ENGENDA GROUP LTD AGAINST PETROINEOS MANUFACTURING SCOTLAND LTD
Smart Summary
Factual and Procedural Background
The dispute arises from a contract entered into in November 2021 between Company A (Petitioner) and Company B (Respondent) relating to turnaround works at Company B's plant in The City. The contract was based on a standard engineering form (NEC 3) with amendments and included provisions for adjudication of disputes. Following contractual performance issues, a series of adjudications took place. The third adjudication was initiated by Company B in August 2022, seeking declarators and payment of damages exceeding £1,134,000 for alleged breaches by Company A, including failure to complete works by the contractual completion date of 17 November 2021. The adjudicator found breaches but declined to award damages due to insufficient proof. Company A then demanded payment of withheld sums, which Company B resisted by serving a pay less notice. This led to a fourth adjudication addressing Company A's entitlement to payment, where the adjudicator found Company B entitled to set off damages for late completion exceeding the disputed sum, effectively defeating Company A's claim for payment.
Legal Issues Presented
- Whether the adjudicator in the fourth adjudication exceeded his jurisdiction by permitting Company B to plead a right to set off unliquidated damages previously found unproven in the third adjudication.
- Whether the dispute determined in the third adjudication was the same or substantially the same as the dispute in the fourth adjudication.
- The proper application of legal principles governing successive adjudications and the extent to which new evidence or arguments may be considered in subsequent adjudications.
Arguments of the Parties
Petitioner’s Arguments
- The adjudicator lacked jurisdiction in Adjudication 4 to consider the claim for unliquidated damages because that issue had already been decided in Adjudication 3.
- Company B’s claim for unliquidated damages was not framed differently in Adjudication 4 but was essentially an attempt to re-litigate the same issue with new evidence.
- The principle of finality in adjudication bars re-adjudication of the same or substantially the same dispute.
- The adjudicator’s conclusion in Adjudication 4 that the claim was different was clearly wrong given references in Adjudication 3 to damages for failure to complete by the completion date.
- New expert evidence in Adjudication 4 does not create a different dispute and cannot justify re-adjudication.
Respondent’s Arguments
- The adjudicator was correct to find that the claim in Adjudication 4 was sufficiently different from that in Adjudication 3 because it was based on a different contractual underpinning and supported by new expert evidence.
- The failure to complete claim in Adjudication 3 was not properly framed or proven as a claim for unliquidated damages, thus leaving room for reconsideration.
- Authorities such as Hitachi Zosen Inova AG v John Sisk & Son Ltd support the possibility of subsequent adjudications where the earlier decision did not finally determine the issue due to lack of evidence.
- The adjudicator’s view on jurisdiction in Adjudication 4 should be given significant weight and only overturned if clearly wrong.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Quietfield Limited v Vascroft Construction Limited [2006] EWHC 174 (TCC) and [2006] EWCA Civ 1737 |
Limits on re-adjudicating the same dispute; new evidence does not necessarily create a new dispute. |
Supported the proposition that new evidence alone does not justify re-adjudication of the same or substantially the same dispute. |
| Hitachi Zosen Inova AG v John Sisk & Son Ltd [2019] EWHC 495 (TCC) |
Distinction between a decision not to value due to lack of evidence and a decision rejecting a claim; allowed subsequent adjudication where valuation was left open. |
Distinguished from the present case as the earlier adjudicator expressly limited his decision, leaving open valuation to a later adjudication. |
| Lewisham Homes Limited v Breyer Group plc [2021] EWHC 1290 |
Set out principles for determining whether disputes in successive adjudications are the same or substantially the same. |
Applied the ten principles from this case to assess the similarity of disputes in Adjudications 3 and 4. |
| Carillion Construction Limited v Smith [2011] EWHC 2910 (TCC) |
Failure to prove loss in an earlier adjudication generally bars re-adjudication of the same issue. |
Supported the conclusion that the adjudicator in Adjudication 4 lacked jurisdiction to reconsider the damages claim previously rejected. |
| Sudlows Limited v Global Switch Estates 1 Limited [2023] EWCA Civ 813 |
Affirmed the principles relating to finality and the fact and degree test in successive adjudications. |
Emphasized that new or more detailed evidence does not necessarily create a new dispute and supported the court’s approach to jurisdiction. |
Court's Reasoning and Analysis
The court began by examining the adjudicator’s findings in the third adjudication, noting that the adjudicator had clearly addressed the respondent’s claim for unliquidated damages based on failure to complete by the contractual date. The adjudicator found Company A liable for breach but rejected the damages claim due to insufficient expert evidence quantifying loss. The court rejected the adjudicator’s later assertion in the fourth adjudication that the claim before him was different, emphasizing that the dispute in the fourth adjudication was substantially the same as that in the third.
The court applied established legal principles governing successive adjudications, including the binding nature of adjudicator decisions until final resolution and the prohibition on re-adjudicating the same or substantially the same dispute. It relied on the ten principles synthesized in Lewisham Homes Ltd v Breyer Group plc, particularly the focus on what the first adjudicator actually decided and the fact and degree test for similarity of disputes.
The court distinguished the present case from Hitachi Zosen Inova AG v John Sisk & Son Ltd, noting that in Hitachi the earlier adjudicator expressly limited his decision and left open the possibility of valuation in a later adjudication. In contrast, here the adjudicator in Adjudication 3 made a definitive finding on liability and rejected the damages claim on evidential grounds, without expressly reserving the issue.
The court further held that the existence of new expert evidence in Adjudication 4 did not create a different dispute and was insufficient to confer jurisdiction on the adjudicator to reconsider the same claim. This aligns with authorities emphasizing that new evidence alone does not justify re-adjudication.
Accordingly, the court concluded that the adjudicator in Adjudication 4 was "clearly wrong" in his jurisdictional analysis and erred by entertaining a claim that had already been determined.
Holding and Implications
The court sustained the petitioner's plea-in-law and granted decree reducing the decision issued in the fourth adjudication.
The direct effect of this decision is that the adjudicator's decision in the fourth adjudication is set aside as having been made without jurisdiction to reconsider the damages claim previously determined. The respondent cannot re-raise the claim for unliquidated damages for late completion in adjudication but must instead pursue such claims through litigation or arbitration. The court made no order on expenses at this time. No new precedent was established beyond the application of established principles to the facts of this case.