Factual and Procedural Background

The petitioner, M/s. Oriental Agencies, entered into a Work Contract dated 2/7/2004 with the Divisional Railway Manager (respondent No. 1) for the procurement and supply of stone ballast at Malia-Miyana Depot. The petitioner submitted the lowest offer which was accepted, and the contract stipulated completion by 16/2/2005. The petitioner supplied 5000 Cum of ballast and stacked it in the allotted space, but further supply was hindered due to lack of additional stacking space and non-allotment of hoppers for loading. Despite repeated requests, the railway authorities did not provide further space or hoppers. Subsequently, the Senior Divisional Manager issued a notice under Clause 62 of the General Conditions of Contract (GCC) citing inadequate progress and ultimately rescinded the contract on 12/7/2005, deciding to carry out the work at the risk and cost of the petitioner. Fresh tenders were invited, and although the petitioner submitted the lowest bid, the contract was awarded to another bidder at a higher price. The petitioner raised claims for damages under Clause 63 of the GCC, but no response was received. The petitioner then invoked the arbitration clause (Clause 64 of the GCC) requesting appointment of an arbitrator, which was not done by the General Manager. Consequently, the petitioner filed the present petition under Section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator and direction for the respondents to submit to arbitration.

Legal Issues Presented

  1. Whether there exists a valid and subsisting dispute arising out of the Work Contract dated 2/7/2004 that requires reference to arbitration.
  2. Whether the petitioner is entitled to appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996, given the rescission of the contract and subsequent actions of the parties.

Arguments of the Parties

Petitioner's Arguments

  • A dispute exists between the parties regarding the Work Contract dated 2/7/2004.
  • The petitioner raised claims under Clause 63 of the GCC which were not responded to by the Divisional Railway Manager.
  • The petitioner invoked the arbitration clause under Clause 64 of the GCC, requesting appointment of an arbitrator, but the General Manager failed to nominate one.
  • The petitioner seeks appointment of an arbitrator by the Court to adjudicate the dispute arising from the contract.

Respondents' Arguments

  • There is no valid or existing dispute requiring arbitration as the petitioner failed to fulfill the contract obligations.
  • The contract was rescinded after due notice due to non-performance by the petitioner.
  • The petitioner accepted the rescission and the decision to invite fresh tenders at the petitioner's risk and cost.
  • The petitioner also participated in the fresh tender process but did not succeed, and only thereafter raised a dispute.
  • Having accepted the rescission and fresh tender process, the petitioner cannot now raise claims or seek arbitration under the original contract.
  • The petition for appointment of an arbitrator is therefore not maintainable and should be dismissed.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court noted that the contract was rescinded by the Railway Authority on 12/7/2005 due to the petitioner's failure to fulfill contractual obligations, with fresh tenders invited at the petitioner's risk and cost. The petitioner did not object to this rescission or the invitation of fresh tenders at the relevant time and even participated in the new tender process. Given this acceptance, the Court held that there was no valid claim or dispute arising out of the original contract that required adjudication or reference to arbitration. The Court emphasized that once a contract is rescinded and fresh tenders invited, it is not open for the party to raise disputes or claims related to the rescinded contract. Accordingly, the petitioner's request for appointment of an arbitrator was not tenable and could not be granted.

Holding and Implications

The petition is dismissed.

The direct effect of this decision is that no arbitrator will be appointed to adjudicate the petitioner's claims arising from the rescinded contract. The petitioner’s acceptance of the rescission and participation in subsequent tendering precludes any arbitration under the original contract. The Court did not set any new legal precedent beyond the application of existing contractual and arbitration principles to the facts of this case.

    M/S Oriental Agencies Thro' It'S Proprietor Petitioner(S) v. The Divisional Railway Manager & 1 (S)

    ORAL ORDER

    1. Present petition has been preferred by the petitioner namely M/s. Oriental Agencies under sec.11 of the Arbitration and Conciliation Act, 1996 to appoint an arbitrator for adjudication of dispute raised by the petitioner in connection with the Work Contract dtd.2/7/2004 bearing No. M3/2003-2004/18, by further directing the respondents to submit to the jurisdiction of the Arbitral Tribunal that may be appointed by this Court.

