Factual and Procedural Background
The Applicants initiated judicial review proceedings challenging a decision of An Bord Pleanala to grant development consent for a strategic housing development comprising 197 dwellings at a location in The State. The decision, dated 16 November 2018 and referenced "ABP-302216-18", was made pursuant to section 9 of the Planning and Development (Housing) and Residential Tenancies Act 2016 ("PD(H)A 2016"), which provides a temporary, streamlined procedure for strategic housing developments distinct from other planning legislation.
An Bord Pleanala conducted an environmental impact assessment and a screening for appropriate assessment under the Habitats Directive, concluding no significant adverse effects would arise. The judicial review was instituted on 14 January 2019, with leave granted on 17 January 2019.
The Applicants seek a pre-emptive or protective costs order, claiming the proceedings attract special costs rules under section 50B of the Planning and Development Act 2000 (as amended) and/or the Environment (Miscellaneous Provisions) Act 2011. The Respondent and the Developer argue that special costs rules apply only to certain grounds related to the Habitats Directive and the EU Floods Directive.
Legal Issues Presented
- Whether the special costs rules under section 50B of the Planning and Development Act 2000 apply to the entirety of the judicial review proceedings or only to specific grounds alleging breaches of certain EU Directives.
- The proper interpretation of the term "decision" under section 50B—whether it refers to the overall planning consent decision or discrete sub-decisions such as screening under the Habitats Directive.
- The applicability and interpretation of costs protection under Part 2 of the Environment (Miscellaneous Provisions) Act 2011 in the context of judicial review proceedings.
- The extent to which EU law, including the Aarhus Convention and relevant CJEU case law, imposes interpretative obligations on Irish courts in relation to costs protection.
Arguments of the Parties
Applicants' Arguments
- The entire proceedings fall within section 50B of the PDA 2000 because the impugned decision was made pursuant to section 9 of the PD(H)A 2016, which gives effect to the EIA Directive and the Habitats Directive.
- It is incorrect to suggest that environmental assessment requirements have merely been grafted onto existing legislation; the 2016 Act changes the procedures substantially.
- EU law cannot be separated from national law; section 1A of the PDA 2000 identifies the EU Directives implemented by the Act.
- Article 9(3) of the Aarhus Convention requires a uniform interpretation across national and EU law, supporting broad application of special costs rules.
- Reliance on CJEU judgment in Case C 470/16 North East Pylon supports their position.
Respondent and Developer's Arguments
- Special costs rules apply only to grounds alleging breach of the Habitats Directive and the EU Floods Directive.
- Citing CJEU Case C 470/16 North East Pylon, they submit that costs can be apportioned between different grounds of challenge, with special costs rules applying only to specific grounds.
- They emphasize three High Court judgments postdating North East Pylon which apportion costs by grounds: Fotovoltaic, Merriman, and North East Pylon No. 5.
- Argue that some grounds, such as those concerning material contravention of the development plan and procedural fairness, are purely administrative law challenges outside the scope of environmental cost protections.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Case C 470/16 North East Pylon |
Interpretation of costs rules under Aarhus Convention and EU Directives; apportionment of costs between grounds of challenge. |
Recognized EU law allows apportionment but held Irish legislation does not provide for such distinction; costs rules apply to entire proceedings. |
| Village Residents Association Ltd. v. An Bord Pleanala [2000] 4 I.R. 321 |
Permits pre-emptive costs orders under Order 99, rule 5. |
Confirmed pre-emptive costs orders possible but refused on facts. |
| McCoy v. Shilleagh Quarries Ltd [2015] IECA 28; [2015] 1 I.R. 627 |
Costs rules under Environment (Miscellaneous Provisions) Act 2011 can be determined at any time. |
Supports timing of costs determination. |
| Conway v. Ireland [2017] IESC 13; [2017] 1 I.R. 53 |
Interpretation of "national law relating to the environment" under Aarhus Convention; interpretative obligation on national courts. |
Applied to confirm broad interpretation of environmental law for costs protection. |
| JC Savage Supermarket Ltd v. An Bord Pleanala [2011] IEHC 488 |
Limits application of section 50B to decisions under specified EU Directives; rejects broad application to all planning cases. |
Distinguished present case as decision was not subject to EIA Directive. |
| McCallig v. An Bord Pleanala (No. 2) [2014] IEHC 353 |
Interpretation of "proceedings" in section 50B; suggested apportionment by grounds. |
Rejected by this court as inconsistent with statutory language and interpretative obligations. |
| Fotovoltaic Energy SRL v. Mayo County Council (No. 3) [2018] IEHC 245 |
Costs apportionment by grounds in environmental litigation. |
Distinguished on statutory provision basis; decision under different statutory provision. |
