Factual and Procedural Background

The complainant (respondent before this Court) booked flat No. T-113/GF (1,164 sq. ft.) in Project TDI City, Tucson Floor, Kundli, Sonepat on 30.04.2010 (Customer ID KTF-10308) and paid Rs. 16,92,286/- by instalments. The opposite parties (petitioner before this Court) allegedly failed to complete construction and cancelled the booking instead of delivering possession. Legal notices dated 03.04.2012 and 08.05.2012 were served without effect. The complainant filed a complaint before the District Forum (Complaint No. 251 of 2012 — Pardeep Mathur v. TDI Infrastructure Ltd.). The District Forum allowed the complaint and directed the opposite parties to hand over possession on deposit of the balance amount with 9% p.a. interest (order dated 29.04.2013). The opposite parties appealed to the Haryana State Consumer Disputes Redressal Commission, Panchkula (State Commission) in Appeal No. 477 of 2013 (Taneja Developers and Infrastructure Ltd. v. Pardeep Mathur). The State Commission partly allowed the appeal by increasing the interest rate from 9% to 10% and upheld the rest of the District Forum's order (impugned order dated 17.09.2013). The petitioner filed this revision petition challenging the State Commission's order and also sought condonation of delay in filing (office report showed 71 days' delay).

Legal Issues Presented

  1. Whether the District Forum had pecuniary jurisdiction to entertain the complaint where the total basic cost of the allotted flat was Rs. 27,50,000/- while the pecuniary limit of the District Forum was Rs. 20.00 lacs.
  2. Whether the delay of 71 days in filing the revision petition should be condoned in view of the explanation offered and Supreme Court precedents condoning longer delays on payment of costs.

Arguments of the Parties

Petitioner's Arguments

  • The total basic cost of the flat was Rs. 27,50,000/-, which exceeded the pecuniary jurisdiction of the District Forum (limited to Rs. 20.00 lacs); therefore, the District Forum erred in entertaining and allowing the complaint.
  • The State Commission further erred in not setting aside the District Forum's order; hence the revision petition should be allowed and the impugned order set aside.
  • In support of condonation of delay, petitioner explained an inadvertent administrative error: after receiving the State Commission order on 27.09.2013, the reception desk mistakenly sent the file to the record room, delaying filing of the revision petition.

Respondent's Arguments

  • The respondent contended that only the balance payment (which was below Rs. 20.00 lacs) was to be paid at the time of filing the complaint; therefore, the District Forum had pecuniary jurisdiction and the State Commission's order was lawful — the revision petition should be dismissed.
  • The respondent opposed condonation of delay, submitting there was no reasonable explanation for the delay.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Civil Appeal Nos. 10120-10121 of 2014 - Jeevanti Devi v. Commercial Motors Condonation of delay (example where 135 days' delay was condoned on payment of cost). Relied upon as authority to condone the 71-day delay subject to payment of costs.
Civil Appeal No. 10289 of 2014 - Ali A.T. v. State Bank of India Condonation of delay (example where 149 days' delay was condoned on payment of cost). Relied upon as authority to condone the 71-day delay subject to payment of costs.
Civil Appeal No. 5071 of 2014 - Taipen Traders Ltd. v. Bhawani Cold Storage Condonation of delay (example where 218 days' delay was condoned on payment of cost). Relied upon as authority to condone the 71-day delay subject to payment of costs.

Court's Reasoning and Analysis

On condonation of delay: The Court noted an office report of 71 days' delay in filing the revision petition. It accepted the petitioner's explanation that the State Commission's order was inadvertently sent to the record room by the reception desk, causing the delay. The Court considered recent Supreme Court decisions that had condoned substantially longer delays (135, 149 and 218 days) on payment of costs and, on that basis, found the explanation sufficient to condone the 71-day delay. Consequently, the Court allowed the condonation application subject to payment of Rs. 5,000/- as costs to the respondent.

On pecuniary jurisdiction: The Court examined the registration form which showed the total basic cost of the allotted flat as Rs. 27,50,000/-. The opposite parties had specifically pleaded before the District Forum that the District Forum lacked pecuniary jurisdiction, but the District Forum allowed the complaint without considering this objection. The State Commission also failed to consider the jurisdictional objection despite its mention in the memorandum of appeal. The Court held that for purposes of pecuniary jurisdiction of the fora below the total cost of the flat must be considered, even if the outstanding amount at the time of filing the complaint was less than Rs. 20.00 lacs. Because the total basic cost exceeded the District Forum's pecuniary limit of Rs. 20.00 lacs, the District Forum had no jurisdiction to entertain the complaint. The District Forum therefore committed an error in entertaining and allowing the complaint, and the State Commission erred in not dismissing it on that ground.

Holding and Implications

The revision petition is allowed; the impugned order dated 17.09.2013 passed by the State Commission is set aside and the District Forum's order dated 29.04.2013 in Complaint No. 251 of 2012 is quashed.

Implications and direct effects:

  • The complaint before the District Forum is dismissed for lack of pecuniary jurisdiction.
  • The condonation of delay in filing the revision petition is allowed subject to payment of Rs. 5,000/- as cost to the respondent, to be paid within 15 days.
  • The Court recorded "no order as to costs" in relation to the substantive dismissal of the complaint.
  • No broader precedent or law-making pronouncement beyond the immediate decision is discussed in the opinion; the decision's practical effect is the dismissal of the complaint for lack of jurisdiction and allowance of the revision petition on that ground.

