Factual and Procedural Background

Defendant, a junior college district, contracted with plaintiff to construct school facilities for $1,071,325. Defendant withheld approximately $137,000 of the final payment, prompting plaintiff to sue for recovery of that sum plus interest and $600 for additional work. Defendant paid $102,523.61 of the withheld amount but retained the remainder, citing offsets. The trial court, without a jury, ruled mostly in favor of plaintiff, awarding $30,204.80 plus interest. Defendant appealed the judgment.

Legal Issues Presented

  1. Whether the contractual provision imposing liquidated damages for late completion applies when delay was caused by defendant's actions and plaintiff did not comply with the contract’s extension-of-time application requirement.
  2. Whether plaintiff’s failure to submit a written application for extension of time bars excusing delays caused by defendant’s conduct.
  3. Whether defendant is entitled to actual damages for late completion in addition to or instead of liquidated damages.
  4. Whether plaintiff is entitled to interest on a portion of the withheld payment from the date of acceptance of the work.
  5. Whether plaintiff is entitled to additional compensation for increased costs due to inconsistent specifications regarding window types.

Arguments of the Parties

Defendant's Arguments

  • Plaintiff cannot excuse late completion caused by defendant’s conduct because plaintiff failed to comply with the contractual requirement to submit a written application for extension of time.
  • The award of interest on the withheld sum was improper as the sum was not certain on the date interest began to accrue.
  • The evidence is insufficient to establish that defendant accepted the work on the date found by the trial court.

Plaintiff's Arguments

  • The delays were excusable because they were caused by matters beyond plaintiff’s control, including defendant’s conduct.
  • Section 1511 of the Civil Code excuses performance delays caused by the creditor (defendant), rendering contractual limitations on excusing such delays ineffective.
  • Interest is properly awarded from the date of acceptance of the work, regardless of the formal acceptance date by defendant's governing board.
  • Plaintiff is entitled to additional compensation for the increased cost of installing a different window type due to inconsistent plans and defendant’s representative’s insistence.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Semas v. Bergmann, 178 Cal.App.2d 758, 762 Owner as creditor under Civil Code section 1511; delays caused by owner excused despite contractual stipulations. Confirmed that defendant is a creditor and contractual provisions denying excuses for delays caused by defendant are inoperative under section 1511.
Progressive Builders, Inc. v. District of Columbia, 258 F.2d 431 Contractor’s failure to notify government of delay did not excuse liability for delay caused by government. Used to contrast with section 1511, emphasizing the harshness of holding contractors liable despite owner-caused delays without statutory protection.
Roberts v. Security T. S. Bank, 196 Cal. 557, 571-573 Contractor not excused for owner-caused delays if contractor failed to comply with extension application provisions. Disapproved to the extent inconsistent with section 1511; found not controlling because it lacked statutory consideration.
Suhr v. Metcalfe, 33 Cal.App. 59, 67-68 Section 1511 not applicable to owner-caused construction delays. Disapproved for lacking analysis and authority supporting its conclusion.
Byson v. City of Los Angeles, 149 Cal.App.2d 469, 473 Acceptance of work may not be arbitrarily delayed to the prejudice of contractor; work deemed accepted when finished. Supported trial court’s finding that acceptance occurred on the date work was completed, not on later formal acceptance date.
Wm. P. Jungclaus Co. v. Ratti, 67 Ind. App. 84 [118 N.E. 966, 968-969] Owner’s right to liquidated damages for delay. Cited as case from jurisdiction without a statute like section 1511, illustrating differing legal context.
Ward v. Haren, 139 Mo. App. 8 [119 S.W. 446, 447 et seq.] Owner’s entitlement to liquidated damages for delay. Similar to above, cited to show contrast with California statutory law.
Trauts Realty Corp. v. Casualty Co. of America, 166 N.Y.S. 807, 809 Owner’s right to liquidated damages. Again cited to demonstrate differing approaches absent a statute like section 1511.
Austin-Griffith, Inc. v. Goldberg, 224 S.C. 372 [79 S.E.2d 447, 452-453] Owner’s ability to enforce liquidated damages. Referenced for comparison; no statute like section 1511 applied.

Court's Reasoning and Analysis

The court focused on the contractual provision imposing liquidated damages for late completion and the requirement that plaintiff apply in writing for extensions of time. It held that under Civil Code section 1511, delays caused by the creditor (here, defendant) excuse the contractor from liability for delay, notwithstanding contractual provisions stating otherwise.

The court rejected defendant’s argument that plaintiff’s failure to comply with the extension application provision barred excusing the delay, reasoning that such a requirement would substantially limit the statutory policy favoring excusability of owner-caused delays. The court disapproved prior California cases that held otherwise because they did not consider section 1511.