| Merriman v. Fingal County Council (unreported, 17 May 2018) |
Costs apportionment by grounds; decision not a development consent. |
Distinguished as decision under section 42, not strategic housing development. |
| North East Pylon Pressure Campaign Ltd. v. An Bord Pleanala (No. 5) [2018] IEHC 662 |
Costs apportionment and scope of section 50B in procedural context. |
Distinguished due to absence of final decision at time of proceedings. |
| Kelly v. An Bord Pleanala [2014] IEHC 400 |
Clarification of statutory framework for planning decisions and environmental assessments. |
Applied to interpret "decision" as overall planning consent, not sub-decisions. |
| Urrinbridge v. An Bord Pleanala [2011] IEHC 400 |
Timing and nature of planning decisions for judicial review purposes. |
Supported interpretation of "decision" as final planning consent. |
| Ecological Data Centres Ltd. v. An Bord Pleanala [2013] IESC 61 |
Statutory interpretation of planning decisions and rights of judicial review. |
Approved approach to timing and nature of decisions. |
| Callaghan v. An Bord Pleanala [2017] IESC 60 |
Obligation of courts to interpret national law in conformity with EU law. |
Supported interpretative obligation relevant to costs rules. |
| O'Connor v. Offaly County Council [2017] IEHC 606 |
Application of Environment (Miscellaneous Provisions) Act 2011 to judicial review proceedings. |
Confirmed 2011 Act can apply to judicial review costs protection. |
| Case C 664/15 Protect Natur |
National courts must disapply procedural rules conflicting with Aarhus Convention obligations. |
Considered in relation to national procedural law and costs rules. |
| Case C 167/17 Klohn |
Costs and retrospective effect under Aarhus Convention and EU law. |
Referenced as evolving jurisprudence impacting costs regime. |
Court's Reasoning and Analysis
The court began by emphasizing that the special costs rules under section 50B are triggered by the nature of the statutory provision pursuant to which the impugned decision is made, not by the individual grounds of challenge. The statutory language refers to "proceedings" simpliciter, with no mention of "grounds". This contrasts with section 50A, which explicitly references "grounds".
Section 9 of the PD(H)A 2016 imposes obligations relating to the EIA Directive and the Habitats Directive, including environmental impact assessments and appropriate assessments. Therefore, the decision to grant planning permission under this section falls within the scope of section 50B, triggering the special costs regime for the entirety of the proceedings.
The court rejected the Respondent's argument that costs should be apportioned between grounds, noting that while EU law permits such apportionment, Irish domestic legislation does not provide for it. The interpretative obligation to give effect to EU law is subject to the contra legem principle, and the plain language of section 50B must be respected.
The court distinguished prior High Court judgments relied upon by the Respondent, explaining that those cases involved decisions made under different statutory provisions not covered by section 50B or involved procedural stages rather than final decisions. The present case's decision was made under a statutory provision that expressly implements relevant EU Directives, justifying the application of section 50B to all grounds.
Regarding the term "decision," the court held that it refers to the overall planning consent decision, not discrete sub-decisions such as screening exercises, to avoid legal uncertainty and ensure consistency with the judicial review scheme.
The court also considered the Environment (Miscellaneous Provisions) Act 2011 but found it unnecessary to rely on it given the application of section 50B. However, it noted that the 2011 Act's costs protection is subject to an environmental damage requirement, which conflicts with EU law as interpreted by the CJEU, and thus the court would adopt a similar approach to costs via its general jurisdiction if needed.
Finally, the court acknowledged the evolving nature of the law in this area, including amendments to legislation and recent CJEU judgments, and recognized that strict adherence to precedent may be less appropriate given the developing jurisprudence and interpretative obligations under EU law.
Holding and Implications
The court's final ruling is to declare that the special costs rules under section 50B of the Planning and Development Act 2000 apply to the entirety of the judicial review proceedings, encompassing all grounds of challenge.
This means that each party shall bear its own costs unless the Applicants succeed in obtaining relief, in which case costs may be awarded in accordance with section 50B's provisions. The court noted that the final decision on costs incidence will rest with the trial judge hearing the substantive judicial review.
The court also indicated it would consider making an order under Order 99 on a pre-emptive basis to protect the Applicants from adverse costs irrespective of the outcome.
No new precedent was established beyond clarifying the interpretation of section 50B in the context of strategic housing development decisions under the PD(H)A 2016, and the ruling aligns with the interpretative obligations imposed by EU law and the Aarhus Convention.