  • Consumer Protection Act, 1986, Section 2(1)(g)-electricity-Sundry
  • Section 25 and 27 of the Consumer Protection Act. Copy
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Attorney(S)
Acts
  • Consumer Protection Act, 1986, Section 2(1)(g)-electricity-Sundry
  • Section 25 and 27 of the Consumer Protection Act. Copy
Smart Summary

Factual and Procedural Background

The complainant had an electric meter connection bearing account No.M53GT530039H installed at his residence and had been regularly paying electricity bills to the opposite parties. The dispute arose when the complainant received a bill dated 16.02.2017 for Rs. 97,950/-, which he alleged was incorrect and illegal. The complainant denied any theft of electricity and contended that no notice was issued by the opposite parties regarding the recovery of this amount. Alleging deficiency in service and unfair trade practices by the opposite parties, the complainant sought withdrawal of the disputed bill, compensation of Rs. 20,000/- for mental agony, and Rs. 5,500/- for litigation expenses.

The opposite parties responded by denying any deficiency in service, asserting that the complainant had not paid electricity consumption charges for a long period, leading to accumulation of arrears. They claimed that Rs. 46,399/- of the disputed amount related to a difference in meter readings as per audit findings and represented actual consumption since November 2015. The opposite parties raised preliminary objections and denied the allegations on merits.

Both parties tendered evidence, after which the matter was heard and reviewed by the court.

Legal Issues Presented

  1. Whether the disputed electricity bill dated 16.02.2017 for Rs. 97,950/- was lawful and correctly raised by the opposite parties.
  2. Whether the opposite parties followed the prescribed procedures under the P.S.P.C.L. regulations for removal, sealing, and testing of the electric meter before raising additional charges.
  3. Whether the opposite parties were justified in charging arrears without issuing a separate bill or notice detailing the charges.
  4. Whether the complainant is liable to pay the disputed amount based on the audit report and meter readings.

Arguments of the Parties

Complainant's Arguments

  • The bill dated 16.02.2017 for Rs. 97,950/- is incorrect and illegal.
  • The complainant has never committed electricity theft.
  • No notice or supplementary bill detailing the disputed amount was issued by the opposite parties.
  • The opposite parties failed to follow regulations regarding removal, packing, sealing, and testing of the electric meter in the presence of the complainant or his representative.
  • Reliance on Regulation 93 of the Electricity Supply Instruction Manual which mandates separate bills and notices for arrears and prohibits recovery after two years unless continuously shown as arrears.
  • Reference to case law: Uttar Haryana Bijli Vitran Nigam Limited & Others Vs Dinesh Sharma (2016 (2) Consumer Law Today 429), holding that sundry charges cannot be imposed without a show cause notice.
  • Reference to case law: Punjab State Electricity Board and another Vs Ashwani Kumar (1993 (2) PLR 447), emphasizing the requirement of notice before imposing penalty.

Opposite Parties' Arguments

  • There is no deficiency in service on their part.
  • The complainant suppressed material facts and has not paid electricity consumption charges for a long time, leading to accumulation of arrears.
  • Rs. 46,399/- was charged based on audit findings reflecting actual consumption since November 2015.
  • Preliminary objections were raised that complicated questions of law and fact are involved and the complaint is false and frivolous.
  • Denied the allegations made by the complainant on merits.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Uttar Haryana Bijli Vitran Nigam Limited & Others Vs Dinesh Sharma, 2016 (2) Consumer Law Today 429 Requirement of issuing a show cause notice before imposing sundry charges in electricity bills; deficiency in service if not followed. The court relied on this precedent to hold that the opposite parties failed to issue any notice before charging the disputed amount, constituting deficiency in service.
Punjab State Electricity Board and another Vs Ashwani Kumar, 1993 (2) PLR 447 Notice is required before imposing penalty and an opportunity to the affected person. The court referred to this case to emphasize that the opposite parties did not comply with procedural requirements of notice before charging penalty or arrears.

Court's Reasoning and Analysis

The court analyzed the evidence and submissions of both parties. It found that the opposite parties failed to produce evidence showing that the electric meter was removed, packed, sealed, and tested in the presence of the complainant or his representative, as required under the P.S.P.C.L. regulations. The court noted that the procedures detailed in Regulation 55 for meter replacement and testing were not adhered to.

Further, the court observed that the opposite parties did not issue any separate or supplementary bill or notice detailing the disputed arrears, contrary to Regulation 93 of the Electricity Supply Instruction Manual, which mandates issuance of separate bills with complete details and relevant instructions for arrears and supplementary charges.

