  • 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets 648.68 670.42 692.58 715.56 739.31Interest on Working Capital (IWC)59. Clause 1(c) of Regulation 28 and Clause 5 of Regulation 3 of the 2014 Tariff Regulations
  • 15.2.2011 52898.71 1657.49 560.50 0.00 0.00 0.00 2217.99 55116.70 Actual 52898.71 1658.56 169.67 150.04 22.95 0.00 2001.22 54899.93Debt: Equity15. Clause 2 of Regulation 12 of the 2009 Tariff Regulations
  • (%) 9.3044 9.3045 9.3046 9.3047 9.3050 Interest 2067.68 1797.89 1528.10 1258.31 988.52Return on Equity (ROE)49. Clause (1) and (2) of Regulation 24 and Clause (2) of Regulation 25 of the 2014 Tariff Regulations
  • Tax) 3229.76 3229.76 3229.76 3229.76 3229.76Depreciation53. Clause (2), (5) and (6) of Regulation 27 of the 2014 Tariff Regulations provide as follows:27. Depreciation:(2)
  • (%) Debt 38429.95 70.00 Equity 16469.98 30.00 Total 54899.93 100.00Interest on Loan (IOL)47. Clause (5) and (6) of Regulation 26 of the 2014 Tariff Regulations
  • 35 years (e) Transmission line 35 years28. Clause (4) of Regulation 17 of the 2009 Tariff Regulations provides as follows:17. Depreciation:(4) Depreciation
  • Clause (2) of Regulation 9 of the 2009 Tariff Regulations.11. Clause (1) of Regulation 9 of the 2009 Tariff Regulations
  • (IWC)33. Sub-clause (c) of clause (1) of Regulation 18 of the 2009 Tariff Regulations
  • Equity (ROE)23. Clause (3), (4) and (5) of Regulation 15 of the 2009 Tariff Regulations
  • equity.Depreciation27. Clause (42) of Regulation 3 of the 2009 Tariff Regulations
  • Equity Ratio45. Clause 3 and 4 of Regulation 19 of the 2014 Tariff Regulations
  • sub-clause (c) of clause (1) of Regulation 18 of the 2009 Tariff Regulations.35.
  • Clause (1) and (3) of Regulation 12 of the 2009 Tariff Regulations.19.
  • tariff12. Clause (2) of Regulation 9 of the 2009 Tariff Regulations
  • clause (3) of Regulation 18 of the 2009 Tariff Regulations
  • Clause (2) of Regulation 7 of the 2009 Tariff Regulations
  • Clause (1) of Regulation 9 of the 2009 Tariff Regulations
  • SECTION 64 ELECTRICITY ACT 2003
  • INCOME TAX ACT 1961
Are you a practicing lawyer?
Enhance your digital presence and reach by creating a Casemine profile.
Upload pleading to use the new AI search
Cites
Cited by
Citation Codes
Equivalent Citations
citation codes
Case Number
Judges
Acts
  • 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets 648.68 670.42 692.58 715.56 739.31Interest on Working Capital (IWC)59. Clause 1(c) of Regulation 28 and Clause 5 of Regulation 3 of the 2014 Tariff Regulations
  • 15.2.2011 52898.71 1657.49 560.50 0.00 0.00 0.00 2217.99 55116.70 Actual 52898.71 1658.56 169.67 150.04 22.95 0.00 2001.22 54899.93Debt: Equity15. Clause 2 of Regulation 12 of the 2009 Tariff Regulations
  • (%) 9.3044 9.3045 9.3046 9.3047 9.3050 Interest 2067.68 1797.89 1528.10 1258.31 988.52Return on Equity (ROE)49. Clause (1) and (2) of Regulation 24 and Clause (2) of Regulation 25 of the 2014 Tariff Regulations
  • Tax) 3229.76 3229.76 3229.76 3229.76 3229.76Depreciation53. Clause (2), (5) and (6) of Regulation 27 of the 2014 Tariff Regulations provide as follows:27. Depreciation:(2)
  • (%) Debt 38429.95 70.00 Equity 16469.98 30.00 Total 54899.93 100.00Interest on Loan (IOL)47. Clause (5) and (6) of Regulation 26 of the 2014 Tariff Regulations
  • 35 years (e) Transmission line 35 years28. Clause (4) of Regulation 17 of the 2009 Tariff Regulations provides as follows:17. Depreciation:(4) Depreciation
  • Clause (2) of Regulation 9 of the 2009 Tariff Regulations.11. Clause (1) of Regulation 9 of the 2009 Tariff Regulations
  • (IWC)33. Sub-clause (c) of clause (1) of Regulation 18 of the 2009 Tariff Regulations
  • Equity (ROE)23. Clause (3), (4) and (5) of Regulation 15 of the 2009 Tariff Regulations
  • equity.Depreciation27. Clause (42) of Regulation 3 of the 2009 Tariff Regulations
  • Equity Ratio45. Clause 3 and 4 of Regulation 19 of the 2014 Tariff Regulations
  • sub-clause (c) of clause (1) of Regulation 18 of the 2009 Tariff Regulations.35.
  • Clause (1) and (3) of Regulation 12 of the 2009 Tariff Regulations.19.
  • tariff12. Clause (2) of Regulation 9 of the 2009 Tariff Regulations
  • clause (3) of Regulation 18 of the 2009 Tariff Regulations
  • Clause (2) of Regulation 7 of the 2009 Tariff Regulations
  • Clause (1) of Regulation 9 of the 2009 Tariff Regulations
  • SECTION 64 ELECTRICITY ACT 2003
  • INCOME TAX ACT 1961
Smart Summary

Structured Summary of the Legal Opinion — Petition No. 389.TT/2014

Factual and Procedural Background

The petition was filed by Power Grid Corporation of India Ltd. ("the petitioner") seeking:

  • Truing up of capital expenditure for the 2009-14 tariff period under Regulation 6 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 ("2009 Tariff Regulations"); and
  • Determination of tariff for the 2014-19 tariff period under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 ("2014 Tariff Regulations").

The subject asset is the Combined Assets of the 400 kV D/C Ranchi–Sipat transmission line with associated bays at Ranchi and Sipat substations and 40% FSC on the 400 kV Ranchi–Sipat line at Ranchi substation under the Kahalgaon-II Phase‑II transmission system in the Western Region (referred to in the opinion as "the transmission asset").

Key factual and procedural milestones recorded in the opinion:

  • Investment approval (Government of India) dated 24.01.2005 at an estimated cost of Rs. 46,402 lakh (including IDC of Rs. 2,898 lakh); a revised cost estimate was approved by the petitioner’s Board on 16.02.2009 for Rs. 57,283.96 lakh (including IDC of Rs. 5,770 lakh).
  • Date of commercial operation (COD) of the combined asset: 01.03.2009.
  • Tariff for the period from COD to 31.03.2009 was allowed by order dated 13.05.2010 (Petition No. 247/2009) under the 2004 Tariff Regulations.
  • Tariff for 2009–14 was allowed by order dated 15.02.2011 in Petition No. 226/2010 based on an admitted capital cost of Rs. 52,898.71 lakh and debt:equity ratio of 70:30.
  • The instant petition was filed on 20.09.2014. Notices under Section 64 of the Electricity Act, 2003 were published; no public comments were received. A hearing was held on 13.01.2016. None of the respondents filed replies. The Commission heard petitioner’s representatives and proceeded to dispose of the petition.

Legal Issues Presented

  1. Whether the additional capitalisation claimed for the Combined Assets during the 2009–14 tariff period (aggregate claimed: Rs. 2,001.22 lakh) can be admitted and included in the trued up capital cost in accordance with Regulations 7 and 9 of the 2009 Tariff Regulations.
  2. Determination of trued up annual fixed charges for the 2009–14 tariff period, including treatment of capital cost, debt:equity, interest on loan, return on equity (grossed up for MAT), depreciation, operation & maintenance (O&M) expenses and interest on working capital in accordance with the 2009 Tariff Regulations.
  3. Determination of tariff for the 2014–19 tariff period using the trued up capital cost as on 01.04.2014 (Rs. 54,899.93 lakh) and application of the 2014 Tariff Regulations for components: capital cost, debt:equity, IOL, ROE (grossed up for MAT), depreciation, O&M norms and interest on working capital.
  4. Entitlements and recoverability issues raised by the petitioner: reimbursement of filing fee and publication expenses; separate billing/recovery of licence fee and RLDC fees & charges; treatment of service tax and recovery of deferred tax liability (as per relevant provisions of the 2014 Tariff Regulations).

