Smart Summary

Factual and Procedural Background

The appeal challenges the order dated 4.4.2014 of the State Consumer Disputes Redressal Commission, Union Territory, Chandigarh (the State Commission) in Complaint Case No. 07/2014, Punita Singh & Anr. vs. Emaar MGF Land Ltd., by which the complaint was allowed. The complainants booked an apartment on 15.11.2007; a provisional letter was issued on 12.12.2007 showing a total sale consideration of Rs.51,18,516/-, and the complainants paid Rs.49,90,807/-. An Apartment Buyers Agreement was executed on 27.2.2008 stipulating possession within 36 months plus a 3-month grace period. Possession was not delivered for over six years (the agreement period extended to about 80 months by the time of the complaint). The complainants alleged deficiency and filed a complaint before the State Commission. The opposite parties (appellants here) resisted on grounds including lack of territorial jurisdiction, limitation, and that time was not the essence of the contract; they admitted receipt of Rs.49,90,807/- and stated that the buyers had defaulted Rs.1,50,000/-. The State Commission allowed the complaint, directed refund of Rs.49,90,807/- with 12% p.a. interest from date of receipt, awarded Rs.2,00,000/- as compensation for harassment and Rs.20,000/- as litigation costs. The appellants appealed to the forum that produced this opinion.

Legal Issues Presented

  1. Whether the complaint was barred by limitation.
  2. Whether the State Commission had territorial jurisdiction to entertain the complaint.
  3. Whether the contractual stipulation providing payment for delayed possession (penalty at Rs.5/- per sq. ft. per month) precluded the complainants from seeking refund of the amounts paid.
  4. Whether the State Commission erred in directing refund with interest and awarding compensation and litigation costs.

Arguments of the Parties

Appellants' Arguments

  • The complaint was barred by limitation.
  • Time was not the essence of the contract and there was a contractual stipulation (penalty clause) for delayed possession which, the appellants argued, should preclude refund; appellants were ready to adjust the penalty for delayed possession.
  • The State Commission lacked territorial jurisdiction to entertain the complaint.
  • The State Commission committed an error in allowing the complaint and directing refund.
  • Appellants admitted receipt of Rs.49,90,807/- and stated that complainants had defaulted Rs.1,50,000/-; they asserted construction was ongoing and likely to complete by November 2014, and prayed for dismissal.

Respondents' Arguments

  • The order of the State Commission was in accordance with law and should be maintained.
  • Reliance on a Coordinate Bench decision in F.A. No. 342 of 2014 Emaar MGF Land Ltd. & Anr. Vs. Karnail Singh & Anr., where a similar complaint was allowed and the appeal was dismissed; the ensuing SLP filed by the builder (SLP (C) No.29392/2014 Emaar MGF Land Ltd. & Anr. Vs. Karnail Singh & Anr.) was dismissed by the Hon'ble Apex Court on 14.11.2014.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
F.A. No. 342 of 2014 Emaar MGF Land Ltd. & Anr. Vs. Karnail Singh & Anr Applied as a coordinate-bench decision where, on similar facts, the State Commission's order allowing the complaint was upheld. The court relied on the similarity of facts and outcome to support that the State Commission's order in the present matter did not suffer illegality and to justify dismissal of the appeal.
SLP (C) No.29392/2014 Emaar MGF Land Ltd. & Anr. Vs. Karnail Singh & Anr Noted to show that the Special Leave Petition filed by the builder against the coordinate-bench decision was dismissed by the Hon'ble Apex Court (order dated 14.11.2014). The dismissal of the SLP was relied upon by respondents and noted by the court as supporting the view that the State Commission's approach in similar cases had been sustained at the highest level.

Court's Reasoning and Analysis

The court examined the admitted facts: booking and payments (Rs.49,90,807/- paid against a sale consideration of Rs.51,18,516/-), the agreement dated 27.2.2008 providing possession within 36 months plus a 3-month grace period, and the failure to deliver possession even after approximately 80 months. The court considered and rejected the limitation argument on the ground expressly recorded in the opinion: until money is refunded or possession is given, the cause of action continues, and therefore the complaint was not barred by limitation.

On the contention based on the delayed-possession penalty clause (Rs.5/- per sq. ft. per month), the court held that the mere existence of such a clause could not deprive the complainants of their right to a refund where the project remained incomplete for an extended period. The court reasoned that a builder cannot be permitted to retain a very large sum (around Rs.50,00,000/-) while paying a trivial monthly penalty (the example noted was that this would amount to a very small percentage per annum), particularly where completion was long delayed (the builder itself indicated an additional multi-year period for completion). The court emphasized that a contractual clause inserted for the benefit of the allottee cannot be used as a weapon against the allottee.

The court also took into account the respondents' reliance on a coordinate-bench decision and the dismissal of the corresponding SLP by the Supreme Court, treating those authorities as supportive of the view that, on similar facts, allowing a refund and related relief was appropriate. On that combined basis, the court concluded there was no illegality in the State Commission's order.

Holding and Implications

APPEAL DISMISSED.

Holding: The appeal filed by the appellants is dismissed at the admission stage and the impugned order of the State Commission stands. The State Commission's directions—to refund Rs.49,90,807/- with 12% per annum interest from the date of receipt and to pay Rs.2,00,000/- as compensation and Rs.20,000/- as litigation costs—remain effective. The appellate court made no order as to costs in respect of this appeal.

