AMICUS AI
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Disposition
Attorney(S)
Smart Summary

Analytical Summary of the Opinion — National Consumer Disputes Redressal Commission (Presiding Member: Prem Narain)

Factual and Procedural Background

The present proceedings are first appeals filed by Sahara Prime City Ltd. & others against multiple orders of the State Consumer Disputes Redressal Commission, Rajasthan dated 16.10.2018, 06.12.2018, 11.10.2018 and 15.01.2019 in Complaint Nos. 86/2017, 119/2017, 128/2017 and 15/2018. The appeals were consolidated and First Appeal No.531 of 2019 (Sahara Prime City Ltd. & Ors. v. Vijay Gupta) was taken as the lead case.

Briefly, the respondent (Vijay Gupta) acquired a transferred booking in the appellants' project "Sahara City Homes, Jaipur." Key factual dates and figures recorded in the opinion:

  • Application for booking by the respondent: 15.03.2005 (transfer of booking made earlier in father's name).
  • Approval of transfer by appellants: 06.06.2008.
  • Booking payment of Rs.1,35,350 made on 12.03.2005.
  • Allotment letter dated 21.08.2009 confirming Unit No. C3/605 for total sale consideration of Rs.27,07,000. The allotment letter contained a clause charging 15% p.a. interest on delayed installments.
  • On 07.09.2009 the respondent sought change to a construction-linked payment plan.
  • The respondent paid a total of Rs.24,80,375 but possession was not delivered; the consumer complaint (No.86/2017) sought refund of Rs.24,80,375 with interest (prayer alleged 18% p.a.), compensation and other reliefs.

The State Commission allowed the complaint, ordering refund of Rs.24,80,375 with 15% p.a. interest from the date of each deposit, Rs.2,00,000 as compensation for mental agony and Rs.50,000 as cost of proceedings (to be paid within one month, otherwise to carry 9% interest).

The appellants challenged that decision in these first appeals. Procedurally, hearings were held for the consolidated appeals; delays in filing the appeals were contested and addressed in the opinion.

Legal Issues Presented

  1. Whether the delay in filing the appeals should be condoned.
  2. Whether the rate of interest awarded by the State Commission on refunded amounts (15% p.a.) was justified, or should be reduced.
  3. Whether the compensation of Rs.2,00,000 awarded by the State Commission for mental agony should be interfered with when interest is awarded on refund.

Arguments of the Parties

Appellants' Arguments

  • The amounts deposited by the complainants were utilized in construction and did not earn interest for the complainants; therefore refund with interest was not justified or should be limited.
  • The 15% p.a. rate of interest awarded by the State Commission is excessive; this Commission and the Supreme Court increasingly order refund with 9% p.a. interest, so the State Commission's rate was not justified.
  • If interest is awarded on the refund, awarding separate compensation (Rs.2,00,000) is not justified because interest operates as compensation.
  • Delay in filing the appeals should be condoned: delay attributable to obtaining orders from head office, arranging counsel in New Delhi and translating documents from Hindi — not intentional.
  • The appellants also raised jurisdictional/contractual defenses (contract was for purchase only, not construction; disputes to be referred to arbitration) and pointed to a Supreme Court order (SEBI v. Sahara Real Estate Corporation Ltd.) imposing a ban on parting with immovable properties.