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Commission's analysis is structured around components of tariff as regulated under the applicable tariff regulations for the two relevant periods (2009–14 under the 2009 Tariff Regulations and 2014–19 under the 2014 Tariff Regulations). The decision follows a methodical application of those regulations to the facts and documentary material submitted by the petitioner.

Overall approach

  • The Commission accepted the petitioner’s admitted capital cost as on 31.03.2009 (Rs. 52,898.71 lakh) as the opening capital cost on 01.04.2009, consistent with the last proviso to Clause (2) of Regulation 7 of the 2009 Tariff Regulations.
  • Additional capitalisation claimed for 2009–14 (total claimed Rs. 2,001.22 lakh) was examined against Clauses (1) and (2) of Regulation 9 of the 2009 Tariff Regulations and admitted subject to prudence checks and supporting auditor certificates; the Commission found the additional capital expenditure allowable as per the Regulations and within approved cost.
  • For the 2014–19 tariff period, the Commission adopted the trued up capital cost as on 01.04.2014 (Rs. 54,899.93 lakh) as the base capital cost per Clause (1) and (3) of Regulation 9 of the 2014 Tariff Regulations for existing projects.
  • Where the 2009 Regulations or 2014 Regulations require grossing up ROE with the applicable tax rate (MAT where applicable), the Commission applied the relevant provisions and used the MAT rates applicable to each year for grossing up (for 2009–14) and the MAT rate applicable in 2013–14 for the 2014–19 computation, subject to truing up as provided by the 2014 Regulations.

Component-wise analysis and application

Capital cost and additional capitalisation

  • Opening admitted capital cost as on 01.04.2009: Rs. 52,898.71 lakh (adopted from earlier order dated 13.05.2010 / 15.02.2011 for truing up).
  • Additional capitalisation claimed by the petitioner (actuals) during 2009–14:
    • 2009–10: Rs. 1,658.56 lakh
    • 2010–11: Rs. 169.67 lakh
    • 2011–12: Rs. 150.04 lakh
    • 2012–13: Rs. 22.95 lakh
    • Total additional capitalisation for 2009–14: Rs. 2,001.22 lakh
  • Total trued up capital cost including additional capitalisation as on 31.03.2014: Rs. 54,899.93 lakh (admitted and used as opening capital cost for 2014–19).
  • The Commission accepted the petitioner’s submission (including auditor certificate) and admitted the additional capitalisation as per the 2009 Tariff Regulations.

Debt:Equity

  • For assets declared under commercial operation prior to 01.04.2009, Regulation 12(2) of the 2009 Tariff Regulations requires use of the debt:equity ratio allowed by the Commission for the period ending 31.03.2009. The same principle is reflected in the 2014 Regulations for the period ending 31.03.2014.
  • The Commission therefore used the admitted debt:equity ratio of 70:30 as on 31.03.2009 and carried forward the 70:30 ratio (as on 31.03.2014) for the 2014–19 tariff calculations.
  • Accordingly, the funding split at trued up capital cost as on 31.03.2014 (Rs. 54,899.93 lakh) is:
    • Debt: Rs. 38,429.95 lakh (70%)
    • Equity: Rs. 16,469.98 lakh (30%)
  • The petitioner provided confirmation and undertakings that additional capitalisation was funded on 70:30 basis and actuals were reflected accordingly.

Interest on Loan (IOL)

  • For 2009–14, the Commission calculated the weighted average rate of interest on the basis of the petitioner’s actual loan portfolio and rates in accordance with Regulation 16 of the 2009 Tariff Regulations. Annexure-I in the opinion contains the portfolio details used.
  • IOL allowed after truing up for 2009–14 (Rs. in lakh):
    • 2009–10: 3,338.88
    • 2010–11: 3,129.94
    • 2011–12: 2,871.24
    • 2012–13: 2,606.73
    • 2013–14: 2,337.47
  • For 2014–19, IOL was computed in accordance with Regulation 26 of the 2014 Tariff Regulations, using the weighted average rate of interest based on rate prevailing as on 01.04.2014 (Annexure-II provides portfolio details). IOL allowed for 2014–19 (Rs. in lakh):
    • 2014–15: 2,067.68
    • 2015–16: 1,797.89
    • 2016–17: 1,528.10
    • 2017–18: 1,258.31
    • 2018–19: 988.52

Return on Equity (ROE)

  • The Commission applied the regulatory formula to gross up the base ROE (base rate 15.50%) with the applicable tax rate (MAT where applicable) as required by the 2009 and 2014 Tariff Regulations.
  • For 2009–14, the ROE was grossed up year-by-year using the actual MAT rates applicable in the respective years (the opinion lists yearwise MAT rates and resulting grossed-up pre‑tax ROE percentages). The ROE allowed after truing up for 2009–14 (Rs. in lakh):
    • 2009–10: 3,009.95
    • 2010–11: 3,173.29
    • 2011–12: 3,185.69
    • 2012–13: 3,190.72
    • 2013–14: 3,229.76
  • For 2014–19 the Commission used the MAT rate applicable in 2013–14 (20.961%) for grossing up ROE, consistent with the 2014 Tariff Regulations, while noting that the grossed-up ROE is subject to truing up against actual tax paid during the tariff period. ROE allowed for 2014–19 (Rs. in lakh) is constant each year:
    • Each year (2014–15 through 2018–19): 3,229.76

Depreciation

  • Depreciation was calculated using the Straight Line Method, applying the rates and useful lives specified by the relevant regulations.
  • For the transmission asset the weighted average useful life at COD was taken as 33 years (as applied for the 2009–14 computations), and depreciation was computed in accordance with Regulation 17 of the 2009 Tariff Regulations for 2009–14.
  • Depreciation allowed after truing up for 2009–14 (Rs. in lakh):
    • 2009–10: 2,837.90
    • 2010–11: 2,886.16
    • 2011–12: 2,894.60
    • 2012–13: 2,899.17
    • 2013–14: 2,899.78
  • For 2014–19 depreciation has been computed in accordance with Regulation 27 of the 2014 Tariff Regulations using the opening depreciable value as on 01.04.2014; depreciation allowed each year 2014–19 (Rs. in lakh): 2,899.78.

Operation & Maintenance (O&M) Expenses

  • For 2009–14, the petitioner’s claimed O&M expenses matched the norms and the amounts approved by the earlier order dated 15.02.2011; the Commission allowed (and trued up) the same amounts for 2009–14:
    • 2009–10: 568.82
    • 2010–11: 601.43
    • 2011–12: 635.87
    • 2012–13: 672.20
    • 2013–14: 710.48
  • For 2014–19 O&M expenses were determined as per the 2014 Tariff Regulations' norms (including per-bay and per-km norms). O&M allowed (Rs. in lakh):
    • 2014–15: 648.68
    • 2015–16: 670.42
    • 2016–17: 692.58
    • 2017–18: 715.56
    • 2018–19: 739.31
  • The petitioner noted possible future impact of wage revision and sought liberty to approach the Commission for revision in O&M norms; the Commission stated any such application will be dealt with under the 2014 Tariff Regulations.

