that overhead construction was the only feasible option for the project.
15
In some cases, the Commission's staff has engaged an independent consultant to verify technical information provided by a CPCN applicant. See Piedmont Env't Council v. Virginia Elec. & Power Co., 278 Va. 553, 570 (2009). Code § 56-46.1(B), however, does not require them to do so. In the present case, the record is sufficient to establish that the Commission verified the load flow modeling, contingency analyses, and reliability needs supporting the Aspen-Golden Project. Accordingly, the appellants' first argument is without merit. C. THE REJECTION OF THE UNDERGROUND CONSTRUCTION OF THE ASPEN-
GOLDEN TRANSMISSION LINES
When evaluating an application for a CPCN for a project involving the construction of an electrical transmission line of 138 kV or more, the Commission "shall consider, upon the request of the governing body of any county . . . in which the line is proposed to be constructed, (a) the costs and economic benefits likely to result from requiring the underground placement of the line and (b) any potential impediments to timely construction of the line." Code § 56-46.1(B). The Commission fully considered the underground construction of the Aspen-Golden transmission lines in this case, expressly adopting the hearing examiner's detailed analysis concerning this issue.
Numerous witnesses testified about the feasibility of the underground construction of the Aspen-Golden transmission lines and the UHP. Based on this testimony, the hearing examiner concluded that underground construction was not feasible for several reasons—including increased costs, engineering challenges, and the time constraints of the Aspen-Golden Project. This conclusion is supported by the record.
The record establishes that underground construction would cost substantially more than overhead construction. Brian Conroy, an engineer employed by RLC, confirmed that the UHP would cost approximately $423,000,000 more than VEPCO's proposal for the overhead
16
construction of the Aspen-Golden transmission lines. Other witnesses explained that the cost of underground construction could greatly exceed Conroy's estimate.
More significantly, the record also establishes that underground construction would present numerous engineering challenges. Noting that 500 kV transmission lines are rarely constructed underground, VEPCO's engineers testified that the underground construction of the Aspen-Golden transmission lines would require specialized materials, work crews, and equipment that may not be readily available. Additionally, VEPCO's engineers explained that the Aspen-Golden transmission lines would be constructed in an area with shallow diabase rock, which would slow the pace of underground construction. VEPCO's engineers also explained that existing underground utility lines in the area would need to be relocated before underground transmission lines could be constructed along the proposed route.
Like the Commission's staff, the hearing examiner determined that the engineering challenges of underground construction would delay the completion of the Aspen-Golden Project. The hearing examiner emphasized that the Aspen-Golden Project needed to be completed by the summer of 2028 to resolve identified violations of NERC reliability standards and resulting thermal overloads that could damage VEPCO's electrical facilities and lead to service interruptions in the region. Given the time constraints of the Aspen-Golden Project, the hearing examiner reasonably rejected the underground construction of a portion of the Aspen- Golden transmission lines.
The hearing examiner expressly noted that the UHP did not meet the statutory criteria for the issuance of a CPCN. Among other things, the hearing examiner explained that the UHP did not provide sufficient environmental impact and environmental justice analyses and that the route of the proposed underground transmission lines was uncertain.
17
These observations were relevant to the hearing examiner's analysis of the feasibility of the underground construction of the Aspen-Golden transmission lines. The hearing examiner recognized that the analytical deficiencies of the UHP would take additional time to resolve, further delaying the completion of the Aspen-Golden Project. The analytical deficiencies of the UHP presented impediments to the timely construction of the Aspen-Golden transmission lines, and therefore, constituted a pertinent factor for the hearing examiner to consider under the express language of Code § 56-46.1(B).
In the present case, the record establishes that the Commission fully considered the underground construction of a portion of the Aspen-Golden transmission lines and reasonably rejected that course of action. We will not disturb the Commission's judgment regarding this issue on appeal.
