Translate
Text Highlighter

Bookmark

PDF

Share

Report a problem
AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Judges
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Judges

Moylist Construction Ltd v. Doheny & others

Smart Summary

Factual and Procedural Background

The Plaintiff/Appellant (“Plaintiff”) was the contractor on a development of eighteen holiday homes in The City. The project was financed in large part by the third-named Defendant/Respondent (“Bank”) which held a mortgage, later enforced by appointing the first-named Defendant/Respondent (“Defendant Receiver”). The developer (“Developer”) owes substantial sums to both the Plaintiff and the Bank and is insolvent. When the Bank took possession through the Defendant Receiver, the Plaintiff claimed it was wrongfully dispossessed of the site, invoked rights said to arise under a standard form building contract, and sued for injunctive relief.

The High Court (Judge Laffoy) refused the interlocutory injunction and, on motions brought by the Defendant Receiver and the Bank, dismissed the actions against them as “bound to fail.” The Plaintiff appealed only the strike-out orders affecting the Defendant Receiver and the Bank; Deloitte & Touche and the interlocutory injunction ruling were not appealed.

Legal Issues Presented

  1. Whether the High Court correctly applied the inherent “bound to fail” jurisdiction in striking out the Plaintiff’s claims against the Defendant Receiver and the Bank.
  2. Whether the complexity of the competing proprietary and contractual rights made summary dismissal inappropriate.
  3. Whether, and to what extent, the Plaintiff could rely on arguments on appeal that were not fully developed in the High Court.

Arguments of the Parties

Plaintiff/Appellant's Arguments

  • The claim raises intricate questions of law and mixed fact—particularly over priority between its contractual licence/possession and the Bank’s mortgage—which cannot be resolved safely on affidavit.
  • Delay in registering the Bank’s charge and the nature of the standard form building contract may create arguable rights that defeat or postpone the Bank’s security.
  • Even if parts of the pleaded case are weak, none is so obviously unstateable that the action is “bound to fail.”
  • Additional legal arguments advanced on appeal should be entertained because the consequence of dismissal is total loss of a plenary trial.

Bank and Defendant Receiver's Arguments

  • The Plaintiff’s pleadings and evidence disclose no sustainable cause of action; therefore the proceedings constitute an abuse of process and should be struck out.
  • The Plaintiff’s case on appeal is materially different from that run in the High Court; if new points had been raised earlier, the Bank would have adduced further evidence.
  • Under well-established authority the court may determine documentary questions on a strike-out motion, and those documents demonstrate the Plaintiff has no title to possession capable of overriding the mortgagee’s rights.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Barry v Buckley [1981] I.R. 306 Recognises the inherent jurisdiction to strike out proceedings that are “bound to fail.” Formed the starting point for analysing whether dismissal here was justified.
Salthill Properties v Royal Bank of Scotland [2009] IEHC 207 Distinguishes inherent jurisdiction from O.19 r.28 applications. Clarified the legal framework used by the High Court and Supreme Court.
Lopes v Minister for Justice [2014] IESC 21 Approves the Salthill distinction and discusses documentary assessment on strike-out. Relied on for the extent to which courts may examine documents.
Keohane v Hynes [2014] IESC 66 Sets limits on factual engagement when considering dismissal motions. Cited extensively to caution against deep factual analysis at motion stage.
McGrath v O’Driscoll [2007] I.L.R.M. 203 In summary judgment, complex issues should not be decided on affidavit. Used by analogy to show similar limits apply to strike-out applications.
Danske Bank v Durkan New Homes [2010] IESC 22 Supreme Court endorsement of the McGrath approach. Reinforced the caution against deciding complex points summarily.
Aer Rianta v Ryanair [2001] 4 I.R. 607 “Very clear” test for absence of defence in summary judgment. Analogised to the “bound to fail” threshold.
Sun Fat Chan v Osseous [1992] 1 I.R. 425 Trials often reveal unforeseen facts; courts should be wary of premature disposal. Supported the Court’s preference for a plenary hearing.
Bakht v The Medical Council [1990] 1 I.R. 515 & Philips v The Medical Council [1991] 2 I.R. 115 Illustrate divergence between affidavit-based and oral evidence findings. Underscored the risk of injustice if no full trial is held.
Bula v Tara Mines (No. 6) [2000] 4 I.R. 412 “Seventeen noughts are still nothing” – multiple weak points do not equal strength. Court noted but distinguished; here the points were not obviously valueless.
Jodifern Ltd. v Fitzgerald [2000] 3 I.R. 321 Warns against using strike-out as a surrogate summary trial. Key authority for refusing to engage in detailed merits analysis at motion stage.
Lough Swilly Shellfish v Bradley [2013] 1 I.R. 227 Conditions for raising new arguments on appeal. Balanced in allowing Plaintiff some latitude at appellate stage.
I.B.R.C. v McCaughey [2014] 1 I.R. 749 Confirms additional leeway where party faces loss of a full trial. Guided the Court in permitting expanded submissions by the Plaintiff.
Headstart Global Fund v Citco Bank Nederland [2010] IEHC 334 Example of technical priority disputes following economic collapse. Cited to illustrate complexity analogous to the present dispute.
Astor Chemical v Synthetic Technology [1990] B.C.L.C. 1 Discusses circumstances where an injunction may restrain enforcement of a charge conflicting with prior contractual rights. Referenced in High Court; Supreme Court noted the legal test (actual knowledge) may itself be debatable.

Court's Reasoning and Analysis

The Supreme Court, per Judge Clarke, undertook a detailed review of the jurisprudence governing strike-out applications. It reiterated that:

  • The default position is that litigants receive a plenary trial; summary dismissal is an exceptional remedy limited to “slam-dunk” cases where the claim is plainly unsustainable.
  • While documentary evidence may be examined, courts must not convert the strike-out motion into a de facto trial, particularly where complex legal construction or mixed facts are involved.
  • Even where legal issues alone are in play, if they are intricate or inter-dependent, they should not be resolved on affidavit.
  • Additional latitude is permissible on appeal when the moving party risks total loss of trial, justifying consideration of certain new arguments advanced by the Plaintiff.

Applying these principles, the Court found the present dispute replete with difficult, intertwined questions: the nature and survival of the Plaintiff’s contractual licence and possession; the Bank’s mortgage rights given the delayed registration; the effect of subsequent agreements between the Defendant Receiver and the Plaintiff; and the potential relevance of the Bank’s knowledge of the building contract. Determining such matters would require close factual inquiry and nuanced legal construction unsuitable for a strike-out motion. Accordingly, it could not be said with the requisite certainty that the Plaintiff’s case was bound to fail.

Holding and Implications

APPEAL ALLOWED. The Supreme Court set aside the High Court order dismissing the proceedings and remitted the case for plenary trial “at the earliest possible date.”

Implications: The decision underscores the narrow compass of the inherent “bound to fail” jurisdiction and signals that courts should refrain from striking out actions where issues of priority, contractual interpretation, or mixed fact and law are complex. No new substantive precedent was created; rather, existing principles were reaffirmed and applied.

To access the original judgment, please Sign In or Subscribe.

Moylist Construction Ltd v Doheny & others

Contains public sector information licensed under the Open Justice Licence v1.0.

Use AI to get other relevant cases.

Comments

Moylist Construction Ltd v Doheny & others
(Mar 4, 2016)