AMICUS AI
Citation Codes
Neutral Citations
2022 DHC 1184
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 17 of the Act
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Neutral Citations
2022 DHC 1184
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Judges
Acts
  • Section 17 of the Act
Smart Summary

Factual and Procedural Background

The Petitioner was awarded a contract on 27th May 2019 for various construction works related to a new crossing station at Dobh. The Petitioner furnished a Performance Bank Guarantee (PBG) equivalent to 5% of the contract amount issued by Bank of Baroda. The contract stipulated a six-month completion period, but the Petitioner alleged delays caused by the Respondent in handing over the site and failure to provide necessary working drawings, preventing timely completion.

Respondent issued notices invoking Clause 62 of the General Conditions of Contract (GCC) for termination of the contract on 15th July 2019 and 1st August 2019, followed by termination on 9th August 2019. The Petitioner initially sought a stay on termination and invocation of the PBG, but the petition was withdrawn with liberty to reapproach the Court.

Subsequently, upon receiving intimation that the Respondent sought encashment of the PBG, the Petitioner filed the present petition seeking interim relief restraining the Respondent from invoking the PBG until the Arbitral Tribunal was constituted. The Court had earlier passed an interim order on 31st October 2019 directing the Respondent to maintain status quo on invocation of the PBG. The Arbitral Tribunal was appointed by a separate order.

Legal Issues Presented

  1. Whether the invocation of the Performance Bank Guarantee by the Respondent was in strict compliance with the terms of the bank guarantee.
  2. Whether the Petitioner is entitled to a stay on invocation of the bank guarantee pending constitution and decision of the Arbitral Tribunal.
  3. The applicability of established legal principles on injunctions against invocation of unconditional bank guarantees.

Arguments of the Parties

Petitioner's Arguments

  • The invocation of the PBG was not in terms of the bank guarantee, specifically lacking mention of loss or damage caused to the Respondent as required.
  • Invocation of the PBG was premature and liable to be stayed.
  • Relied on judgments including M/s. Harprashad and Co. Ltd. v. Sudarshan Steel Mills, Jyoti Structure Ltd. v. Dakshinanchal Vidyut Vitran Nigam Ltd., NHPC Ltd. v. HCC Ltd., and Shri V.V. Gaupta v. New Delhi Municipal Council.

Respondent's Arguments

  • The petition is not maintainable as the law relating to stay on invocation of bank guarantees is settled.
  • The PBG must be honoured as per its terms; the Bank is not concerned with disputes between parties.
  • The Respondent has a contractual right to invoke the PBG due to Petitioner’s failure to perform contractual obligations despite warnings.
  • Relied upon contractual provisions in the Special Tender Conditions and judgments such as Gangotri Enterprises Ltd. v. Union of India, M/s. Hind Construction Contractors v. State of Maharashtra, United Engineers (Malaysia) v. National Highways Authority of India, and R.C.M. Infrastructure v. The State Highway Authority of India.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
U.P State Sugar Corporation v. Sumac International Ltd., AIR 1997 SC 1644 Exceptions to restraint on invocation of unconditional bank guarantees (fraud, irretrievable injury, special equities) Reiterated the limited grounds on which injunction against invocation of bank guarantees can be granted.
C. Himadri Chemicals Industries Ltd. v. Coal Refinery Company, 2007 (8) SCC 110 Principles governing injunctions against bank guarantees Supported the settled legal position regarding bank guarantees.
ANS Constructions Pvt. Ltd. v. Ramagunda Fertilizers & Chemicals Ltd., O.M.P. (I) (COMM.) 156/2019 Legal principles on bank guarantees and injunctions Referenced for the established legal framework on bank guarantees.
M/s. Harprashad and Co. Ltd. v. Sudarshan Steel Mills and Others, 1979 SCC OnLine Del 144 Grounds for injunction against invocation of bank guarantees Relied upon by Petitioner to support argument against invocation.
Jyoti Structure Ltd. v. Dakshinanchal Vidyut Vitran Nigam Ltd. & Ors., 2016 SCC OnLine Del 5035 Invocation of bank guarantees and stay thereof Petitioner cited to substantiate claims regarding improper invocation.
NHPC Ltd. v. HCC Ltd., 2018 SCC OnLine Del 11469 Invocation and injunction of bank guarantees Used by Petitioner in support of stay on invocation.
Shri V.V. Gaupta v. New Delhi Municipal Council & Ors., 2006 SCC OnLine Del 276 Principles on bank guarantee invocation Referenced by Petitioner to bolster argument.
Gangotri Enterprises Ltd. v. Union of India and Others, (2016) 11 SCC 720 Right to invoke bank guarantees post contract termination Relied upon by Respondent to assert contractual rights.
M/s. Hind Construction Contractors v. State of Maharashtra, (1979) 2 SCC 70 Enforcement of bank guarantees Respondent cited to support invocation.
United Engineers (Malaysia) v. National Highways Authority of India, 2008 SCC OnLine Del 182 Invocation of bank guarantees Relied on by Respondent for legal backing.
R.C.M. Infrastructure v. The State Highway Authority of India, 2019 SCC OnLine Jhar 397 Bank guarantee invocation post contract breach Used by Respondent to justify invocation.
Ansal Properties & Industries v. Engineering Projects (India) Ltd., 1997 (41) DRJ Requirement of strict compliance in invocation of bank guarantees Cited to emphasize necessity of invocation in strict terms.
Punj Sons (P) Ltd. v. Hong Kong & Shanghai Banking Corporation and Anr., 1991 (20) DRJ 154 Strict invocation requirements Referenced to support strict compliance principle.
Puri International (P) Ltd. v. National Building Construction Co. Ltds, 1997 (41) DRJ 592 Invocation of bank guarantees Used to reinforce strict terms for invocation.
Basic Tele Services Ltd. v. Union of India, 2009 SCC OnLine Del 1657 Invocation and injunction of bank guarantees Supported legal position regarding invocation.