D. THE CONSIDERATION OF THE BELMONT SCENIC VIEWSHED EASEMENT
The Belmont Scenic Viewshed Easement is held by the County. The purpose of the easement is "to preserve and to maintain an unobstructed view of the historic Belmont Manor House from Route 7." In their pertinent assignment of error, the appellants assert that VEPCO's proposed overhead construction of the Aspen-Golden transmission lines along Route 1AA
"violates the Belmont Scenic Viewshed Easement at least twice, and thus does not minimize, to the extent reasonably practicable, the adverse impacts to scenic, cultural, and historic assets along the route, as required by Code § 56-46.1(B)."7F8
8On brief, the appellants also argue that the alleged violations of the easement precluded the proposed overhead construction of the transmission lines "as a matter of law." This argument falls outside of the scope of the appellants' assignment of error, and it was not presented during the proceedings before the Commission. Consequently, we will not consider this particular argument on appeal. See Rule 5:21(a)(7) (addressing procedural default in appeals arising from a judgment of the Commission).
18
The record establishes that the Commission considered the manner in which the Aspen- Golden Project would impact Belmont Manor. The hearing examiner observed that VEPCO's proposal would require at least two steel monopoles to be constructed in the area subject to the Belmont Scenic Viewshed Easement. The hearing examiner also noted that the language of the easement permitted public utility structures to be constructed within the protected viewshed. After weighing the adverse impacts on Belmont Manor and the alleged violations of the viewshed easement with other factors, the hearing examiner and the Commission concluded that Route 1AA presented the optimal route for the overhead transmission lines. The hearing examiner and the Commission determined that the construction of the transmission lines along Route 1AA minimized overall adverse impacts to scenic, cultural, historic, and environmental assets—notwithstanding the adverse impacts to Belmont Manor and the alleged violations of the viewshed easement. We conclude that this determination is supported by the record.
E. THE CONSIDERATION OF THE LOUDOUN COUNTY COMPREHENSIVE PLAN
Whenever the Commission is required to approve the construction of any electrical utility facility, the locality in which the facility is proposed to be constructed may request that the Commission "receive and give consideration . . . to local comprehensive plans that have been adopted pursuant to Article 3 ([Code] § 15.2-2223 et seq.) of Chapter 22 of Title 15.2." Code § 56-46.1(A). The record in this case clearly establishes that the Commission considered the Loudoun County Comprehensive Plan.
William Giglio testified on behalf of the County about the comprehensive plan. Giglio explained that the comprehensive plan urged electrical service providers to minimize impacts on roadways, heritage resources, and existing residential communities by considering the construction of underground transmission lines where possible. Giglio also asserted that the
19
construction of underground transmission lines was of particular importance along "gateway corridors," such as Route 7.
The hearing examiner expressly addressed the comprehensive plan in her report to the Commission. Although the hearing examiner recognized that the underground construction of the Aspen-Golden transmission lines would more closely align with the County's comprehensive plan, the hearing examiner explained that underground construction was not feasible. The Commission fully adopted the hearing examiner's conclusions, thereby satisfying the statutory requirement to "receive and give consideration to" the comprehensive plan. Citing the provisions of Code § 15.2-2232,8F9 the appellants contend that the Commission was required to determine whether the proposed Aspen-Golden transmission lines were in
"substantial accord" with the County's comprehensive plan. This argument lacks merit. Code § 56-46.1(A) only requires the Commission to "give consideration to" a locality's comprehensive plan. We have recently explained that when the General Assembly directs the Commission to "consider" a certain factor, the Commission is not required to make specific findings related to that factor. West Virginia, 304 Va. at 158. Instead, the Commission is simply required "to reflect" on the factor or "think about [it] with a degree of care or caution." Id. (quoting Webster's Third New International Dictionary 483 (1993)). Other provisions of Code § 56-46.1 establish that the Commission was not required to engage in a "substantial accord" analysis under Code § 15.2-2232. When the Commission approves the construction of an electrical transmission line under Code § 56-46.1, the approved 9In pertinent part, Code § 15.2-2232 provides that if a locality has adopted a comprehensive plan, no new structures shall be constructed unless and until they have been approved by the local planning commission as being "substantially in accord with the adopted comprehensive plan." Code § 15.2-2232(A).
20
transmission line is deemed to comply with local comprehensive plans and zoning ordinances. Code § 56-46.1(F) states: "Approval of a transmission line pursuant to this section shall be deemed to satisfy the requirements of [Code] § 15.2-2232 and local zoning ordinances with respect to such transmission line." This subsection of the statute eliminates the need for any separate "substantial accord" analysis under Code § 15.2-2232 addressing the proposed Aspen- Golden transmission lines.