The court relied on binding precedents holding that imposing sundry charges without prior notice or opportunity to the consumer constitutes deficiency in service. The opposite parties’ failure to comply with these procedural safeguards led the court to conclude that the disputed charges were not recoverable as claimed.

Holding and Implications

The complaint is allowed.

The opposite parties are directed to overhaul the complainant’s account, withdraw the demand of Rs. 46,399/- relating to the difference of meter readings, and correct the bill accordingly. They are further directed to adjust the amount of Rs. 40,000/- already deposited by the complainant in subsequent bills. Compliance with this order is to be made within one month from receipt of the order. Failure to comply entitles the complainant to proceed under Sections 25 and 27 of the Consumer Protection Act.

The decision directly affects the parties by mandating correction of the disputed bill and refund/adjustment of amounts paid. No new legal precedent beyond the application of existing regulations and case law is established.

To access the original judgment, please Sign In or Subscribe.

    Tehal Singh v. Punjab State Power Corporation Limited

    AJIT AGGARWAL PRESIDENT:- Brief facts of the complaint are that an electric meter connection bearing account No.M53GT530039H has been installed in the house of the complainant and has been paying the electricity bills regularly to the opposite parties. It has been pleaded that the complainant received a bill dated 16.02.2017 for Rs.97,950/, which is wrong and illegal. It has been pleaded that the complainant never committed any theft of electricity. The opposite parties have not issued any notice regarding recovery of any amount from the complainant. Pleading deficiency in service and unfair trade practice on the part of the opposite parties, the complainant has prayed that the opposite parties be directed to withdraw the above said bill, to pay Rs.20,000/- as compensation for mental agony, pain and harassment and Rs.5500/- as litigation expenses.

    2. Upon notice, the opposite parties appeared and filed their joint written reply to the complaint raising certain preliminary objections interalia that there is no deficiency in service on the part of the opposite parties; that the complainant has suppressed the material facts from this Forum. The complainant has not paid the consumption charges of the electricity consumed by him since long and the arrears as such has been accumulating; that Rs.46,399/- was charged from the complainant on account of difference of reading in the ledger and the reading as per store challan on account of D-code. The said amount was charged by the Audit vide half margin No.52, resultantly the amount challenged in the present complaint pertains to the actual units of consumption of electricity since November 2015 and the complainant is liable to pay the said amount as per rules and instructions; that complicated question of law and facts are involved in the present complaint and that the present complaint is false and frivolous. On merits the preliminary C.C. No.137 of 2017 //3// objections have been reiterated and the other allegations of the complaint have been denied.

    3. Learned counsel for the complainant tendered into evidence Ex.C-1 to Ex.C-2 and closed evidence on behalf of the complainant. On the other hand, learned counsel for opposite parties tendered into evidence Ex.OPs/1 to Ops/3 and closed evidence on behalf of opposite parties.

    4. We have heard the learned counsel for the parties and have also gone through the file.

    5. The complainant has challenged bill dated 16.02.2017 Ex.C-2 for Rs. 97,950/-. The plea of the opposite parties is that the complainant has not paid the consumption charges of the electricity consumed by him since long and the arrears has been accumulating. Rs.46,399/- was charged from the complainant on account of difference of reading in the ledger and the reading as per store challan on account of D-code. The said amount was charged by the Audit vide half margin No.52, resultantly the amount challenged in the present complaint pertains to the actual units of consumption of electricity since November 2015 and the complainant is liable to pay the said amount as per rules and instructions.

    6. The opposite parties have not produced any evidence to show that the electric meter of the complainant was removed, packed and sealed in the presence and under signatures of the complainant or his representative and the electric meter was never checked in the M.E. Lab in the presence of the complainant or his representative. Therefore, it is crystal clear that no procedure has been adopted by the opposite parties framed under the Rules and Regulations of the P.S.P.C.L. regarding removing, packing, sealing and checking of the defective electric meter C.C. No.137 of 2017 //4// in the M.E. Lab and thereafter raising the demand arising out of the said checking, if any.

    7. As per regulations no.55. Replacement of Meters/Metering Equipment : 55.1 Single Phase Electromechanical Meters : E/M Meters removed from the consumer premises on replacement with the electronic meters shall be returned to M E Labs without any other formality and ME Labs will not carry out any checking/testing of these meters except in case of disputed meters. In case of disputed meters removed under code G, M & R (glass broken, meter burnt & ME seals broken) and in cases where there is sufficient evidence of theft /tampering etc at the time of removal, the JE concerned shall record his observation on the MCO itself and such meters shall be packed and sealed in the presence of consumers for further checking in M E Labs in his presence. Further as per regulation no. 21.4 (d) : In case of testing of a meter removed from the consumer premises in the Licensees laboratory, the consumer would be informed of the proposed date of testing atleast seven days in advance. The signature of the consumer, or his authorized representative, if present would be obtained on the Test Result Sheet and a copy thereof supplied to consumer.