    2. It is the case on behalf of the petitioner that the Divisional Railway Manager - respondent No. 1 herein issued Tender Notice inviting offer for Tender No. DRM/100 of 2003-2004 for procurement of stones Ballast at Malia-Miyana Depot including loading into Hoppers at depot. That the petitioner submitted its offer for Rs. 67,74,536.76 ps. for Scheduled Item No. A and Rs. 8,37,475.92 ps. for Scheduled Item No. B, totaling to Rs. 76,12,012.68 ps. The petitioner being lowest, his offer was accepted. That on 16/4/2004 the respondent No. 1 - DRM issued acceptance letter bearing No. W/623/118 of 2003-2004. According to the petitioner, the petitioner immediately commenced Work Order and thereafter the Contract Agreement No. M3/2004-2005/18 was executed on 2/7/2004. The work was to be completed on or before 16/2/2005. It is the case on behalf of the petitioner that thereafter the petitioner supplied 5000 Cum Ballast at the depot and stacked the Ballast at the space allotted to the petitioner at MALB depot. It is the case on behalf of the petitioner that after supply of the aforesaid quantity of Ballast, the space/plot allotted to the petitioner for stacking Ballast was full, hence supply of remaining Ballast was not possible because of non-allotment of additional plot/space for stacking Ballast. It is the case on behalf of the petitioner that thereafter the petitioner time and again requested for allotment of plot/space for stacking of Ballast and also requested for allotment of plot/space for stacking of Ballast for loading the Ballast which were already stacked into the plot allotted to the petitioner, however, neither additional space/plot nor Hoppers were allotted and therefore, remaining Ballast could not be supplied by the petitioner. It is the case on behalf of the petitioner that instead of providing required space for completing supply, the Senor Divisional Manager on 28/10/2004 issued communication under Clause-62 intimating the petitioner that the petitioner has failed in showing adequate progress of the work and called upon to make good progress within 7 days. It is the case on behalf of the petitioner that thereafter on 16/11/2004, the petitioner again requested the Senior Divisional Manager (NW) for allotment of Hoppers for loading. That thereafter, after few correspondences, the respondent No. 1 unilaterally granted extension on 31/3/2005 to 15/7/2005. upon token penalty of Rs. 5,000 per month or part hereof. As per the petitioner, by communication dtd.11/4/2005 the petitioner requested for waiving penalty clause while granting extension on the ground that supply and stacking of Ballast could not be made possible on account of non-allotment of plot/space for staking Ballast and non-allotment of Hoppers for loading Ballast which were already stacked. That thereafter again there were some further correspondences between the parties and thereafter on 8/6/2006 the Senior Divisional Manager (NW) issued notice bearing No. W/623/118 of 2003-2004 under clause 62 of GCC intimating the petitioner to rescind the contract and to carry out the work at the risk and cost and consequences of the petitioner after 48 hours. According to the petitioner, it filed its objection on 13/5/2005. That thereafter by communication/intimation dtd.12/7/2005 the Senior Divisional Manager (NW) intimated the petitioner that the contract is rescinded as per clause 62 of the GCC and work under contract will be carried on the risk and cost of the petitioner. That thereafter on 5/1/2004, the authority invited fresh offer for the said work vide Order No. DRM/ADI/157 of 2005-2006 vide Tender Notice No. 32/05/06. The petitioner also submitted its offer for the same and stood lowest (i.e Rs. 62,16,000), but the offers were not finalised. It is the case on behalf of the petitioner that thereafter the DRM requested the petitioner on 30/6/2006 to extend the validity of its offer of dtd.10/2/2006 in respect of Tender No. DRM/ADI/157 of 2005-2006 and the petitioner extended the validity of its offer till 27/9/2006. It is the case on behalf of the petitioner that even after extending the validity of the offer, the work was not awarded to the petitioner and the contract was awarded to other bidder at the highest price. That thereafter the petitioner lodged its claim on 22/2/2000 under Clause 63 of the GCC before the DRM (WA) for causing damage of Rs. 10,43,910 but no reply was given by the DRM. That thereafter the petitioner issued notice to the General Manager on 29/7/2006 for nominating arbitrator as per Clause 64 of GCC, as the claim raised by the petitioner in respect of Tender No. M3/05-06/18 was not settled by DRM under Clause-63 of GCC. However, as arbitrator was not appointed by the General Manager (NW), Mumbai, the petitioner has approached this Court by way of present petition invoking clause 64 of the GCC to appoint arbitrator and to relegate parties to the arbitration.

