Factual and Procedural Background
The dispute arises from a contract between Company A (the contractor) and Company B (the employer) for construction works at a primary school in The City. The contract incorporated the Standard Building Contract With Quantities for use in Scotland (2011 Edition). The contract provided for monthly interim payments via Interim Certificates issued by the employer's architect, or, if none were issued, by an Interim Payment Notice issued by the contractor. The final payment was due upon issuance of a Final Certificate by the architect, which stated the Contract Sum and the balance due after accounting for interim payments.
On 10 August 2017, Company A issued an Interim Payment Notice for a sum of approximately £949,556, which the employer did not challenge by issuing a Pay Less Notice. Partial payments were made subsequently, but the full amount was not paid. On 17 July 2019, a Final Certificate was issued adjusting the Contract Sum to approximately £3.34 million and showing a small balance due to the contractor, which was paid.
Company A challenged the Final Certificate within the contractual 60-day period by raising court proceedings, seeking a higher contract sum. Separately, in March 2020, Company A referred an adjudication regarding the unpaid balance under the 2017 Interim Payment Notice, seeking a sum of approximately £427,579 plus interest. The employer contended that the Interim Payment Notice was invalid and that the Final Certificate was conclusive evidence of amounts due.
The Adjudicator ruled in favor of Company A, finding the Interim Payment Notice valid and the Final Certificate not conclusive due to ongoing court proceedings challenging it. The employer did not pay the adjudicated sum, prompting Company A to bring enforcement proceedings. The employer counterclaimed, challenging the adjudicator's decision on the basis that the Final Certificate was conclusive and that the Interim Payment Notice was invalid. The commercial judge enforced the adjudicator's award but dismissed the employer's counterclaim for being raised out of time.
The employer appealed (reclaiming motion), seeking to have the counterclaim upheld and the adjudicator's award set aside. The cross appeal by Company A related to the dismissal of some of its submissions.
Legal Issues Presented
- Whether a Final Certificate under the contract is conclusive evidence of the sums due to a contractor in adjudication proceedings concerning an interim payment.
- Whether an adjudicator's decision that the Final Certificate is not conclusive can be reversed when the adjudication is commenced outside the contractually prescribed 60-day challenge period.
- The interplay between the contractual time limits for challenging the Final Certificate and the adjudication regime, particularly clause 1.9 of the contract.
- Whether the Interim Payment Notice issued by the contractor was valid despite alleged errors in the relevant due date.
- The effect of the employer's failure to pay sums due under an Interim Payment Notice without issuing a Pay Less Notice.
- Whether the employer's counterclaim challenging the adjudicator's decision was valid despite being raised more than 28 days after the adjudicator's decision.
Arguments of the Parties
Employer's Arguments
- The Final Certificate is conclusive evidence of the sums due under the contract once the 60-day challenge period expires, and since the adjudication was commenced after this period, the Final Certificate should have precluded the adjudicator's award.
- The Interim Payment Notice was invalid because it specified an incorrect relevant due date.
- The adjudicator erred in not making a nil award and in allowing the adjudication to proceed outside the contractual time limits.
- The employer's counterclaim challenging the adjudicator's decision was valid and should be upheld despite being raised late, or the court should construe clause 1.9.4 purposively to allow it.
- The employer is entitled to recover any overpayments made pursuant to the adjudicator's award, including interest.
Contractor's Arguments
- The adjudication concerned enforcement of a valid Interim Payment Notice and was not a challenge to the Final Certificate; thus, clause 1.9 time limits do not apply.
- The Final Certificate's conclusive effect was removed by the timeous court challenge within 60 days, which also affected the adjudication.
- The adjudicator's decision was correct to distinguish the adjudication dispute from the Final Certificate dispute.
- The employer's counterclaim was raised out of time under clause 1.9.4 and should be dismissed.
- Minor errors in the Interim Payment Notice should not invalidate it, especially in the absence of a Pay Less Notice.
