Contains public sector information licensed under the Open Justice Licence v1.0.
S&T (UK) Ltd v. Grove Developments Ltd
Factual and Procedural Background
By a contract dated 26th March 2015, Company B engaged Company A to design and construct a hotel at an airport. The contract was a standard form, the JCT Design and Build Contract 2011, with amendments, and the contract sum was approximately £26.4 million. The contractual completion date was 10th October 2016. Delays occurred, with Company A failing to achieve practical completion by that date. On 13th October 2016, Company B served a non-completion notice pursuant to the contract. Practical completion was achieved on 24th March 2017.
On 31st March 2017, Company A submitted interim application number 22 claiming approximately £39.7 million in total value of works, an increase of about £14 million over the previous valuation. Company B failed to issue a Payment Notice within the contractual five-day period but sent a Payment Notice on 13th April 2017 valuing the work at approximately £1.4 million. On 18th April 2017, Company B issued a Pay Less Notice stating the sum due was £0.00, relying on liquidated damages for delay amounting to approximately £2.5 million. On the same day, Company B served notices related to liquidated damages in the required sequence but within seconds of each other.
Company B made no payment in respect of interim application 22. Company A initiated a series of adjudications, including one challenging the validity of the Pay Less Notice. The adjudicator held the Pay Less Notice invalid and ordered payment of approximately £14 million. Company B contested this in the Technology and Construction Court (TCC), where Mr Justice Coulson held that the Pay Less Notice was valid, Company B was entitled to adjudicate to determine the true value of the works, and that Company B had complied with the contractual notice requirements to recover liquidated damages. Company A appealed to the Court of Appeal.
Legal Issues Presented
- Whether the employer's purported Pay Less Notice sent in response to interim application 22 complied with the contractual requirements.
- Whether the employer is entitled to pursue a claim in adjudication to determine the correct value of the works on the date of interim application 22.
- Whether, in April 2017, the employer complied with the contractual requirements in order to maintain its claim for liquidated damages.
Arguments of the Parties
Appellant's Arguments
- The Pay Less Notice was invalid because it failed to "specify" the basis on which the sum was calculated, merely referring to an earlier Payment Certificate and spreadsheet.
- The employer had no contractual entitlement to pursue adjudication on the true valuation of the works after failing to serve a valid Pay Less Notice.
- The notices for liquidated damages were not properly served in the required sequence with sufficient time for the contractor to respond.
- The timing and content of the Pay Less Notice did not meet the statutory and contractual requirements, undermining the employer’s right to withhold payment.
- Criticism of reliance on the Mannai Investment case for interpreting the requirement to "specify" in notices.
Respondent's Arguments
- The Pay Less Notice was valid as it clearly specified the sum due and the basis by reference to a clearly identified and contemporaneously provided spreadsheet.
- The construction industry practice allows notices to refer to detailed calculations in other documents, and the contract did not require the detailed calculations to be contained within the notice itself.
- The employer is entitled to adjudicate to determine the true valuation of the works, even if no valid Pay Less Notice had been served, reflecting the adjudicator’s wide powers and the statutory regime.
- The notices for liquidated damages were served in proper sequence and the contract does not require a minimum interval between such notices.
- The statutory and contractual frameworks promote cashflow and prompt payment, with adjudication serving as a mechanism for resolving valuation disputes subsequently.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749 | Objective approach to the construction of contractual notices. | The court relied on Mannai to hold that the Pay Less Notice was valid as a reasonable recipient would understand the reference to the earlier spreadsheet. |
| Beaufort Developments (NI) Ltd v Gilbert-Ash N.I Ltd [1999] 1 AC 266 | The court’s power to open up and revise interim certificates and the non-conclusive nature of such certificates. | Supported the proposition that courts and adjudicators can determine the true value of work beyond the certificate or notice. |
| Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [2005] EWCA Civ 814; [2005] 1 WLR 3850 | Interim payment entitlement arises on issue or expected issue of certificate; absence of certificate does not bar payment. | Confirmed that adjudicators and courts can review and revise sums due even if certificates are absent or contested. |
| Rupert Morgan Building Services (LLC) Ltd v Jervis [2004] 1 WLR 1867 | Section 111 of HGCRA concerned with cashflow; payment obligation immediate but does not determine final liability; overpayments recoverable. | Supported the view that adjudication can be used to determine correct valuation and recover overpayments. |
| ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC); [2015] BLR 233 | Employer’s failure to serve Payment or Pay Less Notice results in contractor entitlement to payment; second adjudication on valuation may be invalid. | Discussed but court found the reasoning conflicted with other authorities and preferred alternative analysis. |
| Galliford Try Building Ltd v Estura Ltd [2015] EWHC 412 (TCC); [2015] BLR 321 | Employer not entitled to a second adjudication to re-open valuation of interim application if no Payment or Pay Less Notice served. | Held that adjudication jurisdiction is limited in such circumstances; however, payment obligations remain subject to adjudication on later applications. |