The court upheld the trial court’s finding that the delay was excusable, thereby affirming the denial of liquidated damages and also ruling that defendant was not entitled to actual damages for late completion.

Regarding interest, the court found that the sum of $102,523.61 was a sum certain owing after the work was accepted on May 8, 1957, and that plaintiff was entitled to interest from June 12, 1957, despite the formal acceptance occurring later. The court emphasized that acceptance cannot be arbitrarily delayed to prejudice the contractor.

On the $600 additional compensation claim, the court found that inconsistent specifications and defendant’s representative’s insistence justified the award to plaintiff for increased costs.

Holding and Implications

The judgment of the trial court is AFFIRMED.

The court held that liquidated damages cannot be imposed on the contractor for delays caused by the owner, even if the contractor failed to comply with contractual extension-of-time provisions, pursuant to Civil Code section 1511. The decision disapproves contrary prior California cases lacking statutory analysis. Defendant is not entitled to actual damages for the delay, and plaintiff is entitled to interest on withheld payments from the date of work acceptance. Additionally, plaintiff is entitled to reasonable compensation for increased costs due to inconsistent contract specifications. This decision directly resolves the parties’ dispute but does not establish a new precedent beyond clarifying the application of section 1511 and extension-of-time provisions in construction contracts.

PETER KIEWIT SONS' COMPANY, Plaintiff and Respondent, v. PASADENA CITYJUNIOR COLLEGE DISTRICT OF LOS ANGELES COUNTY, Defendant and Appellant.

GIBSON, C.J.

Defendant, a junior college district, entered into a contract to pay plaintiff $1,071,325 for the construction of school facilities. The final payment of approximately $137,000 was withheld by defendant, and this action was brought to recover that sum plus interest and $600 for additional work and materials furnished by plaintiff. Defendant thereafter paid plaintiff $102,523.61 of the sum withheld but retained the remainder, claiming certain offsets. The trial court, sitting without a jury, found for plaintiff with respect to most of the items in dispute, and defendant appeals from the judgment, which awards plaintiff $30,204.80 and specified sums as interest. The principal question presented concerns the effect, if any, to be given to a provision of the contract that, if the work was not completed within the time specified (300 days after notice to start work), the sum of $25 was to be deducted from the final payment as liquidated damages for each day's delay after the expiration of that period until final acceptance by defendant. The agreement also provided that, if plaintiff considered itself entitled to an extension of time for any cause, it must submit in writing to the architect and defendant an application for such extension. Extensions were to be granted only for delays resulting from causes beyond plaintiff's control, including, among other things, strikes, alterations of the work delaying completion, and "any act of neglect, duty, or default" of defendant.

The work was not completed within the time specified, nor within the time allowed by extensions granted by defendant. However, the trial court, in concluding that defendant was not entitled to liquidated damages, found that the late completion was caused by matters beyond plaintiff's control and was entirely excusable. Defendant concedes that the evidence is sufficient to support this finding if it is proper to take into account various delays caused by defendant's conduct as to which plaintiff did not request extensions of time in accordance with the contractual provision set forth above. It is argued that plaintiff cannot be excused in the absence of compliance with that contractual provision.

Section 1511 of the Civil Code provides in subdivision 1 that any delay in the performance of an obligation "is excused" when performance is delayed by "the act of the creditor . . . even though there may have been a stipulation that this shall not be an excuse." (Italics added.) [1] An owner who is a party to a construction contract is a creditor within the meaning of section 1511 ( Semas v. Bergmann, 178 Cal.App.2d 758, 762 [ 3 Cal.Rptr. 277]), and, as the italicized portion of the section makes clear, a provision in an agreement that the contractor is not to be excused for late completion caused by the owner is rendered inoperative by the statute. [2] A provision in a contract which would require the contractor to make an application for an extension of time before he may be excused for a delay caused by the owner's conduct would obviously constitute a substantial limitation on the policy declared by section 1511

In commenting on a case ( Progressive Builders, Inc. v. District of Columbia, 258 F.2d 431) where, in the absence of a statute like section 1511, it was held that a contractor who had not complied with a provision for written notice of the cause of a delay was liable although the delay was caused by the government, a leading authority states: "It seems like pretty tough governmental policy to interpret the contract provision so that the contractor's failure to give notice that the defendant was obstructing completion on time should not only deprive the contractor of his right to damages for such obstruction, but also justify the defendant in withholding a large part of the contract price as `liquidated damages' for a delay caused by the defendant itself." (See 5 Corbin on Contracts (1951) § 1074 [1962 Supp. pp. 50-51, fn. 24].)