Court's Reasoning and Analysis

The Court examined the terms of the Performance Bank Guarantee, which required any demand for encashment to state that the amount claimed is due to loss or damage caused by breach of contract or failure to perform. The invocation letter submitted by the Respondent merely stated that the contract was terminated, without asserting any loss or damage suffered.

The Court emphasized the well-established legal principle that invocation of an unconditional bank guarantee must be strictly in accordance with its terms. The Court noted that injunctions against invocation are only granted under narrow exceptions such as egregious fraud or irreparable injury, none of which were claimed here.

Since the letter of invocation failed to meet the explicit conditions of the bank guarantee, the Court found a prima facie case in favour of the Petitioner. The balance of convenience and risk of irreparable harm also favoured the Petitioner. The Court observed that the Respondents have a contractual right to invoke the PBG but must comply with the stipulated conditions.

The Court also noted that the question of penalties or liquidated damages post termination was a matter for the Arbitral Tribunal and not for the Court at this stage.

Holding and Implications

The Court allowed the present petition and confirmed the interim order dated 31st October 2019, restraining the Respondent from invoking the Performance Bank Guarantee on the basis of the existing invocation letter.

However, the Court clarified that this order does not preclude the Respondent from making a fresh invocation of the bank guarantee if it complies with the terms of the guarantee. The matter is disposed of with directions consistent with these observations.

No new precedent was established; the decision applies the settled legal principles on invocation of unconditional bank guarantees to the facts before the Court, primarily focusing on strict compliance with invocation conditions.

To access the original judgment, please Sign In or Subscribe.

    Marshal Infradevelopers India Private Limited v. Union Of India And Another

    O.M.P. (I) (COMM.) 366/2019 Page 1 of 9

    $~45

    * IN THE HIGH COURT OF DELHI AT NEW DELHI

    Date of Decision: 29th March, 2022 + O.M.P. (I) (COMM.) 366/2019

    MARSHAL INFRADEVELOPERS INDIA PRIVATE LIMITED

    ..... Petitioner

    Through: Mr. Vivekanand, Advocate. versus

    UNION OF INDIA & ANR. ..... Respondents

    Through: Mr. Ashok Singh, Mr. Upendra K. Nagar, Advocates.

    CORAM:

    HON'BLE MR. JUSTICE SANJEEV NARULA

    JUDGMENT

    SANJEEV NARULA, J. (Oral):

    1. By way of a separate order passed today in ARB.P. 12/2020, an Arbitral Tribunal for adjudication of disputes between the parties stands appointed.

    2. In view of the above, before commencing hearing in the matter, Mr. Ashok Singh, counsel for the Respondent, has been queried as to whether he is agreeable for continuation of the interim order granting protection to the Petitioner, till such time that the Arbitral Tribunal decides the instant petition by treating it as one under Section 17 of the Act. Mr. Singh contests and argues that such course would amount to confirmation of the order of injunction of the Bank Guarantee.