    8 He further argued that moreover, as per their own regulations, OPs can not charges the dues relating to previous period without issuing a separate bill giving complete detail of the charges levied. Copy of relevant instructions in which the charges have been levied should also be supplied to consumer but in the present case, no separate bill or notice giving complete detail of the amount charged or period of the amount ever issued to the complainant. So, as per their own regulations and instructions, OPs can not demand this amount and can not add this amount in current in current bill. The Ld Counsel for complainant produced C.C. No.137 of 2017 //5// copy of Electricity supply Instruction Manual of OPs where regulation no. 93 is regarding payment of arrears not originally billed. Relevant regulations is reproduced hereunder: Payment of Arrears not Originally Billed : 93.1 There may be certain cases where the consumer is billed for some of the dues relating to previous months/years or otherwise as arrears on account of under assessment/unauthorized use of electricity or demand / load surcharge pointed out by Internal Auditor/ detected by the authorized officers either owing to negligence of the PSPCL employees or due to some defect in the metering equipment or due to application of wrong tariff/ multiplication factor or due to mistake in connection or other irregularities/malpractices etc. In all such cases, separate bills shall be issued giving complete details of the charges levied. Such charges shall be shown as arrears in the subsequent electricity bills regularly till the payment is made. Supplementary bills shall be issued separately giving complete details of the charges in regard to theft cases, slowness of meters, wrong connection of the meter and unauthorized use of electricity etc. In such cases, the copy of relevant instructions under which the charges have been levied shall also be supplied to the consumer for facilitating the quick disposal of cases by consumer forums if approached by the consumer. 93.2 Limitation: Under Section 56(2) of the Act, no sum due from any consumer shall be recoverable after the period of two year from the date when such sum became first due unless such sum has been shown continuously as recoverable as arrears of charges for electricity supplied. C.C. No.137 of 2017 //6//

    9 The complainant further put reliance on citation 2016 (2) Consumer Law Today 429 titled as Uttar Haryana Bijli Vitran Nigam Limited & Others Vs Dinesh Sharma, wherein it is held that Electricity-Sundry charges can not be charged without show cause notice to complainant. Consumer Protection Act, 1986, Section 2(1)(g)-electricity-Sundry charges added in electricity bill of complainant-Held-NO show cause notice issued to the complainant before imposing penalty-OPs have miserably failed to show that provisional assessment made on the basis of audit report was ever served upon the complainant-In this way, they did not act as per provisions contained in the Electricity Act and it is deficiency in service-Consumer can ask the service provider to give him the details on the basis of which the demand is made, which is not in the present case. Para 7- The appellants have failed to show any notice issued to the complainant before imposing the penalty. Our Honble High Court has also opined in Punjab State Electricity Board and another Vs Ashwani Kumar 1993 (2) PLR 447 that notice is required before imposing the penalty and an order about person who was likely to be affected thereby. In the present case, the appellants OPs have miserably failed to show that previous reading of defective meter was correct. In this way, they did not act as per provisions contained in the electricity Act and it is deficiency in service. Consumer can ask the service provider to give him the details on the basis of which the demand is made, which is not in the present case.

    10 Further as per their own regulations and instructions, OPs can not charge any amount of previous dues or arrears without giving any supplementary bill or notice giving complete detail of charges and also giving copy of relevant instructions in which the charges have been levied. They can not demand the arrear in the current bill as sundry charges and in the present case, the OPs have failed to C.C. No.137 of 2017 //7// produce any evidence or document which proves that they issued any supplementary bill or notice giving complete and full detail of the amount charged by them as arrears of consumption as alleged by them.

    11 Therefore, from the above discussion, we are fully convinced with the arguments and case law produced by complainant and hence, complaint in hand is hereby allowed. Ops are directed to overhaul the account of complainant and withdraw the demand of Rs.46,399/- as difference of reading of old meter and correct the bill and OPs are further directed to adjust the amount or Rs.40,000/- deposited by complainant with Ops vide order dated 2.3.2017 of this Forum in the subsequent bills. Compliance of this order be made within one month of receipt of the copy of the order, failing which complainant shall be entitled to proceed under Section 25 and 27 of the Consumer Protection Act. Copy of order be supplied to parties free of cost as per law. File be consigned to record room. Announced (Ajit Aggarwal) 4.01.2018 President (Baldev Singh Bhullar) Member