Friends of the Irish Environment CLG v An Coimisiun Pleanala and Ors (Approved)

Smart Summary

Factual and Procedural Background

This judgment (delivered by Judge Humphreys) concerns a challenge by the Applicant to a decision dated 13 March 2025 of the planning decision-maker (the Respondent) granting planning permission for a 600 MW combined-cycle gas turbine power plant, a 120 MWh battery energy storage system and ancillary works at a coastal site on the estuary ("the Proposed Development"). The developer/notice party is identified in the record as Company A.

Key milestones in the administrative process included pre-application consultations in 2023-2024, an application lodged 19 April 2024, and a decision to grant permission on 13 March 2025. The Applicant filed judicial review proceedings (statement of grounds) on 7 May 2025 and was granted leave on 12 May 2025. The matter was listed for full hearing on 19 March 2026 and judgment was reserved and later circulated in draft to the parties.

Legal Issues Presented

  1. Whether the Respondent's decision was consistent, "in so far as practicable", with the measures identified in section 15(1) of the Climate Action and Low Carbon Development Act 2015 (as amended).
  2. Whether the Environmental Impact Assessment procedure and the Environmental Impact Assessment Report (EIAR) complied with Articles 1, 5 and Annex IV of the EIA Directive and whether public participation requirements were satisfied.
  3. Whether the Appropriate Assessment (AA) under Article 6 of the Habitats Directive was lawfully carried out (screening/Stage 2 assessment and in‑combination/cumulative effects assessment).
  4. Whether the Applicant failed, by not raising points in the administrative process, to place material before the decision-taker such that relief in judicial review is precluded or discretionary relief should be refused.
  5. Whether any other domestic or EU law grounds pleaded (including arguments invoking the EU Taxonomy/Delegated Regulations or carbon budgeting in the 2015 Act context) established a legal error requiring quashing of the decision.

Arguments of the Parties

Applicant's Arguments

  • The decision is inconsistent with s.15(1) of the 2015 Act (failure to assess consistency with climate objectives, Carbon Budgets and Sectoral Emissions Ceilings).
  • The EIAR miscalculated GHG emissions (used an incorrect factor), so the EIA was defective under Articles 5 and Annex IV of the EIA Directive and public participation was inadequate.
  • The Respondent's Appropriate Assessment screening and conclusions were unlawful because site-specific conservation objectives/measures were absent and cumulative impacts (including loss of Annex I habitats) were not properly assessed.
  • The decision relied on open-ended policy support for new gas generation contrary to the climate framework and may amount to unjustified approval of fossil-fuel infrastructure.

Respondent's Arguments

  • Many of the Applicant's complaints were not raised during the administrative process; judicial review is not ordinarily a forum to introduce new evidence or arguments that could have been raised earlier.
  • The decision-maker addressed climate policy and s.15(1) matters within the permissible spectrum of outcomes (Coolglass framework); conditions were imposed to limit operations in time and to require export for grid back-up only.
  • The EIAR contained sufficient methodological disclosure (forecasting methods, modelling, emission factors) and any commercially confidential material was redacted legitimately; the EIA and EIA conclusion were lawful and reasonable.
  • The Appropriate Assessment, Natura Impact Statement and Inspector's report addressed in‑combination effects; the Applicant has not discharged the onus to show reasonable scientific doubt from the materials before the decision-maker.