Implications: The direct effect is that the respondent/allottees are entitled to the refund with interest and the compensation and costs as awarded by the State Commission. The opinion does not purport to lay down a new legal principle beyond affirming the State Commission's application of consumer-law remedies in a situation of prolonged non-delivery of possession; the court treated the decision as consistent with existing coordinate and higher-court outcomes cited in the opinion.

To access the original judgment, please Sign In or Subscribe.

    Emaar Mgf Land Limited v. Punita Singh

    PER JUSTICE K.S. CHAUDHARI, PRESIDING MEMBER This appeal has been filed by the appellant against the order dated 4.4.2014 passed by the State Consumer Disputes Redressal Commission, UT, Chandigarh (in short, the State Commission) in Complaint Case No. 07/2014 Punita Singh & Anr. Vs. Emaar MGF Land Ltd. by which, complaint was allowed.

    2. Brief facts of the case are that Complainants/Respondents applied for booking of an apartment vide application dated 15.11.2007 to OP/appellants and they were allotted Apartment No.K1-F04-404 measuring 1750 sq. ft. along with car parking on payment of additional charges for preferential location, etc. Provisional letter was issued by OP on 12.12.2007 and total sale consideration was Rs.51,18,516/-. Complainants paid total Rs.49,90,807/-. It was further submitted that Apartment Buyers Agreement was executed between the parties on 27.2.2008 and possession of apartment was to be given by OPs within a period of 36 months with grace period of

    3 months, but OP did not deliver possession inspite of lapse of 6 years. Alleging deficiency on the part of OPs, complainants filed complaint before State Commission. OPs resisted complaint and submitted that State Commission has no territorial jurisdiction and complaint was barred by limitation and time was not the essence of contract. It was further submitted that there was already penalty clause for delayed possession. OP admitted receipt of Rs.49,90,807/- and further admitted that possession could not be handed over to complainants as complainants made default in making payment of Rs.1,50,000/-. It was further submitted that construction activity is in full swing and it will be completed by November, 2014 and prayed for dismissal of complaint. Learned State Commission after hearing both the parties allowed complaint and directed OPs to refund Rs.49,90,807/- with 12% p.a. interest from date of receipt and further directed to pay Rs.2,00,000/- as compensation for harassment and Rs.20,000/- as cost of litigation against which, this appeal has been filed by OPs.

    3. Heard learned Counsel for the parties finally at admission stage and perused record.

    4. Learned Counsel for the appellant submitted that inspite of the fact that complaint was barred by limitation and stipulation for payment on delayed possession, learned State Commission committed error in allowing complaint and directing refund of payment; hence, appeal be allowed and impugned order be set aside. On the other hand, learned Counsel for the respondent submitted that order passed by learned State Commission is in accordance with law and similar order passed by Coordinate Bench has been upheld by Honble Apex Court; hence, appeal be dismissed.

    5. It is not disputed that complainants booked apartment with OPs for a total consideration of Rs.51,18,516/- and made payment of Rs.49,90,807/-. It is also not disputed that as per Apartment Buyers Agreement dated 27.2.2008, possession of apartment was to be given within 36 months with grace period of 3 months and till filing of complaint possession was not given by OPs and as per written statement construction was likely to be completed by November, 2014, meaning thereby, instead of 36 months for handing over possession, construction was not complete till 80 months.

    6. Learned Counsel for the appellant submitted that complaint was barred by limitation, but this argument is devoid of force because till money is refunded or possession is given, cause of action continues and learned State Commission rightly observed that complaint filed by complainants was not barred by limitation.

    7. Learned Counsel for the appellants further submitted that as there was stipulation for payment @ Rs.5/- per sq. ft. per month for delayed possession, refund could not have been allowed by learned State Commission and appellants are ready to adjust penalty for delayed possession. No doubt, there is stipulation for making payment @ Rs.5/- per sq. ft. for delayed possession, but only on the basis of this clause, complainants cannot be deprived from getting refund of the money if project is not completed for a long period. Admittedly, possession was to be handed over within 36 months with 3 months grace period, but it was not completed till filing of complaint and as per written statement it was likely to be completed by November, 2014, meaning thereby, another 3 years period was required by OPs for completing construction. The builder cannot be permitted to retain huge amount of around Rs.50,00,000/- on payment of Rs.7750/- per month as penalty for delayed possession. Clause inserted for benefit of allottee cannot be used as weapon against him. For instance, if a builder does not complete construction for 10 years, by no stretch of imagination, he can be permitted to retain money on payment of meager sum about 1 to 1% p.a. and in such circumstances, learned State Commission rightly allowed complaint and directed OP to refund money deposited along with interest.

    8. Learned Counsel for the respondent also placed reliance on judgment of Coordinate Bench in F.A. No. 342 of 2014 Emaar MGF Land Ltd. & Anr. Vs. Karnail Singh & Anr. in which on similar facts complaint was allowed by State Commission and appeal was dismissed with cost of Rs.5,00,000/- and SLP (C ) No.29392/2014 Emaar MGF Land Ltd. & Anr. Vs. Karnail Singh & Anr. filed by Builder was dismissed by Honble Apex Court vide order dated 14.11.2014.

    9. In the light of aforesaid discussion, I do not find any illegality in the impugned order and appeal is liable to be dismissed.

    10. Consequently, appeal filed by appellants is dismissed at admission stage with no order as to costs. ......................J K.S. CHAUDHARI PRESIDING MEMBER