Interest on Working Capital (IWC)

  • For 2009–14, the rate of interest on working capital was taken as 12.25% (SBI short-term PLR as on 01.04.2009) in accordance with clause (3) of Regulation 18 of the 2009 Tariff Regulations. IWC allowed after truing up for 2009–14 (Rs. in lakh):
    • 2009–10: 219.92
    • 2010–11: 221.61
    • 2011–12: 218.38
    • 2012–13: 214.88
    • 2013–14: 212.01
  • For 2014–19, IWC components and rate were determined under Regulation 28 of the 2014 Tariff Regulations:
    • Components: maintenance spares (15% of O&M), one month O&M and receivables equal to two months of fixed cost.
    • Rate: SBI Base Rate as on 01.04.2014 plus 350 basis points (10.00% + 3.50% = 13.50%).
    • IWC allowed for 2014–19 (Rs. in lakh):
      • 2014–15: 224.52
      • 2015–16: 219.51
      • 2016–17: 214.52
      • 2017–18: 209.58
      • 2018–19: 204.68

Annual Fixed / Transmission Charges — computation and summary

  • For 2009–14 the Commission summarised the trued up annual transmission charges (Annual Fixed Charges) after allowing the components described above. Totals (Rs. in lakh) after truing up for 2009–14:
    • 2009–10: 9,975.47
    • 2010–11: 10,012.42
    • 2011–12: 9,805.78
    • 2012–13: 9,583.70
    • 2013–14: 9,389.50
  • For 2014–19 the Commission determined annual transmission charges on the basis of the trued up capital cost as on 01.04.2014 and the 2014 Tariff Regulations. Annual Transmission Charges allowed (Rs. in lakh):
    • 2014–15: 9,070.42
    • 2015–16: 8,817.36
    • 2016–17: 8,564.74
    • 2017–18: 8,313.00
    • 2018–19: 8,062.06

Other issues addressed

  • Filing fee and publication expenses: The petitioner shall be entitled to reimbursement of filing fees and publication expenses from beneficiaries on a pro‑rata basis in accordance with Regulation 52(1) of the 2014 Tariff Regulations.
  • Licence fee and RLDC fees & charges: The petitioner is entitled to recover licence fee and RLDC fees & charges separately from the respondents in accordance with Regulation 52(2)(b) and Regulation 52(2)(a) respectively of the 2014 Tariff Regulations.
  • Service tax: The petitioner sought to recover service tax on transmission charges if service tax on transmission is removed from the negative list in future. The Commission considered the prayer premature.
  • Deferred tax liability: The petitioner’s request to recover deferred tax liability prior to 01.04.2009 when materialised was dealt with — recovery to be as per Regulation 49 of the 2014 Tariff Regulations when deferred tax liability materializes; entitlement to recover deferred tax liability up to 31.03.2009 directly from beneficiaries or long‑term transmission customers/DICs was acknowledged subject to that regulation.
  • Sharing of transmission charges: Billing, collection and disbursement of the approved transmission charges shall be governed by the Central Electricity Regulatory Commission (Sharing of Inter‑State Transmission Charges and Losses) Regulations, 2010 (as amended), as provided in Regulation 43 of the 2014 Tariff Regulations.

Holding and Implications

Holding:

The Commission allowed the trued up capital cost and annual fixed charges for the Combined Assets for the 2009–14 tariff period and determined the annual transmission charges for the 2014–19 tariff period as set out in the order, and the petition is disposed of.

Specific outcomes (as recorded in the opinion and forming the direct operative effect):

  • Trued up total capital cost as on 31.03.2014: Rs. 54,899.93 lakh (including admitted additional capitalisation of Rs. 2,001.22 lakh for 2009–14).
  • Trued up Annual Fixed Charges for 2009–14 (Rs. in lakh): 2009–10: 9,975.47; 2010–11: 10,012.42; 2011–12: 9,805.78; 2012–13: 9,583.70; 2013–14: 9,389.50.
  • Annual Transmission Charges determined for 2014–19 (Rs. in lakh): 2014–15: 9,070.42; 2015–16: 8,817.36; 2016–17: 8,564.74; 2017–18: 8,313.00; 2018–19: 8,062.06.
  • The petitioner is entitled to recovery (from beneficiaries) of filing fees, publication expenses, licence fee and RLDC fees & charges as detailed in the order. Deferred tax recovery will be governed by Regulation 49 (2014 Tariff Regulations) when materialised. The petitioner's request regarding service tax recovery was considered premature.
  • Billing, collection and disbursement of the approved transmission charges will follow the CERC Sharing Regulations, 2010 (as amended), per Regulation 43 of the 2014 Tariff Regulations.

Implications:

  • Direct effect: The Commission's allowances fix the trued up capital cost and the annual transmission charges for the specified asset for the stated years; beneficiaries and transmission customers will be billed/reimbursed accordingly as per the sharing and billing provisions referenced in the order.
  • No new judicial precedent: The opinion applies and implements the existing 2009 and 2014 Tariff Regulations, regulatory provisions and past Commission decisions to the facts of this petition; the order does not state that it creates any new legal precedent beyond its application to this petition.

Disposition: This order disposes of Petition No. 389.TT/2014.


End of summary — prepared strictly on the basis of the information contained in the provided opinion.

    Power Grid Corporation Of India Ltd. v. Madhya Pradesh Power Management Company Ltd.

    1. The present petition has been filed by Power Grid Corporation of India Ltd. (‘the petitioner’) for truing up of capital expenditure for 2009-14 tariff period under Regulation 6 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (hereinafter referred to as “the 2009 Tariff Regulations”) and determination of tariff for 2014-19 tariff period under Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as “the 2014 Tariff Regulations”) for Combined Assets of 400 kV D/C Ranchi-Sipat transmission line with associated bays at Ranchi and Sipat Sub-station and 40% FSC on 400 kV Ranchi-Sipat Line at Ranchi Sub-station under Kahalgaon-II Phase-II transmission system in Western Region (hereinafter referred as “the transmission asset”).

    2. The respondents are distribution licensees and transmission licensees, who are procuring transmission service from the petitioner, mainly beneficiaries of Western Region.

    3. The petitioner has served the petition to the respondents and notice of this application has been published in the newspaper in accordance with Section 64 of the Electricity Act, 2003 (“the Act”). No comments have been received from the public in response to the notices published by the petitioner under Section 64 of the Act. The hearing in this matter was held on 13.1.2016 None of the respondents have filed any reply to the petition. Having heard the representatives of the petitioner and perused the material on record, we proceed to dispose of the petition.

    4. The brief facts of the case are as follows:—

    a. The investment approval for execution of transmission asset associated with Combined Assets of 400 kV D/C Ranchi-Sipat transmission line with associated bays at Ranchi and Sipat Sub-station and 40% FSC on 400 kV Ranchi-Sipat Line at Ranchi Sub-station under Kahalgaon-II Phase-II transmission system in Western Region was accorded by Government of India vide its letter no. 12/21/2003-PG dated 24.1.2005 at an estimated cost of Rs. 46402 lakh, which included IDC of Rs. 2898 lakh. Subsequently, Revised Cost Estimates (RCE) was accorded by the Board of Directors of the petitioner company vide Memorandum No. C/CP/RCE/Kahalgaon-II Phase-II dated 16.2.2009 for an estimated cost of Rs. 57283.96 lakh including IDC of Rs. 5770 lakh based on 3rd quarter 2008 price level. The date of commercial operation of the combined asset is 1.3.2009

    b. The tariff from COD to 31.3.2009 was allowed vide order dated 13.5.2010 in Petition No. 247/2009 in accordance with Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004.

    c. The tariff for 2009-14 tariff period was allowed vide order dated 15.2.2011 in Petition No. 226/2010 based on admitted capital cost of Rs. 52898.71 lakh and debt:equity ratio of 70:30 for the Combined Assets as on 31.3.2009 in accordance with the 2009 Tariff Regulations. The tariff allowed vide order dated 15.2.2011 for the tariff period 2009-14 is as under:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Depreciation 2837.87 2896.43 2911.22 2911.22 2911.22 Interest on Loan 3338.85 3142.35 2890.65 2619.38 2348.26 Return on Equity 2817.63 2875.79 2890.49 2890.49 2890.49 Interest on WC 215.92 215.88 212.97 209.14 205.40 O&M Expenses 568.82 601.43 635.87 672.20 710.48 Total 9779.08 9731.88 9541.20 9302.43 9065.85

    d. The MAT rate applicable as on 2008-09 was considered to arrive at rate of return on equity for the 2009-14 tariff period, which is required to be adjusted as per the actual MAT rate applicable for the respective year at the time of truing up of tariff for the 2009-14 tariff period.

    e. The instant petition was filed on 20.9.2014

    TRUING UP OF ANNUAL FIXED CHARGES FOR TARIFF PERIOD 2009-14

    5. The truing up of tariff for 2009-14 tariff period has been determined as discussed below.

    Capital Cost

    6. The petitioner has claimed admitted capital cost of Rs. 52898.71 lakh for the Combined Assets as on 31.3.2009 for the purpose of tariff. Further, the petitioner has claimed aggregate additional capitalisation of Rs. 2001.22 lakh for the Combined Assets for the 2009-14 tariff period.

