Contains public sector information licensed under the Open Justice Licence v1.0.
Brandon Plant Hire LTD v. The Companies Acts (Discovery Motion) (Approved)
Factual and Procedural Background
Plaintiff Company A (In Liquidation), acting as a subcontractor to Defendant Company B, was involved in disputes over payments relating to three key developments: Mariavilla, Griffith Wood, and Donnybrook. The parties had entered into a settlement agreement on 11 March 2020 concerning payment disputes. The liquidator of Company A sought various orders, including declarations that the settlement agreement was a fraudulent disposition and orders for payment of monies allegedly due, primarily relating to contract variations and accelerated works. This discovery motion, brought against Company B, concerned six disputed categories of document discovery, with the remainder agreed. No written legal submissions or legal authorities were provided by the parties; the court proceeded based on established discovery principles.
Legal Issues Presented
The opinion addresses a procedural matter and does not frame distinct legal issues.
Arguments of the Parties
Appellant's Arguments
- Requested broad categories of documents related to dealings and meetings concerning the Mariavilla contract, oral instructions and variations to contracts, internal planning processes, and correspondence with Irish Water.
- Relied on pleadings describing a course of dealings where oral variations and accelerated works were agreed and paid for in the past, arguing such documents were relevant and necessary for the liquidator’s case.
- Contended that documents evidencing oral instructions and internal notes were likely to exist and would not be otherwise available to the liquidator.
- Argued that discovery of documents related to Irish Water’s involvement was reasonable given statutory compliance requirements impacting the contract works.
Respondent's Arguments
- Contended that some categories were overly broad, irrelevant, or unnecessary, likely encompassing documents unrelated to the issues in dispute.
- Argued that no documents would exist evidencing oral instructions, or that such documents would be in the liquidator’s possession, undermining the need for discovery.
- Maintained that references to Irish Water in pleadings did not justify discovery of documents relating to Irish Water, as the central issue was whether Company B required works for which Company A was entitled to payment.
- Asserted that discovery requests should be proportionate and limited to relevant documents, noting overlap between some categories and urging narrowing of requests.
- Denied that formal contract procedures were waived in previous dealings, challenging the liquidator’s contention of a course of dealing.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The court analyzed each disputed category of documents in light of relevance, necessity, proportionality, and the pleadings. For Category 14, the court found the request too broad and insufficiently justified, noting that other agreed categories covered relevant documents, and refused the request.
Regarding Category 16, the court held that mere references to Irish Water did not establish relevance or necessity for discovery of correspondence and reports, as the key issue was payment entitlement, not the reason for commissioning works, and refused the category.
For Categories 20 and 22, relating to contractual steps and payment calculations for other developments, the court identified a live dispute about whether informal or oral variations were agreed and paid for, deeming discovery relevant and necessary. However, the court found the categories' formulations unsatisfactory and invited the parties to agree on a more appropriate category, reserving the right to fix terms if they could not agree.
Category 23, concerning documents evidencing oral instructions for variations on Donnybrook contracts, was found relevant and necessary despite the respondent’s objections. The court recognized some overlap with an agreed category but emphasized the importance of internal notes evidencing oral requests, ordering discovery subject to scope and wording to be agreed or fixed by the court.
Category 26, relating to internal planning processes for variations and acceleration of the Mariavilla contract, was not grounded in specific pleadings and was deemed not relevant or necessary. The court refused this category.
The court emphasized proportionality and relevance throughout, refusing overly broad or insufficiently justified categories and encouraging the parties to refine discovery requests to reflect the actual issues in dispute.
Holding and Implications
The court REFUSED discovery for Categories 14, 16, and 26 due to lack of relevance, necessity, or proportionality.
The court ORDERED discovery relating to Categories 20, 22, and 23, subject to the parties agreeing appropriate scope and wording, or the court fixing such terms if the parties fail to agree.
The decision directly affects the parties by delineating the scope of discovery permitted in this matter, focusing on documents relevant to the live disputes over oral variations and payment obligations. No new legal precedent was established, as the court applied well-known principles of discovery to the facts presented.
Please subscribe to download the judgment.

Comments