- The additional interest accrued due to the employer's delay in payment should be retained by the contractor as it is not part of the substantive dispute.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Marc Gilbard's 2009 Settlement Trustees v OD Developments and Projects [2015] EWHC 70 (TCC) |
Final Certificates are conclusive unless challenged within prescribed contractual periods; late proceedings cannot challenge the Final Certificate even if raising the same matters. |
The court accepted the principle that the Final Certificate is conclusive except in timeous proceedings and applied it to find that the adjudication was out of time and thus the Final Certificate should have been conclusive. |
| Jerram Falkus Construction Ltd v Fenice Investments Inc (No. 4) [2011] 138 Con LR 21 |
Adjudicator's decision is final and binding unless challenged within 28 days under the contract. |
The court held that the employer’s counterclaim challenging the adjudicator’s decision was out of time and therefore invalid under clause 1.9.4. |
| Scottish Equitable plc v Miller Construction 2002 SCLR 10 |
Sequential Interim Certificates are re-valuations and not conclusive; each supersedes the previous. |
The court clarified that while Interim Certificates supersede prior ones for valuation purposes, sums certified as due in earlier certificates remain payable and are not superseded for payment purposes. |
| Michael J Lonsdale (Electrical) v Bresco Electrical Services [2020] Bus LR 1140 |
The adjudication regime follows "pay now, argue later" policy to promote cash flow and prompt dispute resolution. |
The court confirmed that the adjudicator's award is binding unless challenged within the contractual time limits, reinforcing the finality of adjudications. |
| Hutton Construction v Wilson Properties (London) [2018] 1 All ER (Comm) 524 |
Defences to enforcement of adjudicator's decisions are limited; courts rarely interfere unless clear error or procedural defects exist. |
The court cited this to emphasize the narrow scope for challenging adjudicator awards in enforcement proceedings. |
| Aspect Contracts (Asbestos) Ltd v Higgins Construction plc [2015] 1 WLR 2961 |
An employer can recover overpayments caused by an adjudicator's decision, including interest. |
The court considered this authority when discussing the repayment of interest in the event of overpayment following adjudication. |
| Grove Developments Ltd v S&T (UK) Ltd [2018] EWCA Civ 2448; [2019] BLR 1 |
Statutory payment regime provides enforceable interim payments; overpayments can be corrected later by adjudication or other proceedings. |
The court referenced this case to illustrate the policy of ensuring cash flow through interim payments, subject to later adjustment. |
| J&B Hopkins Ltd v Trant Engineering Ltd [2020] EWHC 1305 (TCC) |
Adjudicator’s decision on interim payment notices can be enforced despite subsequent interim payment cycles. |
The court used this to support the position that adjudications on interim payments are enforceable and not superseded by later certificates. |
| Harding (t/a M J Harding Contractors) v Paice and Another [2016] 1 WLR 4068 |
Distinguishes between interim and final payments; final certificate states the amount properly due. |
The court endorsed this distinction to explain the differing legal effects of interim certificates and final certificates. |
| Rupert Morgan Building Services Ltd v Jervis [2003] EWCA Civ 1563 |
Section 111 of the 1996 Act addresses cash flow during works, not making certificates conclusive. |
The court cited this to clarify that statutory payment provisions are about cash flow, not finality of certificates. |
| Castle Inns (Stirling) Ltd (t/a Castle Leisure Group) v Clark Contracts Ltd 2006 SCLR 663 |
Final certificate opens up all previous certificates and represents the definitive valuation of contract works. |
The court referred to this to support that final certificates deal with the substantive merits of payment disputes. |
Court's Reasoning and Analysis
The court analysed the contractual payment regime distinguishing between interim payments, Interim Payment Notices, Interim Certificates, and the Final Certificate. It noted that interim payments promote cash flow and are typically made monthly, with the Final Certificate providing a conclusive final valuation of the contract sum.
The court emphasised that the Final Certificate is intended to be conclusive evidence of the contract sum unless challenged within the contractually prescribed 60-day period. The case law, particularly Marc Gilbard's Trustees, was applied to confirm that late challenges, including adjudications commenced after 60 days, cannot dispute the Final Certificate's conclusivity.
However, the court also considered clause 1.9.4, which provides a 28-day window to challenge an adjudicator's decision. The employer's counterclaim challenging the adjudicator's award was raised beyond this period, rendering it invalid.
The court found that the adjudication in this case was commenced after the 60-day period and thus should have been barred from challenging the Final Certificate. The adjudicator erred in finding the Final Certificate non-conclusive in the adjudication. The court also held that the Final Certificate does not supersede the entitlement to interim payments, but once the Final Certificate is issued and unchallenged, it conclusively determines the contract sum.
The court rejected the contractor's argument that the adjudication was merely an enforcement of an Interim Payment Notice unaffected by the Final Certificate. It held that enforcing an Interim Payment Notice post-Final Certificate without timely challenge undermines the contract's finality provisions.
Regarding the validity of the Interim Payment Notice, the court noted that factual disputes about the relevant due date would be resolved in the pending court action and that minor errors would not necessarily invalidate the notice.
In sum, the court concluded that the adjudicator's award should be set aside because the adjudication was out of time and conflicted with the conclusive effect of the Final Certificate, which was subject to a timely court challenge. The employer's counterclaim, although late, raised a valid point that the adjudicator erred in law.
Holding and Implications
The court UPHELD the reclaiming motion (employer's appeal) and REFUSED the contractor's cross appeal.
The court declared that the adjudicator's award based on the Interim Payment Notice was invalid because the adjudication was commenced outside the 60-day challenge period for the Final Certificate, which was conclusive. The employer is entitled to repayment of the sums paid pursuant to the adjudicator's award.
The pending court action challenging the Final Certificate will determine the ultimate correctness of the contract sum and any necessary adjustments, including repayment of any overpayments. The decision clarifies that the Final Certificate's conclusivity prevails over late adjudications and that enforcement of Interim Payment Notices after issuance of a Final Certificate must respect the contract's time limits and finality provisions.
No new legal precedent was established beyond reaffirming the proper application of clause 1.9 and the relevant case law. The ruling underscores the importance of adhering to contractual time limits for challenges to Final Certificates and adjudicator decisions in construction contracts.