    7. Last proviso to Clause (2) of Regulation 7 of the 2009 Tariff Regulations provides that:—

    “Provided also that in case of the existing projects, the capital cost admitted by the Commission prior to 1.4.2009 duly trued up by excluding un-discharged liability, if any, as on 1.4.2009 and the additional capital expenditure projected to be incurred for the respective year of the tariff period 2009-14, as may be admitted by the Commission, shall form the basis for determination of tariff”.

    8. The capital cost admitted as on 31.3.2009 vide order dated 13.5.2010 has been considered as the opening capital cost as on 1.4.2009 for determination of tariff in accordance with Regulation 7 of the 2009 Tariff Regulations. The admitted capital cost of Rs. 52898.71 lakh for the Combined Assets as on 1.4.2009 has been considered to work out the trued up tariff for the 2009-14 tariff period.

    Additional Capital Expenditure

    9. The petitioner has claimed actual additional capitalization of Rs. 1658.56 lakh in 2009-10, Rs. 169.67 lakh in 2010-11, Rs. 150.04 lakh in 2011-12, and Rs. 22.95 lakh in 2012-13 (total Rs. 2001.22 lakh for the 2009-14 tariff period) for the Combined Assets. The petitioner has also submitted the Auditor's Certificate for the cost incurred.

    10. The petitioner has claimed that additional capitalization in 2009-10 is on account of balance and retention payments for which works have been executed within cut-off date in accordance with Clause (1) of Regulation 9 of the 2009 Tariff Regulations and towards Balance and Retention payment. The petitioner has claimed additional capitalization for 2010-14 beyond the cut-off date under Clause (2) of Regulation 9 of the 2009 Tariff Regulations.

    11. Clause (1) of Regulation 9 of the 2009 Tariff Regulations provides as follows:—

    “(1) The capital expenditure incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:

    (i) Undischarged liabilities;

    (ii) Works deferred for execution;…

    Provided that the details of works included in the original scope of work along with estimates of expenditure, undischarged liabilities and the works deferred for execution shall be submitted along with the application for determination of tariff”

    12. Clause (2) of Regulation 9 of the 2009 Tariff Regulations provides as follows:—

    “(2) The capital expenditure incurred on the following counts after the cut-off date may, in its discretion, be admitted by the Commission, subject to prudence check:

    (i) Liabilities to meet award of arbitration or for compliance of the order or decree of a court;

    (ii) Change in law; ….

    (iii) Any undischarged liability towards final payment/withheld payment due to contractual exigencies for works executed within the cut-off date, after prudence check of the details of such deferred liability, total estimated cost of package, reason for such withholding of payment and release of such payments etc.”

    13. The petitioner was directed, vide ROP dated 13.1.2016, to submit the amount and nature of works against which the payments are withheld. Further, petitioner was directed to confirm whether all balance/retention payments for the instant assets have been claimed or some payments are still to be claimed. In reply, the petitioner vide affidavit dated 28.1.2016 submitted that the Commission vide order dated 15.2.2011 in Petition No. 226/2010 has already allowed the additional capital expenditure which is trued up in the instant petition. It is further submitted by the petitioner that the entire scope of the project is complete and there is no additional capitalization/balance-retention payment for 2014-19 tariff period.

    14. The total capital cost of the transmission asset including additional capitalization incurred during 2009-14, works out to Rs. 54899.93 lakh for the Combined Assets. The actual additional capitalization claimed by the petitioner is as per the 2009 Tariff Regulations and is within the approved cost. The actual additional capital expenditure for the purpose of true up of tariff of 2009-14 tariff period has been allowed as shown in following table:—

    (Rs. in lakh)

    Cost as per Investment Approval is 57283.96 lakh Particulars Admitted capital cost as on 31.3.2009 Additional capitalization Total additional capitalization Total capital cost including additional capitalization 2009-10 2010-11 2011-12 2012-13 2013-14 Combined Assets Approved in order dated 15.2.2011 52898.71 1657.49 560.50 0.00 0.00 0.00 2217.99 55116.70 Actual 52898.71 1658.56 169.67 150.04 22.95 0.00 2001.22 54899.93

    Debt: Equity

    15. Clause 2 of Regulation 12 of the 2009 Tariff Regulations provides that:

    “In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2009, debt:equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2009 shall be considered.”

    16. The petitioner has claimed trued up Annual Fixed Charge based on debt:equity ratio of 70:30 as on 31.3.2009 as considered by the Commission in its order dated 15.2.2011 in Petition No. 226/2010. The transmission assets covered in the instant petition were commissioned prior to 1.4.2009

    17. The admitted debt:equity ratio of 70:30 as on 31.3.2009 has been considered as opening debt:equity ratio as on 1.4.2009 for the purpose of truing up of the approved tariff for 2009-14 tariff period as given under:—

    (Rs. in lakh)

    Funding Amount (%) Combined Assets Debt 37029.10 70.00 Equity 15869.61 30.00 Total 52898.71 100.00

    18. With respect to additional capitalization, the petitioner has submitted that the additional capitalization has been funded through debt:equity ratio of 70:30 for 2010-11. The actual loan deployed for all the years are at 70% and balance 30% amount has been deployed as equity. The petitioner was directed to submit an undertaking mentioning the actual equity infused for additional capital in 2009-14 tariff period. The petitioner vide affidavit dated 28.1.2016, has submitted that, actual loan deployed in Form-13 is 70% of additional capitalization for 2009-14, therefore actual equity infused for additional capitalization during 2009-14 tariff period is 30% for the assets covered under the subject petition as indicated in Form-1A as per Clause (1) and (3) of Regulation 12 of the 2009 Tariff Regulations.

    19. The overall debt equity as on 31.3.2014 including additional capitalization is as under:—

    (Rs. in lakh)

    Funding Amount (%) Combined Assets Debt 38429.95 70.00 Equity 16469.98 30.00 Total 54899.93 100.00

    Interest on Loan (“IOL”)

    20. Regulation 16 of the 2009 Tariff Regulations provides the methodology for working out weighted average rate of interest on loan. The petitioner has submitted the weighted average rate of interest on loan based on its actual loan portfolio and rate of interest.

    21. We have considered the submissions of the petitioner and accordingly calculated the IOL based on actual interest rate submitted by the petitioner, in accordance with Regulation 16 of the 2009 Tariff Regulations. The details of weighted average rate of interest are placed at Annexure-I and the IOL has been worked out and allowed as follows:—

    (Rs. in lakh)

    Interest on Loan 2009-10 2010-11 2011-12 2012-13 2013-14 Combined Assets Approved in order dated 15.2.2011 3338.85 3142.35 2890.65 2619.38 2348.26 As claimed by petitioner 3338.86 3129.92 2871.23 2606.72 2337.47 Allowed after true up 3338.88 3129.94 2871.24 2606.73 2337.47

    22. The variation in IOL worked out with reference to the IOL allowed vide order 15.2.2011 is due to variation in additional capitalisation.

    Return on Equity (“ROE”)

    23. Clause (3), (4) and (5) of Regulation 15 of the 2009 Tariff Regulations provides as follows:—

    “(3) The rate of return on equity shall be computed by grossing up the base rate with the Minimum Alternate/Corporate Income Tax Rate for the year 2008-09, as per the Income Tax Act, 1961, as applicable to the concerned generating company or the transmission licensee, as the case may be.

    (4) Rate of return on equity shall be rounded off to three decimal points and be computed as per the formula given below:

    Rate of pre-tax return on equity = Base rate/(1-t)

    Where “t” is the applicable tax rate in accordance with clause (3) of this regulation.

    (5) The generating company or the transmission licensee, as the case may be, shall recover the shortfall or refund the excess Annual Fixed Charge on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax Rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission:

    Provided further that Annual Fixed Charge with respect to the tax rate applicable to the generating company or the transmission licensee, as the case may be, in line with the provisions of the relevant Finance Acts of the respective year during the tariff period shall be trued up in accordance with Regulation 6 of these regulations.”