Respondents' Arguments

  • The appellants themselves charge 15% p.a. interest on delayed installments; by parity, the amounts deposited by complainants should be refunded with 15% p.a. interest.
  • The appellants' reasons for delay in filing appeals are administrative and insufficient; therefore the appeals should be dismissed on the ground of limitation.
  • Regarding compensation, because the State Commission awarded only 15% (and not 18%) interest, complainants are still entitled to separate compensation for mental agony and harassment.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Manoharan Vs. Sivarajan & Ors., Civil Appeal No.10581 of 2013 (decided 25.11.2013) Principles concerning condonation of delay — drawing on State of Bihar v. Kameshwar Prasad Singh and Anantnag v. Katiji about liberal, substantial-justice oriented approach to 'sufficient cause'. The court relied on this authority to condone the delay in filing the appeals, accepting the appellants' reasons and imposing a costs penalty (Rs.50,000) for condonation in each case.
State of Bihar & Ors. v. Kameshwar Prasad Singh & Anr. (quoted within Manoharan) That power to condone delay is to secure substantial justice; listed considerations (no presumption of deliberate delay; liberal approach; avoid throwing out meritorious matters on technicalities). The court reproduced and applied these principles to justify condoning delay in the appeals on the stated grounds.
Collector, Land Acquisition, Anantnag v. Mst. Katiji (referred in Manoharan) Elasticity of the expression 'sufficient cause' in the Limitation Act and the need to prefer substantial justice over technical considerations. The court invoked this precedent in support of a liberal approach to condonation of delay and to explain the rationale for condoning the appellants' delay.
Alok Shanker Pandey Vs. Union of India & Ors., II (2007) CPJ 3 (SC) Principle that interest is not a penalty but an accretion on capital — if a debtor retains money that should have been paid earlier, equity demands repayment of principal with interest to compensate for the use of funds. The court applied this reasoning to hold that when a builder has retained amounts paid by an allottee and a refund is ordered, the forum may award interest to compensate for the period the builder had the use of those funds.
Kolkata West International Pvt. Ltd. Vs. Deva Asis Rudra, II (2019) CPJ 29 (SC) Reduction of rate of interest on refunds by the Supreme Court (from 12% to 9% in that case) — used as a comparative guide for determining a reasonable rate. The court treated this decision as persuasive for reducing high rates of interest on refunds and, having considered it, determined an appropriate but distinct rate (10% p.a.) in the present facts.
SEBI Vs. Sahara Real Estate Corporation Ltd. (contempt petition No.412 of 2012 in Civil Appeal 9813 of 2011) Recorded Supreme Court action (imposition of a ban on the appellants to part with immovable properties) — cited by appellants in their written statement. The opinion records that the appellants raised the existence of this Supreme Court order as part of their defense; the court noted the contention but the final disposition proceeded on the refund/interest/compensation issues rather than expressly relying on that order to dispose of the appeals.

Court's Reasoning and Analysis

The Court's analysis proceeded in two main parts: (A) consideration of delay in filing the appeals, and (B) the core substantive issue of interest and compensation.

A. Condonation of Delay

  • The court examined the reasons advanced for delay: time in translating documents from Hindi to English, time in arranging counsel in New Delhi, and time in obtaining approvals from the appellants' head office.
  • Applying the principles in Manoharan (and the authorities it quotes — State of Bihar v. Kameshwar Prasad Singh and Anantnag v. Katiji), the court found these reasons genuine and concluded that condonation of delay was appropriate because the appellants were not likely to benefit from the delay and substantial justice favored deciding on merits.
  • The court condoned the delay but imposed costs of Rs.50,000 on the appellants to be paid to each complainant as the price for condonation.

B. Interest on Refund and Compensation

  • The court identified the principal substantive controversy as the rate of interest to be awarded on amounts ordered to be refunded by the State Commission. The State Commission had awarded 15% p.a. interest; appellants argued this was excessive and the practice of higher forums tended toward 9% p.a.; respondents argued for parity with the 15% p.a. interest that the builder charges on delayed installments.
  • The court rejected the parity argument where there was no contractual basis for applying 15% p.a. to refunds. The allotment agreement contained a clause for 15% p.a. interest on delayed installments, but there was no contractual term obliging the appellants to pay 15% p.a. when refunding amounts. Accordingly, parity with the delay-charge clause was not automatic.
  • Relying on Alok Shanker Pandey, the court reiterated the equitable principle that interest is compensatory for the use of funds retained by the debtor (builder), and it is within the consumer forum's discretion to award reasonable interest when there is no contract specifying the rate for refunds.
  • Turning to comparative authority, the court noted that the Supreme Court in Kolkata West International had reduced a forum-awarded rate of interest (from 12% to 9%). Considering that line of authority and the facts before it, the court exercised its discretion to moderate the rate from 15% p.a. (awarded by the State Commission) to 10% p.a. in these cases.
  • On compensation (Rs.2,00,000 awarded by the State Commission for mental agony), the court found no justification to disturb that award merely because interest had been modified from 15% to 10%. The court therefore upheld the compensation order.

Holding and Implications

Holding: The court concluded as follows:

APPEALS PARTLY ALLOWED

  • The orders of the State Commission are modified only to the extent that the rate of interest on the refunded amounts shall be 10% p.a. instead of 15% p.a. as earlier ordered by the State Commission.
  • All other aspects of the State Commission's orders (including the award of Rs.2,00,000 as compensation for mental agony and Rs.50,000 as cost in each case) are upheld.
  • The delay in filing these appeals is condoned; however, the appellants are directed to pay Rs.50,000 as costs for condonation to each complainant.
  • The appellants are directed to comply with the modified orders and make payments (refunds with 10% p.a. interest and the costs) within 45 days from receipt of the order.

