Contains public sector information licensed under the Open Justice Licence v1.0.
John Paul Construction LTD v Tipperary Co-Operative Creamery LTD (Approved)
Factual and Procedural Background
This opinion concerns an application for leave to enforce an adjudicator's decision under the Construction Contracts Act 2013. The Applicant ("the contractor") seeks enforcement of a payment dispute decision against the Respondent ("the employer"). The employer resists enforcement on grounds that the adjudicator failed to comply with fair procedures and natural justice, specifically alleging that the adjudicator ignored the substantive defence and allowed a new claim during adjudication. The employer also contends that the adjudicator improperly reopened issues decided in an earlier adjudication between the parties. The adjudicator's decision arises from a construction contract dispute involving multiple delay events and management competence issues.
Legal Issues Presented
- Whether the adjudicator's decision falls within the terms of the payment dispute referred.
- Whether the adjudicator complied with fair procedures and natural justice, including proper consideration of the employer's defence.
- Whether the adjudicator exceeded jurisdiction by reopening issues decided in an earlier adjudication.
- Whether allowing a refined or "new" claim during adjudication breaches fair procedures.
Arguments of the Parties
Employer's Arguments
- The adjudicator ignored substantive defence sections (§3.01 to §3.03) of the employer's response, which detailed alleged failures by the contractor in management and programming, impacting project delays.
- The adjudicator improperly allowed a "new" claim to be introduced during adjudication, breaching fair procedures.
- The adjudicator exceeded jurisdiction by determining issues already decided in a prior adjudication concerning delay event 6.
- Alleged failure to direct an oral hearing was initially raised but sensibly withdrawn.
Contractor's Arguments
- The employer's defence was fully considered by the adjudicator, who addressed the substance of the defence in the context of each delay event.
- The alleged "new" claim was a better particularisation and refinement of the original claim, not a separate claim.
- The adjudicator did not exceed jurisdiction; the issues in the current adjudication differ from those in the prior adjudication.
- The employer's attempt to resist enforcement is effectively an impermissible judicial review beyond the statutory time-limit.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Principal Construction Ltd v. Beneavin Contractors Ltd [2021] IEHC 578 | Principles governing application for leave to enforce adjudicator's decision. | Used to summarize limited grounds for refusal of leave to enforce and the provisional binding nature of adjudicator's decisions. |
| Aakon Construction Services Ltd v. Pure Fitout Associated Ltd (No. 1) [2021] IEHC 562 | Clarification of court's narrow role in leave to enforce and fair procedures requirement. | Applied to emphasize the "pay now, argue later" principle and the limited judicial review at enforcement stage. |
| Pilon Ltd v. Breyer Group plc [2010] EWHC 837 (TCC) | Adjudicator must address the issues referred; failure to consider defence may render decision unenforceable if deliberate and material. | Adopted to guide assessment of alleged failure to consider defence and to distinguish deliberate omission from inadvertent oversight. |
| Carillion v Devonport | Decision enforceability if adjudicator generally addresses issues referred. | Referenced to support that adjudicator's decision is enforceable even if not perfect, provided issues were addressed. |
| Ballast, Broadwell, Thermal Energy | Failure to consider defence due to erroneous restrictive jurisdiction may render decision unenforceable. | Used to illustrate when adjudicator's jurisdictional error affects enforceability. |
| Bouygues and Amec v TWUL | Inadvertent failure to consider an issue generally does not render decision unenforceable. | Applied to reject employer's claim that adjudicator ignored defence absent deliberate exclusion. |
| Cantillon v Urvasco and CJP Builders Ltd v William Verry Ltd [2008] EWHC 2025 (TCC) | Error must be material, i.e., have a potentially significant effect on adjudication outcome. | Used to stress materiality threshold for refusing enforcement on procedural grounds. |
| Keir Regional Ltd v City and General (Holborn) Ltd [2006] EWHC 848 (TCC) | Materiality of error affecting adjudication result. | Supported the court's approach to materiality in adjudication enforcement context. |
| O'Donovan v. Bunni [2020] IEHC 623 | Judicial review may be available to restrain adjudicator in certain circumstances. | Noted but not determinative; court did not rule on judicial review applicability here. |
| NKT Cables A/S v. SP Power Systems Limited [2017] CSOH 38 | Adjudicator must consider substance of defences raised. | Referenced but noted limited precedential value due to fact-specific nature. |
| DC Community Partnerships Ltd v. Renfrewshire Council [2017] CSOH 143 | Adjudicator's consideration of freestanding substantive defences. | Referenced similarly with caution on precedential weight. |
Court's Reasoning and Analysis
The court began by outlining the statutory framework under the Construction Contracts Act 2013, emphasizing that adjudicator decisions are provisional and binding only until superseded by arbitration or court rulings. The court reiterated the "pay now, argue later" principle, allowing immediate enforcement subject to limited judicial scrutiny.
It acknowledged the narrow scope of judicial intervention on leave to enforce applications, focusing on whether the adjudicator's decision was within jurisdiction and complied with fair procedures, particularly the right to be heard and consideration of defences.
Regarding the employer’s allegation that the adjudicator ignored substantive defences, the court undertook a detailed examination of the employer’s response and the adjudicator’s decision. It found that the sections alleged to be ignored (§3.01 to §3.03) were introductory and integrally linked to the detailed defence on delay events. The adjudicator explicitly addressed these issues, including management competence and programming concerns, in the context of each delay event.
The court distinguished between a failure to consider a defence and rejecting it on the merits. It concluded the adjudicator considered and determined the employer’s defence rather than ignoring it. Attempts to revisit the merits of the adjudicator’s findings were rejected as inappropriate at this enforcement stage.
On the complaint about a "new" claim, the court found this was a refinement of the original claim rather than a separate claim, and the employer was afforded reasonable time to respond, consistent with the expedited nature of adjudication.
Regarding the allegation that the adjudicator exceeded jurisdiction by revisiting issues from a prior adjudication, the court found the matters addressed in the current adjudication were distinct, involving extension of time and prolongation costs not previously adjudicated.
The court noted the employer’s attempt to resist enforcement on grounds tantamount to judicial review was misplaced and that the merits of the adjudicator’s decision were properly for arbitration or court proceedings, not the enforcement application.
Holding and Implications
The court GRANTED LEAVE TO ENFORCE the adjudicator's decision dated 23 November 2020.
Judgment was entered against the respondent in the amount of €918,460.16 inclusive of VAT, with interest to accrue from the date of perfection of the order. The decision confirms the enforceability of adjudicator decisions on a provisional basis under the Construction Contracts Act 2013, reinforcing the "pay now, argue later" legislative policy.
The ruling underscores the limited scope of judicial intervention at the enforcement stage, requiring only that the adjudicator consider the defence and act within jurisdiction and fair procedures. It does not set new precedent beyond affirming established principles and clarifies that detailed merits review is reserved for subsequent arbitration or court proceedings.
Please subscribe to download the judgment.

Comments