    24. The petitioner has submitted that MAT rate of 11.330% applicable for 2008-09 was considered in the order dated 15.2.2011 However, for truing up purpose, the computation of ROE for the tariff period 2009-14 has been done on the basis of actual MAT rate applicable during 2009-14. The petitioner has submitted the variation in the MAT rate during 2009-14 as per the Finance Act of the relevant year for the purpose of grossing up of ROE, as below:—

    Particulars MAT Rate (%) Grossed up RoE (Base rate/(1-t)) (%) 2009-10 16.995 18.674 2010-11 19.931 19.358 2011-12 20.008 19.377 2012-13 20.008 19.377 2013-14 20.961 19.610

    25. Accordingly, the RoE as trued up is shown in the table below:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 15.2.2011 2817.63 2875.79 2890.49 2890.49 2890.49 As claimed by the petitioner 3009.95 3173.29 3185.69 3190.72 3229.76 Allowed after trued up 3009.95 3173.29 3185.69 3190.72 3229.76

    26. The variation in return on equity worked out with reference to the return on equity allowed vide order 15.2.2011 is due to variation in additional capitalisation and increase in the applicable MAT rate for the purpose of grossing up of base rate of return on equity.

    Depreciation

    27. Clause (42) of Regulation 3 of the 2009 Tariff Regulations defines useful life as follows:—

    “‘useful life’ in relation to a unit of a generating station and transmission system from the COD shall mean the following, namely:—

    (c) AC and DC sub-station 25 years (d) Hydro generating station 35 years (e) Transmission line 35 years”

    28. Clause (4) of Regulation 17 of the 2009 Tariff Regulations provides as follows:—

    “17. Depreciation:

    (4) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-III to these regulations for the assets of the generating station and transmission system:

    Provided that, the remaining depreciable value as on 31st March of the year closing after a period of 12 years from date of commercial operation shall be spread over the balance useful life of the assets.”

    29. The Commission, in its order dated 15.2.2011 in Petition No. 226/2010, has worked out the depreciation in accordance with Regulation 17 of the 2009 Tariff Regulations.

    30. The weighted average useful life of the transmission asset has been considered as per Regulations 17(4) read with Regulations 3(42) of the 2009 Tariff Regulations. For the purpose of calculation, the weighted average useful life of the asset as on COD has been considered as 33 years. The depreciation for the tariff period 2009-14 has been worked out in accordance with Regulation 17 of the 2009 Tariff Regulations based on admitted capital expenditure as under:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 15.2.2011 2837.87 2896.43 2911.22 2911.22 2911.22 As claimed by petitioner 2837.90 2886.17 2894.61 2899.17 2899.78 Allowed after true up 2837.90 2886.16 2894.60 2899.17 2899.78

    Operation & Maintenance Expenses (“O&M Expenses”)

    31. The petitioner has computed O&M expenses for the assets mentioned in the petition and in accordance with the O&M norms for lines and bays specified in Regulation 19(g) of the 2009 Tariff Regulations.

    32. The O&M Expenses claimed by the petitioner for the 2009-14 tariff period are same as that approved in the tariff order dated 15.2.2011 in Petition No. 226/2010. Accordingly, the O&M Expenses claimed by the petitioner, allowed and trued up are the same, and they are as follows:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 15.2.2011 568.82 601.43 635.87 672.20 710.48 As claimed by the petitioner 568.82 601.43 635.87 672.20 710.48 Allowed after trued up 568.82 601.43 635.87 672.20 710.48

    Interest on working capital (“IWC”)

    33. Sub-clause (c) of clause (1) of Regulation 18 of the 2009 Tariff Regulations provides the components of the working capital for the transmission system and clause (3) of Regulation 18 of the 2009 Tariff Regulations provides for the rate of interest on working capital.

    34. The petitioner has submitted that the rate of interest on working capital has been considered as 12.25% as per clause (3) of Regulation 18 of the 2009 Tariff Regulations and the components of working capital are also considered in accordance with sub-clause (c) of clause (1) of Regulation 18 of the 2009 Tariff Regulations.

    35. The Commission, vide order dated 15.2.2011 in Petition No. 226/2010 approved rate of interest on working capital of 12.25% applicable for 2008-09. In accordance with clause (3) of Regulation 18 of the 2009 Tariff Regulations, rate of interest on working capital shall be on normative basis and in case of transmission assets declared under commercial operation prior to 1.4.2009, shall be equal to short-term Prime Lending Rate as applicable as on 1.4.2009 State Bank of India short-term Prime Lending Rate on 1.4.2009 was 12.25%. Therefore, interest rate of 12.25% has been considered to work out the interest on working capital in the instant case.

    36. The IWC trued up is as under:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Maintenance Spares 85.32 90.21 95.38 100.83 106.57 O & M expenses 47.40 50.12 52.99 56.02 59.21 Receivables 1662.58 1668.74 1634.30 1597.28 1564.92 Total 1795.30 1809.07 1782.66 1754.13 1730.69 Rate of Interest (%) 12.25 12.25 12.25 12.25 12.25 Interest 219.92 221.61 218.38 214.88 212.01

    37. The summary of IWC approved vide order dated 15.2.2011, IWC claimed by the petitioner and the IWC allowed after true up are as follows:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 15.2.2011 215.92 215.88 212.97 209.14 205.40 As claimed by the petitioner 219.92 221.61 218.38 214.88 212.01 Allowed after trued up 219.92 221.61 218.38 214.88 212.01

    38. The variation in IWC is on account of change in receivables due to variation in depreciation, interest and ROE on account of variation in additional capital expenditure and due to variation in ROE on account of applicable MAT rate during the 2009-14.

    ANNUAL FIXED CHARGES FOR 2009-14 TARIFF PERIOD

    39. The detailed computation of the various components of the trued up annual fixed charges for the transmission asset for the tariff period 2009-14 is summarised below:—

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Gross Block Opening Gross Block 52898.71 54557.27 54726.94 54876.98 54899.93 Additional Capitalization 1658.56 169.67 150.04 22.95 0.00 Closing Gross block 54557.27 54726.94 54876.98 54899.93 54899.93 Average Gross block 53727.99 54642.11 54801.96 54888.46 54899.93 Depreciation Rate of Depreciation (%) 5.282 5.282 5.282 5.282 5.282 Depreciable Value 48355.19 49177.89 49321.76 49399.61 49409.94 Elapsed Life of the assets at beginning of the year 0 1 2 3 4 Weighted Balance Useful life of the assets 33 32 31 30 29 Remaining Depreciable Value 48015.40 48838.10 46095.81 46221.92 43333.08 Depreciation 2837.90 2886.16 2894.60 2899.17 2899.78 Interest on Loan Gross Normative Loan 37029.10 38190.09 38308.86 38413.89 38429.95 Cumulative Repayment upto Previous Year 339.79 3177.69 6063.85 8958.46 11857.63 Net Loan-Opening 36689.31 35012.40 32245.00 29455.43 26572.32 Additions 1160.99 118.77 105.03 16.07 0.00 Repayment during the year 2837.90 2886.16 2894.60 2899.17 2899.78 Net Loan-Closing 35012.40 32245.00 29455.43 26572.32 23672.54 Average Loan 35850.85 33628.70 30850.22 28013.88 25122.43 Weighted Average Rate of Interest on Loan (%) 9.3132 9.3073 9.3070 9.3051 9.3043 Interest 3338.88 3129.94 2871.24 2606.73 2337.47 Return on Equity Opening Equity 15869.61 16367.18 16418.08 16463.09 16469.98 Additions 497.57 50.90 45.01 6.89 0.00 Closing Equity 16367.18 16418.08 16463.09 16469.98 16469.98 Average Equity 16118.40 16392.63 16440.59 16466.54 16469.98 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 MAT rate for the respective year (%) 16.995 19.931 20.008 20.008 20.961 Rate of Return on Equity (Pre Tax) (%) 18.674 19.358 19.377 19.377 19.610 Return on Equity (Pre Tax) 3009.95 3173.29 3185.69 3190.72 3229.76 Interest on Working Capital Maintenance Spares 85.32 90.21 95.38 100.83 106.57 O&M Expenses 47.40 50.12 52.99 56.02 59.21 Receivables 1662.58 1668.74 1634.30 1597.28 1564.92 Total 1795.30 1809.07 1782.66 1754.13 1730.69 Interest 219.92 221.61 218.38 214.88 212.01 Annual Transmission Charges Depreciation 2837.90 2886.16 2894.60 2899.17 2899.78 Interest on Loan 3338.88 3129.94 2871.24 2606.73 2337.47 Return on Equity 3009.95 3173.29 3185.69 3190.72 3229.76 Interest on Working Capital 219.92 221.61 218.38 214.88 212.01 Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 O & M Expenses 568.82 601.43 635.87 672.20 710.48 Total 9975.47 10012.42 9805.78 9583.70 9389.50