    1

    3. Although Mr. Singh's contention is incorrect as the Court has only expressed tentative views in the interim order, nevertheless, since the matter pertains to stay on invocation of bank guarantee, counsel for the parties have been heard at length for final disposal of the petition.

    FACTUAL BACKGROUND

    4. The Petitioner vide Letter of Acceptance dated 27thMay, 2019 was awarded the Contract for the work of 'Earth work in filling, Blanketing, construction of station building, Passenger platform Minor bridges, foot over bridge, Limited height subways, Circulating area and other allied works for new crossing station at Dobh in connection with Rohtak-Meham-Hansi New line' [hereinafter, the "Contract"] by the Respondent.

    5. In terms of the afore-noted Letter of Acceptance, Petitioner furnished a Performance Bank Guarantee [hereinafter, "PBG"] - equivalent to 5% of the contract amount - issued by Bank of Baroda [hereinafter, "the Bank"]. This bank guarantee is the subject-matter of the instant petition.

    6. The stipulated period for completion of work under the Contract was six months from the date of issuance of the Letter of Acceptance. Petitioner alleges that Respondent delayed in handing over the site. Nevertheless, immediately after award of work, Petitioner made requisite arrangements to carry out the work under the Contract. It has been further contended that the execution of such work was not possible without working drawings and a clear site being provided by the Respondent, owing to which, Petitioner was prevented from completing the work within stipulated timelines. Respondents

    2

    were oblivious to the difficulties faced by the Petitioner, and in order to cover their failure in performing their obligations, letters dated 15thJuly, 2019 and 1stAugust, 2019 were issued - invoking Clause 62 of the General Conditions of Contract ("GCC") for termination of the Contract. Petitioner, vide communication dated 8thAugust, 2019, responded to the above-stated notices and apprised the Respondent that the work awarded cannot be completed in absence of the working drawings and/ or removal of hindrances at the site. However, instead of appreciating the Petitioner's grievances, the Respondent vide notice dated 9thAugust, 2019, terminated the Contract in terms of Clause 62 of the GCC.

    7. Thereafter, Petitioner approached this Court at the first instance, by way of O.M.P. (I) (COMM.) 279/2019 seeking a stay on termination of the Contract, and as a consequence, a stay on invocation of PBG. However, the said petition was "dismissed as withdrawn", affording the Petitioner liberty to reapproach this Court, since an alternate remedy lay with the Petitioner by way of damages against such termination, and further, as on that date, there was no demand from the Respondent, in relation of the encashment of the

    PBG.

    8. Subsequently, Petitioner received intimation from the Bank that Respondent had sought encashment of PBG. In these circumstances, Petitioner has approached this Court seeking interim measures restraining the Respondent from invoking PBG, till such time that the Arbitral Tribunal is constituted.

    3

    9. This Court, on 31stOctober, 2019, prima facie noticing that the invocation dated 11thOctober, 2019 was not in terms of PBG, directed Respondent to maintain status quo, as existing on the date of the order. Since then, the present petition has been pending and on account of restricted Court functioning in wake of COVID-19 pandemic, the matter was being adjourned en bloc.

    ARGUMENTS ADVANCED

    10. Mr. Vivekanand, counsel for the Petitioner, has invoked several grounds for seeking a stay on invocation of PBG - mainstay being that the invocation is not in terms of the PBG. On this short ground, he states that the petition is liable to be allowed. In support of this contention, reliance has been placed upon the judgments in M/s. Harprashad and Co. Ltd. v. Sudarshan Steel Mills and Others,1Jyoti Structure Ltd. v. Dakshinanchal Vidyut Vitran Nigam Ltd. & Ors.,2NHPC Ltd. v. HCC Ltd.3and Shri V.V. Gaupta

    v. New Delhi Municipal Council & Ors.4

    11. On the other hand, Mr. Ashok Singh, counsel for the Respondents, contends that the present petition is not maintainable in view of the law relating to the stay on invocation of bank guarantees - which is no longer res integra. He submits that (i) the PBG must be honoured in accordance with the terms thereof and (ii) the Bank is not concerned with the relationship between the parties; and (iii) the terms of the PBG also explicitly stipulate this

    1 1 979 SCC OnLine Del 1 44.

    2 2 016 SCC OnLine Del 5035.

    3 2018 SCC OnLine Del 11469.

    4 2006 SCC OnLine Del 276.