    Tdi Infrastructure Limited v. Pradeep Mathur

    K.S. Chaudhari, Presiding Member:— This revision petition has been filed by the petitioner against the order dated 17.09.2013 passed by the learned Haryana State Consumer Disputes Redressal Commission, Panchkula (in short, ‘the State Commission’) in Appeal No. 477 of 2013 - Taneja Developers and Infrastructure Ltd. v. Pardeep Mathur by which, while allowing appeal partly, order of District Forum allowing complaint was modified.

    2. Brief facts of the case are that Complainant/respondent applied for a flat bearing No. T-113/GF measuring 1164 Sq. ft. in Project TDI City, Tuscon Floor in Kundli, Sonepat vide Customer ID No. KTF-10308 dated 30.4.2010 and deposited Rs. 16,92,286/- with the opposite parties/petitioner from time to time. However, the opposite parties failed to complete the construction of the flat. As there was no progress in construction at the site, the complainant approached the opposite parties to know the reason but the opposite parties did not give any satisfactory reply. Legal notice dated 3.4.2012 and 8.5.2012 were also served upon the opposite parties but to no effect. Instead of delivering possession of the flat, the opposite parties cancelled the booking of the flat. Alleging deficiency on the part of OP, complainant filed complaint before District Forum. OP resisted complaint and submitted that the allotment of the flat was cancelled due to non-payment of dues by the complainant. It was further stated that the basic cost of the flat was Rs. 27,50,000/- whereas the pecuniary limit of the District forum was upto Rs. 20.00 lacs and therefore the complaint before the District forum was not maintainable. Denying the allegations of the complainant, the opposite parties prayed for dismissal of the complaint. Learned District Forum after hearing both the parties allowed complaint and directed OP to handover possession of flat on depositing balance amount by complainant with 9% p.a. interest. Appeal filed by OP was partly allowed by learned State Commission vide impugned order increased rate of interest from 9% to 10% and rest of the order was upheld against which, this revision petition along with application for condonation of delay was filed.

    3. Heard learned Counsel for the parties finally at admission stage and perused record.

    4. Petitioner has filed application for condonation of delay. As per office report, there is delay of 71 days in filing revision petition. Petitioner submitted in the application that after receiving order on 27.9.2013, reception desk inadvertently and by mistake sent it to record room along with file and at the time of quarterly evaluation, status of pending matters came to be known and thereafter record was traced and revision petition was filed. Learned Counsel for the petitioner submitted that by inadvertence record was consigned to record room, so, revision petition could not be filed in time; hence, delay may be condoned. Learned Counsel for the respondent submitted that as there is no reasonable explanation for condonation of delay, application be dismissed. As there is delay of 71 days with reasonable explanation regarding sending file to the record room by inadvertence, I deem it appropriate to condone delay in the light of latest judgments of Hon'ble Apex Court in (1) Civil Appeal Nos. 10120-10121 of 2014 - Jeevanti Devi v. Commercial Motors; (2) Civil Appeal No. 10289 of 2014 - Ali. A.T. v. State Bank of India; and (3) Civil Appeal No. 5071 of 2014 - Taipen Traders Ltd. v. Bhawani Cold Storage by which delay of 135 days, 149 days and 218 days, respectively in filing revision petition was condoned on cost. Consequently, application for condonation of delay is allowed and delay stands condoned subject to payment of Rs. 5,000/- as cost to the respondent.

    5. Learned Counsel for the petitioner submitted that flat was booked for Rs. 27,50,000/- and inspite of no pecuniary jurisdiction with District forum, learned District forum committed error in entertaining and allowing complaint and learned State Commission further committed error in dismissing appeal; hence, revision petition be allowed and impugned order be set aside. On the other hand, learned Counsel for the respondent submitted that as only balance payment which was below Rs. 20.00 lacs was to be paid, learned District Forum has pecuniary jurisdiction and order passed by learned State Commission is in accordance with law; hence, revision petition be dismissed.

    6. Perusal of registration form clearly reveals that total basic cost of the flat which was allotted to complainant was Rs. 27,50,000/-. OP specifically pleaded in written statement that District Forum had no pecuniary jurisdiction to entertain the complaint, but learned District forum inspite of recording submissions of Counsel for the OP failed to consider this objection and allowed complaint without any pecuniary jurisdiction. Perusal of impugned order also reveals that learned State Commission has not considered this aspect inspite of specific objection in memo of appeal.

    7. As flat was allotted on total basic cost of Rs. 27,50,000/- inspite of the fact that less than Rs. 20.00 lacs were outstanding in the complainant at the time of filing complaint, for the purposes of pecuniary jurisdiction of Fora below, total cost of flat was to be considered and as District forum was having pecuniary jurisdiction upto Rs. 20.00 lacs, District Forum had no jurisdiction to entertain complaint pertaining to flat costing Rs. 27,50,000/- and learned District forum committed error in entertaining and allowing complaint and learned State Commission further committed error in not dismissing complaint and revision petition is to be allowed.

    8. Consequently, revision petition filed by the petitioner is allowed and impugned order dated 17.09.2013 passed by the learned State Commission in Appeal No. 477 of 2013 - Taneja Developers and Infrastructure Ltd. v. Pardeep Mathur of District forum dated 29.4.2013 passed in Complaint No. 251 of 2012 - Pardeep Mathur v. TDI Infrastructure Ltd. is set aside subject to payment of cost of Rs. 5,000/- for condonation of delay within 15 days and complaint stands dismissed with no order as to costs.