Company A / Developer's Arguments

  • The EIAR and supporting modelling adequately considered operational efficiency, lifecycle and upstream emissions and complied with the EIA Directive requirements.
  • The project was consistent with national policy (including the Climate Action Plan) and national needs for flexible generation; the Respondent lawfully adopted the Inspector's assessment and conclusions.
  • Reliance on the EU Taxonomy to challenge a planning decision is misplaced because that Regulation targets financial market disclosure rather than planning consent decisions.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Friends of the Irish Environment v. An Bord Pleanála & Anor. [2019] IEHC 80 Earlier litigation history relating to the project and referral questions to the CJEU on Habitats Directive issues. Referred to as part of litigation history showing extensive prior challenges.
Friends of the Irish Environment Ltd v An Bord Pleanála, C-254/19, EU:C:2020:680 CJEU conclusion that renewal of permission can require Appropriate Assessment (AA). Recorded as part of the project's litigation history supporting AA obligations.
Friends of the Irish Environment CLG v. Minister ... [2020] IEHC 383 Procedural ruling (refusal to refer list of Projects of Common Interest issue to CJEU). Noted in the procedural history of related proceedings.
Friends of the Irish Environment CLG v. Minister ... [2021] IEHC 177 Dismissal of certain challenges to Projects of Common Interest list. Noted in the litigation history.
Friends of the Irish Environment CLG v. Minister ... [2022] IECA 298 Court of Appeal dismissal of appeal concerning referral to CJEU. Noted in the litigation history.
Shannon LNG Limited v. An Bord Pleanála [2024] IEHC 555 High Court quashed the commission's refusal of permission for related project. Recorded as a prior decision relevant to the overall project history.
Reilly v. An Coimisiún Pleanála [2025] IEHC 659 Eight-fold path / criteria for obtaining relief by judicial review of planning decisions. Adopted and applied as the framework for assessing whether relief should be granted.
Foran v. An Coimisiún Pleanála & Glenveagh [2026] IEHC 23 Recent authority cited in relation to judicial review tests. Summarily cited as part of the legal landscape on reviewability.
Coolglass v. An Coimisiún Pleanála [2026] IESC 5 Interpretation of s.15(1) Climate Action and Low Carbon Development Act 2015: spectrum of possible outcomes and practicability qualification; enforceability by courts. Central to the court's assessment of the s.15 challenge and margin of evaluation available to the Respondent.
Sweeney v. Fahy [2014] IESC 50 Judicial review concerns legality not merits; limits on substituting judicial view for administrative decisions. Used to emphasise the court's restraining principle in review.
State (Keegan) v. Stardust Compensation Tribunal [1986] I.R. 642 Principle that judicial review is not an appeal on the merits. Reiterated as part of the standard legal framework for review.
Meadows v. Minister for Justice, Equality and Law Reform [2010] IESC 3 Judicial review focuses on legality; onus of proof principles. Referenced in support of onus and scope of review principles.
R (Cart) v. Upper Tribunal [2011] UKSC 28 Distinguishing merits from legal points in judicial review. Used to caution against treating factual or evaluative disputes as pure law.
O'Sullivan v. Health Service Executive [2023] IESC 11 Draft judgment procedure and limits on parties' engagement with drafts. Cited for procedural directions regarding circulation of draft judgment and confidentiality.
O'Sullivan v. Sea Fisheries Protection Authority [2017] IESC 75 On the risks of treating administrative procedure as a trial-like process. Quoted to discourage over-formalisation of administrative processes.
Attorney General v. Crosland (No. 2) [2021] UKSC 58 Why restriction on publication of draft judgments is in the interests of administration of justice. Cited in relation to confidentiality of draft judgments.
Harrington v. An Bord Pleanála [2014] IEHC 232 Assertion alone does not create scientific doubt for AA purposes. Applied to require evidential demonstration of scientific doubt in AA/EIA challenges.
An Taisce v. An Bord Pleanála (No. 2) [2021] IEHC 422 Onproof and evidential requirements in environmental assessment challenges. Referred to for the principle that applicants must establish inadequacy by admissible evidence.
Sweetman v. An Bord Pleanála (Sweetman XV) [2020] IEHC 39 Pleading requirements in EU law transposition and complex environmental arguments. Cited to emphasise precise pleading and particularity required for EU law challenges.
IL and Others v Land Nordrhein-Westfalen, C-535/18, EU:C:2020:391 Data in EIA must enable public to have an accurate impression of project impact. Referenced for the transparency standard in EIA but applied with the requirement that applicant bear burden of proof.
Case C-521/12 Briels Measures that compensate after the fact do not guarantee absence of adverse effects for AA purposes. Discussed in the context of whether compensation can substitute for avoidance/reduction of significant effects.
Sweetman v An Bord Pleanála, C-258/11, EU:C:2013:220 Risk of lasting harm or irreparable destruction to priority habitats cannot be authorised. Cited and distinguished on factual basis: court accepted that no lasting/irreparable risk was shown on the materials before the decision-maker.
Kennedy v. An Bord Pleanála [2024] IEHC 570 Pleading and evidential standards in environmental judicial review. Used to support the need for adequate evidential foundation for challenges.
Mulloy v. An Bord Pleanála [2024] IEHC 86 Reading administrative decisions in a valid way if reasonably open. Applied to interpret apparent errors in the Inspector's report as valid readings where possible.
Byrnes v. Dublin City Council [2017] IEHC 19 Discretion in judicial review; jurisdictional infirmity not automatically void ab initio. Referred to when considering discretion against certiorari.
Save Cork City Community Association CLG v. An Bord Pleanála [2022] IESC 52 Proportionality in granting certiorari; technical procedural error may be disproportionate to quash. Considered in exercise of discretion whether to quash on technical grounds.
Other authorities cited in the judgment Various principles on pleading, onus of proof, discretion, evaluation and reading decisions in context. Used throughout the analysis to articulate and apply settled judicial review principles.