| Harding (trading as M J Harding Contractors) v Paice [2015] EWCA Civ 1231; [2016] 1 WLR 4068 | Employer entitled to pursue adjudication to determine final account valuation even after making payment under defective Pay Less Notice. | Confirmed employer’s right to recover overpayments through adjudication or litigation despite initial payment obligations. |
| Wilson and Sharp Investments Ltd v Harbour View Developments Ltd [2015] EWCA Civ 1030 | Payment obligations under HGCRA do not preclude employer from challenging disputed items later. | Supported the principle that payment and valuation disputes can be separately addressed. |
| Kersfield Developments (Bridge Road Ltd) v Bray & Slaughter Ltd [2017] EWHC 15 (TCC); 170 Con LR 40 | Where a default notice mechanism fixes an interim payment, there is no contractual basis to revise that payment by reference to a proper valuation. | Rejected employer’s attempt to re-open valuation by adjudication after default notice fixed sum. |
| Imperial Chemical Industries v Merit Merrell Technology Ltd (No. 2) [2017] EWHC 1763 (TCC); 173 Con LR 137 | Employer entitled to recover overpayments after repudiation of contract; interim assessments subject to correction at later stage. | Supported view that interim valuations are provisional and can be corrected later through adjudication or litigation. |
| Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc [2015] UKSC 38; [2015] 1 WLR 2961 | Employer entitled to recover overpayments by implied term or restitution following adjudicator’s re-evaluation. | Used to support employer’s right to recover overpayments made under interim applications. |
| Melville Dundas Ltd v George Wimpey UK Ltd [2007] UKHL 18; [2007] 1 WLR 1136 | Purpose of HGCRA is to promote cashflow through prompt interim payments. | Supported purposive interpretation that payment obligations precede adjudication on valuation disputes. |
| Marks & Spencer Plc v BNP Paribas [2015] UKSC 72; [2016] AC 742 | Principles for implying terms into contracts. | Used to reject implication of a requirement for a reasonable lapse of time between notices under the contract. |
| Haywood v Newcastle Upon Tyne Hospitals NHS Foundation Trust [2018] UKSC 22; [2018] 1 WLR 2073 | Notice is effective only upon receipt. | Applied to hold that notices sent by employer were received in proper sequence despite close timing. |
Court's Reasoning and Analysis
The court addressed each of the three issues in turn. On the first issue, the court considered the statutory and contractual requirements for a Pay Less Notice, focusing on the requirement that the notice "specify" both the sum due and the basis of calculation. The adjudicator had held that merely referencing an earlier document was insufficient, but the judge and the Court of Appeal adopted an objective approach, relying on Mannai Investment, to find that a reasonable recipient familiar with the documents would understand the basis of the sum. The court rejected a strict "bright line" rule requiring all calculations to be contained within the notice itself.
Regarding the second issue, the court acknowledged the conflicting authorities but concluded that the employer is entitled to adjudicate on the true valuation of the works even if no valid Pay Less Notice was served, provided the employer has complied with the immediate payment obligation under section 111 of the Amended Act. The court emphasized the distinction between the immediate payment obligation (cashflow) and the ultimate valuation of the works (justiciable issue). The adjudication regime is subordinate to the payment regime, and the employer must pay the notified sum before commencing a "true value" adjudication. This interpretation aligns with the statutory purpose of promoting prompt payments followed by dispute resolution.
On the third issue, the court considered the sequence and timing of notices required to recover liquidated damages for delay. Although the notices were sent within seconds of each other, the court held the contract required only that the notices be given in sequence, not that any specific interval elapse. The court rejected the appellant's argument for implying a reasonable lapse of time, citing established principles on implying terms and the need for certainty in commercial contracts.
Throughout the analysis, the court reviewed relevant case law, statutory provisions, and the contractual terms, carefully balancing the need for certainty and commercial practicality with the protection of parties' rights under the legislation and contract.
Holding and Implications
The Court of Appeal DISMISSED the appeal, affirming the decision of the Technology and Construction Court.
The court held that:
- The employer's Pay Less Notice was valid and effective despite referencing a previously issued detailed spreadsheet.
- The employer is entitled to pursue adjudication to determine the true valuation of works on an interim application, even if no valid Pay Less Notice was served, but only after complying with the immediate payment obligation under the statute and contract.
- The employer complied with the contractual notice requirements to recover liquidated damages for delay, as the notices were served in the correct sequence and no minimum interval between notices was required.
The decision confirms the interplay between prompt payment obligations and adjudication rights under the Housing Grants, Construction and Regeneration Act 1996 (as amended), reinforcing the importance of compliance with statutory and contractual notice requirements while preserving the right to dispute valuations through adjudication. No new precedent was set beyond clarifying these points in the context of the contract and facts before the court.
Please subscribe to download the judgment.
Comments