Implications: The direct consequences are limited to the parties in these appeals — the appellants must refund the amounts ordered by the State Commission with interest at 10% p.a., pay the separately awarded compensation and the condonation costs. The court adjusted the interest rate downward from the State Commission's 15% but left the compensation intact. The opinion does not purport to lay down a new general precedent; it applies existing Supreme Court authorities and exercised the forum's discretion in the facts before it.

Prepared strictly from the text of the provided opinion. No information has been added beyond what appears in that opinion.

To access the original judgment, please Sign In or Subscribe.

    SAHARA PRIME CITY LIMITED & 2 ORS. v. VIJAY GUPTA

    NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

    NEW DELHI

    FIRST APPEAL NO. 531 OF 2019

    (Against the Order dated 16/10/2018 in Complaint No. 86/2017 of the State Commission Rajasthan)

    1. SAHARA PRIME CITY LIMITED & 2 ORS.

    SAHARA INDIA CENTRE 2, KAPOORTHALA COMPLEX

    ALIGANJ

    LUCKNOW

    UP

    2. M/S. SAHARA PRIME CITY LTD

    SAHAR CITY HOMES TONK ROAD

    JAIPUR

    3. SAHAR ACITY HOMES SALES & MARKETING CO OP

    ABOVE SATGURU TRADERS NEAR POLICE CHOWKI,

    RAMGANJ

    AJMER ...........Appellant(s) Versus

    1. VIJAY GUPTA

    S/O. J.P. GUPTA, R/O. 57-58, DIVYA KRIPA,

    MANAVPURAV COLONY, BARAL ROAD VIJAY NAGAR

    AJMER

    RAJASTHAN ...........Respondent(s)

    BEFORE:

    HON'BLE MR. PREM NARAIN,PRESIDING MEMBER For the Appellant : Ms. Rhea Dube, Advocate For the Respondent : For the Respondent:

    In FA/531/2019 : Mr. Vijay Gupta, in person Dated : 07 Jul 2020

    ORDER

    These first appeals have been filed by the appellant Sahara Prime City Ltd. & ors against the order dated 16.10.2018, 06.12.2018, 11.10.2018 & 15.01.2019 of the State Consumer Disputes Redressal Commission, Rajasthan (in short 'the State Commission') passed in Complaint No.86/2017, 119/2017, 128/2017 & 15/2018. As the facts of these cases are similar and same issues are involved in these appeals, they are being decided together. First Appeal No.531 of 2019, Sahara Prime City Ltd. & Ors. Vs. Vijay Gupta shall be taken as lead case.

    2. Brief facts of the case are that on 15.03.2005, the respondent applied for the booking of a unit in the project "Sahara City Homes, Jaipur", of the appellants by transfer of a booking that had been previously made in the name of the respondent's father. On 06.06.2008, the appellants approved the transfer of the unit booked by the respondent's father in the name of the respondent. On 12.03.2005, booking amount of Rs.1,35,350/- was paid by the respondent

    1

    to the appellants with respect to the said unit. On 21.08.2009, the appellants issued the allotment letter confirming the booking of the unit No.C3/605 in Sahara City Homes, Jaipur in favour of the respondent for the total sale consideration of Rs.27,07,000/-. It was stated in the allotment letter that in case of delay of payment of installments by the respondent, the respondent would be charged 15% p.a. interest on the said installment amount from the date on which such payment was due. On 07.09.2009, the respondent requested the appellants regarding the change of his payment plan to that of construction linked plan. The complainant has paid a total amount of Rs.24,80,375/-. As possession was not delivered, the consumer complaint No.86 of 2017 was filed by the respondent contending that possession of the flat was not handed over to the respondent within stipulated time, there is deficiency of service on the part of the appellants and a sum of Rs.24,80,375/- was prayed for refund along with interest at the rate of 18% p.a. along with the compensation for the mental, physical harassment amounting to Rs.20,00,000/-, Rs.2,00,000/- for cost of the proceedings, bank charges amounting to Rs.8,00,000/-, rent expenses amounting to Rs.20,00,000/- and for the delay in possession amounting to Rs.2,61,945/-. The appellant filed their written statement before the State Commission contending that complaint of the respondent is baseless since the contract between the appellants and the respondent was only for the purchase of a unit/flat and not for the construction of the same by the site owner with a contractor. The State Commission had no jurisdiction to entertain the complaint because matter was to be referred to arbitration in case of any dispute. Further, the Hon'ble Supreme Court in the contempt petition bearing No.412 of 2012 in the civil appeal 9813 of 2011 titled as SEBI Vs. Sahara Real Estate Corporation Ltd. imposed ban on the appellants to part with any of the immovable properties. However, the State Commission passed the following order:-

    "In view of the above, the complaint is allowed and the complainant is entitled to get Rs.24,80,375/- along with 15% interest from the date of each deposit. The complainant is further entitled to get Rs.2 lakhs as compensation for mental agony and Rs.50,000/- as cost of proceedings which should be paid to the complainant within one month otherwise it will carry 9% interest from the date of the order."

