Factual and Procedural Background
The Applicant sought judicial review challenging a foreshore licence granted by the Minister of State under the Foreshore Act 1933. The licence authorized certain survey operations related to a proposed wind farm array. The licence was granted in January 2021 and published in February 2021. The judicial review proceedings were instituted in April 2021, seeking to quash the Minister of State's decision of 28 January 2021. Leave to proceed was granted unopposed in June 2021. No application for a stay on the implementation of the foreshore licence was made, despite the developer opposing any such stay and providing updates on the progress of activities. The substantive judicial review hearing was initially scheduled for March 2024 but was rescheduled to July 2024. In February 2024, the respondents raised for the first time that the proceedings were moot because the authorized activities had been completed prior to the hearing.
Legal Issues Presented
- Whether a legal challenge to the validity of a development consent becomes moot when the applicant fails to secure a stay and the authorized works have been completed before the judicial review hearing.
Arguments of the Parties
Respondents' Arguments
- The proceedings are moot because the activities authorized by the foreshore licence have been carried out and completed.
- The developer has completed all intended activities and has undertaken not to carry out further surveys, intending to surrender the licence without retrospective effect.
- The limited and temporary nature of the authorized activities supports the argument that no effective remedy can be provided by the court.
- The principle of mootness applies broadly, including beyond planning law, as illustrated by examples such as completed criminal prosecutions.
Applicant's Arguments
- The proceedings are not moot because the High Court can still provide an effective remedy despite completion of the activities.
- The court is obliged under EU law to eliminate unlawful consequences of breaches of the Habitats Directive and EIA Directive, including by ordering remedial assessments or remediation works even after project completion.
- The absence of a stay does not render the judicial review moot; developers proceed at their own risk.
- The applicant seeks a novel additional relief to deny the developer the benefit of survey data obtained under the impugned licence, though this relief was not pleaded expressly.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Commission v. Ireland (Derrybrien Wind Farm), Case C-261/18, EU:C:2019:955 |
National courts must eliminate unlawful consequences of breaches of the EIA Directive, including remedial measures after project completion. |
Confirmed the court’s obligation to order remedial assessments or remediation even if works are completed. |
| AquaPri, Case C-278/21, EU:C:2022:864 |
Similar remedial obligations apply under the Habitats Directive. |
Supported the principle that remedial measures remain available post-completion. |
| Commission v. Ireland, Case C-215/06, EU:C:2008:380 |
Domestic law permitting regularisation of unlawful operations must not circumvent EU environmental law. |
Emphasized that remedial procedures must not encourage circumvention of EU law. |
| North Wall Property Holding Company Ltd v. Dublin Docklands Development Authority [2009] IEHC 11 |
Distinction between judicial review of development consent and separate enforcement proceedings regarding works carried out. |
Illustrated that legal challenges can proceed despite completion of works, with enforcement matters dealt with separately. |
| Odum v. Minister for Justice and Equality [2023] IESC 3 |
Traditional doctrine of mootness requires a live controversy with full adversarial context. |
Clarified the rationale for mootness and distinguished it from inability to provide effective remedy. |
| Seery v. An Bord Pleanála [2001] IEHC 13 |
Proceeding with works subject to judicial review is done at developer’s risk. |
Supported the proposition that failure to obtain stay does not validate works. |
| Toole v. Minister for Housing, Local Government and Heritage [2023] IEHC 317 |
Completion of works may render legal challenge moot but must be assessed in context of interlocutory injunction principles. |
Distinguished from present case, where detailed mootness issue was determined. |
| Okunade v. Minister for Justice Equality and Law Reform [2012] IESC 49 |
Principles governing interlocutory injunctions. |
Referenced in discussion of stay applications and effective remedy considerations. |
| Balz v. An Bord Pleanála [2020] IESC 22 |
Interaction between judicial review and enforcement proceedings, including stays pending substitute consent. |
Illustrated practical sequencing of judicial review and enforcement actions. |
| Grafton Group v. An Bord Pleanála [2023] IEHC 725 |
Requirement to plead declaratory relief in terms. |
Used to support submissions on pleading obligations for novel relief sought. |
| Henderson v. Henderson |
Rule against relitigation of matters that could have been raised previously. |
Referenced regarding preclusion of raising unpleaded issues in subsequent proceedings. |
Court's Reasoning and Analysis
The court identified the central issue as whether judicial review proceedings challenging a development consent become moot if the applicant fails to obtain a stay and the authorized works are completed before the hearing. The respondents argued that no effective remedy could be provided once the works were done, justifying mootness.
The court distinguished this argument from the traditional mootness doctrine, which requires a live controversy and full adversarial context. Here, the controversy remained live as to the validity of the consent and legal consequences of the works carried out.
Relying on EU law principles and CJEU jurisprudence, the court emphasized that national courts must take all necessary measures to eliminate unlawful consequences of breaches of the Habitats and EIA Directives, even post-completion of works. This includes ordering remedial assessments or remediation works.
The court rejected the notion that failure to obtain a stay renders the judicial review moot, emphasizing that developers proceed at their own risk. The timing of the hearing relative to completion of works does not determine the outcome. The rule of law mandates that the merits be decided and remedies considered.
The court noted the temporary and limited nature of the activities authorized but found this insufficient to negate the possibility of effective remedies. The question of environmental impact and consequences must be addressed at the substantive hearing, not on a strike-out motion.
The court also considered a novel relief sought by the applicant to deny the developer the benefit of survey data obtained under the licence. This relief was not pleaded and therefore could not be granted without an amendment to the pleadings.
Finally, the court discussed the procedural context of judicial review and enforcement proceedings, noting that remedies concerning works carried out are often pursued in enforcement proceedings following a successful judicial review.
Holding and Implications
The court DENIED the Minister's motion to strike out the judicial review proceedings as moot.
The court held that the completion of the activities authorized by the foreshore licence does not render the judicial review moot because the High Court retains the ability and obligation to provide effective remedies to eliminate unlawful consequences of breaches of EU environmental law, including remedial assessments or remediation works.
The court granted the applicant liberty to apply for leave to amend the statement of grounds to plead the novel relief concerning the use of survey data. Directions were given for any such application to be filed and heard prior to the substantive hearing.
No new precedent was set; the decision reaffirmed established principles that judicial review proceedings remain live despite completion of works and that remedies under EU environmental law extend beyond project completion.