    4

    condition. Thus, Respondents have the right to invoke the PBG since the Petitioner failed to meet the contractual obligations and improve the rate of progress, despite the issuance of warnings letters and since the Respondents suffered losses on account of non-performance of the Contract by the Petitioner. Mr. Singh also placed reliance upon contractual provisions contained in the terms of the 'Special Tender Conditions and Instructions to Tenderers',5which vest with Respondents - the right to invoke PBG in the event the Contract stands terminated. Besides, reliance is placed upon the judgments in Gangotri Enterprises Ltd. v. Union of India and Others,6M/s. Hind Construction Contractors v. State of Maharashtra,7United Engineers (Malaysia) v. National Highways Authority of India8 and R.C.M. Infrastructure v. The State Highway Authority of India.9

    ANALYSIS

    12. The Court has considered the contentions of the parties. The law on bank guarantees is well-established and its principles have been reiterated by the Courts in many cases. It would suffice to note that the restraint on invocation of an unconditional bank guarantee can only be granted in cases falling amongst the well-known exceptions recognised by the Court viz. egregious fraud, irretrievable injury, and special equities.10

    5 Clauses 5 and 5 .2 of the Special Tender Conditions and Instructions to Tenderers.

    6 (2016 ) 11 SCC 720.

    7 (197 9) 2 SCC 7 0.

    8 2008 SCC OnLine Del 18 2.

    9 2019 SCC OnLine Jhar 39 7.

    10 See U.P. State Sugar Corporation v. Sumac International Ltd. AIR 1997 SC 1644; C. Himadri Chemicals Industries Ltd. v. Coal Refinery Company, 2007 (8) SCC 110; ANS Constructions Pvt. Ltd. v. Ramagunda Fertilizers & Chemicals Ltd. O.M.P. (I) (COMM.) 156/2019 dated 24thMay, 2019.

    5

    13. In the instant case, the ground urged by the Petitioner is centred around terms of the PBG. Therefore, in order to rule on the objection urged by the Petitioner, it is necessary to take note of the salient terms of the instant PBG, which reads as under:

    "2. We Bank of Baroda, further agree that (and promise) to pay the amounts

    due and payable under this guarantee without any demur merely on a demand from the Government through the FA&CAO/Const, Northern Railway, Kashmere Gate, Delhi-110006, stating that the amount claimed is due by way of loss or damage caused to or would be caused or suffered by the Government by reason of any breach by the said contractor of any of the terms of conditions contained in the said agreement or by reason of the contractor failure to perform the said agreement. Any such demand made on the Bank shall be conclusive as regards the amount due "and payable by the Bank under this guarantee. However, our liability under this guarantee shall be restricted to an amount not exceeding Rs 62,51,115/- (Rupees Sixty Two Lakh Fifty One Thousand One Hundred Fifteen Only).

    3. (a) We Bank of Baroda further undertake to pay to the Government any money so demanded notwithstanding any dispute or dispute raised by the contractor (s) in any suit or proceeding pending before any court or Tribunal relating to liability under this present being absolute and unequivocal, (b) The payment so made by us under this bond shall be a valid discharge of our liability for payment there under and the contractor(s) shall have no claim against us for. making such payment.

    4. We Bank of Baroda to further agree that the guarantee herein contained shall remain in full force and effect during the period that would be taken for the performance of the said agreement and that it shall continue to be enforceable till all the dues of the Government under or by virtue of the said agreement have been fully paid and its claims satisfied or discharged by Dy. Chief Engineer/Const/TKJ, Northern Railway, Tilak Bridge, New Delhi on behalf of the Government, certify that the terms and conditions of the said agreement have been fully and properly carried out by the said contractor(s) and accordingly discharges this guarantee."

    [Emphasis Supplied]

    14. In light of the afore-noted terms, Respondent invoked the PBG in question, in the following terms:

    "No:- 18/Const/A/cs/Books/BG/Encashment/14/08/2020 Dated 11.10.2019

    6

    The Branch Manager Bank of Baroda, Rohtak (Main) Branch, Taleram Complex, Near SYS restaurant, Rohtak-124001, Haryana

    Reg:- Encashment of BG No.07521GPER002219 dated 20.07.2019 for Rs 62,51,115/- valid up to 19.08.2020 of M/s Marshal Infradevelopers India Private Limited, House No.17, Sector-14, Rohtak-124001

