Per contra the Learned Counsel for the Defendant argued that delivery of the goods could not be made for reasons beyond control. It is a case of failure to perform contractual obligation because of supervening events beyond control resulting in frustration of contract. The Learned Counsel relied upon the principle of law laid down in Satyabrata Ghosh vs Mugneeram Bangur & Co. and Ors.
(AIR 1954 SC 44).
There was a time when contractual duties were regarded as absolute. There was no excuse for any supervening event which made contractual performance impossible. In Paradine vs Jane [(1647) Aleyn 26], this principle was expounded by a British Court. It was decided that when a party by his own contract creates a duty or charge upon himself, he is bound to make it good, if he may, notwithstanding any accident by inevitable necessity, because he might have been provided against it by his contract. The doctrine of absolute contract probably never applied where a contract called for personal performance by a party who died or was permanently incapacitated. Another early exception to it was recognised in cases of supervening illegality. In Taylor vs Caldwell [(1863) 3 B. & S. 826] Blackburn,
9
J, relied on the first exception as bases for formulating the general rule of discharge which became known as the doctrine of frustration. Owing its genesis in Taylor vs Caldwell, this doctrine of frustration entered into its growth in subsequent period. In Krell vs Henry [(1903) 2 K.B 740] the doctrine was further expounded and applied to cases where the event which renders the contract in capable of performance is the cessation or non-existence of an express condition or state of things, going to the root of the contract and essential to its performance. In India, the doctrine of frustration is embodied in section 56 of the Indian Contract Act, 1872. The section states:
".56. Agreement to do impossible act. -An agreement to do an act impossible in itself is void.
Contract to do an act afterwards becoming impossible or unlawful.—A contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful.1
Compensation for loss through non-performance of act known to be impossible or unlawful.—Where one person has promised to do something which he knew, or, with reasonable diligence, might have known, and which the promisee did not know, to be impossible or unlawful, such promisor must make compensation to such promisee for any
10
loss which such promisee sustains through the non- performance of the promise."
In Satyabrata Ghose v. Mugneeram Bangur & Co.,[(1953) 2 SCC 437], B.K. Mukherjee, J, speaking for three Judges' Bench, explained that the first paragraph of the section lays down the law in the same way as in England. It speaks of something which is impossible inherently or by its very nature, and no one can obviously be directed to perform such an act. The second paragraph enunciates the law relating to discharge of contract by reason of supervening impossibility or illegality of the act agreed to be done. The wording of this paragraph is quite general, and though the illustrations attached to it are not at all happy, they cannot derogate from the general words used in the enactment. This much is clear that the word "impossible" has not been used here in the sense of physical or literal impossibility. The performance of an act may not be literally impossible but it may be impracticable and useless from the point of view of the object and purpose which the parties had in view; and if an untoward event or change of circumstances totally upsets the very foundation upon which the parties rested their bargain, it can very well be said that the promissor finds it impossible to do the act which he promised to do. It is further explained as follow:
"17. In the large majority of cases however the doctrine of frustration is applied not on the ground that the parties themselves agreed to an implied term which operated to release them from the performance of the contract. The relief is given by the court on the ground of subsequent impossibility when it finds that the whole purpose or basis of a contract was
11
frustrated by the intrusion or occurrence of an unexpected event or change of circumstances which was beyond what was contemplated by the parties at the time when they entered into the agreement. Here there is no question of finding out an implied term agreed to by the parties embodying a provision for discharge, because the parties did not think about the matter at all nor could possibly have any intention regarding it. When such an event or change of circumstance occurs which is so fundamental as to be regarded by law as striking at the root of the contract as a whole, it is the court which can pronounce the contract to be frustrated and at an end. The court undoubtedly has to examine the contract and the circumstances under which it was made. The belief, knowledge and intention of the parties are evidence, but evidence only on which the court has to form its own conclusion whether the changed circumstances destroyed altogether the basis of the adventure and its underlying object [Morgan v. Manser, (1948) 1 KB 184] . This may be called a rule of construction by English Judges but it is certainly not a principle of giving effect to the intention of the parties which underlies all rules of construction. This is really a rule of positive law and as such comes within the purview of Section 56 of the Contract Act."
It was also explained that if the parties do contemplate the possibility of an intervening circumstance which might affect the performance of the contract, but expressly stipulate that the contract would stand despite such circumstance, there can
12
be no case of frustration because the basis of the contract being to demand performance despite the happening of a particular event, it cannot disappear when that event happens.
In Naihati Jute Mills Ltd. v. Khyaliram Jagannath (AIR 1968 SC
522) the doctrine was again considered by the three Judges' Bench of the Supreme Court of India. In the language of the Court:
"5. Section 56 of the Contract Act inter alia provides that a contract to do an act which, after the contract is made becomes impossible, or by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful. It also provides that where one person has promised to do something which he knew, or, with reasonable diligence might have known, and which the promisee did not know to be impossible or unlawful, such a promisor must make compensation to such promisee for any loss which such promisee sustains through the non- performance. As envisaged by Section 56, impossibility of performance would be inferred by the courts from the nature of the contract and the surrounding circumstances in which it was made that the parties must have made their bargain upon the basis that a particular thing or state of things would continue to exist and because of the altered circumstances the bargain should no longer be held binding. The courts would also infer that the foundation of the contract had disappeared
13
either by the destruction of the subject-matter or by reason of such long interruption or delay that the performance would really in effect be that of a different contract for which the parties had not agreed. Impossibility of performance may also arise where without any default of either party the contractual obligation had become incapable of being performed because the circumstances in which performance was called for was radically different from that undertaken by the contract."
