Contains public sector information licensed under the Open Justice Licence v1.0.
Thomson v An Bord Pleanala (Approved)
Factual and Procedural Background
On 25th June 2020, a developer applied to the local county council for permission to erect a telecommunications mast in a village. The council validated the application and received objections from the Applicants. A senior planner reported that the proposed mast would be visually obtrusive due to its location near dwellings and amenities, recommending refusal in line with ministerial guidelines which advise against masts in towns or villages except as a last resort.
The council refused permission on 26th November 2020. The developer appealed, arguing coverage needs and willingness to share the mast with other operators. The council and Applicants made submissions opposing the appeal. The planning board's inspector recommended refusal, but the board granted permission on 17th June 2021.
Following the decision, the Applicants considered challenging the board's decision but did not initially do so due to cost risks and other concerns. The statutory 8-week period to challenge the decision expired in August 2021. Construction began but was alleged by the Applicants to be non-compliant with the permission, leading to complaints and applications for declarations. Enforcement notices and warning letters were issued to the developer.
The Applicants investigated other similar board decisions involving the same telecommunications company and identified a pattern of permissions granted despite council refusals. They engaged with political representatives and media, uncovering concerns about the impartiality of a key board member involved in many such decisions. An internal board review was conducted but its report was not published following legal advice. The former deputy chairperson resigned amidst related allegations and prosecution.
Proceedings challenging the board’s decision were issued on 28th November 2022. The Applicants sought various reliefs including quashing the permission, declarations, investigation directions concerning file allocation and board member conduct, extension of time to apply for judicial review, and injunctions related to the mast’s re-erection.
Legal Issues Presented
- Whether the Applicants are entitled to an extension of time to seek judicial review of the board’s decision granting permission for the telecommunications mast.
- Whether the board’s decision was invalid due to bias or appearance of bias related to non-random allocation of files and excessive granting rates.
- Whether the board members failed to comply with the Code of Conduct under the relevant planning legislation.
- Whether a board member was disqualified from office due to a composition or arrangement with creditors, affecting the validity of the decision.
- Whether the board erred in law in its interpretation of the Development Plan and Ministerial Guidelines, including adequacy of reasons for departure from policy.
- Whether a stay or injunction should be granted preventing re-erection of the mast pending determination of proceedings.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Adam v. Minister for Justice [2001] IESC 38 | Principles governing ex parte orders and their reconsideration on an inter partes basis. | The court acknowledged the ex parte nature of the initial extension of time order and the need to reconsider it inter partes. |
| SC SYM Fotovoltaic Energy SRL v. Mayo County Council (No 1) [2018] IEHC 20 | Test for extension of time under planning legislation; distinction between initial period and total period. | The court applied the two-limb test for extension of time, emphasizing that failure to apply within the initial 8 weeks must be outside applicant's control. |
| Sweetman v. An Bord Pleanála [2017] IEHC 46 | Consideration of good and sufficient reason for extension of time. | Supported a holistic approach to assessing extension applications. |
| Reidy v. An Bord Pleanála [2020] IEHC 423 | Extension of time principles and weighing of unexplained periods. | Confirmed that not every moment must be accounted for in extension applications. |
| Keegan v. Garda Síochána Ombudsman Commission [2012] IESC 29 | Flexibility in allowing amendments to proceedings brought in time. | Referenced to distinguish amendments from late initiation of proceedings. |
| Arthropharm (Europe) Ltd v. The Health Products Regulatory Authority [2022] IECA 109 | Strictness of time limits for initiating proceedings in commercial context. | The court applied a reasonably strict approach to the initial time limit. |
| Talbotgrange Homes Ltd. v. Laois County Council [2009] IEHC 535 | Applicants are not entitled to delay proceedings awaiting all evidence. | Held that waiting for additional evidence is not a basis for extension. |
| Irish Skydiving Club Ltd. v. An Bord Pleanála [2016] IEHC 448 | Time limits run from decision date but allow for knowledge of problem. | Applied the principle that time runs from when applicant knew or ought to have known of the issue. |
| Heaney v. An Bord Pleanála [2022] IECA 123 | Extension of time test and holistic assessment of circumstances. | Informed the court's holistic approach to the extension application. |
| McBain v McDonald [1991] 1 I.R. 284 | Limitation principles and access to evidence within limitation period. | Analogized to planning context that delay in bringing proceedings despite available evidence is not excused. |
| Krikke v Barranafaddock Sustainable Electricity Limited [2022] IESC 41 | Importance of time limits notwithstanding errors on the face of decisions. | Confirmed that even clear errors do not obviate need for timely challenge. |
| In re Planning and Development Bill 1999 [2000] IESC 20 | Legislative authority for time limits and extension criteria in planning law. | Confirmed validity of statutory time limits and criteria for extension. |
Court's Reasoning and Analysis
The court applied the statutory test for extension of time under section 50(8) of the Planning and Development Act 2000, requiring (a) good and sufficient reason and (b) that circumstances causing delay were outside the applicant’s control. The court found that certain grounds (notably the alleged errors in interpretation of the Development Plan and Ministerial Guidelines) were evident at the time of the decision and thus not outside the Applicants’ control, disqualifying those grounds from extension.
For grounds relating to alleged bias, failure to comply with the Code of Conduct, and the disqualification of a board member due to creditor arrangements, the court accepted that these matters were not initially obvious and thus met the "outside control" limb. However, the Applicants became aware of relevant information by mid-2022, including statistical anomalies, board minutes, and media reports. The court held that the Applicants should have initiated proceedings within eight weeks of acquiring sufficient information, but failed to do so.
The court rejected the Applicants’ strategy of waiting for ongoing investigations and inquiries before commencing judicial review, emphasizing that waiting for admissions or further evidence does not justify delay. The court underscored the importance of legal certainty and fairness to third parties, particularly commercial interests, in upholding strict time limits.
In balancing the public interest in probity and transparency against the need for certainty, the court concluded that the Applicants’ delay was unjustified. Although the issues raised were important and meritorious, the court’s role is limited to deciding properly pleaded issues within procedural rules and time limits.
Holding and Implications
The court SET ASIDE the order granting an extension of time and leave to apply for judicial review, and REFUSED the application for extension of time and leave to apply for judicial review.
Consequently, the developer (Company A) was released from its undertaking not to proceed with the development, allowing re-erection of the telecommunications mast subject to compliance with planning permission. No new precedent was established; the decision reinforces the strict application of statutory time limits for judicial review in planning cases and the necessity for applicants to act promptly once sufficient information is available.
Please subscribe to download the judgment.
Comments