| The Griffon [2013] EWCA Civ 1567 |
Saleform as the commonly used standard form for second-hand tonnage; discussion of Clause 13 and its practical effect. |
Used to show the Saleform's commercial context and to support the view that clause-based cancellation and compensation rights were intended as valuable contractual remedies in trade practice. |
| Coventry City Council v Vassell [2011] EWHC 1542 |
Illustration that the word "fail" is ambiguous and may or may not import fault. |
Cited by the Court when discussing the possible meanings of "fail" in Clause 14 and related clauses. |
| Classic Maritime Inc v Limbungan Makmur Sdn Bhd [2019] EWCA Civ 1102 |
Principle that headings are admissible in contractual construction but are not conclusive. |
Relied on when considering the significance of the heading "Sellers' default" to the meaning of Clause 14. |
| ABC Electrification Ltd v National Rail Infrastructure Ltd [2020] EWCA Civ 1645 |
Authority noting that "default" can naturally be understood as failure to fulfil a legal requirement or obligation. |
Supported the conclusion that the heading "Sellers' default" carries a pejorative, obligation-related meaning relevant to Clause 14. |
| The Democritos [1976] 2 Ll Rep 149 |
Establishes that a cancelling clause can import an implied obligation to use reasonable diligence to deliver by the cancelling date (not an absolute obligation). |
Adopted as a close analogy; the Court extracted from it the implied due-diligence obligation relevant to Clause 5 and Clause 14(B). |
| Smith v Dart & Son (1884) 14 QBD 105; Nelson & Sons v The Dundee East Coast Shipping Co Ltd (1907) 44 SLR 661; United States Gypsum Transport Co v Dampskibs Aktiselskapet Karmoy (1930) 48 Fed Rep (2nd) 376 |
Historical authorities supporting the idea that reasonable diligence suffices (as opposed to absolute obligation) for delivery by a cancelling date. |
Referenced within the discussion of The Democritos to show the lineage of the implied-diligence principle. |
| Sharp Corp Ltd v Viterra BV [2024] UKSC 14 |
Guidance that an appeal under s.69 proceeds on the basis of the findings of fact in the award. |
Cited to confirm that factual findings of the Tribunal are binding for the s.69 appeal and to explain the scope of legal review. |
| Bunge Corporation v Tradax Export SA [1981] 1 WLR 711 |
Authority on consequences of time clauses and delivery timing (referred to in the Judge's treatment of time obligations). |
Mentioned as an argument explored below but not determinative in the Court's reasoning on Clause 14. |
| The Golden Victory [2007] UKHL 12 |
Principle that damages assessment takes account of what has actually happened by the time of assessment (compensatory principle). |
Invoked when discussing how damages should reflect events that occurred after breach, and relevance to assessment if Buyers keep contract alive or cancel. |
| Financings Ltd v Baldock [1963] 2 QB 104 |
The principle that exercising a contractual right of termination does not, without more (i.e. repudiatory breach), give rise to loss of bargain damages. |
Identified as the "Financings principle" and discussed at length; the Court accepted its existence but held it did not resolve the construction of Clause 14(B) where the clause itself confers a right to compensation. |
| Phones 4U Ltd (in administration) v EE Ltd [2018] EWHC 49 |
Example of the Financings principle applied in commercial contracts. |
Referenced as authority where loss of bargain was not recoverable when termination arose from contractual right rather than accepted repudiation. |
| The Kos [2012] UKSC 17 |
Affirmation of the principle that termination for non-repudiatory default does not automatically produce loss of bargain damages. |
Referred to in the discussion of the Financings principle and the distinction between contractual termination and termination for repudiatory breach. |
| The Spar Capella [2015] EWHC 718; [2016] EWCA Civ 982 |
Discussion of whether prompt payment clauses are conditions and whether the option to cancel confers damages absent repudiation. |
Relied upon by the Respondent; the Court held that Clause 14(B) contains clear words granting a right to compensation and therefore the comparison did not determine the issue before the Court. |
| Novasen SA v Alimenta SA [2013] EWHC 345 |
Statement that clear words are required to confer novel contractual remedies where no remedy exists at law; caution when standard-form trade clauses confer recovery where no loss has been suffered. |
Considered but distinguished: Clause 14(B) does not seek to grant recovery where no loss exists, and the Court considered the clause as conferring an express right to appropriate compensation. |
| Bunge SA v Nidera BV [2015] UKSC 43 |
Observation that a damages clause should not operate arbitrarily; in the absence of clear words it should produce results approximating true loss. |
Applied to caution against arbitrary readings but did not override the plain wording of Clause 14(B) as a clause granting compensation for loss caused by proven negligence. |
| The Rewa [2012] EWCA Civ 153 |
Guidance cautioning excessive reliance on historical drafting archaeology when interpreting standard clauses. |
Quoted to note that previous forms may be reviewed but that the Court should not over-elaborate interpretation through excessive historical excavation; nevertheless the Court considered earlier Saleform decisions relevant. |
| Stocznia Gdynia SA v Gearbulk Holdings Ltd [2009] EWCA Civ 75 |
A case where the court accepted that termination exercised under a contractual right could be viewed as having been effectively caused by the other party's breach. |
Cited for the proposition that termination chosen by an innocent party in response to breach can properly be regarded as resulting from the other's breach for causation purposes. |
| The Solholt [1981] 2 Ll Rep 574; [1983] 1 Ll Rep 605 |
Saleform (earlier revision) case where a court allowed buyers' claim for loss of bargain following sellers' failure to deliver by the cancelling date. |
Treated as particularly relevant precedent for the proposition that Clause 14-type provisions can entitle a cancelling buyer to loss of bargain damages; discussed as supportive though on earlier form wording. |
| The Al Tawfiq [1984] 2 Ll Rep 598 |
Another Saleform decision consistent with The Solholt on recovery of loss of the bargain where sellers failed to deliver for reasons for which they were responsible. |
Referred to as supporting the line of authority that purchasers can claim loss of bargain under Saleform-style default provisions. |
| Parbulk v Kristen Marine [2010] EWHC 900 |
Reference to wording equivalent to Clause 14(B) and the proposition that proving negligence can allow a wider measure of damages (eg loss of profit). |
Cited as an instance where the court indicated that proof of negligence by sellers opened the door to a wider measure of damages under a Saleform clause. |
| The Ile aux Moines [1974] 1 Ll Rep 263; [1974] 2 Ll Rep 502 |
Instances where damages for loss of bargain were assumed recoverable for failure to deliver a ship. |
Noted but the Court recorded limited assistance because the contract terms were not set out in the reports. |
| Beaufort Developments (NI) Ltd v Gilbert-Ash (NI) Ltd [1999] 1 AC 266 |
Authority on the value of looking at earlier judicial interpretation of standard forms in understanding drafting evolution. |
Quoted as supporting the argument that prior judicial interpretation of earlier Saleform iterations is relevant when construing revised wording. |
| Samarenko v Dawn Hill House Ltd [2013] Ch 36 |
Referenced in connection with whether particular defaults amount to repudiatory breaches. |
Mentioned as background to The Griffon discussion of Clause 13 and repudiation; not applied to overturn the Court's primary construction of Clause 14(B). |