    DETERMINATION OF ANNUAL TRANSMISSION CHARGES FOR 2014-19

    40. The petitioner has claimed the transmission charges as under:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Depreciation 2899.78 2899.78 2899.78 2899.78 2899.78 Interest on Loan 2067.68 1797.90 1528.10 1258.30 988.52 Return on Equity 3229.76 3229.76 3229.76 3229.76 3229.76 Interest on Working Capital 224.52 219.51 214.52 209.58 204.69 O&M Expenses 648.68 670.42 692.58 715.56 739.31 Total 9070.42 8817.37 8564.74 8312.98 8062.06

    41. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets Maintenance Spares 97.30 100.56 103.89 107.33 110.90 O&M expenses 54.06 55.87 57.72 59.63 61.61 Receivables 1511.74 1469.56 1427.46 1385.50 1343.68 Total 1663.10 1625.99 1589.07 1552.46 1516.19 Rate of Interest (%) 13.50 13.50 13.50 13.50 13.50 Interest 224.52 219.51 214.52 209.58 204.69

    Capital Cost

    42. Clause (1) and (3) of Regulation 9 of the 2014 Tariff Regulations provide as follows:—

    “(1) The Capital cost as determined by the Commission after prudence check in accordance with this regulation shall form the basis of determination of tariff for existing and new projects.”

    “(3) The Capital cost of an existing project shall include the following:

    (a) the capital cost admitted by the Commission prior to 1.4.2014 duly trued up by excluding liability, if any, as on 1.4.2014;

    (b) additional capitalization and de-capitalization for the respective year of tariff as determined in accordance with Regulation 14; and

    (c) expenditure on account of renovation and modernisation as admitted by this Commission in accordance with Regulation 15.”

    43. The trued up capital cost of Rs. 54899.93 lakh for the Combined Assets as on 1.4.2014 is considered for the purpose of tariff for tariff period 2014-19.

    Additional Capital Expenditure

    44. The petitioner has not claimed any additional expenditure for the tariff period 2014-19. Accordingly, no additional capital expenditure has been considered for the 2014-19 tariff period.

    Debt: Equity Ratio

    45. Clause 3 and 4 of Regulation 19 of the 2014 Tariff Regulations provide as under:—

    “(3) In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2014, debt:equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2014 shall be considered.

    (4) In case of the generating station and the transmission system including communication system declared under commercial operation prior to 1.4.2014, but where debt: equity ratio has not been determined by the Commission for determination of tariff for the period ending 31.3.2014, the Commission shall approve the debt:equity ratio based on actual information provided by the generating company or the transmission licensee as the case may be.”

    46. The petitioner has considered debt:equity ratio as 70:30. Debt equity ratio of 70:30 as on 31.3.2009 was considered by the Commission in its order dated 15.2.2011 in Petition No. 226/2010. The admitted debt equity ratio of 70:30 for the tariff period ending 31.3.2014 has been considered as opening debt:equity ratio as on 1.4.2014 The details of the debt:equity considered for the purpose of tariff for 2014-19 tariff period is as follows:—

    (Rs. in lakh)

    Combined Assets Admitted as on 31.3.2014 Funding Amount (%) Debt 38429.95 70.00 Equity 16469.98 30.00 Total 54899.93 100.00

    Interest on Loan (“IOL”)

    47. Clause (5) and (6) of Regulation 26 of the 2014 Tariff Regulations are reproduced as under:—

    “(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio after providing appropriate accounting adjustment for interest capitalized:

    Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered:

    Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.

    (6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.”

    48. The weighted average rate of IOL has been considered on the basis of rate prevailing as on 1.4.2014 The IOL has been worked out in accordance with Regulation 26 of the 2014 Tariff Regulations. The details of weighted average rate of interest are placed at Annexure-II and the IOL has been worked out and allowed as follows:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross Normative Loan 38429.95 38429.95 38429.95 38429.95 38429.95 Cumulative Repayment upto Previous Year 14757.41 17657.18 20556.96 23456.74 26356.52 Net Loan-Opening 23672.54 20772.77 17872.99 14973.21 12073.44 Additions 0.00 0.00 0.00 0.00 0.00 Repayment during the year 2899.78 2899.78 2899.78 2899.78 2899.78 Net Loan-Closing 20772.77 17872.99 14973.21 12073.44 9173.66 Average Loan 22222.66 19322.88 16423.10 13523.32 10623.55 Weighted Average Rate of Interest on Loan (%) 9.3044 9.3045 9.3046 9.3047 9.3050 Interest 2067.68 1797.89 1528.10 1258.31 988.52

    Return on Equity (“ROE”)

    49. Clause (1) and (2) of Regulation 24 and Clause (2) of Regulation 25 of the 2014 Tariff Regulations specify as under:—

    “24. Return on Equity:

    (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with regulation 19.

    (2) Return on equity shall be computed at the base rate of 15.50% for thermal generating stations, transmission system including communication system….

    …………….”

    “25. Tax on Return on Equity:

    (2) Rate of return on equity shall be rounded off to three decimal places and shall be computed as per the formula given below:

    Rate of pre-tax return on equity=Base rate/(1-t)

    Where “t” is the effective tax rate in accordance with Clause (1) of this regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or non-transmission business, as the case may be, and the corresponding tax thereon. In case of generating company or transmission licensee paying Minimum Alternate Tax (MAT), “t” shall be considered as MAT rate including surcharge and cess.”

    50. The petitioner has computed ROE at the rate of 19.610% after grossing up the ROE with MAT rate as per the above regulations. The petitioner has further submitted that the grossed up ROE is subject to truing up based on the actual tax paid along with any additional tax or interest, duly adjusted for any refund of tax including the interest received from IT authorities, pertaining to the tariff period 2014-19 on actual gross income of any financial year. Any under-recovery or over-recovery of grossed up ROE after truing up shall be recovered or refunded to the beneficiaries on year to year basis.

    51. The petitioner has further submitted that adjustment due to any additional tax demand including interest duly adjusted for any refund of the tax including interest received from IT authorities shall be recoverable/adjustable after completion of income tax assessment of the financial year.

    52. We have considered the submissions made by the petitioner. Regulation 24 read with Regulation 25 of the 2014 Tariff Regulations provides for grossing up of return on equity with the effective tax rate for the purpose of return on equity. It further provides that in case the generating company or transmission licensee is paying Minimum Alternative Tax (MAT), the MAT rate including surcharge and cess will be considered for the grossing up of return on equity. The petitioner has submitted that MAT rate is applicable to the petitioner's company. Accordingly, the MAT rate applicable during 2013-14 has been considered for the purpose of allowing return on equity, which shall be trued up with actual tax rate in accordance with Regulation 25(3) of the 2014 Tariff Regulations. Accordingly, the ROE determined by the Commission is given below:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Opening Equity 16469.98 16469.98 16469.98 16469.98 16469.98 Addition due to Additional Capitalization 0.00 0.00 0.00 0.00 0.00 Closing Equity 16469.98 16469.98 16469.98 16469.98 16469.98 Average Equity 16469.98 16469.98 16469.98 16469.98 16469.98 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 Tax rate for the year (%) 20.961 20.961 20.961 20.961 20.961 Rate of Return on Equity (Pre Tax) (%) 19.610 19.610 19.610 19.610 19.610 Return on Equity (Pre Tax) 3229.76 3229.76 3229.76 3229.76 3229.76

    Depreciation

    53. Clause (2), (5) and (6) of Regulation 27 of the 2014 Tariff Regulations provide as follows:—

    “27. Depreciation:

    …(2) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission. In case of multiple units of a generating station or multiple elements of transmission system, weighted average life for the generating station of the transmission system shall be applied. Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis

    (5) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-II to these regulations for the assets of the generating station and transmission system:

    Provided that the remaining depreciable value as on 31 March of the year closing after a period of 12 years from the effective date of commercial operation of the station shall be spread over the balance useful life of the assets.

    (6) In case of the existing projects, the balance depreciable value as on 1.4.2014 shall be worked out by deducting the cumulative depreciation as admitted by the Commission upto 31.3.2014 from the gross depreciable value of the assets.”