Court's Reasoning and Analysis

The court applied established judicial review principles (summarised as an eight-fold path). Central to the analysis were: (i) the requirement that challenges be assessed through the lens of the material that was before the decision-maker at the time of decision; (ii) the onus of proof resting on the Applicant to demonstrate legal error or to establish reasonable scientific doubt in AA/EIA contexts; (iii) the distinction between legality and merits — the court will not substitute its view for the expert evaluative judgments of the decision‑taker; and (iv) the discretionary nature of certiorari.

Applying those principles, the court emphasised the Supreme Court's guidance (Coolglass) that s.15(1) imposes a legally enforceable consistency duty but one that operates as a spectrum of permissible outcomes qualified by "in so far as practicable." The court held that the Respondent had addressed climate policy and s.15 matters and that the decision fell within the spectrum of permissible outcomes, particularly given the national policy context and the conditions imposed (time‑limited operation and grid-backup conditions).

The court further concluded that many of the Applicant's core complaints had not been raised during the administrative process. Absent autonomous obligations plainly engaged and in the absence of evidential material before the decision-maker creating reasonable scientific doubt, the court would not admit or decide de novo merits-based disagreements introduced for the first time in judicial review. The Applicant had not discharged the evidential onus to show that the EIAR/EIA or the AA were defective such that the Respondent's reasoned conclusions fell outside the margin of evaluation.

On specific points: alleged miscalculation of GHG emissions, alleged misuse of sectoral thresholds/Carbon Budgets, and alleged improper reliance on policy support for gas generation were treated as either merits disputes or matters that the Applicant failed to raise before the Respondent; the court found no demonstrable legal error on the face of the materials. Regarding habitat loss, the court accepted the Respondent's and Inspector's reasons that the limited, likely transient loss did not create a risk of lasting or irreparable harm to the SAC on the evidence before the decision-maker.

The court also observed that where a valid reading of the decision is available, a decision should be read as valid rather than parsed into invalidity by semantic quibbles. Finally, even if errors existed in points not raised in the process, the court indicated it would likely exercise its discretion against ordering certiorari in the circumstances described.

Holding and Implications

HOLDING: The proceedings are DISMISSED.

Implications: The direct effect is that the Respondent's decision granting permission stands subject to the conditions imposed (including time-limited operation to 31 December 2050 and restrictions requiring export to the national grid as back-up). The court found no legal error warranting quashing the decision on the pleaded grounds and noted that no new precedent was established beyond the application of existing principles (including the Coolglass interpretation of s.15(1), the established onus and evidential rules in environmental judicial review, and the discretionary approach to certiorari where applicants failed to raise issues in the administrative process).

To access the original judgment, please Sign In or Subscribe.

Friends of the Irish Environment CLG v An Coimisiun Pleanala and Ors (Approved)

Contains public sector information licensed under the Open Justice Licence v1.0.