Coming to the case in hand, the letter dated 26th
July, 2000 (Ext.-K), the Defendant terminated the agreement on plea of labour problem and strike. In the written statement plea was taken that chimney of the Defendant's factory was damaged and some labour trouble also cropped up. On account of these intervening events beyond control of the Defendant stipulated T.N. Shellac could not be supplied and the Defendant expressed inability to give effect to the proposal of the Plaintiff. The Defendant adduced evidence to show that chimney and boiler of the factory broken down disabling them to supply. It is not the Plaintiff's case that these incidents were forceable and existed at the time of making of the contract or acceptance of the proposal. It is in the evidence of D.W.1 that because of breakdown of chimney and boiler in the factory, production became standstill, consequently stipulated supply of T.N. Shellac could not be made. Evidence shows that running and working of chimney and boiler are so essential for production that break-down of the same disabled the Defendant to perform its part of contract.
14
In Dhanrajamal Gobindram v. Shamji Kalidas & Co., (AIR 1961 SC 1285) the Supreme Court of India considered the issue of force majeure. It was explained:
"17. McCardie, J. in Lebeaupin v. Crispin [(1920) 2 KB 714] has given an account of what is meant by "force majeure", with reference to its history. The expression "force majeure" is not a mere French version of the Latin expression "vis major". It is undoubtedly a term of wider import. Difficulties have arisen in the past as to what could legitimately be included in "force majeure". Judges have agreed that strikes, breakdown of machinery, which, though normally not included in "vis major" are included in "force majeure". An analysis of rulings on the subject into which it is not necessary in this case to go, shows that where reference is made to "force majeure", the intention is to save the performing party from the consequences of anything over which he has no control. This is the widest meaning that can be given to "force majeure", and even if this be the meaning, it is obvious that the condition about "force majeure" in the agreement was not vague. The use of the word "usual" makes all the difference, and the meaning of the condition may be made certain by evidence about a force majeure clause, which was in contemplation of parties."
Break down of machineries are included in force majeure, as observed above. It is neither alleged nor in evidence that break down of machineries was a ploy of
15
the Defendant to avoid contractual obligation. Therefore, from the facts and circumstances of the case and material evidences, it is clear that the Defendants were prevented from supplying stipulated T.N. Shellac by supervening circumstances beyond control. This is a case of frustration of contract, as contemplated in section 56 of the Indian Contract Act, 1872 and not a case of breach of contract.
Issue No.3 is decided in favour of the Defendant.
Issue No.4, 5 and 6 are taken up together. As discussed and concluded above, this is a case of frustration of contract and the contract is void. Under section 65 of the Act, when an agreement is discovered to be void, or when a contract becomes void, any person who has received any advantage under such agreement or contract is bound to restore it, or to make compensation for it to the person from whom he received it. In Kuju Collieries Ltd. v. Jharkhand Mines Ltd., [(1974) 2 SCC
533] it was explained that the second part of the section refers to a contract becoming void. That refers to a case where an agreement which was originally enforceable and was, therefore, a contract, becomes void due to subsequent happenings. In both these cases any person who has received any advantage under such agreement or contract is bound to restore such advantage, or to make compensation for it to the person from whom he received it. In South East Asia Marine Engg. & Constructions Ltd. (SEAMEC LTD.) v. Oil India Ltd., (2020) 5 SCC 164, it has been succinctly elucidated by three Judges Bench of the Supreme Court of India that when the parties have not provided for what would take place when an event which renders the performance of the contract impossible, then Section 56 of the Contract Act applies. When the act contracted for becomes
16
impossible, then under Section 56, the parties are exempted from further performance and the contract becomes void. With reference to section 65 of the Indian Contract Act, 1872, it was observed:
"23. In India, the Contract Act, 1872 had already recognised the harsh consequences of such frustration to some extent and had provided for a limited mechanism to ameliorate the same under Section 65 of the Contract Act, 1872. Section 65 provides as under:
"65. Obligation of person who has received advantage under void agreement, or contract that becomes void.—When an agreement is discovered to be void, or when a contract becomes void, any person who has received any advantage under such agreement or contract is bound to restore it, or to make compensation for it, to the person from whom he received it."
The aforesaid clause provides the basis of restitution for "failure of basis".
We are cognizant that the aforesaid provision addresses limited circumstances wherein an agreement is void ab initio or the contract becomes subsequently void."
17
Issue No.4, 5 and 6 are, therefore, decided against the Plaintiff. On hearing rival submissions and appreciation of material evidences and for reasons discussed above this Court is of opinion that the instant suit of the Plaintiff fails on merit and is liable to be dismissed.
Hence, it is ordered that the instant suit is dismissed on merit without cost on merit.
The instant suit is disposed of along with pending applications.
(Sugato Majumdar, J.)