    ************** The above mentioned BG is sent herewith lor immediate encashment and remit the amount through Bank Draft in favour of FA&CAO/Const./Northern Railway, Kashmere Gate, Delhi, as the contract has been terminated & the amount of BG has been forfeited by the Railway. DA; (BG Original-Four Pages, Original)"

    [Emphasis Supplied]

    15. It would be trite to state that invocation has to be strictly in terms of the bank guarantee.11On a bare perusal of the afore-noted Letter of Invocation, it manifests that the same does not satisfy the conditions as stipulated in the PBG. In the Letter of Invocation, Respondents have simply mentioned that the Contract has been terminated. It does not state whether the alleged breach on the part of the Petitioner resulted in any loss(es) and/ or damage(s) to the Respondents. Whereas, the terms of the PBG extracted hereinabove clearly stipulate that the demand must state "that the amount claimed is due by way of loss or damage caused". Respondent can certainly invoke the PBG in event of any breach in terms and conditions contained in the Contract; or for any failure on part of the Petitioner, however, the essential pre-requisite is that the

    11 See Ansal Properties & Industries v. Engineering Projects (India) Ltd., 1997 (41) DRJ; Punj Sons (P) Ltd. v. Hong Kong & Shanghai Banking Corporation and Anr., 1991 (20) DRJ 154; Puri International Ltd. v. National Building Corporation and Anr., 1997 (41) DRJ 592, Basic Tele Services Ltd. v. Union of India 2009 SCC OnLine Del 1657.

    7

    claim should be towards loss(es) and/ or damage(s), which must be asserted. Thus, the Respondent's bare assertion that the Contract has been terminated, does not meet the conditions for invoking the PBG. Mr. Singh is correct in submitting that Respondents have a contractual remedy for invocation of PBG in event of termination of the Contract, nonetheless the enforcement of such a stipulation would still require conditions of the PBG to be met. Further, the judgements cited by Mr. Singh are not applicable to the factual matrix of the present case - as they do not deal with the ground for injunction of PBG, as has been urged by the Petitioner.

    16. The Court, in the instant petition, is to only analyse whether such invocation is in terms of the PBG. On this issue, ex facie the Letter of Invocation does not meet the stipulated requirements, as it makes no mention of loss(es) and/ or damage(s) suffered due to termination. Therefore, in the opinion of the Court, the Petitioner is entitled to an order of restrain. On the afore-noted ground along, the Court finds a prima facie case in favour of the Petitioner. The balance of convenience also lies in favour of the Petitioner and irreparable loss would be caused in case a restraint order was not passed in its favour.

    17. Before parting, the Court would also like to note that during the course of arguments, Mr. Vivekanand has handed over a reply received by the Petitioner in response to an RTI application dated 8thFebruary, 2021, wherein it has been stated as under:

    "Sub:- Information sought out in RTI no. NRCOG/R/E/21/0071) Dated

    29.01.2021.

    Ref: - Online RTI Registration No. NRCOG/R/E/21/0071 Dated 29.01.2021

    8

    In reference to above the point wise reply related to the work "Earth work in filling. Blanketing, construction of station building, Passenger platform Minor bridges, foot over bridge, Limited height subways, Circulating area and other allied works for new crossing station at Dobh in connection with Rohtak-Meham-Hansi New line" awarded to M/s Marshal Infra developers India Private Limited on 27/05/2019 is as under

    1. Copy of letter of acceptance attached.

    2. Date of Start: 27/05/2019

    3. Original intended completion date: 26/11/2019

    4. Termination date: 13/08/2019

    5. No amount of liquidated damage (LD) or any penalty imposed on contractor from 24/05/2019 to 12/08/2019.

    6. No amount of liquidated damage (LD) or any penalty imposed on contractor on 13/08/2019.

    7. No amount of liquidated damage (LD) or any penalty imposed on contractor after 13/08/2019.

    This is for your information please."

    [Emphasis Supplied]

    18. The above reply suggests the Respondents have themselves not levied any liquidated damages/ penalty till date, despite termination of the Contract in 2019. Be that as it may, this is an aspect that should be examined by the Arbitral Tribunal and not by this Court.

    19. In view of the above, the present petition is allowed and the interim order dated 31stOctober, 2019, stands confirmed. It is however clarified, that the present order does not preclude the Respondent from invoking the bank guarantee by way of fresh invocation, if so advised.

    20. With the above directions, the present petition is disposed of.

    SANJEEV NARULA, J

    MARCH 29, 2022/as