Dwr Cymru Cyfyngedig (Welsh Water) v. Corus UK Ltd

Smart Summary

Factual and Procedural Background

This appeal concerns part of an order made by Judge Hart on an application by the Plaintiff, Company A, for summary judgment under CPR rule 24.2. The claim relates to amounts alleged to be due from the Defendant, Company B, in respect of the supply of non-potable water to its steelworks between 1st April 2004 and 31st March 2006.

The appeal focuses on the interpretation of an agreement made on 20th December 1993 ("the 1993 Agreement") between Company A and British Steel plc, the predecessor of Company B, for the supply of water to the steelworks. The issue concerns whether the contractual provisions in the 1993 Agreement continued to govern the supply and charging after the agreement’s expiry on 31st March 2004, or whether statutory provisions and subsequent charges schemes applied.

Legal Issues Presented

  1. Whether clause 17 of the 1993 Agreement was intended to have contractual effect, creating rights and obligations between the parties after 31st March 2004.
  2. If clause 17 has contractual effect, whether it provides a workable mechanism for determining the terms of supply, particularly charges, after the agreement’s expiry.
  3. Whether the statutory powers of the Director General of Water Services (or successor Authority) under sections 55 and 56 of the Water Industry Act 1991 apply to the supply after 31st March 2004.
  4. Whether the introduction by Company A of a charges scheme for non-potable water from 1st April 2004 was consistent with the 1993 Agreement or constituted a breach of contract.
  5. Whether, if the contractual mechanism for determining terms fails, the court can enforce the contract by determining reasonable terms itself.

Arguments of the Parties

Plaintiff's Arguments

  • Clause 17 does not confer contractual rights after 31st March 2004 but merely reflects the statutory position under the Water Industry Act 1991.
  • The reference to the Director determining terms in clause 17 acknowledges the Director’s powers under the statute, which do not extend to determining charges if a charges scheme is in place.
  • The parties did not intend to provide for continued contractual supply after expiry; rather, water supply would continue under statutory provisions.
  • The introduction of a charges scheme by Company A was lawful and did not breach the Agreement.
  • Even if clause 17 has contractual effect, the Director’s power to determine terms is statutory and limited; without that power, the contractual mechanism fails and is unenforceable.

Defendant's Arguments

  • Clause 17 was intended to have contractual effect, providing a right to continued supply on terms to be agreed or determined by the Director.
  • The 1993 Agreement is a successor to an earlier agreement that included a renewal right, evidencing intention for continued contractual supply.
  • The supply of water pursuant to the contract involves a request under section 55 of the Water Industry Act, so the Director has power to determine terms under section 56.
  • Company A’s introduction of a charges scheme that interferes with the agreed mechanism breaches the contract.
  • If the Director lacks power to determine terms due to the charges scheme, Company A is liable for breach of contract damages.
  • If the contract’s mechanism fails, the court can determine reasonable terms to give effect to the parties’ intentions.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sudbrook Trading Estate Ltd v Eggleton [1983] 1 A.C. 444 Contractual mechanism failure does not necessarily render an agreement unenforceable if the court can ascertain reasonable terms. Used to support the possibility that the court could determine reasonable terms where the contractual mechanism fails, although no final decision was reached on this point.

Court's Reasoning and Analysis

The court began by considering whether clause 17 of the 1993 Agreement was intended to have contractual effect. It rejected the Plaintiff’s argument that clause 17 merely described the statutory position, reasoning that the inclusion of an entire clause with binding language (“shall continue to have the right”) suggested an intention to create contractual rights and obligations beyond the expiry date.

The court analysed the statutory framework under the Water Industry Act 1991, particularly sections 55 and 56, which govern non-domestic water supplies and the Director’s powers to determine terms where parties fail to agree. It found that the supply under the Agreement fell within section 55(1), and thus the Director had power to determine terms under section 56(1)(b), as assumed by the parties.

The court noted that sections 142 and 143 allow water undertakers to make charges schemes and enter into individual agreements. However, section 56(5)(a) restricts the Director’s power to determine charges if a charges scheme is in place at the time of the request. The court held that the relevant request for supply was made before any charges scheme was introduced, meaning the Director retained power to determine charges under the Agreement.

The court concluded that Company A’s introduction of a charges scheme that interfered with the agreed mechanism for determining charges would amount to a breach of contract. If the Director’s power were lost due to the charges scheme, Company A would be liable for damages to Company B.

Finally, the court considered whether the failure of the contractual mechanism would render the Agreement unenforceable. While acknowledging the difficulty due to many terms being left undecided, it did not exclude the possibility that the court could determine reasonable terms with expert assistance, but found it unnecessary to decide this as the earlier conclusions resolved the appeal.

Holding and Implications

The court ALLOWED THE APPEAL.

The holding establishes that clause 17 of the 1993 Agreement was intended to have contractual effect, entitling the Defendant to continued water supply on terms to be agreed or determined by the Director under the statutory framework. The Plaintiff’s unilateral introduction of a charges scheme interfering with this mechanism constituted a breach of contract. The Defendant is thus entitled either to have charges determined under the agreed mechanism or to recover damages for breach if the mechanism is frustrated.

No new precedent was set beyond the application of established principles of contract construction and statutory interpretation. The decision clarifies the interplay between contractual renewal clauses and statutory regulatory schemes in the context of water supply agreements.

To access the original judgment, please Sign In or Subscribe.

Dwr Cymru Cyfyngedig (Welsh Water) v Corus UK Ltd

Contains public sector information licensed under the Open Justice Licence v1.0.

Use AI to get other relevant cases.

Comments

Dwr Cymru Cyfyngedig (Welsh Water) v Corus UK Ltd
(Mar 30, 2007)