Factual and Procedural Background
The dispute arises from a contract between Company A ("Hitachi") and Company B ("Sisk") concerning the design and construction of a multi-fuel power plant at an existing coal-fired power station in The City. Company A engaged Company B under a contract dated 29 March 2012 for design and construction services exceeding £44 million. The contract included provisions for variations, interim payments, and adjudications, with specific clauses governing valuation and substantiation of additional works, referred to as "Events". This case focuses on Event 1176, involving acceleration works to the boiler hall construction.
Company B submitted multiple payment applications and adjudications concerning Event 1176. The second adjudication, conducted in 2016 by Adjudicator Pontin, found Event 1176 to be a variation requiring valuation but declined to assign a value due to insufficient substantiating evidence. Subsequent mediation and the sixth adjudication addressed related claims but did not resolve the valuation issue for Event 1176 conclusively.
In 2017, Company B submitted a revised payment application for Event 1176, which Company A rejected, asserting that the claim lacked contractual merit and relying on the prior adjudicator's decision as final and binding. Company B referred the dispute to adjudication for the eighth time, seeking valuation and payment for Event 1176. The adjudicator again was Mr Pontin, who concluded he had jurisdiction to determine the valuation and subsequently awarded Company B a substantial sum for Event 1176.
Legal Issues Presented
- Whether the adjudicator in the eighth adjudication had jurisdiction to decide the sums payable for additional works under Event 1176, given that the same or substantially the same question had been addressed in the earlier, second adjudication.
- Whether the dispute referred in the eighth adjudication was the same or substantially the same as that decided in the second adjudication, thereby affecting the adjudicator's jurisdiction.
- The implications of the contractual provisions regarding the finality of adjudicator decisions when not referred to the Court within ten business days.
Arguments of the Parties
Appellant's Arguments (Company A)
- The adjudicator in the second adjudication had already decided the value of Event 1176 as nil due to insufficient evidence, making that decision final and binding.
- The claim in the eighth adjudication was the same or substantially the same as that in the second adjudication, thus the adjudicator lacked jurisdiction to reconsider it.
- The non-referral of the second adjudication decision to the Court within ten business days rendered it final and precluded a second adjudication on the same matter.
- Company B should be permanently barred from recovering payment for Event 1176 outside of a final payment application.
Appellee's Arguments (Company B)
- The adjudicator in the second adjudication decided only liability for Event 1176 as a variation but did not decide its valuation due to lack of substantiating evidence.
- The eighth adjudication concerned a new dispute about valuation supported by substantially more evidence than previously submitted.
- The dispute in the eighth adjudication was not the same or substantially the same as that in the second adjudication, thus the adjudicator had jurisdiction.
- Company B had complied with contractual requirements and was entitled to pursue valuation and payment for Event 1176 in the eighth adjudication.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| Quietfield Ltd v Vascroft Construction Ltd [2007] BLR 67 |
Adjudicator lacks jurisdiction to decide disputes that are the same or substantially the same as previously decided adjudications; importance of what the first adjudicator actually decided. |
The court applied the principle that a second adjudicator must not decide the same dispute already decided, emphasizing the scope and content of the first adjudicator's decision in determining jurisdiction. |
| Carillion Construction Ltd v Smith [2011] EWHC 2910 (TCC) |
Factors to consider when assessing whether disputes are the same or substantially the same; focus on ambit and scope of claims. |
The court noted that focusing solely on what the first adjudication decided could lead to error; the scope of claims is important but not comprehensive alone. |
| Harding v Paice [2015] EWCA Civ 1231; [2016] 1 WLR 4068 |
Emphasizes that the first adjudicator's actual decision determines what remains for subsequent adjudication; the decision's content is critical. |
The court adopted the approach that jurisdiction depends on what the first adjudicator decided, not just the claims referred. |
| Brown v Complete Buildings [2016] EWCA Civ 1; [2016] BLR 98 |
The adjudicator's view on jurisdiction is influential but not binding on the court. |
The court maintained ultimate authority to determine jurisdiction despite the adjudicator's opinion. |
| Henderson v Henderson (1843) 3 Hare 100 |
Doctrine of issue estoppel and prevention of repetitive litigation. |
The court clarified that while analogous principles exist, adjudication has distinct procedural characteristics and should not be conflated with final litigation estoppel principles. |
Court's Reasoning and Analysis
The court began by identifying the key question: whether the adjudicator in the eighth adjudication had jurisdiction to decide the valuation of Event 1176 given the prior adjudication. The court examined the second adjudicator's decision and found that while liability for Event 1176 as a variation was established, no valuation was determined due to insufficient evidence. The "nil" valuation in the second adjudication was a consequence of lack of substantiation, not a final valuation.
The court emphasized the importance of focusing on what the first adjudicator actually decided rather than the scope of the claims referred. It held that the dispute referred in the eighth adjudication—valuation supported by new and more detailed evidence—was not the same or substantially the same as the dispute decided in the second adjudication.
The court rejected Company A's argument that the non-referral of the second adjudication decision to the Court within ten business days rendered the valuation final and binding for all purposes, noting that such a result would be draconian and inconsistent with the contractual scheme allowing for adjustments and interim payments.
The court also considered policy reasons underpinning interim adjudications, which promote cash flow and allow for correction of valuations later, and found no evidence of oppressive conduct by Company B in pursuing the claim.
Accordingly, the court concluded that the adjudicator in the eighth adjudication had jurisdiction to determine the valuation of Event 1176.
Holding and Implications
The court held that the adjudicator in the eighth adjudication had jurisdiction to decide the valuation of Event 1176 and that the adjudicator's decision awarding Company B payment for Event 1176 should be enforced.
The direct effect of this decision is that Company B is entitled to pursue valuation and payment for Event 1176 in successive adjudications where prior adjudications did not conclusively determine valuation due to lack of evidence. The ruling affirms the principle that adjudicator decisions are binding only to the extent of what was actually decided, and that insufficient evidence leading to a nil valuation does not preclude future adjudications on the same matter with better substantiation.
No new precedent was established beyond applying existing principles concerning adjudicator jurisdiction and the finality of decisions under the contract and statutory scheme.