    54. The petitioner has computed depreciation considering capital expenditure of Rs. 54899.93 lakh for Combined Assets as on 31.3.2014 We have considered the submission made by the petitioner with reference to depreciation. Depreciation is allowed as per the methodology provided under Regulation 27 of the 2014 Tariff Regulations. The details of the depreciation allowed are given hereunder:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets Opening Gross block 54899.93 54899.93 54899.93 54899.93 54899.93 Additions during the year due to projected additional capitalization 0.00 0.00 0.00 0.00 0.00 Closing Gross block 54899.93 54899.93 54899.93 54899.93 54899.93 Rate of Depreciation 5.282 5.282 5.282 5.282 5.282 Depreciable Value 49409.94 49409.94 49409.94 49409.94 49409.94 Remaining Depreciable Value 40433.30 37533.52 34633.74 31733.97 28834.19 Depreciation 2899.78 2899.78 2899.78 2899.78 2899.78

    Operation & Maintenance Expenses (“O&M Expenses”)

    55. The petitioner has computed normative O&M Expenses as per sub-clause (a) of clause (3) of regulation 29 of the 2014 Tariff Regulations. Accordingly, the petitioner's entitlement to O&M Expenses has been worked out as given hereunder:—

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets Actual No of bays (nos.) 400 kV Bays 6 6 6 6 6 Norms as per Regulation 400 kV Bays (Rs. lakh/bay) 60.30 62.30 64.37 66.51 68.71 Total (Rs. in lakh) Line Length (km) Double circuit/double conductor (km) 361.8 373.8 386.22 399.06 412.26 405.77 405.77 405.77 405.77 405.77 (Rs. lakh/km) 0.707 0.731 0.755 0.78 0.806 Total (Rs. in lakh) 286.88 296.62 306.36 316.50 327.05 Total (Rs. in lakh) 648.68 670.42 692.58 715.56 739.31

    56. The petitioner has submitted that O&M Expenses for the 2014-19 tariff period have been arrived on the basis of normalized actual O&M Expenses during the period 2008-13. The petitioner has further submitted that the wage revision of the employees of the petitioner is due during 2014-19 and actual impact of wage hike, which will be effective at a future date, has not been factored in fixation of the normative O&M rate specified for the tariff period 2014-19. The petitioner has prayed to be allowed to approach the Commission for suitable revision in the norms of O&M Expenses for claiming the impact of such increase.

    57. The O&M Expenses have been worked out as per the norms of O&M Expenses specified in the 2014 Tariff Regulations. As regards impact of wage revision, we would like to clarify that any application filed by the petitioner in this regard will be dealt with in accordance with the appropriate provisions of the 2014 Tariff Regulations.

    58. The details of O&M Expenses allowed are given hereunder:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets 648.68 670.42 692.58 715.56 739.31

    Interest on Working Capital (“IWC”)

    59. Clause 1(c) of Regulation 28 and Clause 5 of Regulation 3 of the 2014 Tariff Regulations specify as follows:—

    “28. Interest on Working Capital

    (c)(i) Receivables equivalent to two months of fixed cost;

    (ii) Maintenance spares @ 15% of operation and maintenance expenses specified in regulation 29; and

    (iii) Operation and maintenance expenses for one month”

    “(5) ‘Bank Rate’ means the base rate of interest as specified by the State Bank of India from time to time or any replacement thereof for the time being in effect plus 350 basis points;”

    60. The petitioner has submitted that IWC was computed for the tariff period 2014-19 considering the SBI Base Rate as on 1.4.2014 plus 350 basis points. The rate of interest on working capital considered for the purpose of computation of tariff is 13.50%.

    61. The interest on working capital is worked out in accordance with Regulation 28 of the 2014 Tariff Regulations. The rate of interest on working capital considered is 13.50% (SBI Base Rate of 10% plus 350 basis points). The interest on working capital as determined is shown in the table below:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Maintenance Spares 97.30 100.56 103.89 107.33 110.90 O & M expenses 54.06 55.87 57.71 59.63 61.61 Receivables 1511.74 1469.56 1427.46 1385.50 1343.68 Total 1663.10 1625.99 1589.06 1552.46 1516.18 Rate of Interest 13.50 13.50 13.50 13.50 13.50 Interest 224.52 219.51 214.52 209.58 204.68

    Annual Transmission Charges

    62. The Annual Transmission Charges allowed for the transmission asset is given hereunder:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Combined Assets Depreciation 2899.78 2899.78 2899.78 2899.78 2899.78 Interest on Loan 2067.68 1797.89 1528.10 1258.31 988.52 Return on Equity 3229.76 3229.76 3229.76 3229.76 3229.76 Interest on Working Capital 224.52 219.51 214.52 209.58 204.68 O & M Expenses 648.68 670.42 692.58 715.56 739.31 Total 9070.42 8817.36 8564.74 8313.00 8062.06

    63. The detailed computation of various components of annual fixed charges for the tariff period 2014-19 is summarized below:—

    (Rs. in lakh)

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross Block Opening Gross Block 54899.93 54899.93 54899.93 54899.93 54899.93 Additional Capitalization 0.00 0.00 0.00 0.00 0.00 Closing Gross Block 54899.93 54899.93 54899.93 54899.93 54899.93 Average Gross Block 54899.93 54899.93 54899.93 54899.93 54899.93 Depreciation Rate of Depreciation 5.282 5.282 5.282 5.282 5.282 Depreciable Value 49409.94 49409.94 49409.94 49409.94 49409.94 Elapsed Life of the assets at beginning of the year 5 6 7 8 9 Weighted Balance Useful life of the assets 28 27 26 25 24 Remaining Depreciable Value 40433.30 37533.52 34633.74 31733.97 28834.19 Depreciation 2899.78 2899.78 2899.78 2899.78 2899.78 Interest on Loan Gross Normative Loan 38429.95 38429.95 38429.95 38429.95 38429.95 Cumulative Repayment upto Previous Year 14757.41 17657.18 20556.96 23456.74 26356.52 Net Loan-Opening 23672.54 20772.77 17872.99 14973.21 12073.44 Additions 0.00 0.00 0.00 0.00 0.00 Repayment during the year 2899.78 2899.78 2899.78 2899.78 2899.78 Net Loan-Closing 20772.77 17872.99 14973.21 12073.44 9173.66 Average Loan 22222.66 19322.88 16423.10 13523.32 10623.55 Weighted Average Rate of Interest on Loan (%) 9.3044 9.3045 9.3046 9.3047 9.3050 Interest 2067.68 1797.89 1528.10 1258.31 988.52 Return on Equity Opening Equity 16469.98 16469.98 16469.98 16469.98 16469.98 Additions 0.00 0.00 0.00 0.00 0.00 Closing Equity 16469.98 16469.98 16469.98 16469.98 16469.98 Average Equity 16469.98 16469.98 16469.98 16469.98 16469.98 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 MAT Rate for the year 2013-14 (%) 20.961 20.961 20.961 20.961 20.961 Rate of Return on Equity (Pre Tax) (%) 19.610 19.610 19.610 19.610 19.610 Return on Equity (Pre Tax) 3229.76 3229.76 3229.76 3229.76 3229.76 Interest on Working Capital Maintenance Spares 97.30 100.56 103.89 107.33 110.90 O & M expenses 54.06 55.87 57.71 59.63 61.61 Receivables 1511.74 1469.56 1427.46 1385.50 1343.68 Total 1663.10 1625.99 1589.06 1552.46 1516.18 Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Interest 224.52 219.51 214.52 209.58 204.68 Annual Transmission Charges Depreciation 2899.78 2899.78 2899.78 2899.78 2899.78 Interest on Loan 2067.68 1797.89 1528.10 1258.31 988.52 Return on Equity 3229.76 3229.76 3229.76 3229.76 3229.76 Interest on Working Capital 224.52 219.51 214.52 209.58 204.68 O & M Expenses 648.68 670.42 692.58 715.56 739.31 Total 9070.42 8817.36 8564.74 8313.00 8062.06

    Filing Fee and Publication Expenses

    64. The petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses, in terms of Regulation 52 of the 2014 Tariff Regulations. The petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with clause (1) of regulation 52 of the 2014 Tariff Regulations.

