Factual and Procedural Background
These Part 8 proceedings were brought by Company A ("Harrington"), subcontractors employed by Company B ("Multiplex") on the Wembley Stadium project and two other projects at Mansfield and Liverpool. The Wembley project history and contract were treated as representative of all three projects. Company A had engaged Company C ("Tyroddy") as fix-only reinforcement sub-subcontractors. The dispute concerns the enforceability of adjudicator decisions made in favour of Company C, arising from adjudications initiated by Company C against Company A regarding retention monies withheld under the sub-subcontracts.
The contractual relationship was evidenced by a letter dated 6 June 2003 from Company A to Company C outlining rates and terms, including a 5% retention initially agreed but subsequently reduced to 3%. Interim valuations and payment certificates were issued over the course of the works from 2003 to 2006, with retention sums withheld. After completion, no final account was agreed or settled between the parties.
Approximately four and a half years later, Company C referred the contracts to adjudication seeking payment of the outstanding retention monies. The adjudicator was appointed and issued decisions in favour of Company C, ordering payment of retention sums. Company A initiated these Part 8 proceedings challenging the adjudicator’s decisions on grounds including breach of natural justice and contract interpretation.
Legal Issues Presented
- Whether the adjudicator’s decisions enforcing payment of retention monies were valid and enforceable.
- Whether there was an implied contractual term that retention monies are only payable following completion of a final account process.
- Whether Company A could rely on defences such as set-off, abatement, or retainer based on an overvaluation of work to defeat Company C’s claim for retention monies.
- Whether the adjudicator committed a material breach of natural justice by failing to consider Company A’s defence relating to the final account and overpayment claims.
Arguments of the Parties
Company C's Arguments
- The contract provided for deduction of retention at 5%, reduced in practice to 3%, and an implied term should be recognized that retention monies are payable on completion and after defects liability periods, based on normal trade custom.
- Company A had mismanaged valuations and overpaid Company C on multiple contracts, and their claims of overpayment were out of time and unfounded.
- Company A had a contractual duty to value the works accurately; their failure to do so did not negate Company C’s entitlement to retention monies.
- Company A’s evidence of overvaluation was unreliable and should be rejected by the adjudicator.
Company A's Arguments
- Retention monies were only provisional "on-account" payments and the final amount due was contingent on agreement of a final account, which had not been done.
- Company C had not submitted or agreed a final account, so the retention amount could not be established or become due.
- The adjudication initiated by Company C was opportunistic and contradicted the parties’ normal dealings and agreements on payment of retentions.
- Company A disputed the valuation of the last interim certificate and asserted it was not the correct and proper value of the contract works.
- Company A contended that any implied term for repayment of retention must include a requirement that the final account be agreed or settled first.
- Company A sought the adjudicator to decide the amount of the final account and retention due, and to require repayment if the final account was less than previously paid.
Table of Precedents Cited
| Precedent |
Rule or Principle Cited For |
Application by the Court |
| CJP Builders Limited v William Verry Limited [2008] BLR 545 |
Material breach of natural justice in adjudication where adjudicator decides on unargued factual or legal basis without parties’ opportunity to comment. |
Used to assess whether the adjudicator failed to consider Company A’s defence and breached natural justice by excluding relevant evidence. |
| Cantillon Ltd v Urvasco Ltd [2008] BLR 250 |
Framework for assessing breaches of natural justice in adjudication: materiality and opportunity to comment on decisive issues. |
Supported the analysis of whether the adjudicator’s failure to consider Company A’s defence was a material breach. |
| Pilon Limited v Breyer Group plc [2010] BLR 452 |
Adjudicator’s jurisdiction and natural justice; failure to consider defence may render decision unenforceable. |
Reinforced the principle that adjudicator must address referred issues and consider fundamental defences. |
| Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 |
Common law and equitable rights such as set-off and abatement are not excluded unless clearly expressed in contract. |
Supported the conclusion that Company A could raise overpayment and set-off defences despite contract silence. |
| Humes Buildings Contractors Ltd v Charlotte Homes (Surrey) Limited (unreported, 2007) |
Failure of adjudicator to raise material jurisdictional issue with parties and to allow submissions constitutes breach of natural justice. |
Analogous to the present case where adjudicator excluded final account defence without hearing parties on jurisdictional point. |
| Carillion v Devonport |
Adjudicator’s decision is enforceable if it generally addresses the referred issues, even if wrong. |
Referenced to explain when adjudicator’s decision may be unenforceable due to erroneous restrictive view of jurisdiction. |
Court's Reasoning and Analysis
The court carefully examined the contractual documents and the adjudication process. It identified that the contract provided for retention but was silent on the timing for payment, and that it was common in construction for retention to be released in two moieties: on practical completion and after the defects liability period.
The court found no implied contractual term requiring retention to be payable only after final accounting. Retention represented monies already due, payable within a reasonable time after completion, subject to defences such as set-off or abatement.
However, the court found that the adjudicator took an erroneously restrictive view of his jurisdiction by excluding from consideration Company A’s defence that the retention claim depended on the outcome of a final account process and overpayment claims. This defence was a viable and material issue within the dispute and should have been adjudicated upon.
The adjudicator also failed to give the parties an opportunity to be heard on the jurisdictional point of whether final account issues were excluded, thus breaching the rules of natural justice. This breach was material and more than peripheral, rendering the adjudicator’s decisions unenforceable.
The court emphasized that the adjudicator acted honestly and transparently but nonetheless made a legal error by ignoring a fundamental defence and failing to observe procedural fairness.
On the substantive contract interpretation, the court held that while Company A could not rely on the contract to delay payment of retention until final account agreement, it could raise defences based on overpayments or set-offs as a matter of law, since the contract did not exclude such rights.
Holding and Implications
The court held that the adjudicator’s decisions ordering payment of retention monies were NOT ENFORCEABLE due to material breaches of natural justice arising from the adjudicator’s erroneous restriction of jurisdiction and failure to consider Company A’s relevant defences.
The direct effect is that Company A is not presently bound to pay the retention sums awarded by the adjudicator, and the adjudicator’s decisions cannot be enforced as judgments of the court.
The court did not establish new legal precedent but reaffirmed established principles regarding adjudicator jurisdiction, natural justice, and the interpretation of retention clauses in construction contracts. It clarified that defences based on overpayment or set-off may be raised even if the contract is silent on final accounting, and that adjudicators must consider such defences when properly raised.