    Shri Jaichandlal Ashok Kumar & Company Pvt. Ltd. v. Nawab Yossuf & Anr.

    The Court: The parties entered into a development agreement. The respondents were the owners of the property at 5B, Outram Street, Calcutta whereas the appellant was the developer. The appellant would contend, he did whatever was required under the agreement, yet the respondents did not perform their obligations. The respondents would contend, the appellant allowed the sanction plan to be lapsed. Today they are in a precarious condition. The Arbitrator held in favour of the appellant to the extent, the appellant was able to prove their discharge of obligation under the contract and they were entitled to specific performance. The Arbitrator, however, denied relief on the ground, during the pendency of the arbitration the original owner died, the heirs became sentimental and were not willing to part with the property.

    Mr. Bachawat, learned Counsel appearing for the respondents, however, disputes such contention. The Arbitrator awarded an amount having a rough idea about the damage that the developer was likely to suffer in view of frustration of the contract. The Arbitrator awarded a sum of Rs. 5 crores approximately apart from costs. The parties applied for setting aside. The appellant filed the application for setting aside on the ground, they were not given the specific performance. The respondents were obviously unhappy in view of the finding of the Arbitrator as against them. The learned Single Judge upheld the award to the extent that held in favour of the appellant, they were able to perform their obligations and were entitled to specific performance, yet declined to grant any seal of approval on the pecuniary damage that the Arbitrator allowed. While doing so the learned Judge recorded a concession. We feel it relevant to quote it.

    “The award is upheld to the extent that it found that the claimant in the reference was entitled to specific performance of the agreement but ought not be granted the same. The award is set aside, on the concession of the claimant in the reference, in its grant of damages in lieu of specific performance and the quantification thereof. It will be open to the claimant in the reference to seek compensation in lieu of specific performance in a further reference that it may initiate wherein the claim will be considered in accordance with law in the light of the finding that the claimant was otherwise entitled to specific performance of the agreement.”

    Being aggrieved, the appellant has come up before us. Mr. Bachawat appearing for the respondents submits, he is also inclined to prefer an appeal, however, cannot do so in absence of his Advocate-on-Record who is unwell and out of station for medical check up.

    Our attention has been drawn to an order passed by the learned Single Judge just after publishing of the award appearing at pages 156-157 of the petition wherein His Lordship, to protect the interest of the parties, restrained the respondents from transferring in any form the premises no. 5B, Outram Street, Calcutta without excluding lands equivalent to Rs. 5 crores. His Lordship further observed, “in the event any transfer is effected, the same be done with the leave of the Court. In the event sums aggregating to Rs. 5 crores is deposited in Court, such leave need not be taken.” The parties suffered the said order since July 18, 2008. We are told, the learned Judge subsequently confirmed the said order.

    Whether the award was rightly set aside or not, is a question to be decided at the final hearing of the appeal. We are approaching the vacation. It may not be possible for us to decide the issue finally at this stage. Moreover, the parties would have to complete the formalities. Hence, we expedite the hearing of the appeal.

    There would be an order in terms of prayer (a) of the petition.

    The parties are all represented by their respective Advocates. Hence, service of notice of appeal is dispensed with. The appellant would be at liberty to file requisite number of informal paper book incorporating all papers used before the learned Single Judge within two weeks after the Summer Vacation. As soon as paper book is filed, place the appeal for hearing. In default, place it for final order.

    On the question of interim protection lot is argued on Section 18 of the Arbitration Act, 1940. Significant to note, the award was published under the old arbitration law. For our benefit Section 18 is quoted below:

    “18. POWER OF COURT TO PASS INTERIM ORDERS -(1) Notwithstanding anything contained in Sec.17, at any time after the filing of the award, whether notice of the filing has been served or not, upon being satisfied by affidavit or otherwise that a party has taken or is about to take steps to defeat, delay or obstruct the execution of any decree that may be passed upon the award, or that speedy execution of the award is just and necessary, the Court may pass such interim orders as it deems necessary.

    (2) Any person against whom such interim orders have been passed may show cause against such orders, and the Court after hearing the parties, may pass such further orders as it deems necessary and just.”

    Mr. Bachawat would contend, Section 18 is not an automatic provision that would presuppose passing of an order protecting the interest of the appellant. We fully agree with Mr. Bachawat on that score. Mr. Bachawat would further contend, the learned Single Judge imposed the fetter on them at a stage when they were confronted with an award of Rs. 5 crores approximately. Today, when the appeal is preferred, the award merged in the order of the learned Single Judge whereby the appellant would at best claim a sum of Rs. 35 lakhs. Hence imposition of such fetter would not be warranted. Moreover, the appellant would also not be interested to get such protection.

    It is true, the appellant would seriously contend before us, we should restrain the respondents from dealing with the property itself. On a query made by this Court, Mr. Bachawat would inform us he is not aware of any other worth the respondents have apart from this property. He is, however, very candid to say, in the absence of his Advocate-on-Record he cannot assist this Court any further on the issue.

    Section 18 is an enabling provision for the Court to consider and pass order giving interim protection to the parties when the award is delayed or obstructed for being implemented. It is rather preservation of the subject of controversy. There cannot be any straight-jacket formula where the court would be fitting the facts to get the result as to whether an application of the like nature would be allowed or not. The underlying principle would emanate from the idea of postponement of the final judgment. When a lis is brought to the Court, the litigant is technically entitled to be considered for the relief immediately, yet formalities would have to be complied with. The opposite party has to be summoned. He has to be given adequate opportunity to defend the proceeding. In the process, there would be delay. The interest of the lis, should thus be protected at the end of the day the winning party should not be favoured with a paper decree without having any chance of execution. Similar principle is followed other way round. If a party loses in a litigation and he prefers an appeal that is considered to be continuation of the original litigation, the Court of Appeal may grant some protection to the appellant protecting the subject of controversy. The question would thus remain, what would be the yardstick. It is an age-old principle, the yardstick is based upon perception of the Court to have a prima facie view on the lis and the balance of convenience.

    Applying our understanding of law as expressed hereinbefore, in the present scenario we would find, a party having an award of Rs. 5 crores was asking for more than what he got. His application for setting aside to that extent, was not allowed. On the contrary, to the extent he got the award on the principal issue, had the seal of approval of the learned Single Judge. We are of the view, the learned Judge possibly misunderstood the appellant while recording the concession. The appellant was consistent with his prayer for specific performance.

    They did not get it from the Arbitrator. They did not get it from the learned Single Judge as well. However, before they could know the result of the application for setting aside, in course of hearing they made themselves clear, nothing sort of specific performance would satisfy them.

    All the above, are our prima facie view. The questions would definitely be gone into by us at the regular hearing. We feel, interest of justice would subserve, if we restore the order dated July 18, 2008 that the parties suffered for long. It is for the parties to expedite the process of preparation of the appeal making the same ready for hearing. We can assure them, to the best of our ability, we would try to dispose of it at an early date.

    GA No. 1417 of 2013 is disposed of without any order as to costs.