Contains public sector information licensed under the Open Justice Licence v1.0.
Pearce Brothers v. Irons
Factual and Procedural Background
The dispute arose from a contract between Company A, machine-makers and engineers, and Defendant, a millowner, concerning the supply and installation of machinery, including a 40-horsepower horizontal condensing engine and associated gearing. The contract, initially valued at £800 with staged payments, was later altered, resulting in a balance claim of £756 by Company A, eventually settled by a single bill for £400. The machinery was installed and operated for about fourteen months but did not work satisfactorily, exhibiting rough operation and ultimately resulting in the breakage of a pinion.
Company A made repeated attempts to remedy the defects, but the pinion broke. A new pinion was installed by Company A, and they sought to recover the cost of £97, 18s. 8d. from Defendant. Defendant contested this charge, arguing that the original pinion was defective and that Company A was liable for the replacement cost. The Sheriff-substitute remitted the question of the pinion's sufficiency to a skilled reporter, who found the original pinion defective due to improper sizing. The Sheriff and subsequently the Sheriff upheld this finding on appeal. Company A challenged the competency of the remit and the reporter's evidence, arguing for a full proof on liability issues. The court ultimately upheld the remit and the findings of the reporter.
Legal Issues Presented
- Whether Defendant was liable to pay for the replacement pinion given the alleged defects in the original pinion supplied by Company A.
- Whether the interlocutor remitting the matter to a skilled reporter was competent and binding, particularly regarding the mode of proof.
- Whether Defendant’s prior payment of the contract balance barred him from challenging the sufficiency of the original machinery.
Arguments of the Parties
Appellant's (Company A) Arguments
- The report of the skilled reporter was incompetent because it was based on evidence rather than solely on the reporter’s independent skill and examination.
- The interlocutor remitting to the reporter was incompetent insofar as it authorized taking evidence.
- Defendant, having accepted and paid for the original machinery, was barred from pleading its insufficiency.
- They sought to set aside the report and have a full proof on the liability issues, arguing that there were averments on record not remitted to probation.
Respondent's (Defendant) Arguments
- The payment of the balance did not bar Defendant from contesting the defects because the machinery was still under observation and being remedied when payment was made.
- The remit to the skilled reporter was proper and effectively “of consent,” binding the parties to that mode of proof.
- The reporter’s findings, based on examination and information from parties, were entitled to full weight as the opinion of a man of skill.
- Company A was liable for the replacement pinion because the original was defective due to improper size and pitch, causing its breakage.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The court analysed the nature of contracts for machinery, distinguishing them from simple sales of goods by emphasizing that machinery must be tested in operation before its sufficiency can be assessed. The court accepted that Defendant’s payment of the contract balance did not preclude him from later asserting defects, as the machinery was still undergoing adjustments and observation.
The court found that the remit to a skilled reporter was proper and binding, even though the interlocutor was not expressly stated to be “of consent.” The court held that the absence of explicit wording did not undermine the remit’s consent nature, which could be inferred from the circumstances and conduct of the parties, including their failure to object or appeal the mode of proof at earlier stages.
The court gave weight to the reporter’s findings, who had conducted a reasonable inquiry including questioning the parties. The reporter concluded that the original pinion was defective due to its excessive diameter and pitch, causing rough operation and eventual breakage. This defect rendered Company A liable for the replacement pinion’s cost.
The court rejected Company A’s request for a full proof on liability, holding that such a course would contradict established precedents. The court affirmed the findings of the Sheriff-substitute and Sheriff, except for a part of the interlocutor concerning the condition of the new pinion, which was beyond the pleadings.
Holding and Implications
The court held that Defendant was not liable for the expense of installing the new pinion because the original pinion broke due to defects attributable to Company A. The prior payment of the contract balance by Defendant did not bar him from asserting this liability.
The interlocutor remitting the matter to a skilled reporter was effectively “of consent,” binding the parties to the mode of proof fixed thereby, and Company A was not entitled to reject the reporter’s findings or seek a full proof on the issues of liability.
The decision directly affects the parties by denying Company A’s claim for the replacement pinion cost and confirms the procedural propriety of remitting technical questions to a skilled reporter with binding effect. No new legal precedent was established beyond reaffirming existing principles on remits and machinery contracts.
Please subscribe to download the judgment.

Comments