    3. Mr. Mehul Rathod, learned advocate appearing on behalf of the petitioner has submitted that there is dispute between the petitioner and the respondents and despite the claim raised by the petitioner on 22/2/2006, no reply was given by DRM and thereafter the petitioner invoked arbitration clause under clause 64 of GCC calling upon the General Manager, Western Railway, Mumbai to appoint arbitrator as per clause 64 of GCC and despite the same, the respondent No. 2 did not nominate arbitrator for adjudicating the claims and therefore, it is requested to appoint arbitrator to adjudicate the disputes between the parties arising out of Work Contract Agreement dtd.2/7/2004.

    4. Present petition is opposed by Mr. Mukesh A. Patel, learned advocate appearing on behalf of the respondents - Railway Authorities. It is submitted that as such there is no valid and/or existing dispute between the parties which is required to be referred to arbitration. It is submitted that despite various notices, the petitioner did not fulfill the contract and did not supply Ballast and therefore, the respondents authority had no other alternative but to rescind the contract and issue fresh tender at the risk and cost of the petitioner and after issuing notice upon the petitioner the contract was rescinded and fresh tender/bids were invited. It is submitted that the petitioner as such accepted rescinding of the contract and accepted decision of the railway authority in inviting fresh tender at the risk and cost of the petitioner. Not only that but the petitioner also submitted its bid/offer and having failed to get the contract, subsequently the petitioner has raised the dispute. It is submitted that once the petitioner has accepted rescinding of the contract, it is not open for the petitioner to raise any claim with respect to the contract which was already rescinded and decision to rescind the contract has been accepted by the petitioner. Therefore, it is submitted that as such there is no valid disputes and/or disputes at all and therefore, there is no question of appointment of arbitrator and referring the parties to the arbitration. Submitting accordingly it is requested to dismiss the present petition.

    5. Heard the learned advocates appearing on behalf of the respective parties.

    6. At the outset, is is required to be noted that in the present petition, the petitioner has requested to appoint arbitrator to adjudicate the dispute raised by the petitioner in connection with the Work Contract dtd.2/7/2004 bearing No. M3/2003-2004/18. It is to be noted that on non-fulfilling of the terms and conditions of the contract agreement and on non-supply of Ballast, the said contract awarded to the petitioner has been rescinded by the Railway Authority vide communication dtd.12/7/2005 and it wad decided to invite fresh tenders for the supply of remaining quantity at the risk and cost of the petitioner. The said decision to rescind the contract and to invite fresh tender was intimated to the petitioner on 12/7/2005. It appears that the petitioner accepted the said termination of the contract and inviting fresh tenders/offers at the risk and cost of the petitioner. Nothing is on record that the petitioner objected rescinding and/or terminating the contract and inviting fresh tender at the risk and cost of the petitioner, after intimation/communication dtd.12/7/2005. On the contrary, on 5/1/2006 the respondent authority invited offer for the said work vide Order No. DRM/ADI/157 of 2005-2006 vide Tender Notice No. 32/05/06 and therefore, it is not open for the petitioner now to raise any dispute/claim with respect to earlier contract which was already rescinded and fresh tenders were invited at the risk and cost of the petitioner which was never objected by the petitioner. Under the circumstances, there is no valid claim which is required to be adjudicated and referred to the arbitration. Once having accepted rescinding the contract and inviting offers afresh at the risk and cost of the petitioner, subsequently it is not open for the petitioner to raise any dispute/claim with respect to contract which is already rescinded and which has been accepted by the petitioner by not raising any dispute and/or even raising any claim at the relevant time. Under the circumstances, the prayer of the petitioner to appoint arbitrator to adjudicate the aforesaid claim, cannot be accepted and granted.

    7. Under the circumstances and for the reasons stated hereinabove, present petition deserves to be dismissed and is accordingly dismissed. Notice is discharged.