Huntaven Properties Ltd v. Hunter Construction (Aberdeen) Ltd & Ors

Smart Summary

Factual and Procedural Background

The case concerns defects in an external concrete hardstanding constructed as part of a project, involving several parties contracted to design, inspect, and carry out remedial works. The defects included delamination, spalling, potholes, and fibre balling, which were identified following inspections in 2009 and 2010. The pursuer issued a notice in March 2010 under the contract’s defect liability provisions, requiring remedial work. The first defender accepted responsibility for the defects and carried out remedial works between August and November 2010, which initially appeared effective. However, deterioration reoccurred by May 2011.

The pursuer brought a preliminary proof before answer focusing on prescription (statute of limitations) issues without addressing the full merits of the breach of contract or negligence claims. The pursuer alleged breaches of contract and concurrent delictual faults against the first, third, and fourth defenders related to defective design, inadequate mixing and specification of concrete, and failure to specify air entrainment, which contributed to the slab’s deterioration.

Legal Issues Presented

  1. Whether the obligations to make reparation for the alleged breaches had prescribed under the Prescription (Scotland) Act 1973.
  2. When the obligations to make reparation became enforceable, specifically the date of concurrence of injuria (wrongful act) and damnum (loss or damage).
  3. Whether any error induced by the defenders or relevant acknowledgements postponed the running of the prescriptive period.
  4. The effect of continuing acts, neglects, or defaults on the computation of the prescriptive period.
  5. Whether the pursuer had actual or constructive knowledge of the loss and the cause of the defects within the prescriptive period.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Strathclyde Regional Council v W A Fairhurst & Partners 1997 SLT 658 Assessment of material loss, injury, or damage for prescription purposes. Used to determine that defects in September 2009 constituted material damage, not trivial or negligible.
Pelagic Freezing (Scotland) Limited v Lovie Construction Limited [2010] CSOH 145 Effect of defects liability period on the accrual of cause of action and prescription. Rejected the argument that defects liability period postpones injuria and damnum; defects were actionable before expiry of that period.
Stewart Milne Westhill Limited v Halliday Fraser Munro [2016] CSOH 76 Assessment of material damage and knowledge for prescription. Supported the view on when material damage occurred and the pursuer’s knowledge thereof.
ANM Group Limited v Gilcomston North Limited 2008 SLT 835 When injuria arises in construction contracts and effect of contractual remedies on prescription. Distinguished in this case; contractual remedies do not postpone accrual of cause of action.
Westminster Corporation v J Jarvis & Sons Ltd [1970] 1 WLR 637 Definition of practical completion in construction contracts. Applied to interpret practical completion as completion of all construction work for the phase.
Musselburgh & Fisherrow Co-operative Society Ltd v Mowlem Scotland Ltd 2004 SCLR 412 Identification of specific breaches for prescription calculation. Used to emphasize the need to identify particular breaches rather than general duties.
Jackson v Clydesdale Bank plc 2003 SLT 273 Effect of contractual remedies on common law rights and prescription. Confirmed that contractual remedies do not exclude common law claims or affect prescription.
David T Morrison & Co Ltd (t/a Gael Home Interiors) v ICL Plastics Ltd 2014 SC (UKSC) 222 Awareness of loss for prescription under s. 11(3) of the Prescription Act. Clarified that only awareness of loss is required, not awareness of actionable cause.
Gordon v Campbell Riddell Breeze Paterson LLP 2016 SC 548 Prescription and knowledge of loss. Supported the principle that knowledge of loss triggers the prescriptive period.
Heather Capital Limited (In Liquidation) and Duffy v Levy & McRae; Heather Capital Limited (In Liquidation) and Duffy v Burness Paull LLP Effect of induced error on prescription periods. Applied to determine periods excluded from prescription due to error induced by defenders' conduct.

Court's Reasoning and Analysis

The court analyzed the timing and nature of the defects and the pursuer’s knowledge to determine when the obligations to make reparation became enforceable. It held that material damage occurred by September 2009 (polishing, spalling, cement removal) and certainly by January/February 2010 (delamination and fibre balling). The court rejected the pursuer’s submission that no damnum occurred before the completion of remedial work in November 2010, holding that latent defects and their physical manifestations constituted actionable damage at earlier dates.

The court distinguished between general contractual obligations and specific breaches, emphasizing that the acts or omissions constituting breaches were complete by practical completion of the relevant project phase, not continuing through the defects liability period. It held that remedial works under Clause 17.2 constituted separate obligations.

Regarding prescription, the court applied the Prescription (Scotland) Act 1973, sections 6, 10, and 11, considering whether the pursuer had actual or constructive knowledge of loss and whether any error induced by defenders postponed the prescriptive period. It found that the pursuer was aware of material damage by October 2009 and February 2010 but did not know the precise causes until later. The court held that the pursuer could not with reasonable diligence have discovered the absence of air entrainment and fibre over-abundance earlier than July 2010.

The court examined the conduct of the defenders to determine if error was induced, excluding periods from prescription. It found that the first defender’s words and conduct between April and July 2010 induced error, delaying the start of prescription for certain obligations. It rejected similar submissions against the third and fourth defenders, finding no inducement of error by their conduct.

The court also considered whether the first defender’s involvement in remedial works constituted relevant acknowledgment of obligations, concluding that only the obligation related to fibre mixing (failure (i)) was acknowledged, preserving that claim from prescription.

Finally, the court rejected the pursuer’s alternative submission that damnum occurred at slab construction, holding instead that latent defects existed then but actionable damage arose only with physical manifestation.

Holding and Implications

The court’s decision was as follows:

  • The obligation to make reparation against the first defender for failure to properly mix and spread fibres (failure (i)) has not prescribed. Although the obligation arose by February 2010, error induced by the first defender between April and July 2010 delayed prescription, and relevant acknowledgment through remedial works in 2010 preserved the claim.
  • The obligations to make reparation against the first defender for failure to warn about absence of air entrainment and for defective design (failures (ii) and (iii)) have prescribed. These obligations became enforceable by October 2009 and subsisted for more than five years without relevant acknowledgment.
  • The obligation to make reparation against the first defender for breach of Clause 17.2 (defects liability) has not prescribed. It became enforceable in November 2010, less than five years before the claim.
  • The obligations to make reparation against the third and fourth defenders have prescribed. These arose by October 2009 and subsisted for more than five years without relevant acknowledgment.

The court put the case out by order to discuss the appropriate interlocutor to give effect to this decision and any further procedure.

No new precedent was established; the decision applies established principles of prescription and contract interpretation to the facts of defective construction and remedial works.

To access the original judgment, please Sign In or Subscribe.

Huntaven Properties Ltd v Hunter Construction (Aberdeen) Ltd & Ors

Contains public sector information licensed under the Open Justice Licence v1.0.