Order
1. Heard Mr Anupam Lal Das, learned counsel appearing for Respondent 4 Jaiprakash Associates Ltd. (JAL). Though many a contention has been raised by Mr Das, yet, we are not inclined to entertain the same keeping in view our orders dated 11-9-2017 (2018) 18 SCC 611 and 25-10-2017 (2018) 18 SCC 615. We have been told by Mr Das that JAL has deposited a sum of Rs 550 crores before the Registry of this Court. It is submitted by Mr Das that only 8% of the homebuyers/allottees are inclined to take refund whereas others have expressed their inclination to have the flats.
2. We would intend to make it absolutely clear that, for the present, we are only concerned with those homebuyers who intend to have refund. In the next phase, we may consider the grievances, if any, of the homebuyers who intend to have the flats. In that regard, we think it appropriate to hear Mr Parag P. Tripathi, learned Senior Counsel appearing for Interim Resolution Professional (IRP) and Mr Jayant Bhushan and Mr Sanjay Hegde and others, learned Senior Counsel appearing for some Associations of homebuyers who intend to have their flats.
3. As our order for deposit of Rs 2000 crores has not been complied with, we intend to pass the following directions:
3.1. JAL shall deposit a further sum of Rs 200 crores in two instalments, as agreed by the Managing Director who is present in Court today. The first instalment of Rs 100 crores shall be deposited by 15-4-2018 and the second instalment of Rs 100 crores shall be deposited by 10-5-2018;
3.2. It is submitted by Mr Pawanshree Agrawal, learned Amicus Curiae that as per his portal an amount of Rs 1300 crores, at present, is required to be refunded towards the principal sum for those homebuyers who, as of today, seek refund. The figure of Rs 1300 crores is as per the record of JAL.
In view of the aforesaid, we would require Mr Agrawal to prepare a projectwise chart indicating the number of persons in respect of that project and the stage of completion of the respective projects so that appropriate order can be passed for disbursement of the amount on pro rata basis to the homebuyers;
3.3. Mr Agrawal, learned Amicus Curiae shall keep the portal operational. However, the requests of only those persons on the portal who have sought refund, as of today will be considered at this stage;
3.4. The submission of the homebuyers who are seeking refund is that the developer is making demands towards monthly instalments. We direct that no demand towards outstanding or future instalments shall be raised by the developer to the flat buyers who have, as of today, expressed the option to obtain refund. The demands raised by the developer in respect of the homebuyers who have already opted for refund till today, shall remain stayed;
3.5. The IRP may proceed to finalise the resolution plan but the same shall be implemented after taking leave of this Court.
3.6. The National Company Law Tribunal (NCLT) shall decide subject to the directions which we have given hereinabove.
4. Before we fix the next date, we must note that we have been apprised that Mr Shekhar Naphade, learned Senior Counsel who was appointed to espouse the cause of the homebuyers before the Committee of Creditors has expressed his inability to continue as such.
5. In view of the aforesaid, a need has arisen to appoint someone else in place of Mr Shekhar Naphade and accordingly we appoint Mr Gaurav Agrawal, Advocate. It is further clarified that Mr Gaurav Agrawal shall be guided by our previous orders.
6. Let the matter be listed on 16-4-2018 so that this Court can take note of whether the developer has complied with the direction of depositing the first instalment and to pass directions with regard to disbursement of the amount deposited on pro rata basis on the basis of the report submitted by Mr Pawanshree Agrawal.