    Licence Fee and RLDC Fees and Charges

    65. The petitioner has requested to allow the petitioner to bill and recover licence fee and RLDC fees and charges, separately from the respondents. The petitioner shall be entitled for reimbursement of licence fee and RLDC fees and charges in accordance with Clause (2)(b) and (2)(a), respectively, of Regulation 52 of the 2014 Tariff Regulations.

    Service Tax

    66. The petitioner has sought to recover service tax on transmission charges separately from the respondents, if at any time service tax on transmission is withdrawn from negative list in future. We are of the view that the petitioner's prayer is premature.

    Deferred Tax Liability

    67. The petitioner has sought recovery of deferred tax liability before 1.4.2009 from the beneficiaries or long term consumers/DICs as and when materialized under Regulation 49 of the 2014 Tariff Regulations. The deferred tax liability shall be dealt as per Regulations 49 of the 2014 Tariff Regulations, as amended. Accordingly, the petitioner is entitled to recover the deferred tax liability upto 31.3.2009 whenever the same materializes, directly from the beneficiaries or long term transmission customers/DICs.

    Sharing of Transmission Charges

    68. The billing, collection and disbursement of the transmission charges approved shall be governed by the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from time to time, as provided in Regulation 43 of the 2014 Tariff Regulations.

    69. This order disposes of Petition No. 389.TT/2014.

    Annexure-1

    DETAILS OF LOAN BASED ON ACTUAL LOAN PORTFOLIO DURING TARIFF PERIOD 2009-14

    COMBINED ASSETS

    (Rs. in lakh)

    Particulars Interest Rate (%) Loan deployed as on 1.4.2009 Additions during the tariff period Total BOND XVIII-DOCO-01-JAN 2009- 8.15 100.00 0.00 100.00 BOND XVIII-DOCO-01-MAR-2009- 8.15 26.00 0.00 26.00 BOND XIX-DOCO-01-JAN-2009 9.25 8704.00 0.00 8704.00 BOND XIX-DOCO-01-MAR-2009 9.25 556.00 0.00 556.00 BOND XXI-DOCO-01-JAN-2009 8.73 2852.00 0.00 2852.00 BOND XXI-DOCO-01-MARCH-2009 8.73 158.00 0.00 158.00 BOND XXII-DOCO-1-JAN-2009 8.68 3841.00 0.00 3841.00 BOND XXII-DOCO-01-MAR-2009- 8.68 232.00 0.00 232.00 BOND XXIV-DOCO-01-JAN-2009- 9.95 5504.00 0.00 5504.00 BOND XXIV-DOCO-01-MAR-2009- 9.95 363.00 0.00 363.00 BOND XXVII-DOCO-01-JAN-2009- 9.47 8831.00 0.00 8831.00 BOND XXVII-DOCO-01-MAR-2009- 9.47 769.00 0.00 769.00 BOND XXVIII-DOCO DRAWAL ON-01-JAN-2009-01-JAN-2009 9.33 4335.46 0.00 4335.46 BOND XXVIII-DOCO DRAWAL ON-01-MAR-2009-01-MAR-2009- 9.33 87.54 0.00 87.54 BOND XXX-ADD CAP FOR 2009-2010-Loan 1- 8.80 0.00 277.00 277.00 BOND XXXI-ADD CAP FOR 2009-2010-Loan 2- 8.90 0.00 883.99 883.99 BOND XXXI-ADD CAP FOR 2010-2011-Loan 3- 8.90 0.00 118.77 118.77 BOND XXXI-ADD CAP FOR 2011-2012-Loan 4- 8.90 0.00 105.03 105.03 BOND XXXI-ADD CAP FOR 2011-2012-Loan 4- 8.90 0.00 16.07 16.07 Total 36359.00 1400.86 37759.86

    WEIGHTED AVERAGE RATE OF INTEREST ON LOAN DURING TARIFF PERIOD2009-14

    COMBINED ASSETS

    (Rs. in lakh)

    Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Gross Opening Loan 36359.00 37519.99 37638.76 37743.79 37759.86 Cumulative Repayments of Loans upto Previous Year 0.00 10.50 1871.83 4533.16 7563.08 Net Loans Opening 36359.00 37509.49 35766.93 33210.63 30196.78 Add: Drawal(s) during the year 1160.99 118.77 105.03 16.07 0.00 Less: Repayment(s) of Loan during the year 10.50 1861.33 2661.33 3029.92 3146.66 Net Closing Loan 37509.49 35766.93 33210.63 30196.78 27050.12 Average Net Loan 36934.25 36638.21 34488.78 31703.71 28623.45 Interest on Loan 3439.78 3410.04 3209.88 2950.07 2663.21 Rate of Interest on Loan (%) 9.3132 9.3073 9.3070 9.3051 9.3043

    Annexure-2

    DETAILS OF LOAN BASED ON ACTUAL LOAN PORTFOLIO DURING TARIFF PERIOD 2014-19

    COMBINED ASSETS

    (Rs. in lakh)

    Particulars Interest Rate (%) Loan deployed as on 1.4.2014 Additions during the tariff period Total BOND XVIII-DOCO-01-JAN 2009- 8.15 100.00 0.00 100.00 BOND XVIII-DOCO-01-MAR-2009- 8.15 26.00 0.00 26.00 BOND XIX-DOCO-01-JAN-2009 9.25 8704.00 0.00 8704.00 BOND XIX-DOCO-01-MAR-2009 9.25 556.00 0.00 556.00 BOND XXI-DOCO-01-JAN-2009 8.73 2852.00 0.00 2852.00 BOND XXI-DOCO-01-MARCH-2009 8.73 158.00 0.00 158.00 BOND XXII-DOCO-1-JAN-2009 8.68 3841.00 0.00 3841.00 BOND XXII-DOCO-01-MAR-2009- 8.68 232.00 0.00 232.00 BOND XXIV-DOCO-01-JAN-2009- 9.95 5504.00 0.00 5504.00 BOND XXIV-DOCO-01-MAR-2009- 9.95 363.00 0.00 363.00 BOND XXVII-DOCO-01-JAN-2009- 9.47 8831.00 0.00 8831.00 BOND XXVII-DOCO-01-MAR-2009- 9.47 769.00 0.00 769.00 BOND XXVIII-DOCO DRAWAL ON-01-JAN-2009-01-JAN-2009 9.33 4335.46 0.00 4335.46 BOND XXVIII-DOCO DRAWAL ON-01-MAR-2009-01-MAR-2009- 9.33 87.54 0.00 87.54 BOND XXX-ADD CAP FOR 2009-2010-Loan 1- 8.80 277.00 0.00 277.00 BOND XXXI-ADD CAP FOR 2009-2010-Loan 2- 8.90 883.99 0.00 883.99 BOND XXXI-ADD CAP FOR 2010-2011-Loan 3- 8.90 118.77 0.00 118.77 BOND XXXI-ADD CAP FOR 2011-2012-Loan 4- 8.90 105.03 0.00 105.03 BOND XXXI-ADD CAP FOR 2011-2012-Loan 4- 8.90 16.07 0.00 16.07 Total 171.52 37759.86 0.00 37759.86

    WEIGHTED AVERAGE RATE OF INTEREST ON LOAN DURING TARIFF PERIOD 2014-19

    COMBINED ASSETS

    Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross Opening Loan 37759.86 37759.86 37759.86 37759.86 37759.86 Cumulative Repayments of Loans upto Previous Year 10709.74 13856.40 17003.06 20149.72 23296.38 Net Loans Opening 27050.12 23903.46 20756.80 17610.14 14463.48 Add: Drawal(s) during the year 0.00 0.00 0.00 0.00 0.00 Less: Repayment(s) of Loan during the year 3146.66 3146.66 3146.66 3146.66 3146.66 Net Closing Loan 23903.46 20756.80 17610.14 14463.48 11316.82 Average Net Loan 25476.79 22330.13 19183.47 16036.81 12890.15 Interest on Loan 2370.46 2077.70 1784.94 1492.18 1199.43 Rate of Interest on Loan (%) 9.3044 9.3045 9.3046 9.3047 9.3050
    Use AI to get other relevant cases.

    Comments

    Power Grid Corporation Of India Ltd. v. Madhya Pradesh Power Management Company Ltd.
    (Jan 29, 2016)