F. THE CONSIDERATION OF THE ADVERSE IMPACTS OF THE ASPEN-GOLDEN
PROJECT
When considering an application for a CPCN for a project involving the construction of an electrical transmission line of 138 kV or more, the Commission "shall determine that the line is needed and that the corridor or route chosen for the line will avoid or reasonably minimize adverse impact to the greatest extent reasonably practicable on the scenic assets, historic and cultural resources . . . , and environment of the area concerned." Code § 56-46.1(B). This determination involves the consideration of a "multitude of factors." BASF Corp.,
289 Va. at 400. "When presented with an application for transmission line construction, the Commission must 'balance' adverse impacts along with other 'factors' and 'traditional considerations.'" Id. at 394-95 (quoting Board of Supervisors, 216 Va. at 100). The term
"minimize" does not require the elimination of all impact. Id. at 399. After weighing the pertinent factors, the Commission "must decide within the parameters of the statute what best serves the 'total public interest.'" Id. at 395 (quoting Board of Supervisors, 216 Va. at 104). After considering numerous factors, the hearing examiner and the Commission approved the construction of overhead transmission lines along Route 1AA, concluding that this course of action would minimize adverse impacts to scenic assets, historic and cultural resources, and the environment to the greatest extent reasonably practicable. The record supports this conclusion.
21
VEPCO's witnesses testified that Route 1AA was designed to collocate with existing roadways and pass through commercial and industrial areas, avoiding residential areas and historic resources to the greatest extent possible. The record confirms that Route 1AA avoids several residential communities, wetlands, and other areas of environmental significance, including creeks, ponds, and forested areas. The record also establishes that the route avoids crossing the Lansdowne Viewshed Easement, which protects views from nearby residential communities. Additionally, the record establishes that the route minimizes the impact of the overhead transmission lines on the operation of a helipad at a nearby hospital. While underground construction of the transmission lines may have avoided some of the adverse visual impacts of the Aspen-Golden Project, the hearing examiner and the Commission determined that underground construction was not feasible for several reasons—including costs, engineering challenges, and time constraints. Therefore, the hearing examiner and the Commission concluded that underground construction did not present a viable option for minimizing the adverse impacts of the Aspen-Golden Project.
In the present case, the Commission fulfilled its statutory duty to consider the adverse impacts of the Aspen-Golden Project and the efforts taken to minimize those impacts. After doing so, the Commission reasonably determined that the adverse impacts arising from the project were minimized to the greatest extent reasonably practicable. We will not disturb the Commission's decision on appeal.
G. THE REFUSAL TO IMPOSE ADDITIONAL CONDITIONS ON THE ASPEN-
GOLDEN PROJECT
The Conservancy argues that the Commission erred when it refused to impose additional conditions addressing the adverse visual impacts of the Aspen-Golden Project. Significantly, the Conservancy did not address these conditions during the proceedings before the hearing
22
examiner. The Conservancy first requested the imposition of the conditions in its comments addressing the hearing examiner's report. Neither the Conservancy nor the County presented any evidence regarding the requested conditions or provided specific information to explain how the conditions would minimize the visual impacts of the overhead transmission lines. Under these circumstances, the Commission did not abuse its discretion when it declined to impose the conditions at issue. See West Virginia, 304 Va. at 162-63 (applying an abuse of discretion standard when reviewing the Commission's refusal to impose additional conditions in a CPCN).
H. THE APPROVAL OF THE APOLLO-TWIN CREEKS PROJECT
The appellants also contend that the Commission erred by approving the Apollo-Twin Creeks Project. Noting that the Apollo-Twin Creeks transmission lines were planned to collocate with the Aspen-Golden transmission lines for approximately one mile, the appellants argue that the Commission should have included provisions in the CPCN for the Apollo-Twin Creeks Project to accommodate the underground construction of the Aspen-Golden transmission lines.
The appellants' challenge to the approval of the Apollo-Twin Creeks Project is entirely contingent on the success of their arguments challenging the overhead construction of the Aspen- Golden transmission lines. We have determined that the Commission did not err by approving
23
transmission lines. We conclude that the Commission did not err by issuing the CPCN for the Apollo-Twin Creeks Project.
III. CONCLUSION
For the reasons stated, we affirm the judgments of the Commission. Affirmed.