    3. Hence the present appeal.

    4. Heard the learned counsel for the appellants as well as respondent in person in FA/531/2019 & 532/2019 and the learned counsel for the respondent in 534/2019 and none appeared in FA/533/2019 even after service of notice, hence, hearing from respondent Surendra Singh has been dispensed with as the appeals are on similar grounds and the defence of the respondents is also similar.

    5. Learned counsel for the appellants stated that the State Commission has ordered refund of the deposited amount by the respondents/complainants along with 15% p.a. interest from the date of respective deposits till actual payment. Apart from this, the State Commission has also awarded a compensation of Rs.2,00,000/- in each case for mental agony and Rs.50,000/- as cost of litigation in each case. Learned counsel contended that the amount deposited by the complainants has been utilized in the construction and the amount deposited by the complainants did not earn any interest, therefore, the same should not have been ordered to be refunded along with interest. Moreover, the rate of interest awarded by the State Commission is very high. These days, this Commission as well as Hon'ble Supreme Court are ordering refund along with 9% p.a. interest and therefore, there was no justification for the State

    2

    Commission to have ordered refund along with 15% p.a. interest.

    6. The learned counsel for the appellants further argued that the State Commission has also awarded a compensation of Rs.2,00,000/- in each case for mental agony, whereas, the same is not justified when the interest is being awarded on the amount of refund. This is an accepted principle of law that if the interest is being awarded, then separate compensation is not justified as interest is also in the form of compensation. The learned counsel also requested to condone the delay in filing the present appeals as the delay has happened on account of getting orders from the head office, in arranging a counsel at New Delhi and in getting the translation of all the documents as all documents were in Hindi. The delay is not intentional.

    7. On the other hand, respondents/complainants in First Appeal No.531 of 2019 & 532 of 2019 stated that the appellant has charged interest @15% p.a. on the amount of instalment if paid with delay. On the principle of parity, they stated that the deposited amount by the complainants with the builder should also be refunded along with 15% p.a. interest. Learned counsel appearing on behalf of respondent/complainant in First Appeal No.534/2019 also agreed with the arguments advanced by the respondents/complainants in First Appeal No.531/2019 & 532/2019. The leaned counsel further stated that the reasons given in the application for condonation of delay in filing the present appeals are only administrative in nature which cannot be considered as sufficient cause for condoning the delay. Hence the appeals deserve to be dismissed only on the ground of limitation.

    8. In respect of compensation of Rs.2,00,000/-, the respondents/complainants stated that the compensation of Rs.2,00,000/- has been awarded for mental agony that has been suffered by the complainants. Moreover, this Commission has taken a view that if 18% p.a. interest is awarded then no other compensation is required to be given. In the present case, only 15% p.a. interest has been awarded and therefore, the complainants are entitled to separate compensation for mental agony and harassment.

    9. I have carefully considered the arguments advanced by both the sides and have examined the record. First of all, it is seen that there is delay in filing these appeals. The main reasons for delay appear to be time taken in getting all the documents translated from Hindi to English, time taken in arranging a counsel at New Delhi and time taken in getting the approvals from the head office of the company. These reasons seem to be genuine and by delaying the appeals, the appellant is not expected to be benefited. Hon'ble Supreme Court in Manoharan Vs. Sivarajan & Ors, Civil Appeal No.10581 of 2013, decided on 25.11.2013 (SC) has observed the following:-

    "9. In the case of State of Bihar & Ors. v. Kameshwar Prasad Singh & Anr., it was held that power to condone the delay in approaching the Court has been conferred upon the Courts to enable them to do substantial justice to parties by disposing the cases on merit. The relevant paragraphs of the case read as under:

    "11. Power to condone the delay in approaching the Court has been conferred upon the Courts to enable them to do substantial justice to parties by disposing of matters on merits. This Court in Collector, Land Acquisition, Anantnag v. Mst. Katiji (1987)ILLJ 500 SC held that the expression 'sufficient cause' employed by the legislature in the Limitation Act is adequately elastic to enable the Courts to

    3

    apply the law in a meaningful manner which subserves the ends of justice-that being the life purpose for the existence of the institution of Courts. It was further observed that a liberal approach is adopted on principle as it is realised that:

    1. Ordinarily a litigant does not stand to benefit by lodging an appeal late.

    2. Refusing to condone delay can result in a meritorious matter being thrown out at the very threshold and cause of justice being defeated. As against this when delay is condoned the highest that can happen is that a cause would be decided on merits after hearing the parties.