Roberts v. Security T. S. Bank, 196 Cal. 557, 571-573 [ 238 P. 673], which contains language to the effect that a contractor may not be excused for delays caused by the owner where the contractor had failed to comply with a provision requiring him to apply for extensions of time, did not mention section 1511 of the Civil Code, and the decision rests largely on the ground that, under another contractual provision, the architect on the job had made a binding factual determination that a delay was not justified. The case of Suhr v. Metcalfe, 33 Cal.App. 59, 67-68 [164 P. 407], although it mentions section 1511, erroneously concluded, without analysis or citation of authority, that the section was not applicable to acts of an owner causing late completion of a construction contract. Decisions from other jurisdictions relied on by defendant do not appear to have involved a statute like section 1511 ( Wm. P. Jungclaus Co. v. Ratti, 67 Ind. App. 84 [118 N.E. 966, 968-969]; Ward v. Haren, 139 Mo. App. 8 [119 S.W. 446, 447 et seq.]; Trauts Realty Corp. v. Casualty Co. of America, 166 N.Y.S. 807, 809; Austin-Griffith, Inc. v. Goldberg, 224 S.C. 372 [ 79 S.E.2d 447, 452-453].)

[3] It should be pointed out that, in the absence of a contractual provision for extensions of time, the rule generally followed is that an owner is precluded from obtaining liquidated damages not only for late completion caused entirely by him but also for a delay to which he has contributed, even though the contractor has caused some or most of the delay. (See 5 Williston on Contracts (3d ed. 1961) p. 764; 15 Am.Jur. 696; 152 A.L.R. 1349, 1359.) Acceptance of the reasoning urged by defendant would mean that, solely because there has been noncompliance with an extension-of-time provision, the position of an owner could be completely changed so that he could withhold liquidated damages for all of the period of late completion even though he alone caused the delay.

[4] Noncompliance with a provision requiring an application for an extension of time is not a proper basis for holding a contractor liable in liquidated damages for late completion caused by the owner's conduct. The cases of Roberts v. Security T. S. Bank, supra, 196 Cal. 557, and Suhr v. Metcalfe, supra, 33 Cal.App. 59, are disapproved insofar as they are inconsistent with this view.

It follows from what we have said that the trial court's finding of excusability must be upheld. This means not only that the denial of liquidated damages must be affirmed but also that defendant is not entitled to any actual damages for late completion. There is no need to determine whether the denial of liquidated damages could also be affirmed on the ground that the provision for such damages was invalid or that defendant waived compliance with the provision for extensions of time.

Defendant claimed actual damages, apparently as an alternative to enforcement of the provision for liquidated damages, and the trial court determined that no award for actual damages was justified.

One of the matters in controversy other than the denial of liquidated damages is an award to plaintiff of interest on the sum of $102,523.61, which was paid to plaintiff on May 3, 1958, after commencement of this action. Under the agreement, final payment on the contract price was to be made by defendant 35 days after the date of "acceptance of the work by the Owner," found by the trial court to be May 8, 1957. The court thus awarded plaintiff interest on $102,523.61 from June 12, 1957, until May 3, 1958.

[5] We cannot accept defendant's assertion that the $102,523.61 was not a sum certain owing to plaintiff on June 12, 1957, and that, therefore, the award of interest was improper. Although the final payment of approximately $137,000 was in dispute to some extent on June 12, 1957, the record clearly warrants the conclusion that plaintiff's right to the sum of $102,523.61 was not in controversy since the money withheld in excess of that sum was adequate to satisfy all the offsets claimed by defendant.

Defendant also challenges the interest award on the ground that the evidence is insufficient to show that defendant accepted the work on May 8, 1957. This contention rests largely on the fact that the governing board of defendant did not formally accept the work until January of 1958, designating October 3, 1957, as the acceptance date. [6] Obviously, however, acceptance may not be arbitrarily delayed to the prejudice of a contractor, and work should be viewed as accepted when it is finished even though a governmental body specifies a later date. (See Byson v. City of Los Angeles, 149 Cal.App.2d 469, 473 [ 308 P.2d 765]; 13 McQuillin on Municipal Corporations (3d ed. 1950) pp. 426-427.) There is sufficient evidence to support the trial court's finding that the work was to be regarded as completed on May 8, 1957.

[7] Another item in dispute is an award of $600 beyond the contract price with respect to the type of window installed by plaintiff. The plans and specifications prepared by defendant were inconsistent as to the type of window to be used, and plaintiff, with the approval of defendant's architect, made its bid on the basis of one of the alternatives. A.J. Glaser, who was defendant's representative on the job, insisted on the other alternative, although notified by plaintiff that an increase in cost would be involved. Plaintiff installed the type of window required by Glaser and, under the circumstances, it was proper to compensate plaintiff for the increased cost, which the court found on sufficient evidence amounted to $600.

The judgment is affirmed.

Traynor, J., Schauer, J., McComb, J., Peters, J., Tobriner, J., and Peek, J., concurred.