Ballycar Green Energy Ltd v An Coimisiun Pleanala and Anor

Smart Summary

Factual and Procedural Background

This was a contested application for leave to seek judicial review against the Second Respondent, a statutory aviation consultee. The Applicant challenged the First Respondent’s refusal of permission for a 12-turbine wind farm in County Clare and sought, among other relief, a declaration concerning the Second Respondent’s conduct during the planning process. [1][2][3][4][5]

The Applicant alleged that the Second Respondent’s objections were decisive and that it failed to engage adequately regarding aviation safety, including by withholding radar data and preventing engagement with relevant technical experts. [6][7][8][9]

The Second Respondent opposed leave, arguing that the claim was out of time under Order 84 of the Rules of the Superior Courts and that the pleadings disclosed no arguable or adequately formulated case against it. [10]

Legal Issues Presented

  1. Whether the Applicant’s claim against the Second Respondent was out of time because it should have been brought under Order 84 within three months of the Second Respondent’s final planning submission. [11][12][13][14]
  2. Whether the Applicant’s pleadings adequately identified the case against the Second Respondent. [15][16][17]

Arguments of the Parties

Applicant’s Arguments

  • The Second Respondent’s objection was critical to the refusal of planning permission. [8]
  • The Second Respondent failed to engage constructively, provide underlying radar data, or facilitate engagement with relevant third parties, preventing the Applicant from developing site-specific mitigation measures. [9]
  • The pleadings clearly identified the case against the Second Respondent, although the Applicant was willing to amend them if necessary. [18]
  • Section 50(2) of the Planning and Development Act 2000 governed the proceedings and did not prevent additional relief being sought against a third party involved in the planning process. [19][20][21]
  • The alleged procedural unfairness crystallised only when the final planning decision was made, so the Applicant was entitled to wait until that decision before commencing proceedings. [22][23]

Second Respondent’s Arguments

  • The relief sought was a direct and significant challenge to the Second Respondent’s conduct, not a challenge to a planning decision made by it. [24]
  • The Second Respondent was only a prescribed body or statutory consultee, made no planning determination, and could not be joined through certiorari; the declaration was therefore the only proposed basis for joining it. [25]
  • Section 50 applied only to the challenge against the First Respondent’s decision. Any claim against the Second Respondent was governed by Order 84. [26][27]
  • Time began to run no later than the Second Respondent’s final submission on 11 February 2026, and no application to extend time had been made. [12]
  • The pleadings were deficient because the sole core ground was directed to the First Respondent’s decision and did not expressly identify a ground against the Second Respondent. [15][28]

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
North East Pylon Pressure Campaign Ltd v. An Bord Pleanála [2018] IEHC 622 Time generally begins to run when a formal decision with irreversible effects is made, normally the final decision in the process. The Court relied on the principle that applicants should ordinarily await the final planning decision before challenging earlier procedural matters. [23][29][30][31]
Spencer Place Development Company Ltd v. Dublin City Council [2020] IECA 268 Section 50 should be interpreted to avoid fragmented or satellite litigation. The Court adopted the view that associated relief should ordinarily be heard together after the final substantive planning decision. [23][32][33][34]
Ballyboden Tidy Towns Group v. An Bord Pleanála [2024] IEHC 66 A challenge to an intermediate document forming part of the planning process may be brought within the period for challenging the final planning decision. The Court treated the case as supporting the Applicant’s entitlement to wait until the First Respondent’s final decision, despite the Second Respondent not being the decision-maker. [23][35][36][37][31]
Environmental Trust Ireland v. An Bord Pleanála [2022] IEHC 540 Core grounds must expressly identify the legal basis of a challenge, and particulars cannot introduce new grounds. The Court distinguished the pleading objection, finding that the Second Respondent understood the case made against it and that amendment was unnecessary. [15][16][17][38]

Court’s Reasoning and Analysis

The Court first considered the pleading objection. It found that the Applicant’s complaint was sufficiently clear: the Second Respondent was alleged to have refused constructive engagement, withheld technical information, and prevented contact with relevant experts. [16]

Although the summary of the core ground did not expressly mention the Second Respondent, the Court considered it a concise synopsis of the detailed grounds. The reliefs and the detailed pleading identified the case to be met, so the pleadings were not inadequate. The Second Respondent was nevertheless permitted to renew that complaint at the hearing. [17][38]

The Court then considered limitation. It accepted that the Second Respondent was not the planning decision-maker, but rejected the argument that proceedings necessarily had to be issued within three months of its last submission. That approach could require proceedings before the final planning decision and could produce multiple sets of proceedings concerning substantially the same matter. [13][14][39]

The Court considered that result illogical and disruptive to the planning list. It therefore applied the principles in Spencer Place Development Company Ltd, North East Pylon Pressure Campaign Ltd, and Ballyboden Tidy Towns Group, concluding that applicants should ordinarily await the final planning decision so that related relief can be addressed in one proceeding. [32][33][34][30][36][37][31]

The Court held that the relevance and consequences of the alleged conduct arose when the final planning decision was made. The Applicant was therefore entitled to wait until the First Respondent’s decision before commencing proceedings against the Second Respondent. [40][37]

Holding and Implications

Leave granted. The Applicant was given leave to issue judicial review proceedings against the Second Respondent. This was without prejudice to the Second Respondent’s right to argue at the hearing that the pleadings were deficient. [41][42]

The direct effect was that the Applicant’s claim against the Second Respondent could proceed notwithstanding the time-limit objection. The opinion does not identify any broader implication or state that a new precedent was established.

To access the original judgment, please Sign In or Subscribe.

Ballycar Green Energy Ltd v An Coimisiun Pleanala and Anor