    3. 'Every day's delay must be explained' does not mean that a pedantic approach should be made. Why not every hour's delay, every second's delay? The doctrine must be applied in a rational common sense pragmatic manner.

    4. When substantial justice and technical considerations are pitted against each other, cause of substantial justice deserves to be preferred for the other side cannot claim to have vested right in injustice being done because of a non-deliberate delay.

    5. There is no presumption that delay is occasioned deliberately, or on account of culpable negligence, or on account of mala fides. A litigant does not stand to benefit by resorting to delay. In fact he runs a serious risk.

    6. It must be grasped that judiciary is respected not on account of its power to legalize injustice on technical grounds but because it is capable of removing injustice and is expected to do so."

    10. Relying on the above judgment of the Hon'ble Supreme Court and on the grounds mentioned in the application for condonation of delay, I deem it appropriate to condone the delay in each appeal at a cost of Rs.50,000/- to be paid to the complainant in each case. The main issue relates to award of interest on the amount of refund by the State Commission against which the present appeals have been filed. The complainants are trying to defend the award of 15% p.a. interest on the ground that the appellant is charging 15% p.a. interest on the amount of instalment, if delayed and on the principle of parity, the complainants should also be allowed interest @15% p.a. On the other hand, the appellants have stated that presently this Commission and Hon'ble Supreme Court are awarding interest @9% p.a. on amount of refund. The provision in respect of levying 15% p.a. interest on the delayed instalments is present in the agreement which has been signed by both the sides, whereas, there is no such agreement between the parties for payment of 15% p.a. interest, if the amount is to be refunded to the complainants in any eventuality. Clearly a builder utilizes the amount paid by the allottees in the project and generally the amount is not available for earning any interest for a long time. However, as the amount remained with the builder and the amount has been ordered to be refunded, the builder is responsible to pay interest as held by the Hon'ble Supreme Court in Alok Shanker Pandey Vs. Union of India &Ors., II (2007) CPJ 3 (SC) as under:-

    4

    "9. It may be mentioned that there is misconception about interest. Interest is not a penalty or punishment at all, but it is the normal accretion on capital. For example if A had to pay B a certain amount, say 10 years ago, but he offers that amount to him today, then he has pocketed the interest on the principal amount. Had A paid that amount to B 10 years ago, B would have invested that amount somewhere and earned interest thereon, but instead of that A has kept that amount with himself and earned interest on it for this period. Hence equity demands that A should not only pay back the principal amount but also the interest thereon to B."

    11. When there is no contract between the parties for paying interest on the amount of refund, it is the discretion of the consumer forum to award reasonable interest in the matter. Clearly, the interest cannot be awarded on the basis of parity in such cases where there is no agreement for providing such an interest on the amount of refund. The Hon'ble Supreme Court in Kolkata West International Pvt. Ltd. Vs. Deva Asis Rudra, II (2019) CPJ 29 (SC)

    has reduced the rate of interest on the amount of refund from 12% per annum as awarded by this Commission to 9% per annum. Accordingly, I deem it appropriate to allow refund with 10% interest per annum in the facts and circumstances of the cases.

    12. When the interest rate has been ordered to be changed from 15% p.a. to 10% p.a., I do not find justification for setting aside the order of the State Commission in respect of the compensation of Rs.2,00,000/-.

    13. Based on the above discussion, these appeals no.531 of 2019, 532 of 2019, 533 of 2019 and 534 of 2019 are partly allowed and the orders of the State Commission passed in four complaints are modified to the extent that the appellants shall refund the amounts mentioned in the orders of the State Commission in each case along with 10% p.a. interest instead of 15% p.a. interest as ordered by the State Commission. With this modification, the orders of the State Commission passed in Complaint cases No.86 of 2017, 119 of 2017, 128 of 2017 and 15 of 2018 are upheld. The appellant shall also pay Rs.50,000/- (fifty thousand only) as cost for condoning the delay to the complainant in each case. The orders be complied with by the appellants within a period of 45 days from the date of receipt of this order.

    ......................

    PREM NARAIN